lean construction and delay analysis input in delay

110
Lean Construction and Delay Analysis Input in delay mitigation Master thesis International Master of Science in Construction and Real Estate Management Joint Study Programme of Metropolia UAS and HTW Berlin Submitted on 20.01.2020 from Mohamed Nassim Maidi S0562621 First Supervisor: Prof.Dr.-Ing. Dieter Bunte Second Supervisor: Architect Eric Pollock

Upload: others

Post on 06-Feb-2022

30 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Lean Construction and Delay Analysis Input in delay

Lean Construction and Delay Analysis Input in

delay mitigation

Master thesis

International Master of Science in Construction and Real Estate Management

Joint Study Programme of Metropolia UAS and HTW Berlin

Submitted on 20.01.2020 from

Mohamed Nassim Maidi

S0562621

First Supervisor: Prof.Dr.-Ing. Dieter Bunte

Second Supervisor: Architect Eric Pollock

Page 2: Lean Construction and Delay Analysis Input in delay

ii

Acknowledgement

I wish to show my gratitude to God who helped me to fulfill my ambition, gave

me strength and belief, then to my parents who pushed me by their prayers and their

support.

I am very grateful to my wife who fought like a soldier, against her sickness,

being patient of my absence and within the kids ,and to all my family ,Hichem, Imad,

Moussa ,Soumiya ,Bilel, Abderrahmane,Sarah,Haifaa,Salem.

My second family: Abdellaoui Berkahoum, Bedja Mohamed, Imane, Mohamed, Tarek,

Lakhdar, Soundous.

My gratitude to my supervisors, Professor Dieter Bunte from the University of

Applied Sciences of Berlin and Architect Eric Pollock from the University of Applied

Sciences of Helsinki for their guidance for this thesis and for their valuable courses

along the Master‟s degree program.

I appreciate too much the class of International Site Management and Project

Management given by Professor Mika Lindholm and Professor Nicole Riediger which

contributed positively to my research.

I thank also my ex-tutor and my friend Dr.-Ing.Mohamed Badaoui for his

support, Dr.-Ing.Hadji Saleh,Dr.Ing Abdallah Rahmani, Professor Abdullah Alsehaimi for

his guidance, and Tutor Donald Jordan for his recommendations.

Finally, I would like to thank those who supported me in my life: Mahmoud

Elazazzy, Daoudi Abdelaziz,Taher Bekkay, Ali Naami, Issam Abdeli ,Mohamed Ben

Amar, Oussama Taibi ,Zakariya Albarakani,Merna Emara, Sherif Abd Elhalim,Samir

Toufik,Ahmed Gahlan, Kei Kyung, Omar Mabrouk, Waqar Rose, Adel Seddik , Ben

Naoui Abderahmane Kaakaa, , Ouanouki Toufik, Houa Kheireddine, Mourad

Benzineb,Salet Rachid, , Taher Tahah ,Mahmoud benkhelil, Hichem Djeddaoui ,and all

the others.

Page 3: Lean Construction and Delay Analysis Input in delay

iii

Conceptual Formulation

Page 4: Lean Construction and Delay Analysis Input in delay

iv

Page 5: Lean Construction and Delay Analysis Input in delay

v

Page 6: Lean Construction and Delay Analysis Input in delay

vi

Abstract

This paper introduces an explanatory research by the mean of Content Analysis to

figure out the delay causes, their corrective actions, and the most efficient lean

construction technique, the outcome of this analysis is compared to Delay Analysis

Techniques which is conducted by a Case study along within a benchmarking of the

application of Last Planner System. A Mind Mapping is conducted to picture all the

possible links that combine LPS with the most adequate Delay Analysis Techniques.

The purpose is to build a process to be as a robust preventive mechanism against

delay, and consequently the nominated Delay Analysis Technique is a lean based

because the inner CPM Process is updated from the LPS program. The forensic part of

Delay Analysis is not considered in this research; only the technical part is taken into

consideration.

Key words: Lean Construction, LPS, Delay, CPM, Delay Analysis Techniques

Page 7: Lean Construction and Delay Analysis Input in delay

vii

Table of Contents

Acknowledgement..................................................................................................... ii

Conceptual Formulation .......................................................................................... iii

Abstract ..................................................................................................................... vi

Table of Contents .................................................................................................... vii

Table of Figures........................................................................................................ xi

List of Tabulations .................................................................................................. xii

List of Abbreviations .............................................................................................. xiii

List of Symbols ....................................................................................................... xv

1 Introduction ........................................................................................................ 16

1.1 Objectives ...................................................................................................... 17

1.2 Research Scope and Boundaries .................................................................. 17

1.3 Research Method .......................................................................................... 18

1.4 Research Structure ....................................................................................... 18

2 Literature Review ............................................................................................... 19

2.1 Brief introduction to project management ...................................................... 19

2.1.1 Project Definition ................................................................................... 19

2.1.2 Project management ............................................................................. 19

2.2 Construction Planning ................................................................................... 19

2.2.1 Definition ............................................................................................... 19

2.2.2 Planning Objectives .............................................................................. 20

2.2.3 Planning Techniques ............................................................................ 20

2.3 Traditional Push Planning .............................................................................. 21

2.4 Pull methods .................................................................................................. 22

Page 8: Lean Construction and Delay Analysis Input in delay

viii

2.5 CPM role and criticisms ................................................................................. 23

2.5.1 CPM Role .............................................................................................. 23

2.5.2 Criticisms of CPM ................................................................................. 25

2.6 Production Theory ......................................................................................... 30

2.6.1 Workflow Notion .................................................................................... 31

2.6.2 Load and Capacity ................................................................................ 32

2.7 Lean Construction ......................................................................................... 32

2.7.1 Lean Project Delivery: ........................................................................... 35

2.7.2 Takt-Time Planning ............................................................................... 36

2.7.3 The Five S‟s .......................................................................................... 36

2.7.4 Last Planner System ............................................................................. 37

2.7.5 Last Planner System Benchmark .......................................................... 40

2.7.5.1 Pull Planning ................................................................................... 41

2.7.5.2 Lookahead Planning ....................................................................... 42

2.7.5.3 Constraint Analysis ......................................................................... 43

2.7.5.4 Task Breakdown ............................................................................. 44

2.7.5.5 Collaborative Design of Operations................................................. 44

2.7.5.6 Reliable promising........................................................................... 44

2.7.5.7 Visual Control .................................................................................. 44

2.7.5.8 Daily Huddles .................................................................................. 44

2.7.5.9 Countermeasures............................................................................ 44

2.7.5.10 Metrics ........................................................................................ 45

2.8 Delay in Construction Industry ....................................................................... 46

2.9 Delay Analysis Techniques ........................................................................... 48

2.9.1 Additive Methods of Delay Analysis ...................................................... 49

Page 9: Lean Construction and Delay Analysis Input in delay

ix

2.9.2 Impacted as-planned ............................................................................ 49

2.9.3 Time impact analysis ............................................................................ 52

2.9.3.1 Windows analysis............................................................................ 52

2.9.4 The Collapsed as-built .......................................................................... 54

3 Research Methodology ...................................................................................... 57

3.1 Overview ....................................................................................................... 57

3.2 Methodology .................................................................................................. 57

3.3 Content Analysis ........................................................................................... 58

3.3.1 Validate Content Analysis ..................................................................... 60

3.3.1.1 Which data are analyzed? ............................................................... 60

3.3.1.2 How are they defined? .................................................................... 60

3.3.1.3 What is the population from which they are drawn? ........................ 60

3.3.1.4 Is the context relative to the data analyzed? ................................... 61

3.3.1.5 What are the boundaries of the analysis? ....................................... 61

3.3.1.6 What is the target of the interference? ............................................ 61

3.4 Six-Step Research Sequence ....................................................................... 61

3.4.1 Starting with Research Questions ......................................................... 61

3.4.1.1 Research Questions ........................................................................ 61

3.4.2 Decide on Sampling Strategy ................................................................ 62

3.4.3 Define the recording unit ....................................................................... 62

3.4.4 Construct Categories for Analysis ......................................................... 62

3.4.5 Test the codes and samples for reliability and validity .......................... 63

3.4.5.1 Reliability ......................................................................................... 64

3.4.5.2 Validity ............................................................................................ 65

3.4.6 Carry out the Analysis ........................................................................... 65

Page 10: Lean Construction and Delay Analysis Input in delay

x

3.5 Introduction to Dedoose software .................................................................. 66

3.6 Case Study .................................................................................................... 69

3.6.1 Case Study Description......................................................................... 70

3.6.2 Float Mapping ....................................................................................... 73

3.6.3 Extracting Float Values ......................................................................... 74

3.6.4 Float Map Creation ............................................................................... 74

3.6.5 Driving Activities identification ............................................................... 76

3.6.6 As-built critical path ............................................................................... 77

3.6.7 Case study main findings ...................................................................... 82

4 Research questions answers ............................................................................ 83

4.1 Question One ................................................................................................ 85

4.2 Question Two ................................................................................................ 88

4.3 Question Three .............................................................................................. 90

4.4 Question Four ................................................................................................ 92

4.4.1 Mind Mapping: ...................................................................................... 93

5 Conclusion and Recommendations ................................................................. 95

Appendices .............................................................................................................. 97

Appendix I ................................................................................................................ 97

Appendix II ............................................................................................................. 102

Appendix III ............................................................................................................ 104

Appendix IV ................................................................... Error! Bookmark not defined.

Declaration of Authorship .................................................................................... 105

References ............................................................................................................. 106

Page 11: Lean Construction and Delay Analysis Input in delay

xi

Table of Figures

Figure 1: A traditional Push Planning System .............................................................. 21

Figure 2: The Toyota Way Model ................................................................................. 30

Figure 3 Lean Project Delivery System ........................................................................ 35

Figure 4: The formation of assignments in the Last Planner planning process ............ 37

Figure 5: The Last Planner System: The Last Planner System .................................... 39

Figure 6: Should-Can-Will-Do ...................................................................................... 41

Figure 7: Last Planner System with Lookahead Process Highlighted .......................... 42

Figure 8: Functions of a Lookahead Process ............................................................... 43

Figure 9: DCAP/PDCA combined cycles ...................................................................... 45

Figure 10: Impacted as –planned (IAP) ........................................................................ 50

Figure 11: As-built sequence with as-built logic. .......................................................... 51

Figure 12: Windows Analysis ....................................................................................... 54

Figure 13:As-planned sequence with as-planned logic. ............................................... 55

Figure 14: As-built sequence. ....................................................................................... 55

Figure 15: As-built sequence with as-built logic. .......................................................... 56

Figure 16: Categorization cluster ................................................................................. 69

Figure 17:Float Deterioration Chart .............................................................................. 73

Figure 18: Driving Critical path ..................................................................................... 76

Figure 19: Code Cloud ................................................................................................. 83

Figure 20: Fine-tuned Co-Occurrence matrix ............................................................... 84

Figure 21: Delay Causes .............................................................................................. 86

Figure 22:Corrective actions ........................................................................................ 87

Figure 23:CPM influence on Flow ................................................................................ 89

Figure 24: Pareto Analysis Chart ................................................................................. 90

Figure 25: Delay Analysis Lean-Based Process Map................................................... 93

Page 12: Lean Construction and Delay Analysis Input in delay

xii

List of Tabulations

Table 1: Categories of Delay Analysis .......................................................................... 49

Table 2 :Strengths and weaknesses of the IAP Technique. ......................................... 52

Table 3: Strengths and weaknesses of the impacted as-planned technique. ............... 53

Table 4: Kappa interpretation benchmark ..................................................................... 64

Table 5: Keywords categorization ................................................................................. 68

Table 6: Available programs ........................................................................................ 71

Table 7: Raw data for the float map .............................................................................. 75

Table 8: Driving activities. ............................................................................................. 77

Table 9: Concurrent driving critical paths ...................................................................... 78

Table 10: Illustration of critical paths............................................................................. 79

Table 11: Delays mapped against the as-built critical path. .......................................... 80

Table 12: Employer risk event table.............................................................................. 81

Table 14: LPS Contribution among Lean techniques ................................................... 91

Table 15: Fine-Tuned Co-Occurrence (LPS &CPM) Matrix .......................................... 92

Page 13: Lean Construction and Delay Analysis Input in delay

xiii

List of Abbreviations

5S: Seiri ,Seiton ,Seisō, Seiketsu and Shitsuke

AACE: International Recommended Practice 29R-03

AEC: Architecture, Engineering, Construction

ASAB: As-planned versus as-built

BIM: Building Information Modeling

CAB: Collapsed as-built

CCM: Critical Chain Management

CLP: Constraint Logic Programming

CP: Construction Phase

CPM: Critical Path Method

DCAP: Detect-Correct-Analyze-Prevent

DES: Discrete Event Simulation

DIQ: Design Information Quality

EOT: Extension of Time

ES: Early Start

EVM: Earned Value Method

IAP: Impacted as-planned

IGLC: International Group of Lean Construction

IPD: Integrate Project Delivery

IRR: Inter/Intra-rater reliability

JIT: Just-In-Time

LBMS: Location Based Management System

LC: Lean Construction

LOB: Line of Balance

LPDS: Lean Project Delivery System

LPS: Last Planner System

LSM: Linear Scheduling Method

LWS: Lean Work Structuring

PDCA: Plan, Do, Check and Act

Page 14: Lean Construction and Delay Analysis Input in delay

xiv

PERT: Program Evaluation Review Technique

PP: Planning Phase

PPC: Percent Plan Complete

QASDAS: Computer Assisted Qualitative Data Analysis software

RCA: Root Cause analysis

RFI: Request for Information

RFID: Radio Frequency Identification

RSM: Repetitive Scheduling Method

SCL: Society of Construction Law

SCM: Supply Chain Management

SDB: Set-Based Design

TA: Task Anticipated

TFV: Transformation, Flow and Value

TIA: Time-Impact Analysis

TMR: Task Made Ready

TPS: Toyota Production System

TVD: Target Value Design

VM: Visual Management

VSM: Value Stream Mapping

WIP: Work-In-Process

WP: Weekly Planning

WS: Work Sampling

WWP: Weekly Work Plan

Page 15: Lean Construction and Delay Analysis Input in delay

xv

List of Symbols

Ƙ:Cohen’s Kappa Coefficient

: Proportion of agreed unites

: The proportion of units that might be agreed by chance.

Page 16: Lean Construction and Delay Analysis Input in delay

1 Introduction

Construction Industry suffers from delay which occurs by a lot of reasons. These

reasons include human factors, machine and equipment factors, and system factors.

Humans intervention factors such as labor related matters, the lack of know-how of the

planner, the superintendent for instance, machine and equipment factors such as

depreciation and improper tools, and system factors is the one related to IT and

software.

Lean construction is dedicated towards how to minimize waste in construction industry,

how to control the flow and maintain the pace in order to mitigate delay.

Lot of techniques are developed to serve the AEC field, one of the best known is LPS

which dedicated to monitor and control the flow, fit the gaps of the CPM shortcomings.

Delay Analysis Techniques are developed to estimate and quantify delays, it is divided

into prospective and retrospective techniques, and these techniques are developed

based on the experience got through claims and how to assess liability, nevertheless

legal and claims matters will not be discussed in this research.

Delay Analysis Techniques are based on CPM, whereas LPS is the monitoring tool of

CPM, the idea of benefiting from both techniques and use the best technique from both

sides of Lean Construction and Delay Analysis is the core basis of this research.

So far, there is no lean (LPS) based Delay Analysis since Lean priciples don‟t support

the use of CPM in nowaday‟s complex projects (Koskela, cited in Huseyin , Irem, &

Talat, 2017) .

In the next sections a proposed mechanism of delay prevention using one of the Delay

Analysis Techniques based on LPS process.

Page 17: Lean Construction and Delay Analysis Input in delay

17

1.1 Objectives

The objectives of the research is to investigate major delay causes and their corrective

actions, examining the contribution of the CPM is causing delay, analyzing the most

used Lean Construction, and figuring out how to bridge Delay Analysis Techniques and

Lean Construction most used techniques.

These objectives will be generated by answering the following research questions:

1) What are the reasons causing delay in construction projects and their corrective

actions?

2) Are Most of the occurring delays generated because of the shortcoming of

CPM?

3) What are the most used and effective techniques of lean construction and its

contribution to delay mitigation?

4) What is the possible relationship, common ground between Delay Analysis

Practice and the most used Lean construction technique?

1.2 Research Scope and Boundaries

This research will only focuses on Delay Analysis Techniques,forenscic part will be

ignored,a case study will be conducted in Delay Analysis,A benchmarking outcome of

LPS will be used within the case study,Only IGLC papers will be used for the content

analysis which will be explained in details in the part of content analysis.

As an outcome,a Mid map will be geerated from MindManager to illustrate the possible

bridge between Delay Anaysis and LPS.

Page 18: Lean Construction and Delay Analysis Input in delay

18

1.3 Research Method

Research objectives will be reached through critical Literature review of Lean

Construction,pitfals of the traditional Management,delay and delay in construction

Industry.

A Content Analysis will be conducted by a qualitative software Dedoose, and Excel

Tables and Charts wil be gnererated.

A case Study will be conducted in Delay Analysis to be compared within the outcome

achieved and the LPS benchmarking,and Finaly a Mind Map will be developed to

picture the outcome.

The benchmarking and the case study were chosen based on the quality of the author

and the publisher and also the time accordance of the publication.

1.4 Research Structure

The thesis is divided into five chapters,Introduction, then chapter two is a literature

review that highlights the subjects related to the research questions,starting from

Management ending up with Lean Contruction.

Chapter three,Content Analysis Methodology ,and the case study.

Chapter four,dedicated to the answers of the research question within the Mind

Mapping,and finlay chapter five which represents the conclusion and recommendations.

Page 19: Lean Construction and Delay Analysis Input in delay

19

2 Literature Review

2.1 Brief introduction to project management

2.1.1 Project Definition

Project has been defined as per the guide of the project management body of

Knowledge as per PMBOK (2000), “a project is a temporary endeavor undertaken to

create a unique product or service” (P. 4).

2.1.2 Project management

Project management has been defined according to PMBOK (2000), “the application of

knowledge, skills, tools, and techniques to project activities to meet project

requirements” (P. 6).

It has been also described by Williams (2008), “project management is everything you

need to make a project happen on time and within budget to deliver the needed scope

and quality” (P. 2).

2.2 Construction Planning

2.2.1 Definition

Planning has been defined as per Neale, Neale, & Stephenson (2016), “the creative and

demanding mental activity of working out what has been done, how, by whom, and with

what” (P. 6).

The planning term is a term that can touch all the stages of construction, from feasibility

to turnkey or commissioning, it requires a nonstop process (Neale, Neale, &

Stephenson, 2016).

Page 20: Lean Construction and Delay Analysis Input in delay

20

2.2.2 Planning Objectives

Five essential objectives have been highlighted in a general context (Neale, Neale, &

Stephenson, 2016):

Analysis: investigating the manner the job will be done with, the sequence of the

tasks should be manageable and within budget;

Anticipation: because of the covered uncertainty and risk in activities, a plan

should be done in a way to overcome these obstacles and unforeseen issues;

Scheduling resources: it is the process of investigating what is available and

economic for an optimal decision;

Coordination and Control: coordination between the players and controlling

time and cost;

Data production: to be used as a basis for future plans (Neale, Neale, &

Stephenson, 2016).

2.2.3 Planning Techniques

They are made to help in analyzing the plan, how to manage the information, and the

method it will be liaised to others, usually four essential techniques are often used in

planning which are (Neale, Neale, & Stephenson, 2016):

Bar chart: easy to implement, straightforward method, but it requires a lot of

change and drafting;

Line of Balance: it is dedicated principally for repetitive projects, easy tool to

plan, difficult to be used in monitoring in complex projects;

Linear Programs: Two-dimensional techniques dedicated to linear projects such

as tunnels and roads;

Network Analysis: logic-based technique, strong, adequate to the complex

project and can be fed smoothly to the computer, such as CPM and PERT.

Page 21: Lean Construction and Delay Analysis Input in delay

21

2.3 Traditional Push Planning

(Hopp and Spearman as cited in Ballard G. 2000) , the traditional push system is

complemented with a pull technique, which needed especially in the circumstances of

variability. Production is a part of Project management; it is somehow indirectly linked to

it (Ballard G.2000).

Figure 1: A traditional Push Planning System (Ballard G. 2000).

It has been criticized that Production did not give importance to Flow and Value, a

workflow of materials and information is what should be controlled, and corrective action

should be taken against processing methodology, buffer location and sizing, local

control strategies (Huovila and Koskela, as cited in Ballard G,2000).

It has been stated that the study of Lauri Koskela to apply manufacturing concept in

Construction is what drove him to come up with the theory of production (Tommelein

and Ballard, as cited in Tommelein.D.Iris,1998). Consequently, Managers should be

Page 22: Lean Construction and Delay Analysis Input in delay

22

aware of the ambiguity of this concept, so they can be realistic once they set their

demands, being optimistic about the production Process may lead to nonsensical

results and lead to failure. Push system could increase the waste because it has been

evaluated driven and having factors that recompense the uncertainty which has been

anticipated, Push System cannot rectify the changing that has occurred, but the Pull

System can do it (Tommelein, 1999).

The mission of Push systems is to issue the information from the Master schedule, for

instance, to the system of predefined due dates (Ballard G. 2000). Push systems can be

represented by traditional techniques other than CPM such as PERT; activities are

pushed by the previous one to keep the relationship of precedency (Tung Yang P. G.,

2001).Moreover, some critics have been directed to Push controlling, and been

considered dominant in the case of LBMS management, stated the fact that successors

were launched even the predecessors have been delayed, which led delays and less

productivity (Seppanen, 2012).

2.4 Pull methods

Pull method can be used as a feedback mechanism to alert the upstream level of what

is needed in the downstream level, while pushed products cause a greater waste, not

only by catching resources, but also maximizing their cycle time. In addition, Pull can

adapt changes of the requirement rather than push which cannot (Tommelein, 1999). It

has been also clarified that pulling is the action of checking the availability of information

and resources (Jun, Chua, & Hwee, 2000). Pull action has been defined also, as

moving the activity finish time to another activity start time (Yang I. 2002).

Pulling could be defined as a method to bringing up Information and Materials to

Production Process, Conversely to Push Method, which is based on Completion Dates,

looking for causes of the intersection of interdependent actions (Ballard G. 2000).

Pull scheduling has been proposed to the construction process as a lean method to

enhance the performance of it, knowing that CPM scheduling is a push-driven

approach, where the activity in a passive way, should wait to fully be resourced in order

Page 23: Lean Construction and Delay Analysis Input in delay

23

to be ready, consequently, resources overloaded and waited in a buffer which led to

poor planning productivity (S.Mohammad, 2012).

2.5 CPM role and criticisms

2.5.1 CPM Role

Bottlenecks of construction usually found on CPM critical activities, it has been noticed

that Productivity can be enhanced if detecting those activities in advance, but it has

been criticized with the appearance of Lookahead planning stating that CPM has

neglected Information and resources related to workflow. CPM-Based Scheduling

assumes while CPM and Lookahead have the same objectives, then constraints would

be the same (SHEN Li Jun, 2000).CPM also has been criticized for its failure to shape

the Non-value adding activities (Tung Yang P. G., 2001).

According to Koskela (1992), “These managerial principles violate principles of flow

process design and improvement and thus lead to non-optimal flows and expansion of

non-value-adding activities” (P.31).

In Traditional CPM, if a task takes place without affecting the completion time of the

project we call it float, if we delay the start time of non-critical activities, it gives the

opportunity of different use of resources such as Leveling, as Ballard stated, they can

be used as “Schedule buffers” (Yang T. , 2002). (Harris and Ioannou, as cited in Yang

I,2002), for repetitive nature projects, they have been criticized because it happens that

the production rate is different from crew to another, it leads to waiting for the time

between the predecessor and successors which is unproductive). Continuous workflow

cannot be achieved with the mean of CPM unless detailed and corrective action

analysis has to be taken in every step (Yang T. , 2002) .Creating a CPM schedule is a

way creating a network of a sequence of activities that related to each other, each

activity has its own scope and duration, which facilitate to get limit dates, using forward

and backward pass. If we consider CPM as a product, and if we apply lean to CPM, we

would say that the perfect schedule is the one delivered promptly and without waste. To

enhance the process, we have to know how to deliver the value, eliminating the non-

value adds, by concentrating on the flow in the planning process, identifying the

Page 24: Lean Construction and Delay Analysis Input in delay

24

demands and the deliveries that have values at the same time (Bob Huber, 2003).CPM

schedule has been criticized for its shortcomings of deliveries, the interaction of

resources is overlooked, unrestrained capacity plans, and due dates could not be

reached (Vaidyanathan, 2003).

Some factors that would cause waste in time and cost are resource availability and

continuity constraints in CPM and PERT scheduling; it can be clearly noticeable in

repetitive activities. The early start leads to workflow disruptions when resource

continuity is been restrained, for this issue, some methods have been considered such

as LOB, RSM, and LSM to mitigate disruptions, taking these constraints into

consideration by restricting the number of interruptions and shiftless time (idle time),

harmonizing the production rates, work break-even and postponing activities to avoid

interruptions (Sriwuwarnat & Photios, 2007).Nevertheless, some critics have been made

for these techniques announcing that these methods do not consider uncertainty and

variability; they just depend on average production rate (Tommelein et al., as cited in

Sriwuwarnat & Photios ,2007).

The authors suggested using buffers as a control tool of “when to start” to avoid

interruptions, which has been called “lead-time buffer” (Sriwuwarnat & Photios,

2007).The same argument has been settled, criticizing the shortcoming of CPM and

linear scheduling method LSM too, of non-ability to detect the activity-resource

continuity and concurrency-overlap process stated by, it can just maintain the

sequences only when the alternate one is found (Jaafari , as cited in David K.H, 2009).

Moreover, CPM maximizes resources and adds extra time to delayed critical activities,

comparing to LBMS, this last is more solid in productivity. Future researches have been

suggested by the author to simulate and compare these two techniques under different

circumstances and in several ways (Seppanen, 2012).

Another statement has been highlighted that the CPM has been used in a hospital

project as a contractual document and a reporting tool for the owner, along with three

weeks lookahead based on weekly metrics, The CPM has been established by James

E.Kelly and Morgan R.Walker in the ‟50s, in order to substitute the weakness of

traditional planning; stating that one of the crucial problems affecting technical

Page 25: Lean Construction and Delay Analysis Input in delay

25

management is to coordinate a lot of activities which have a common goal, claiming the

limitless of the use of CPM (Lauri Koskela G. H., 2014).CPM has been addressed as

the most crucial revolution in construction management in the 20th century, despite, it is

still having criticized as insufficient for controlling, a paradox has been raised by Lauri

Koskela stating, why still using CPM despite its shortcomings even if it cannot achieve

or produce likely acceptable outcomes? (Lauri Koskela G. H., 2014).

CPM has been inserted to construction Management as a production tool, and then it

has been shifted to be used as contract control by the client (Howell & al., as cited in

Lauri Koskela G. H,2014). stated that the mission of planning is to steer action before it

happens (Theory), to hold the operation under control (as planned), and to follow up the

work (as should be done in practice) (Laufer and Tucker, as cited in Lauri Koskela G.

H., 2014). They claimed that management interest has been diverted intensively to

control “at the expense of planning”; the interest was investigating the deviations causes

rather than enhancing the plan (Lauri Koskela G. H., 2014).

Contract document for schedules and activities sequence, performance control, delay

assess, progress and payment arrangement (Jaafari, as cited in sears, 2010). Activities

are considered as “black boxes”, how is going to be done is held to the contractor

(Sears, as cited in Lauri Koskela G. H ,2014).

2.5.2 Criticisms of CPM

It has been claimed that CPM is limited suitable for site management (Peer, as cited in

Lauri Koskela G. H.2014). It has been claimed too that CPM has put more unnecessary

input of management in a bureaucratic environment of management (Applebaum , as

cited in Lauri Koskela G. H.2014). CPM does not work properly at the operation level; it

does not keep the workflow continuous, a discontinuity between stakeholders in terms

of handovers (Peer, as cited in Lauri Koskela G. H., 2014). An argument about the

buffer safety time that misused by CPM, buffers are accompanied activities to

accommodate uncertainty, and the issue is when the predecessor‟s activity will really

Page 26: Lean Construction and Delay Analysis Input in delay

26

finish in order preparing for the next step clearly and accurately (Lauri Koskela G. H.,

2014).

Goldratt 1997, as cited in Lauri Koskela G. H., (2014), another argument stating that

finished activities probably not launched early, assuming that in future a pressure will be

practiced letting them finish early. The theory of constraint is to shift safety time to a

strategic level, taking an example of adding project buffers and concentrating on finish

time. CPM could be used to show main critical conflicts (disturbances) but most of the

projects have an outstanding uncertainty which leads to, productivity changes, capacity

loss, and deviations, which often happen too late in case of CPM, opposite to LOB

which deviations detected immediately), these deviations are not set clearly, as with the

LOB method (Seppänen & Aalto, as cited in Lauri Koskela G. H., 2014).it has been

stated that traditional practice is a zero-sum, where different parties with a common goal

are out of the overall process which makes a decision is done from a personal

perspective (Sacks and Harel, as cited in Lauri Koskela G. H,2014). It is been stated

that is difficult to envelop a systematic assessment of CPM in construction, the

shortcomings so far, are not pointed out directly to the most crucial one, some visions

and developments have been introduced such as CCM, LOB, but they are still not the

main used methods, the issue that the critics did not touch the validity evaluation of

critical path method, they have been presented solely, and there is no systematic

evaluation so far, albeit, it remains the most dominant effective tool in the field of project

management (Lauri Koskela G. H., 2014).

CPM has been considered as an optimization tool, leading to a minimum duration of the

project, but it is no longer the same in construction management and in quantitative

methods. In construction management, CPM also presented as a planning tool than an

optimization tool. The main hypothesis behind CPM is finding the best available shortest

task, namely optimal, which requires that planned tasks also should be optimal; to

provide an optimal plan, otherwise fail will occur if only one task is a non-optimal one.

Unfortunately, before Ballard (2000), the methodology is “neglect of validation”, Ballard

realized that roughly half of the tasks were realized as planned in a WP, which leads to

the point that the other half of tasks is non-optimal, which weakens the rational of CPM.

Page 27: Lean Construction and Delay Analysis Input in delay

27

One of the crucial reasons for non-optimal tasks (based on RCA) to be done is

margining the other input than the focus on the previous task which leads to a chronic

problem in starting tasks. Obviously, this is the very idealization required for rendering

the problem of planning mathematically amenable (Koskela & Ballard, as cited in Lauri

Koskela G. H.,2014). Koskela confirmed that there is no issue with CPM, there is an

issue with the way they apply it (Lauri Koskela G. H., 2014).

Morris 1997, as cited in Lauri Koskela G. H.(2014) argued that the application of

operations research during the Second World War was a reason to develop modern

management, which progressed around CPM with no exaggeration. Debatably, the

practice has not improved and pushed idealization to realism, but contrarily idealization

has weakened the practice leading to a loss of realism. CPM has been established as a

tool of optimization by quantitative methods, which is based on axiomatic research, but

there was no valid test has been set empirically, which made the discovery of the

unrealistic of CPM was not possible for the last forty years. The dominance of CPM has

been supported despite the shortcomings; the method has never been tested and

validated empirically as mentioned before, a subtle change in purpose from production

to contract management, which weakens the validation of optimality, as an outcome, in

term of construction management methodology, it has been proposed that testing and

validation should take place. CPM does not take into consideration the readiness of

work to be done, (Mossman 2012 as cited in Bo Terje Kalsaas, 2014).

The sequence of activities in the critical path will cause a delay of all the projects if no

action of mitigation is taken (Kelly and Walker 1959, as cited in Bo Terje Kalsaas,

2014). CPM approach is limited in terms of maintaining the construction workflow

(Koskela and Howell 2008 as cited in Pingbo Tang, 2014), they have been criticized for

their limitation of identifying the use and location of the resources while handling the

planned tasks (Pingbo Tang, 2014).It has been argued that CPM schedules contain

repetitive cycles of activities which are independent in location and which inevitably lead

to delay or waiting time, suggesting LOB to solve this issue by figure-hugging the

unseen waste in the schedule (Russell Kenley, 2015), moreover, CPM is also lacking

from: spatial information, continuity, and visualization (Lauri Koskela A. K., 2015).

Page 28: Lean Construction and Delay Analysis Input in delay

28

LPS has been considered the most widely held technique being used in construction

projects, it was basically designed to fill the gaps of production management, and

especially those that occurred and left by CPM, nevertheless, gaps still exist in planning

and scheduling and their interface with LPS and LBS is not yet assimilated. Even

though, CPM remains the engine of all the software of planning, like Primavera and MS

Project (Senior, 2009).

Conversely to traditional project control, Decision making should not be centralized by

distributed in a production system which is dynamic by nature. LPS will is described and

evaluated against these criteria, production processes can be divided into these parts

(Ballard G., 2000):

An Input-Output converting tool;

Time and space related flow of Information and Materials;

A value generating tool.

The LPS symbolizes the control notion as causing an event to comply to plan,

conversely to traditional project control where the action takes place after the fact

variance detected, production was mainly specific to industrial engineering, to present

similar type of production manufacturing in the meaning of creating or making, rather

than designing (Ballard G., 2000).

Lauri Koskela 1999, as cited in Ballard G.,(2000), proposed for production control,

stated that:

Firstly, work should only start when all the prerequisites of completion are on

hand to mitigate the suboptimal conditions;

Secondly, PPC should be used as a measure for the assignment to decrease the

variability;

Thirdly, investigate the causes of non-completion to be removed to guarantee a

continuous process;

Fourthly, hold a buffer that is adequate for different crews to avoid the loss of

productivity;

Fifthly, Lookahead planning is suggested to handle the coming assignments that

are already made ready, ensuring the non-emerging of the material buffer

(Ballard G., 2000).

Page 29: Lean Construction and Delay Analysis Input in delay

29

It has been stated that, buffers have the capacity to mitigate variation and fluctuations in

the production process (Sakamoto, Horman, & Thomas , 2002). Hopp and Spearman ,

as cited in Ballard G., (2000), an effective design production control should mitigate

“Variability” that exists in quality, in time of the process, in deliveries. Because

neglecting the factor leads to greater variability, Variability could be generated from:

Lead time from flow‟s buffers;

Lower resources utilization;

Lost throughput;

Assignments are sound regarding their prerequisites;

Assignments are measured and monitored;

Investigate and remove Non-completion causes;

A buffer should be maintained for each crew or production unit (Hopp and

Spearman , as cited in Ballard G.,2000).

Page 30: Lean Construction and Delay Analysis Input in delay

30

2.6 Production Theory

TPS is a manufacturing approach is the fundamental of lean production, which is

dedicated to eliminate waste and add value, it has been founded in 1950 by Taiichi

Ohno who said “All we are doing is looking at the timeline from the moment the

customer gives us an order to the point when we collect the cash. And we are reducing

that timeline by removing the non-value-added wastes” (Liker, 2004)

Figure 2: The Toyota Way Model (Liker, 2004)

Five principals of lean thinking have been introduced as Value, Value Stream, Flow, Pull

and Perfection (Womack & Jones, 2003).

Value: is the way of knowing precisely what is needed by the customer, it has

been considered the first move in lean thinking, it is delivering the right service

the right way, otherwise delivering the wrong service in a correct way would be a

Muda (waste).

Value Stream: is the group of necessary actions that examine the product and /or

service through a process of problem resolving tasks, information and data

management tasks, and conversion tasks.

Flow: after defining the value and the value stream it is time to maintain (pacing)

the flow of the steps that add value.

Page 31: Lean Construction and Delay Analysis Input in delay

31

Pull: it is the way of making the orders stable by letting it pulled by the customer

rather than pushing products.

Perfection: transparency is considered the most spur of perfection, impediment

shows up as much as we pull and hidden waste too, learning from customers to

improve the flow and pull process.

It has been defined that Lean thinking identifies variability and its distribution of the

workflow continuity, one of its doctrines is to harmonize and line up the production

process (Womack and Jones, as cited in Tommelein.D.Iris, 1998).

Because Lean production main role is to reduce waste and eliminating non-adding

value activities, Koskela has established a set of rules to make this happen (Lauri

Koskela, as cited in Patrick T.I.Lam, 2001):

The requirement must be through a systematic way;

Minimize variability;

Minimize cycle times;

Minimize steps

Increase flexibility;

increase transparency;

Build continuous improvement;

Balance flow improvement with transformation one;

Benchmark (Lauri Koskela, as cited in Patrick T.I.Lam, 2001).

2.6.1 Workflow Notion

Production needs to be done in a certain sequence and rate, and the way it makes

production behaves as desired is called Workflow (Ballard H. G., 2000).

Koskela 1992, as cited in Tommelein, (1999), a workflow has also seen crucial because

work and materials which are struggling without flow, are idling money and space.

Page 32: Lean Construction and Delay Analysis Input in delay

32

2.6.2 Load and Capacity

A stable Workflow could be verified when Load matches the capacity or vice versa, and

to mitigating or avoiding variability, but preferably that planners adjust Load.

The load can be changed by whether speeding up the workflow or by slowing it down,

on the other hand, Capacity could be changed to adequate Load by adding or

minimizing resources (Ballard G.,2000)

2.7 Lean Construction

A crucial purpose of Lean Construction is to maintain Continuous workflow, the dilemma

here, to have continuous resources use in CPM (Ballard and Tommelein, as cited

inYang T. , 2002).It demands a detailed analysis of activity by activity network and

correction actions. (Yang I., 2002).

The purpose of Lean schedule too is to achieve the requirements of the contract,

company rules, design, supply and delivery in one document and in the earliest possible

time, exploiting the minimum resources, the clue is to recognize the schedule‟s

consumer, and discriminate what could be the value of the schedule (Huber & Reiser,

2003).

Koskela is the one who presented construction as a product, and how the TFV concept

to the AEC field (Koskela 1992). This concept is considering the flow of materials and

Information via experts, to generating customer Value (Koskela and Ballard 2003).

Flow is the principal idea of lean construction, the flow has been divided into three sorts:

by material, by the assembly, and by location. Location and assembly flow represent the

movement through the building and the sequences of it simultaneously (Tan, Horman,

Messner, & Riley, 2003).

Lean thinking has been addressed as a method to enhance construction procedures

and add value, argumentation has been made about the tools to integrate lean are not

well established, Some issues have been faced while shifting from Original schedule to

lean schedule, where dummy represents the activities to be set within the critical path.

Page 33: Lean Construction and Delay Analysis Input in delay

33

In the Lean schedule, these activities were removed taking noncritical activities to the

Critical path (Ansell, Holmes, Evans, Pasquire, & Price, 2007).

T.S.Abdelhamid (2009) study stated the following :

A holistic facility design and delivery philosophy with an overarching aim of

maximizing value to all stakeholders through systematic, synergistic, and

continuous improvements in the contractual arrangements, the product design,

the construction process design, and methods selection, the supply chain, and the

workflow reliability of site operations.(P.2)

Lean paradigm has been deeply used (Invested)in planning forthcoming works, for this

purpose the authors developed a tool OODA Loop which has been used as a decision-

making tool to bridge the gap of actions that planners couldn‟t predict/foreseen

(Anticipate) (T.S.Abdelhamid, 2009). Planning Phase has a lot of reasons for the delay

but can be grouped into two groups, those which generated from the project such as

design compatibility and variation, insufficient information of specs, documents conflicts,

and the other group which is generated from the communication and cooperation

between stakeholders, the authors claimed that the number of RFIs is dramatically

increased in PP compared to CP, referring to two crucial reasons: the time frame of the

planning phase is longer, and no information details delivered to contractors (Matias &

Cachadinh, 2010).

Lack of workers and predictable task time have been solved using LPS , for a more

effective master schedule (sequence and duration), leading to fewer workers, only

activities than CAN be done WILL be considered within Pull technique, another

technique that has been taken into consideration is 5 Why‟s for waste reduction (Joao

Matias, 2010). TFV Transformation-Flow-Value theory has been described as a flow of

materials from cradle to grave before the final construction is done.

Koskela, as cited in Lindhard & Wandahl, (2012),“the material flow is undergoing,

moving, waiting, inspection, and transformation before the final construction is finished”

(P.5).Each activity is attached to time and cost, the only activity adding value is the

transformations, the others are waste. The purpose is mitigating or reduces waste and

restructures the Value-adding activities to be effective, knowing that adding value is

satisfying the customer's demand and requirements. Johnson & Kaplan 1987, cited in

Page 34: Lean Construction and Delay Analysis Input in delay

34

Lindhard & Wandahl, (2012), “value of any commodity, service, or condition, utilized in

production, passes over into the object or product for which the original item was

expended and attaches to the result, giving it its value” (P.5).

In order to increase value, we must identify and fulfill the needs of the customers which

are the following: activity and the customer during the transformations. Koskela ,as cited

in Lindhard & Wandahl, (2012) ,“the very complexity of a product or process increases

the costs beyond the sum of the costs of individual parts or steps” (P. 5).

Womack 1996, as cited in Senior, (2012),defined Lean Thinking, “More autonomy in

production decisions and enriched jobs as a consequence of the lean principles

regarding distributed decision making, multi-skilling, and pursuit of perfection” (P. 2).

Henrich et al., as cited in Senior, (2012), defined value as the concept which links the

requirements of the customer within the most optimal method.

Lean Construction has played a big role in production enhancement, has been brought

this concept to the construction industry which led to open the door to development

,Koskela presented a lean theory based on Operational management, developed lean

construction in planning and controlling stream, it has been described as an method that

touch all the stages all construction in order to minimize non adding values tasks and to

produce maximum of value, the author described Lean by „doing more with less‟.

The author has described other techniques that have used as a lean tool such as

(S.Mohammad, 2012):

Quick mobilization.

Pull Scheduling.

Six Sigma.

Just-In-Time.

These techniques have proved a significant influence to minimize waste, reduce

schedule variance, and to enhance the quality (S.Mohammad, 2012).

Lean Construction has considered the issue of communication between the players, by

integrating the philosophy of collaboration in each phase, it can advocates decision

making at the last moment with Pull technique which provides high flexibility to manage

activities scheduling and supplies. It is been argued that big spaces of the construction

site have been used as storage areas, which led to cost overruns, this issue could have

Page 35: Lean Construction and Delay Analysis Input in delay

35

been solved using lean construction JIT system, where resources should be requested

when they are needed, and consequently reducing the cost of storage and the cash

flow,5S and WIP techniques also have been suggested by the authors for better

standardization, safety in construction, and materials delay (Matias & Cachadinh, 2010).

Ballard and Howell , as cited in Senior, (2012), the main role of Lean construction could

be defined as providing the requested product in the same time maintaining the optimal

value and the less possible waste.

2.7.1 Lean Project Delivery:

It has been defined as a model of project management; its process is to bring into a line,

Ends, Means and Constraints, taking into consideration the customer requirement and

the constraints that might disturb getting to their ends. (Ballard G. , 2008)

LPDS is described as an integrated system to help to make an even flow between

multiple activities and between other players (Kpamma & Adjei-Kumi, 2013).

Figure 3 Lean Project Delivery System (Ballard G., 2008)

Page 36: Lean Construction and Delay Analysis Input in delay

36

2.7.2 Takt-Time Planning

The name comes from the German term „Takt‟ which mean „Beat‟,takt-time Frandson et

al, as cited in Frandson, Berghede, & Tommelein, 2014).It is the time which the supply

rate should meet the demand rate, takt-time planning helps to create a continuous flow

(Frandson, Berghede, & Tommelein, 2014).

The authors stated that Takt-Planning is based on work structuring, it has been

developed to respond to the requirement of work structuring by an iterative way of the

following steps:

Data collection;

Zone definition;

Trade sequence generation;

Individual trade duration;

Workflow balancing;

Production schedule (Frandson et al., as cited in Frandson, Berghede, &

Tommelein, 2014).

2.7.3 The Five S’s

Defined the five S as a set of programs to mitigate waste which causes problems to the

process, this five S are (seiri which means Sort, seiton which means Straighten,

seiketsu which means Shine, and shitsuke which means sustain), the definitiion in

English as follow (Liker, 2004):

Sort: sorting out the needed item and those we don‟t need.

Straighten: Everything should be placed, and a place should be set for everything.

Shine: The cleaning process plays an inspection role that investigates the status of

work. Standardize: maintaining and monitoring the three first steps.

Sustain: maintaining continuous improvement.

Page 37: Lean Construction and Delay Analysis Input in delay

37

2.7.4 Last Planner System

The name came from the last person who produces the assignments which identify the

communications of requirements (Ballard and Howell, as cited in Ballard, 2000).

These assignments which are a set of planning products are also a responsibility of all

the organization, the concept is what WILL be done that goes with SHOULD with the

CAN Constraints(Ballard, 2000).

Figure 4: The formation of assignments in the Last Planner planning process (Ballard G. , 2000)

But, when it would be impossible to differentiate between SHOULD and CAN, where it

should be eliminating problems, but not neglect them, then uncertainty is increased

leading to failure of control.

Ballard states that the need for orienting the focus from control to Workflow is the link

between them. LPS is composed of two components: Production Control which

enhances the progress of assignments by means of continuous learning, corrective

actions, and the second step is Workflow Control which makes the workflow in the best

possible pace.

Planning at the production level depends on the quality of plans delivered by LPS; the

quality of assignments should verify the following:

Well defined assignments (Enough details to make them ready and clear);

Logic Sequence along with right commitment and right execution strategy;

Page 38: Lean Construction and Delay Analysis Input in delay

38

An adequate amount of work;

Practical Selected work (Available resources, perquisites on hand) (Ballard2000).

It could be easy that front line supervisors fulfill what has been set for assignments

quality restrictions, but it is not clear for in-process inspection that cannot be measured

directly, but it will be easy through plan execution where we can measure the PPC

(Percent Plan Complete) .The Higher is the PPC, the higher productivity and Progress

we have, reflecting the right work with the right available resources. It is also an

Indicator of how Committed (WILL) is the front-line supervisor. Measuring LPS

Performance is not only making changes but also investigating the root causes of failed

executions, reasons why certain work is not done starting by lead supervisors should

be identified or directly person responsible for that execution, some reason could be

(Ballard, 2000):

Inadequate provided information to the Last Planner;

Failure to apply the assignments quality steps;

Lack of coordination;

Priority shifting;

Error in the level of design or vendor (Ballard2000).

Last Planner is a mechanism that turns what it SHOULD be done to what it CAN be

done, by preparing a WWP committed by last planners (foremen, squad Bosses) to

what really, they WILL do. (Ballard2000).

Page 39: Lean Construction and Delay Analysis Input in delay

39

Figure 5: The Last Planner System: The Last Planner System (Ballard G., 2000).

The last planner of Production Control consists of Planning which is setting goals in

which sequences and Control which creates causes events to approach the wanted

planning, start re-planning whenever it is needed if the planning is no more feasible or

no longer wanted, and start learning when failing to comply to plan (Ballard G., 2000).

The last planner is considered the most used technique, there is no clear lean

scheduling but LPS uses the master plan to start and as a tool of following up(tracking),

(from the milestone perspective) (Ballard, 2000).LPS tries to defeat the shortcomings

generated from CPM, by maintaining a steady planning system and by dealing(tackle)

with flow feature(aspect).It has been argued that decision making should be adapted by

field managers as they know best to handle decisions ,for this purpose, it has been

addressed LPS to solve this decisions (Ballard, as cited in Senior, 2012)

Page 40: Lean Construction and Delay Analysis Input in delay

40

2.7.5 Last Planner System Benchmark

A benchmark process has been set by (Ballard & Tommelein, 2016) :

1) SHOULD step:

Pull planning

2) Lookahead planning/make ready:

Constraint Analysis

Task breakdown

Collaborative design of Operations

3) Workflow reliability:

Reliable promising.

Visual Control

Underloading resources

Daily huddles

4) Learning from plan failure:

Analysis of breakdowns

PDCA

DCAP

5) Metrics:

PPC

TMR

TA

Occurrency of Plan failure.

Page 41: Lean Construction and Delay Analysis Input in delay

41

Figure 6: Should-Can-Will-Do (Ballard & Tommelein, 2016)

2.7.5.1 Pull Planning

Pull planning is part of LPS, it serves to pace and sequence activities, develop phase

schedule and setting the milestones or important event to be pulled.

Page 42: Lean Construction and Delay Analysis Input in delay

42

2.7.5.2 Lookahead Planning

Another concept meaning should appear which is Lookahead Process is, it is commonly

used in industry, it basically reflects what SHOULD be done, but within LPS, it could be

more than that.

Figure 7: Last Planner System with Lookahead Process Highlighted (Ballard,2000)

Lookahead plays an interlink between the Master plan and the WWP, it indicates which

activities that should be done in which week and prepare them to be ready for execution

according to the assignment criteria of the Last planner (Hammond, Choo, Austin,

Tommelein, & Ballard, 2000), lookahead also could be considered as a guide to loop

the constraints of resources and Information; these last issues could decrease the

performance and generate variation (Jun, Chua, & Hwee, 2000).

The next phase of the project that should be looked-ahead is the Phase Schedule that

helps to handle actions that go beyond the Lookahead (Ballard G. , The Last Planner

System of Production Control (PHD dissertation), 2000), It is been clarified also that the

goal of Phase Schedule is to generate a plan that everybody engages, a plan in which

the activities are tied to the Lookahead process making the assignments prepared for

WWP (Ballard & Howell, An Update on Last Planner, 2003).

Page 43: Lean Construction and Delay Analysis Input in delay

43

Figure 8: Functions of a Lookahead Process (Ballard G. ,2000)

Nevertheless, assignments should be submitted to Constraint Analysis in order to

guarantee what should be ready for execution, it facilitates the shifting from one

lookahead window to another (Ballard G.,2000).

2.7.5.3 Constraint Analysis

Constraints could be a crucial problem in front of the implementation of LPS; such

constraints are non-acceptance to change, absence of self-evaluation, short term vision,

and Misunderstanding of the PPC Indicator (Alarcón, Diethelmand, & Rojo, 2002).

Moreover, constraints usually differ according to the assignments; it helps to early

warning of issues and problems that give a time or a lead time to plan how to solve

them. Constraints could be shown up in Design, Equipment, Labor, and all other

constraints, assuming that throw it under the wall syndrome would occur once the

constraint analysis is absent (Ballard G.,2000).

Page 44: Lean Construction and Delay Analysis Input in delay

44

2.7.5.4 Task Breakdown

Dividing project into phases,process,opertations then steps.

2.7.5.5 Collaborative Design of Operations

It requires the engagement of all participants from first-line supervisors, to crafts

workers.

2.7.5.6 Reliable promising

By building a commitment network based on respect, taking into consideration the

ability to respond to the requirement.

2.7.5.7 Visual Control

Information should be transparent and posted to the public; it should be updated in a

real-time process to rectify and deviation from the production system.

2.7.5.8 Daily Huddles

A daily meeting to liaise commitment issues to be solved and those have been

achieved.

2.7.5.9 Countermeasures

An analysis to avoid the reoccurrences of breakdown, 5 whys implementation would be

an effective tool to investigate why some tasks have not been achieved, PDCA a should

be conducted to check whether the results generated from the root cause analysis is

supported, and DCAP to detect the deviation from the target than taking action to

correct the path of production.

Page 45: Lean Construction and Delay Analysis Input in delay

45

Figure 9: DCAP/PDCA combined cycles (Ballard & Tommelein, 2016)

2.7.5.10 Metrics

Four metrics have been dedicated to this benchmarking process:

PPC (Percent Plan Complete): to assess the workflow reliability, by calculating

the completed tasks by the planned ones.

TA (Task Anticipated): after setting a target week, TA measures those

anticipated tasks dedicated to the target week and see the percentage of the

accomplishment.

TMR Tasks Make Ready: it should be done within the lookahead step to remove

the likely possible constraints.

Frequency of failure of the plan: a step to discover Reasons for Variance.

Page 46: Lean Construction and Delay Analysis Input in delay

46

2.8 Delay in Construction Industry

Design changes are considered the main reason for construction delays; weekly Plans

WP and Daily planning have been addressed to overcome changes and delays (A.Ghio,

1997).Koskela (1992) stated that AEC fields used to consider conversion work and

neglect the flow issue, saying that flow is crucial in order not to idle the materials,

therefore holding up(Tying up) resources and space leading to waiting and cycle time

increasing, and as a result longer project duration (Tommelein Iris.D, 1999).

Unforced idleness caused by floats in repetitive projects causing waste and waiting

which lead to possible delays (Harris and Ioann, as cited in Tung Yang P. G.,

2001).Ashley, as cited in Tung Yang P. G., (2001), pointed out that contractors that

have left the job, they usually do not get to work on time, causing a serious delay.

Comeback delays could be mitigated by avoiding overlapping of the crews, crews

should be kept productive even in a slow rate, authors suggested RSM approach to

maintain the undistributed flow of resources (Yang I., 2002).To avoid delays generated

from overlapping tasks, a proper time lag should be left between tasks to keep conflicts

away. It is been stated that as much the buffers are small as the project will be delivered

soon with better performance, however, the predecessors and successors should not

cross each other, otherwise, variability increases leading to a delay (Mosanobu

Sakamoto, 2002) Another reason for the delay is the delayed procurement because

usually delays in a schedule based on CPM are not reflected on procurement plans,

Lack of Visibility, resource utilization, and date due to performance, the authors

suggested SCM approach to solving this issue (Vaidyanathan, 2003) Buffers are

considered as a tool to deal with variability that usually causes a delay in schedule,

recent empirical research stating that WIP could be used as Buffers, a simulation

approach has been suggested to provide the best WIP buffer based on lean

construction (González Vicente, 2006).

Design delays, poor planning and poor integration of suppliers in the planning system

are the major reasons for waste in the construction industry (Marcus P.Sterzi, 2007).

It has been pointed out too that if preceding tasks were not finished, delays would

happen, then the lack of information and poor output, some other important reasons

Page 47: Lean Construction and Delay Analysis Input in delay

47

are: weather, technical approvals, and ineffective assumption of workload, moreover, it

has been noticed that buffers have not been used, which demonstrates a poor planning

(Mary Ansell, 2007).

Some factors also cause delay and waste in the capital when ignored:

Restrictions in resource availability;

Restrictions in resource continuity;

Issues in Indirect and direct cost;

Penalties generated from the interruptions.

This can be noticed in repetitive tasks at ES dates using CPM and PERT because ES

schedules omit the resource continuity which causes a discontinuity inflow, which leads

to waste in time and cost. To solve this issue, and maintain resource availability and

resource continuity into the production line, some methods can fulfill this matter such as

LOB, LSM, and RSM. These techniques are useful in terms of reducing interruptions,

postpone activities to avoid idle time, and equalize the rate of production, but they do

not take into consideration variability and uncertainty, they are more deterministic by

considering the average rates of production in repetitive projects. But, the average

production rate concept is not enough when practiced, (Tommelein et al as cited in

Photios G.Loannou, 2007). For this purpose, another approach has been proposed to

solve the issue of scheduling in repetitive projects by “Lead-Time Buffer” (Photios

G.Loannou, 2007).Productivity has influenced by the variability, to ensure that the buffer

is executable to eliminate likely discontinuities of flow; each project has to set a strategy

to make an adequate buffer size to mitigate variability. Some metrics, such as PPC,

WPP, and Weekly support activity plan to assure an early decision making and helping

maintain the planned buffer size.

Minimized flow interruption has been achieved, which makes the project target achieved

as scheduled. Results are confirmed as stated by Koskela, as cited in Izquiredo &

Arbulu, 2008), “productivity and duration can be improved at the same time by

improving the reliability of workflow within the system” (P.5).

Delay as the time span between the dates of completion agreed in the contract and the

real completion of the project, it has been declared that delay is the most crucial issue

affecting this industry; the reasons have been highlighted in multiple studies. It has been

Page 48: Lean Construction and Delay Analysis Input in delay

48

stated that ineffective planning is the dominant factor of causing a delay, then the poor

site management simultaneously. A Quantitative study has been conducted to come out

with two things: causes of delay could be generated from the management or the

environment of the project (AlSehaimi & Koskela, 2008).

It has been stated that root cause has not been touched by previous studies, for this

matter author recommended constructively and action research should be carried out in

construction management practice to solve the issue of performance, knowledge, and

tenacious managerial obstacles. Hopp and Spearman, as cited in Chin, (2009),

suggested that one-piece flow has a very beneficial impact, because of its short cycle

time which leads to maintaining a low work-in-process. For instance, the shop drawing

most often is not submitted to reviewers as one piece but in batches which (requires

more time to review) also stated that the schedule category has been classified as the

most crucial cause, then the coordination, and finally the procedure. RFI, Lack of

information and engineering revisions have been declared the most frequent to occur

(Chang, 2009).

2.9 Delay Analysis Techniques

Delay analysis has different methods; each one differs from the other depending on the

case, choosing the most adequate one to calculate the effect on CPM is the most

important step in the decision process of delay analysis. In some situations, it is

required to go for both prospective and retrospective methods; prospective methods are

designated to illustrate the consequence of delay on finishing while retrospective

methods are to examine the actual effect of the same delay event,

Determining the unmitigated and non-eliminated effect is important to quantify the EOT

to be authorized (Caletka & Keane, 2015).

Primary Delay analysis techniques DATs are:

As-planned versus as-built (ASAB)

Collapsed as-built (CAB)

Impacted as-planned (IAP)

Time impact analysis (TIA)

Page 49: Lean Construction and Delay Analysis Input in delay

49

They fall under three general approaches as shown in table 1, and each primary

technique has a secondary method.

Table 1: Categories of Delay Analysis (Caletka & Keane, 2015)

2.9.1 Additive Methods of Delay Analysis

Additive methods are basically applied in a prospective way, delays occurred to

completion should be forecasted or predicted, it relies on the as-planned CPM or the

one lately updated. Additive methods have a theoretical framework, they are based on

available information at the time of delay happening, where the cause is recognized but

the effect is to be predicted (Caletka & Keane, 2015).

2.9.2 Impacted as-planned

It relies on the as-planned program, it utilizes the original baseline, and delays will be

injected in the baseline program as a new task, they have to be gathered with the

affected tasks and to be submitted to schedule again, the difference between the

original schedule and the new generated one shows the variance that will be used for

the EOT entitlement as per the SCL (Hegazy, 2012).

Page 50: Lean Construction and Delay Analysis Input in delay

50

Figure 10: Impacted as –planned (IAP) (AACE ,2011)

The IAP is a quick way of delay analysis; it is independent of the real schedule, it does

not require reports and documents. But , this method has been criticized because it

does not reflect what actually happened (Hegazy, 2012).Impacted as-planned is

considered the easiest form of CPM, the SCL (The Society of Construction Law

Protocol) names this technique as „IAP‟, this technique is a tool to assist getting the

EOT entitlement, but not cost prolongation (Caletka & Keane, 2015).

Page 51: Lean Construction and Delay Analysis Input in delay

51

Figure 11: As-built sequence with as-built logic (Caletka & Keane, 2015).

Impacted as-planned integration steps have been stated in (AACE, 2011) as follow

(Hegazy, 2012):

The CPM program has to be approved as the baseline schedule.

Critical and non-critical paths have to be well defined.

Agreed EOTs have to be identified along with necessary documents; also delays

have to be quantified.

Insert and reschedule the activities and observe the effect.

The variance occurred between the as-planned and the impacted is the EOT to

be entitled to the contractor.

Page 52: Lean Construction and Delay Analysis Input in delay

52

Verify if the CPM has a continuous path without delay.

Table 2 : Strengths and weaknesses of the IAP Technique (Caletka & Keane, 2015).

2.9.3 Time impact analysis

The difference between TIA (Time impact analysis) and IAP is that TIA uses multiple

base programs and IAP uses single base programs (baseline).

The SCL Protocol states that TIA is the most appropriate technique that could

determine the amount of extension of time, it is based on “what if” scenarios of CPM

baseline programs.

A periodic update of the schedule could affect TIA negatively, and also the window‟s

size (Alkass; Hegazy & Zhang,as cited in Hegazy,2012 ), This method has been

criticized for the inability to take into consideration the fluctuations in the CPM (Hegazy,

2012).It has been also criticized for the possibility to have some errors and bad

assumptions because of its retrospective nature (Hegazy & Zhang, as cited in

Hegazy,2012).

2.9.3.1 Windows analysis

It is an alternative of TIA, it has another name „snapshot‟ analysis, and it has proved a

very reliable logical analysis (KAO & Young ; Farrow, 2001; Alkass ;as cited in

Page 53: Lean Construction and Delay Analysis Input in delay

53

Hegazy,2012).It takes into consideration both an as-built and an as-planned program, it

is based on what actually happened, this way it is been called the actual method too

(Farrow, as cited in Hegazy,2012).This method fragment the as-built and as planned

into snapshots in a periodic way and extract the information from the as-built (changes

in relationship, actual dates, and durations), then extracting information concerning the

period from the as planned program, implementing these information to as-planned to

generate the impacted as-planned schedule, after executing the program, a gap in

period will occur between the as planned and the impacted as planned which is the

amount of delay that should be recorded . The first window will be a baseline for the

second process until the end of the project and have the EOT entitlement. This method

has been recommended by the SCL to be the most credible one (brimah, as cited in

Hegazy, 2012).

Table 3: Strengths and weaknesses of the impacted as-planned technique (Caletka & Keane, 2015).

Page 54: Lean Construction and Delay Analysis Input in delay

54

Figure 12: Windows Analysis(Hollway,as cited in Hegazy,2012)

2.9.4 The Collapsed as-built

It is been stated that a comparison should be made between the actual schedule and

what would have happened, but for excusable delay,It is a one process simulation on

the network A, Another name is But-For technique, the concept is to eliminate delays

and reschedule to see the resulting effect on completion, and repeat for each delay,

then we get a collapsed as-built after mitigating all delays, rescheduling the CAB and

comply it to as-built to see the differences which represent the EOT (Hegazy, 2012).

The implementation procedure as stated by ( AACE, 2011)

The program should reflect the real status, which came from the updated

baseline which is basically the CPM model.

Define the critical and non-critical paths.

Agreed EOTs have to be identified along with necessary documents; also delays

have to be quantified.

Page 55: Lean Construction and Delay Analysis Input in delay

55

CAB should be established from eliminating the delay by delay and reschedule to

recognize the impact, no modification should be done to the CAB program.

CBA should have:

o As-built CP with the critical and proximate critical activities

o Baseline CP along with the lengthiest track.

o All contractual milestones and chain measures

Make the calculations and judgment of delay relativity. Compare the as-built

schedule with the collapsed one, the variance should be the extension of time

granted to the contractor (Caletka & Keane, 2015).

The collapsed as-built (CAB) relies on the “what if” scenario too, based on the critical

path method, it does the actual durations and sequences, conversely to IAP which

integrate delays to a plan and assess what would impact the completion.CAB is a

deductive method, using the “what if” scenario, what if those delays have not occurred?

This method is not prospective, it is hypothetical same as TIA and IAP with some

changes in weaknesses (Caletka & Keane, 2015).

Figure 13:As-planned sequence with as-planned logic (Caletka & Keane, 2015).

Figure 14: As-built sequence (Caletka & Keane, 2015).

Page 56: Lean Construction and Delay Analysis Input in delay

56

Figure 15: As-built sequence with as-built logic (Caletka & Keane, 2015).

The Impact as-planned, Time Impact analysis, and Collapsed as-built techniques are

cause-based techniques, they recognize the delay event then assess the effect based

on the models. It has been recommended to prepare all the necessary documents,

contractual provisions, and related records of progress to precise what events should be

added or removed from the program. The as-built techniques are effect-based; they

begin from the effect then detecting the nearest (proximate) event (Caletka & Keane,

2015).

Figure 15: Collapsed as-built Delay Analysis Method ( AACE, 2011)

Page 57: Lean Construction and Delay Analysis Input in delay

57

3 Research Methodology

3.1 Overview

The purpose of this chapter is to define the research methodology, for this issue

International Group of Lean Construction (IGLC) database has been used to extract

information about delay related to Lean and to compare it with delay analysis protocol in

order to know the reasons behind delay, their corrective actions, and different

techniques used by the Delay Analysis, filtering the most dominant factors that caused

delays and investigates the relation to CPM, testing the frequency of the most used and

effective method and see if there is a link between this later and delay analysis

techniques to propose a way to know how to make delay analysis techniques lean and

the same time it will be such a mechanism that prevents delay and its consequences.

Content analysis was used to investigate and predict the hidden meaning behind

different papers of IGLC conferences from 1997 to 2019.

3.2 Methodology

This study is conducted by content Analysis, interpretation of coding extracted from

Dedoose, Pareto analysis to test the frequency of the Lean Construction's most used

tool, and Mind mapping within coding co-occurrences to picture the relationship

between delay analysis techniques. An embedded Case study of Delay Analysis will be

conducted to enhance the answer to the fourth research question and substitute the

limitations of the content analysis. Data were collected from the IGLC group, and then it

has been fed to QASDAS software (Dedoose) to proceed with the coding process.

Codes have been categorized to draw a clear picture of the cluster of keywords and

codes in order to facilitate the comprehension of the subject and different aspects

covered by the database. Codes and co-occurrence codes have been explored by excel

pivot tables and charts to visualize the results, and test the frequency of most used lean

construction tools.

Page 58: Lean Construction and Delay Analysis Input in delay

58

3.3 Content Analysis

Content Analysis is a systematic strong tool to compress big data content to a fewer

data content, through proper coding rules (Stemler, 2001).

Content Analysis is a mean of coding and categorizing the qualitative data in order to

turn them into quantitative (Saunders , Lewis, & Thornhill, 2016)

Categories should:

be related to the scope and purpose of the research topic;

be exhaustive;

be mutually exclusive, each data should be in one analytical category;

be independent, data are related but not the same characteristics;

Be developed from a single classification to avoid conceptual confusion

(Saunders , Lewis, & Thornhill, 2016).

Tesch, as cited in Zhang & Wildemuth, (2017) defined that “Qualitative content analysis

allows you to assign a unit of text to more than one category simultaneously” (P. 321).

Krippendorff (2004), has been stated that content analysis is “a research technique for

making replicable and valid inferences from texts (or other meaningful matter) to the

contexts of their use” (P.18).

Page 59: Lean Construction and Delay Analysis Input in delay

59

Figure 16: Content analysis process (Elo & Kyngas, 2008).

Content Analysis is divided into two parts „deductive and inductive‟:

Inductive Content analysis: it has been notified that, if there is insufficient knowledge

about the area of study, then Inductive approach is recommended (Elo & Kyngas,

2008).Deductive Content analysis: Catanzaro 1988, as cited in Elo & Kyngas, (2008),

deductive content analysis is conducted when we want to test existing data again in a

new perspective. In this study, Inductive content analysis will be conducted in a

Page 60: Lean Construction and Delay Analysis Input in delay

60

qualitative way, investigating the meaning and the interference between codes for the

proposed research question.

As shown in figure 16, inductive approach passes through:

Open coding;

Coding sheets;

Grouping;

Categorization;

Abstraction;

Model, Conceptual map, Conceptual system.

The time span of studied papers is 22 years from 1997 to 2019.

3.3.1 Validate Content Analysis

Six questions should be defined in the content analysis process (Krippendorff, 2004):

1) t data are analyzed?

2) How are they defined?

3) What is the population from which they are drawn?

4) Is the context related to the data analyzed?

5) What are the boundaries of the analysis?

6) What is the target of the interferences? (Krippendorff,2004).

The following are the answers of the above-mentioned questions:

3.3.1.1 Which data are analyzed?

Data has been extracted from the IGLC (International Group of Lean Construction),

which is considered as the state of art of Lean Construction researches.

3.3.1.2 How are they defined?

Data has been analyzed from the IGLC group; papers from 1997 to 2019 were

analyzed, this group is considered reliable and related to the AEC industry.

3.3.1.3 What is the population from which they are drawn?

All the research from the first published paper to 2019 that have been generated by the

research term “delay”, which are 89 papers, the first has been published in 1997.

Page 61: Lean Construction and Delay Analysis Input in delay

61

3.3.1.4 Is the context relative to the data analyzed?

In fact, the IGLC group is dedicated to all lean related subjects that touch the

construction industry

3.3.1.5 What are the boundaries of the analysis?

Lean construction papers that were related to delay term only will be considered.

3.3.1.6 What is the target of the interference?

The target of interference is if the delay caused in the construction industry are treated

by lean means only in term of cause or effect, or there are other dominant factors,

according to our research questions, taking into consideration only CPM and Lean

construction players.

3.4 Six-Step Research Sequence

Content analysis is conducted by six steps: (Robson, as cited in Jacobs,2010):

1) Start with a research question;

2) Decide on the sampling strategy;

3) Define a recording unit;

4) Construct categories for analysis;

5) Test the codes and samples for reliability and validity;

6) Carry out the analysis.

3.4.1 Starting with Research Questions

The purpose of this study is to know the reasons for the delay, the contribution of CPM

and possible common ground between Lean Construction and Delay Analysis which is

mainly based on CPM. For this issue, IGLC research articles between 1997 and 2019

have been studied.

3.4.1.1 Research Questions

Four questions have been formulated to run the analysis:

1) What are the reasons causing a delay in construction projects and their lean

corrective actions?

Page 62: Lean Construction and Delay Analysis Input in delay

62

2) Are Most of the occurring delays generated because of the shortcoming of CPM?

3) What are the most used and effective techniques of lean construction and its

contribution to delay mitigation?

4) 4-What is the possible relationship, common ground between Delay Analysis

Practice and the most used Lean construction technique?

3.4.2 Decide on Sampling Strategy

Data has been collected from the International Group of Lean Construction (IGLC),

which represents researchers from Field and Academia of AEC Industry from all over

the world. It has been stated that these conferences represent a state of art of lean

construction applications and researches (Alves & Tsao, 2007)

The focus of this study is all the papers contain the term “Delay”, which are 89 papers

from 1997 to 2019.

3.4.3 Define the recording unit

All papers have been taken into consideration which is “Document sampling”. Keywords

have been taken into consideration along with own codes. The bias of keywords chosen

by the authors has been acknowledged since there are no restrictions to describe IGLC

conferences (Alves & Tsao, 2007). Code reliability will be tested by means of inter

rater/Intra rater reliability as will be explained later.

3.4.4 Construct Categories for Analysis

Robson, as cited in Jacobs, (2010),researchers can get a perception on a text by testing

the frequency of words because every word accounts for quite a big part of the text ,it is

been addressed that other categories in the content analysis could be used such as:

„subject matter, direction, values, goals, methods, actors, and location‟. In this study, we

aim to investigate high-frequency words and subject matter related to research

questions, in this research, categories will be based on the codes that have been done

with the help of QACDAS software „Dedoose‟.

Page 63: Lean Construction and Delay Analysis Input in delay

63

Keywords will be used as a comparative tool for our codes to assess reliability.

Keywords and codes clusters have arisen into three categories: common root words,

related words, and Words with embedded meaning (Alves & Tsao, 2007)

Common root words: some words appear in a frequent way merged with other

words, such as (Waste time, waste causes, waste control…), they all fall under

„waste‟.

Related words: words which share the same interest field such as (Takt-time

planning, Last planner…), they all fall under Lean Construction

Words with embedded meaning: such (PPC, WWP...), they fall under the Last

planner cluster.

it has been defined (Robson, 2002) “Exploratory analysis explores the data, trying to

find out what they tell you and Confirmatory analysis seeks to establish whether you

have actually got what you expected to find” ( P. 399).

Categories within related keywords will be attached in the Appendix I.

3.4.5 Test the codes and samples for reliability and validity

Coding could be done through the selection of the whole text,portion of the

text,paragraph,word,or word sense,in this study we opted to go for text coding.

Figure 17: Text Coding in Dedoose (own Work)

Page 64: Lean Construction and Delay Analysis Input in delay

64

3.4.5.1 Reliability

Reliability could be conducted by the following as stated by (Stemler, 2001):

Stability or intra-rater: The inter-rater reliability means if the author or the same

coder can get the same codes if he tries again.

Reproducibility: Do coding schemes lead to the same text being coded in the

same category by different people?

It is been explained that reliability could be measured by evaluating the percentage of

agreements between the raters by summing up the same codes of units done by the

raters then divide it by the total number of units.

A doubt of shortfall might be raised that coding might be based on chance, for this issue

Cohen‟s Kappa coefficient has been set (Stemler, 2001):

Ƙ=

: Proportion of agreed unites

: The proportion of units that might be agreed by chance.

Kappa Statistics Strength of Agreement

<0.00 Poor

0.00- 0.20 Slight

0.21- 0.40 Fair

0.41- 0.60 Moderate

0.61- 0.80 Substantial

0.81- 1.00 Almost Perfect

Table 4: Kappa interpretation benchmark (Landis & Koch 1977, as cited in Stemler, 2001)

Page 65: Lean Construction and Delay Analysis Input in delay

65

Miles and Huberman, 1994, as cited in, Marguerite (2017), another formula has been

described for Inter-rater Reliability IRR:

Reliability =

Cohen 1960, as cited in Stemler (2001) clarified that three assumptions have to be

conducted to assure proper using of the Kappa measurement:

1) Units should be coded independently;

2) Categories should be independent, mutually exclusive, and exhaustive;

3) Raters should work independently to avoid agreement that comes in a

consensus way.

Inter-rater reliability has been conducted within a classmate with a coefficient of 0.76

which is substantial (Appendix II).

Intra-rater reliability has been conducted with the author himself getting the strength of

0.74 which is substantial (Appendix III).

3.4.5.2 Validity

it has been defined (Krippendorff, 2004) that: “Validity is that quality of research results

that leads us to accept them as true, as speaking about the real world of people,

phenomena, events, experiences, and actions”(P.313).

Validity is that quality of research results that leads us to accept them as true, as

speaking about the real world of people, phenomena, events, experiences, and actions.

IGLC Group doesn‟t validate the conference unless it should be examined by a jury of

three specialists which gives credit and trustworthiness (Jacobs, 2010).

3.4.6 Carry out the Analysis

Coding has been done by CAQDAS (Computer Assisted Qualitative Data Analysis

software), in our case, we used Dedoose to explore codes cluster, codes co-

occurrence, frequency of codes.

Page 66: Lean Construction and Delay Analysis Input in delay

66

3.5 Introduction to Dedoose software

Dedoose is an Internet-based platform app from QASDAS family, for analyzing

qualitative and mixed methods research (Dedoose, 2020).

Steps have been carried out using Dedoose:

All the 89 papers were uploaded to Dedoose as shown in figure 18.

1) feeding the papers into Dedoose in a Pdf format:

Figure 18:Uploading articles to Dedoose(own work)

Dedoose interface shows the papers uploaded along with the date of upload and the

user name, at the left side it shows the number of media or papers uploaded the

number of excerpts, number of code, and code applications.

The lower panel at the right and sometimes it appear at the left, shows the name of

codes, and gives the opportunity to search for codes, see the attached excerpts,

rearrange by number or alphabetically.

Page 67: Lean Construction and Delay Analysis Input in delay

67

2) After uploading the papers, it can be seen as follow:

Figure 19:Coding Procss (own Work)

Coding process can be done by selecting the text as in figure 19, pressing the spacebar

to name the code. After the coding process is done for the whole papers, a cluster of

codes will be resulted from the software to as a cloud to give insight about our research.

Page 68: Lean Construction and Delay Analysis Input in delay

68

Categories have been launched to group the patterns and confirm the consistency of

the sample data gathered.

Categories Keyword Frequency

Scheduling 1674

Culture and Human aspect 955

Delay 902

Lean Construction 836

Last Planner 806

Supply Chain Management 580

Production Management 439

Waste 423

Design Management 384

Client/Customer 313

Information technology 278

Preassembly /prefabrication 202

Performance Measurement 189

Value 119

Construction 114

Safety 97

Lean Production 89

Project Management 53

Work Structuring 46

Cost 42

Quality 42

complexity 18

Implementation 6

Table 5: Keywords categorization

Page 69: Lean Construction and Delay Analysis Input in delay

69

From the figure 16, the sample data gathered focuses more about scheduling, Culture

and human aspect, delay, and Lean Construction which react positively to our research

questions,in this study the focus will be on categories contains CPM and LPS.

Figure 16: Categorization cluster

3.6 Case Study

In this section, a case study of Delay Analysis will be analyzed to figure out the

technique that has been used to answer to the claim raised by employer and the Joint

venture. Because there were no case study that links both Delay Analysis and Last

Planner System, the author opted to use the outcomes generated from Content

Analysis along within this case study, and the Last Planner System Benchmark then to

be developed by a mind map analysis to answer the last research question which is:

19%

11%

10%

10% 9%

7%

5%

5%

4%

4%

3%

2% 2% 1%

1%

1%

1% 1%

1%

0%

0%

0%

0%

Frequency

Scheduling

Culture and Human aspect

Delay

Lean Construction

Last Planner

Supply Chain Management

Production Management

Waste

Design Management

Client/Customer

Information technology

Preassembly /prefabrication

Page 70: Lean Construction and Delay Analysis Input in delay

70

What is the possible relationship, common ground between Delay Analysis Practice and

the most used Lean construction technique? (Caletka & Keane, 2015)

Another purpose of this embedded case study along with Mind Mapping and

Benchmarking is the limitations of Content Analysis. This method has been adapted to

robust the answer which summarize the outcome, seeking to create a Lean based

Delay analysis technique and the same time, it would be such a mechanism to prevent

delay. This case study were conducted by anonymous, it has been published in Delay

analysis Construction contracts book by (Caletka & Keane, 2015),Wiley Blackwell

(Caletka & Keane, 2015).

3.6.1 Case Study Description

This case study was conducted to present an airport terminal expansion; a joint venture

consortium has been called to do both rehabilitation of the control tower and also the

extension of the runway of the existing airport (Caletka & Keane, 2015).

The work stated on October 1st, 2006 and it supposed to finish on August 1st, 2007, but

the work has been finished on January 28th, 2008.

A dispute has been raised to claim for a time extension and has been transferred to the

court (Caletka & Keane, 2015).

The Planning expert on behalf of the Joint Venture opted to go for Time-Impacted

Analysis, the planning expert from the employer part claimed that the Joint Venture

doesn‟t deserve any recovery because he didn‟t follow the instructions to accelerate,

another argument is that the Joint Venture wouldn‟t have finished on time because there

was a delay originally in the Runway extension work (Caletka & Keane, 2015).

Available information in this case was (Caletka & Keane, 2015):

As-planned baseline is submitted and approved

Contemporaneously updated CPM programs

Contemporaneously prepared as-built program

Agreed employer risk events.

Page 71: Lean Construction and Delay Analysis Input in delay

71

From the below table 6, it is clear there was a delay of 28 days from the updated CPM

on October the 6th,which has been reported as a float (-28 days float) (Caletka & Keane,

2015).

Table 6: Available programs (Caletka & Keane, 2015)

Delay events have been detected on the Runway extension and also on Control tower

rehabilitation. Criticisms have been raised about TIA, stated that TIA could not provide a

continuous linear CPM, it has been shifted from place to another, whereas TIA did not

linked the events (Caletka & Keane, 2015)

It has been clarified that TIA has been used to „set the clock to zero‟; it updates the

program by providing progress data, It has been argued that TIA did not provide a help

to precise the compensable delay period, EOT or pricing prolongation, it just showed

the impact of delays against the updated program. Another argument has been

Page 72: Lean Construction and Delay Analysis Input in delay

72

highlighted stating that TIA is based on prospective program, so, it is considered as

theoretical such as IAP (Impacted as-planned), claimed that conclusion could be

different within retrospective method and to be compared to as-built program (Caletka &

Keane, 2015).

Update/Windows Analysis, or simply windows analysis, this technique is based on

(Caletka & Keane, 2015):

Best available clue;

programming technical expertise

Common sense.

To finally provide results based on reality and reliable with the available facts. This

approach helped to identify the following (Caletka & Keane, 2015):

1) Quantifying each window‟s delay;

2) Figuring out activities that were driving the CPM, and their location on each

window;

3) Check if there is any near critical paths are existing through the project;

4) Who was responsible for the last mentioned issue?

The first step is conducted using „Float deterioration‟, which has been developed to

illustrate how far the deviation is behind the schedule each project has been slipped

from month to month basis (Caletka & Keane, 2015).

As could be seen on the chart that, Runway extension is behind schedule with 45 days,

Terminal building within 133 days behind schedule, and Control tower within 168 days

late.it has been argued here that it was not driving the CPM during the project (Caletka

& Keane, 2015).

Page 73: Lean Construction and Delay Analysis Input in delay

73

Figure 17:Float Deterioration Chart (Caletka & Keane, 2015)

3.6.2 Float Mapping

Kris R. N. and Patricia D. G, as cited in Caletka & Keane, (2015) stated that:

Windows analysis is especially helpful when a critical path program which was

updated on a regular basis was employed on the project. To delay project

completion, the critical activities of the project must have been delayed. The

window analysis only analyses critical activities occurring during specific periods

of time on a project. The periods analyzed are the same periods of time as those

when the project was updated. For instance, if the project was updated monthly

then the window analysis would be monthly. (P. 231)

It is necessary to know which activities were critical ,SCL Protocol, as cited in Caletka &

Keane, (2015) defined that “critical path –The sequence of activities through a project

network from start to finish, the sum of whose durations determines the overall project

duration.3 There may be more than one critical path depending on workflow logic”

(P.232).

SCL Protocol, as cited in Caletka & Keane, (2015) stated also “critical path analysis

(CPA) and CPM –The critical path analysis or method is the process of deducing the

Page 74: Lean Construction and Delay Analysis Input in delay

74

critical activities in a program by tracing the logical sequence of tasks that directly affect

the date of project completion”(P.232).

3.6.3 Extracting Float Values

Extracting raw data from the float values for all activities in every updated schedule,

including all information of activity data such as constraints, durations, start and

finish...etc.it is important to extract data to leave no bias of critical areas (Caletka &

Keane, 2015).

3.6.4 Float Map Creation

The float map has been created using the tasks in CPM programs accompanied with

their float from monthly basis to detect critical tasks within the largest negative floats,

aligning floats with the right activity as showed in table 7.This table has been got from

the raw data float map, those floats with minus sign represent a completion of the

activity, the asterisk means the activity is still not existing until a later schedule. This

project has been updated monthly (Caletka & Keane, 2015).

Page 75: Lean Construction and Delay Analysis Input in delay

75

Table 7: Raw data for the float map (Caletka & Keane, 2015)

Page 76: Lean Construction and Delay Analysis Input in delay

76

3.6.5 Driving Activities identification

Activities have been considered Driving if they fulfill the following two factors (Caletka &

Keane, 2015):

Activity should be part of the „Longest path‟ to finish.

Activity should be running or programmed to run within the update period.

Taking into consideration that the longest path fluctuates and often been modified this is

why monthly update is necessary.

Figure 18: Driving Critical path (Caletka & Keane, 2015)

Page 77: Lean Construction and Delay Analysis Input in delay

77

3.6.6 As-built critical path

The activities in black met the requirements of driving critical path, as shown in table

8,the issue that Critical path could is not clear, this is why an assessment should be

conducted based on float values that have been reported and the planner experience

(Caletka & Keane, 2015).

Table 8: Driving activities (Caletka & Keane, 2015).

Page 78: Lean Construction and Delay Analysis Input in delay

78

Driving activities have been filtered and grouped by location as seen in the table 9

(Caletka & Keane, 2015):

Table 9: concurrent driving critical paths. (Caletka & Keane, 2015)

It has been stated that near critical paths tend to be critical, and also delays which

pushed near critical activities to be critical along within the concurrent effect, from the

float map an as-built path has been assumed, near critical activities have been identified

by linking successors within the predecessors (Caletka & Keane, 2015).

Page 79: Lean Construction and Delay Analysis Input in delay

79

Table 10: Illustration of critical paths (Caletka & Keane, 2015)

This method has advantages such as (Caletka & Keane, 2015):

It uses the real time available program

It detects the dynamicity of CPM

It detects the logic change, duration and intentions

It could detect more than Critical path

Intuitive and easy

It detects loss and gain between progress updates

It shows the actual influence of the delay

It is not theoretical, no need to collapsed CPM

It can detect critical delays in the update period when the work is actually run.

It detects when cost is actually incurred.

The employer risk events that have been agreed should be investigated and see if there

were a part of the critical path, and which were just a concurrent events (Caletka &

Keane, 2015).

Page 80: Lean Construction and Delay Analysis Input in delay

80

Table 11: Delays mapped against the as-built critical path. (Caletka & Keane, 2015)

Page 81: Lean Construction and Delay Analysis Input in delay

81

The employer risk event along with float loss/gain windows that have been aligned in

the windows where they were happened (Caletka & Keane, 2015).

Table 12: Employer risk event table (Caletka & Keane, 2015).

After the float deterioration map has been set in a monthly basis, attaching the events to

the actual delays has occurred, in order to facilitate to the court to summarize the

outcome and compare the as-built CP delays to the argued one generated from TIA.

Acceleration has been claimed by both sides by analyzing the progress actually

achieved and to being compared against each activity with every window, then updating

the non-accelerated logic. It has been recommended that a proper presentation should

be submitted for delay claims instead of a bunch of papers which causes confusion

(Caletka & Keane, 2015).

4-D Model has been recommended for pre-planning and forensic delay, other tools also

have been stated (Caletka & Keane, 2015):

CPM program and CPM extracts

Blow-up/Call outs documents

Page 82: Lean Construction and Delay Analysis Input in delay

82

Animations

They showed a technical accuracy for both progress and events over time while

animations belong to other two categories which are demonstration and reconstruction.

Demonstration animation helped to show an overview of the process and the way of

work, for the purpose of educating the tribunal, while reconstruction showed the

sequence of events, it illustrated the as-planned versus as –built sequence to give

insight of theory of what really happened (David K.H, 2009).

In this stage of reconstruction animation, information that has been delivered to the

legal party is (Caletka & Keane, 2015):

Who made the animation, what is the level of the accuracy

Which hardware and software used for this purpose

Documents used for the animation

Finally, Weather data has to be taken into consideration to figure out which month

exceeded the threshold to support the claim (Caletka & Keane, 2015).

3.6.7 Case study main findings

TIA is not adequate to such case.

IAP is not adequate too.

Update/Windows Analysis is suitable to accommodate real time events, it

helped to quantifying delay by the mean of float deterioration, identifying

activities that were driving the CPM, their location on each window, check if

there is any near critical paths that are exist through the project, and the

responsible for the last mentioned issue.

Importance to generating the float map.

Creating the as-built program.

Employer risk events have to be considered.

Importance to check the acceleration.

Importance of animation for demonstration and reconstruction.

The importance to take weather depiction in consideration (Caletka & Keane,

2015).

Page 83: Lean Construction and Delay Analysis Input in delay

83

4 Research questions answers

This chapter delivers the research questions along with answers that have been

generated from the outcomes of the critical review the content analysis methodology,

case study and mind mapping.

Before going through the answers, the author would like to expose the outcome that has

been quantified from the content analysis method, and those that have been launched

from Dedoose.

The Code Cluster:

The cloud of codes provides a general idea about what have been coded mostly,

presenting a rough weight of the codes used along the research.

Figure 19: Code Cloud(own Work)

Page 84: Lean Construction and Delay Analysis Input in delay

84

The Code-Co-Occurrences:

The code-Occurrence Matrix gives information about how codes meet each other in the

same excerpt, overlapped, and their frequency.it provides a rational framework to

interpret information (Dedoose, 2020).

Figure 20: Fine-tuned Co-Occurrence matrix(own Work)

The author will attach the original table to the CD because of the huge dimension of the

matrix.

Page 85: Lean Construction and Delay Analysis Input in delay

85

4.1 Question One

1) What are the reasons causing delay in construction projects and their

corrective actions?

Reasons of delay in this study are deducted from the texts linked to the codes.

From the chart in figure 16, it summarizes all the delay causes that have been weighed

from the literature review, it is obvious from the chart that variability is the dominant

factor, then, Procurement, Early design, and RFI follows (Figure 20)

It has been stated that Variability is a main opponent of successful of project management

(Davis, 2009).it has been stated also that variability is the main cause of delays (Damaj,

Fakhreddine, Lahoud , & Hamzeh, 2016).

The results confirm these statements which enhance the reliability of the outcomes.

The correction action been taken as in chart (Figure 21) that goes with the variability

could be summarized in LPS,LOB, BIM which reflects the combination of Visualization,

Buffer and controlling necessary (Koskela,; Yang and Ioannou,; Sakamoto, Horman and

Thomas; Kemmer,; Bølviken,Rooke and Koskela ,as cited in Deschamps, Esteves,

Rossetto, Tomazi, & Pereira Da Silva ,2015)

Page 86: Lean Construction and Delay Analysis Input in delay

86

Figure 21: Delay Causes(own Work)

0 5 10 15 20 25 30

Variability

Early Design

Procurement

RFI

Design changes

Omissions

delayed payment

delayed inspection

Changes due to requirements

Poor planning

Huge Batch Size

Deviation in plan

Unrealistic schedule

impropoer design

rework

Bureaucratic

Delay in funds

Corruption

Absenteeism

Lack of Proper Communication

DIQ Design Information Quality

Ineffective Information process

Delayed aprovals

Large WIP

Variability and large flow time

SCs Alternative supply papers

Incomplete Progress Information, schedule…

Delays due to mobility, schedules

Forecasting in Traditional Planning

Reactionary behavior of superintendent and…

Unforeseen and uncertain Conditions

Excess Inventory

Demobilization

Time of decision Making (Systems dynamic).

New laws, Lack of project details

Design revision and changes, Lack of information

Existence of contradictions between documents

Lack of interaction between stakeholders in the…

Existence of contradiction between documents in…

Errors in information and its specs.

Critical Requirement  (Constraint managemet)

Late Follow-Up,Long engineering review

Schedule, Coordination, Procedures

Traditional Management

Interruption due to CPM and PERT in repetitive…

Noncompletion of preceding activities

Flaws in the planning system, ineffective…

Procurement

Uncertainty

Comeback delays

Unforced idleness

Delay in case of future changes

Delay Causes

code occurency

Page 87: Lean Construction and Delay Analysis Input in delay

87

Figure 22:Corrective actions(own Work)

0 5 10 15 20 25 30

LPS,LOB,Buffering,lookahead,BIM,risk matrix,WIP Buffer

BIM

collective explanatory interactions

House Of quality,

LC,FTI(Forward Thinking Index)+LPS

LDP(Lean Design Process)

House of quality

Self-help appraoch

LPS

House Of quality

LPS+SCM

LOB

BIM

LPS

Lean Design Process

TFV+LPDS,WIP, LPS, Pull technique

LPS+VSM

LPS,Self-help appraoch

Lean concepts

SCM

DES,Takt Planning+LOB

LPS,4D Modeling

LPS

WIP-RFI Corelation

Queuing theory, Just-In-Time, Time based Completion, Fast…

SCM

LPS,4D Modeling

5S, LPS

Look ahead+4D

LBMS

OODA Loop +LPS

FTI(Forward Thinking Index)+LPS

Appropriate sizing of Buffer ,JIT+ Location of buffer

VNMT,LBMS,LPS

LPS

Multidisciplinary teams, Collaborative Environment

Collaborative environment

Pull techniques, delayed commitment

Kanban+ Collaborative environment

JIT, WIP

5S, WIP

CLP Constraint logic Programming ,PDM Precedence…

5Whys+Fishbone (check the fishbone Identifying root …

One-Piece Flow (less cycle time),Keep the lowest WIP as…

LPS

Lead time Buffer, LSM, LOB ,RSM

Updated buffered Program,Buffer Analysis, Delay Analysis

LPS+SCM

SCM

PWI Project waste Index,PIT Productivity Improvement…

RSM

Pull system

Corrective Actions

Code Occurrency

Page 88: Lean Construction and Delay Analysis Input in delay

88

4.2 Question Two

2) Are Most of the occurring delays generated because of the shortcoming of

CPM?

As Koskela stated that CPM lacks from spatial information, continuity, and visualization,

moreover, CPM has been criticized of not being able to detect variability until it

happens. It causes gaps in production, as we can see from our results which confirm

the statement of Lauri Koskela as mentioned in the literature review.

We can see that Variability is the most dominant factors caused by the CPM; the other

factors fluctuate between cause and effect.

The author proposed to divide these factors based on Flow concept suggested by Lauri

Koskela (Koskela, Kraemer, Henrich, & Kagioglou, 2007) :

Flow Variability: which means how variability affected the process?

Even Flow: to maintain a smooth leveling and continuous process

Non –adding Value: the main objective is to eliminate waste

Value flow: To produce a continuous flow

The seven preconditions, to prohibit making-do waste (Koskela, Kraemer,

Henrich, & Kagioglou, 2007):

1. Components and Materials

2. Connecting works-previous works

3. Construction design (Information)

4. Equipment

5. External conditions

6. Space

7. workers

Because flow and CPM accomplish each other, it has been stated on the literature

review that CPM is the mean of flow ,the author opted to show the weight of variability

against all other factors

Page 89: Lean Construction and Delay Analysis Input in delay

89

69%

31%

Chart Title

Seven Preconditions+Value Flow+Even Flow+Non-Adding Values

Variability

Figure 23:CPM influence on Flow(own Work)

CPM direct influences is 31%,it doesn‟t contradict the shortcoming and the claims

stated in the literature review, it has been stated that the real issue couldn‟t be tackled

directly and there is no issue within the CPM but within the way the apply it.

Another concept has attracted the author is the Flow min-cut theorem which proves that

CPM and Flow accomplish each other.

From the chart on figure 23,the author states that third of the flow disturbance comes

from the CPM, whether it is from the making-do, know-how, or other issues related to

method‟s validation. Because CPM is the tool used to present the flow, they can be

used interchangeably in construction field, the 31% of variability generated from the

CPM is responsible of the 69% the other factors, and the 69% influence the CPM

stability as well. Once the variability is tackled by the mean of Lean the other out-

coming issues will be reduced.

Page 90: Lean Construction and Delay Analysis Input in delay

90

4.3 Question Three

3) What are the most used and effective techniques of lean construction and its

contribution to delay mitigation?

Pareto Analysis has been used to identify the most significant tool of lean construction

based on the code frequency extracted from the qualitative software Dedoose.

Figure 24: Pareto Analysis Chart(own Work)

From Figure 24, the author confirmed that the most used technique in Lean

Construction is The Last Planner System, as we know that Lean tools have been

created to maintain the flow variability, this finding runs smoothly within the answer two

of the research questions.

LPS represents 43.28 % (Table13) from the contribution of all techniques which

nominates this technique to be the most efficient, and to be used to represent as a

comparison tool against Delay Analysis Protocol.

0.00%

20.00%

40.00%

60.00%

80.00%

100.00%

120.00%

0

10

20

30

40

50

60

70

80

90

100

Last

Pla

nn

er®

Sys

tem

(LP

S)B

uild

ing

Info

rmat

ion

Mo

de

ls (

BIM

)5

SJu

st in

Tim

e (J

IT)

Takt

Pla

nn

ing

and

Tak

t C

on

tro

lK

anb

anV

alu

e S

trea

m M

app

ing

(VSM

)ID

PV

isu

al m

anag

em

en

t (V

M)

FTI

5 W

hys

Hei

jun

kaP

DC

AV

alu

e E

ngi

ne

erin

gD

e-C

ou

plin

gD

iscr

ete

eve

nt

sim

ula

tio

n (

DES

)Le

an p

roje

ct d

eliv

ery

sys

tem

…Se

t-B

ased

De

sign

(SB

D)

Six

Sigm

aTF

VW

ork

Sam

plin

g (W

S)A

ctiv

ity-

Flo

w M

od

el

AFW

SM(S

tru

ctu

rin

g M

eth

od

)A

gen

t-b

ase

d M

od

el

Ergo

no

mic

sG

emb

aIn

tegr

ate

d P

roje

ct D

eliv

ery

(IP

D)

Kai

zen

Lean

Wo

rk S

tru

ctu

rin

g (L

WS)

RFI

DTa

rget

Val

ue

Des

ign

(TV

D)

Page 91: Lean Construction and Delay Analysis Input in delay

91

Lean Tools Code Frequency Total Total Accumulation

Last Planner® System (LPS) 87 43.28% 43.28%

Building Information Models (BIM) 16 7.96% 51.24%

5 S 9 4.48% 55.72%

Just in Time (JIT) 9 4.48% 60.20%

Takt Planning and Takt Control 9 4.48% 64.68%

Kanban 8 3.98% 68.66%

Value Stream Mapping (VSM) 8 3.98% 72.64%

IDP 7 3.48% 76.12%

Visual management (VM) 6 2.99% 79.10%

FTI 5 2.49% 81.59%

5 Whys 4 1.99% 83.58%

Heijunka 3 1.49% 85.07%

PDCA 3 1.49% 86.57%

Value Engineering 3 1.49% 88.06%

De-Coupling 2 1.00% 89.05%

Discrete event simulation (DES) 2 1.00% 90.05%

Lean project delivery system (LPDS) 2 1.00% 91.04%

Set-Based Design (SBD) 2 1.00% 92.04%

Six Sigma 2 1.00% 93.03%

TFV 2 1.00% 94.03%

Work Sampling (WS) 2 1.00% 95.02%

Activity-Flow Model 1 0.50% 95.52%

AFWSM(Structuring Method) 1 0.50% 96.02%

Agent-based Model 1 0.50% 96.52%

Ergonomics 1 0.50% 97.01%

Gemba 1 0.50% 97.51%

Integrated Project Delivery (IPD) 1 0.50% 98.01%

Kaizen 1 0.50% 98.51%

Lean Work Structuring (LWS) 1 0.50% 99.00%

RFID 1 0.50% 99.50%

Target Value Design (TVD) 1 0.50% 100.00%

Table 13: LPS Contribution among Lean techniques(Own Work)

Page 92: Lean Construction and Delay Analysis Input in delay

92

4.4 Question Four

4) What is the possible relationship, common ground between Delay Analysis

Practice and the most used Lean construction technique?

From the code co-occurrences matrix, the author opted to develop a mind map to

investigate the explanation behind the codes.

The author used the codes that fall in both categories in the same time and the same

place (Excerpts), which reflects the shared common ground.

Code Co-

Occurrence

BIM Buffer Delay Delay

Analyis

LBMS LOB Looahead Workflow

CPM 1 2 6 4 8 3 1 2

LPS 4 1 11 1 7 1 9 5

Code Co-

Occurrence

Production Pull Waste Float Planning

CPM 1 1 2 3 1

LPS 6 1 2 1 2

Table 14: Fine-Tuned Co-Occurrence (LPS &CPM) Matrix (Own Work)

Some of the codes will be eliminated because the non-significance and the overlapping.

Some codes are just explanatory, such as Delay which means that delay has been

coincided by the two codes CPM and LPS; it is an explanation of delay causes and/or

corrective actions as has been seen in the previous answers.

The bridges that link LPS and CPM (Delay Analysis) are: BIM, Buffer, LBMS,LOB, and

Float, the other codes are just an explicit explanation content.

Page 93: Lean Construction and Delay Analysis Input in delay

93

4.4.1 Mind Mapping:

Mind mapping has been used with MindManager software to organize and expose

relationships between different codes generated from the co-occurrence matrix, case

study and the literature review ,it also has been conducted to draw a more

transparency process map for better describing the linkage between last planner system

and delay analysis.

Figure 25: Delay Analysis Lean-Based Process Map (Own Work)

Page 94: Lean Construction and Delay Analysis Input in delay

94

From the mind map presented in Figure 25, generated from the MindManager software,

the bridges that link Delay Analysis Protocol and The Last Planner System could be

summarized in one phrase: It is the relation between Prospective Buffer Analysis and

Retrospective Float Mapping trying to figure out the best possible As- built critical path

updated by the mean of LPS.

The process should start within LBMS (Location Based Management System),it can

fluctuate between the planning stage and the control stage what make it best tool to

report the shortcoming of CPM to LPS.it proved a significant performance, it addresses

the shortcoming of CPM (Olivieri , Olli, & Granja, 2018). Forwarding the next step to be

controlled with LPS and coming back to CPM to update it accordingly. Then Delay

Analysis best techniques intervene to manage the float and get the best possible as-

built program.

Finally, LPS philosophy should be continued once we get the best possible schedule to

learn from the errors likely possible to happen and investigate the root causes to be

eliminated.

Page 95: Lean Construction and Delay Analysis Input in delay

95

5 Conclusion and Recommendations

AEC industry nowadays is still suffering from delay consequences and funds overrun,

The content analysis provided the most frequent issues caused delay: variability, early

design, procurement, RFI related matters, and the other causes which are a result of

the generated variability from the shortcoming of CPM.

Shaping the CPM to provide value should be done through the Lean Construction

Practice (LPS), LBMS and Delay Analysis Practice.

Last Planner System proved a significant presence in term of solving problems related

to delay such variability ,procurement, design changes, it appeared almost in all delay

corrective actions, but it requires some times some adjustment from other tools such as

Takt-Planning and LBMS.

Preventing delay is a process that gathers Lean philosophy armed with visualization in

order to not affect the completion date, maintain the buffers and Delay Analysis to

control the float that might be generated from the critical path in through the process.

The implementation of LPS with delay analysis and LBMS would create a robust

mechanism from the theoretical perspective.

The prospective techniques of Delay Analysis in the point of view of the author will lead

to zero sum if they are used with LPS for one reason: they will conflict within the

lookahead process, because inserting theoretical delay under LPS process will be

eliminated automatically leading to no validation, regarding to the nature of LPS which is

eliminating delay. This confirm that the only possible way is to use the retrospective

windows analysis to benefit from the systematic float analysis used by Delay analysis

As a result the author conclude that Delay Analysis based on Lean is a robust

techniques to prevent delay but there is nothing to claim to the court once it is applied

with LPS, it will serve as a delay mitigation tool rather than forensic tool lading

assumingly to a perfect situation where AEC industry would not conflict to assess

liability.

Page 96: Lean Construction and Delay Analysis Input in delay

96

The author would recommend the following:

Actions research is highly recommended to diagnose the process weaknesses

The use of BIM such as VICO to implement LBMS

The integration of crew-centric planning for better decision-making (Bob Huber,

2003).

Work under a unified platform such as oracle‟s cloud which is dedicated to bridge

Lean scheduling and CPM.

Integration of WIP buffer in repetitive projects (a simulation model to manipulate

the iteration) (González Vicente, 2006).

Page 97: Lean Construction and Delay Analysis Input in delay

97

Appendices

Appendix I

Categorization table adapted from (Alves & Tsao, 2007).

Categories keyword Frequency Categories

keyword Frequency

client / customer Information Technology

• client 123 • 3D / 4D CAD 70

• client involvement 3D modeling 46

• client requirements 8 • 4D CAD modelling

• client requirements management • 4D visualization 3

• customer 149 • bar-code technology

• customer lead-time • computer aided design (CAD) 11

• customer needs 8 • computer integration

• customer needs analysis • computer simulation 10

• customer purpose • computer tools

• customer satisfaction 7 • construction simulation 3

complexity • digital fabrication

• complex dynamic systems • digital prototypes

• complex projects 9 • fuzzy logic 4

• complex systems 8 • GPS system 5

• process complexity • Internet 33

• product complexity 1 • IT 2

• stakeholder complexity • java 18

construction • knowledge discovery in

• construction management 114 databases (KDD)

cost • mobile phone 7

• activity based costing and • networking simulation

management • neural network

• activity-based costing • process simulation

• activity-based costing (ABC) • simulation model 39

• cash flow 13 • simulation modeling 8

• construction cost • simulation optimization 6

• construction overhead costs 6 • virtual reality 13

Page 98: Lean Construction and Delay Analysis Input in delay

98

• cost control 3 last planner

• cost forecasting • commitment planning 6

• cost information 1 • commitments management 1

• cost management 10 • first-run study

• cost performance • Last Planner Method 1

• cost reduction 3 • last planner methodology

• designing to target cost 5 • last planner system 171

• kaizen costing • lookahead plan 10

• poor quality costs • lookahead planning 29

• poor-quality costing • percent plan complete 19

• profit point analysis (PPA)

• percent plan complete (PPC) 213

• project financial management • phase planning 3

• resource-based costing • PPC 213

• return on investment 1 • the last planner system 113

• target cost • weekly work plan 18

• target costing • weekly work planning 9

• transaction cost economics lean construction 836

• transaction costs analytical lean production 89

modeling performance measurement

culture and human aspects • benchmarking 12

• behavior 34 • construction performance 5

• behavioral development measures

• behaviour model 2 • construction process 142

• change 588 benchmarking

• change management 2 • performance indicators 28

• changed organisational structure

• performance measurements

• cognition 2 • performance metrics 2

• cognitive engineering • performance tracking

• cognitive systems engineering

• qualitative benchmarking

• collaborative work 90 preassembly / prefabrication

• collaborative working • assembly 61

environments • assembly package

• construction culture • disassembly

• cultural barriers • fabrication 137

• culture and subculture 49 • fabrication shop 2

• culture of quality • lean prefabrication

• design sociology • off-site fabrication 1

Page 99: Lean Construction and Delay Analysis Input in delay

99

• education 15 • off-site manufacturing

• field personnel 4 • preassembly

• HRM • pre-assembly 1

• human behavior 5 • precast fabrication

• human centered focus • prefabrication

• human error 2 • pre-fabrication

• human resource development

• volume element prefabrication

• human resource management 3 production management

• incentive 29 • production control 108

• lean leadership behavior

• production improvement 1

• lean transformation policy 1 • production planning 186

deployment • production planning and control 138

• learning organization • production/operations

• learning region management

• middle manager role 1 • project production 6

• motivation 15 • project production system

• organisational change project management

• organisational learning 3 • project and planning control

• organization 107 • project control 12

• organization development • project controls 2

• organizational change • project organization 9

• organizational culture • project planning 30

• organizational learning 3 quality

• project culture • internal quality audits

• quality and change management • quality assignment 6

• worker's evaluation • quality assurance 16

design management • quality control 18

• briefing 9 • quality management 2

• concurrent design 2 • quality management systems

• concurrent design and 4 • total quality management

construction safety

• concurrent design for production • accident 11

• dependency structure matrix 2 • accident theory

• DePlan • boundaries 4

• design • construction safety

• design and documentation 44 • hazard 21

Page 100: Lean Construction and Delay Analysis Input in delay

100

quality • hazard identification 1

• design brief 1 • macroergonomics

• design concept 11 • occupational ergonomics 55

• design coordination 6 • occupational safety

• design criteria 2 • safety in construction

• design criteria change • safety management 1

• design dictionary • safety training

• design fixity • working conditions 4

• design for maintenance scheduling

• design for production and • coordination

constructability • CPM 150

• design intent document 1 • CPM as product

• design postponement • cross-functional teams 3

• design process 111 • distributed scheduling 6

• design quality 12 • float management

• design rationale systems • flowline 10

• design review 14 • line of balance 22

• design rework 1 • line-of-balance

• designing 78 • multi-diciplinary team

• detail design 1 • multi-skilled workers

• detailed design 0 • multiskilling

• early design 26 • multi-tasking

• engineering design 7 • planning 1201

• information-based design • planning and control 219

dependency matrix • planning system 29

• key design parameter • repetitive scheduling 2

• lean design 21 • schedule planning 5

• lean design management 8 supply chain management

• predesign 1 • construction supply chain 58

• product design 17 management

• product development process

• construction supply chains 37

• resource planning 3 • logistic centers 1

• resource-driven scheduling • logistics 52

• set-based design 2 • logistics planning 3

implementation • supply chain 363

• project implementation 5 • supply chain analysis 2

• strategies of implementation

• supply chain integration 4

• systemic 1 • supply chain 58

Page 101: Lean Construction and Delay Analysis Input in delay

101

implementation management in

Delay Analysis construction

Claims • supply chain mapping 1

TIA • supply chain strategies

IAP • supply chains

CAB • total supply chain 1

Windows Analysis value

• chain of value for clients

• customer value 9

• value based management

• value chain 4

• value chain management

• value creation 11

• value generation 19

• value loss

• value management 7

• value parameters

• value stream 38

• value stream analysis 4

• value stream mapping 20

• value stream maps 4

• value-added time 3

• value-based management

• value-stream mapping

waste

• materials waste 11

• time waste/Delay 9

• waste causes 1

• waste control

• waste rates

• waste time 1

• wastes 401

work structuring 46

Page 102: Lean Construction and Delay Analysis Input in delay

102

Appendix II

Inter-Rater Reliability (conducted by Mahmoud Elazzazy, Classmate)

INTER-RATER RELIABILITY TEST, Coefficient=0.76

Author Literature Page/Line Code Agreement

David K.H.Chua and

K.W.Yeoh

A Framework for

Construction

Requirements based

Planning Utilizing

Constraints Logic

Programming

page 2 paragraph

1,page2 para 4

Constraints,CPM

Agreed,

Agreed

Diego Cisterna,Luis

Fernando

Alarcon,Isabel Alarcon

Use of Risk Matrix as

Selector of Activity

Priority Execution

Base on Project

History

Page 3and

4paragraph Risk matrix,CPM

Agreed,

Disagreed

Jose Clemente and

Nuno Cachadinha

BIM-Lean Synergies in

the Management on

MEP Works in Public

Facilities of Intensive

use-A case Study

page4,paragraph

2/3 Bim-Lean,VSM

Disagreed,

Agreed

Andres

Covarrubias,Claudio

Mourgues,and Paz

Arroyo

VSM for Improving the

Certificate of

occupancy process in

real estate projects-A

Chilean case study

page 2 paragraph

2 VSM Agreed

Patrick

Dallasega,Andrea

Revolti,Camilia

Follini,Christoph Paul

Schimnaski,Dominik

Tobias Matt

BIM-Based

Construction Progress

Measurement of Non-

Repetitive HVAC

Installation Works page 3 paragraph

4 BIM - LPS Disagreed

Omar

Damaj,Mohamad

Fakhreddine,Makram

Lahoud,and Farook

Implementing

Ergonomics In

Construction To

improve Work

page

3/paragraph2and

page 9 paragraph

1

Ergonomics,

delay

Agreed,

Disagreed

Page 103: Lean Construction and Delay Analysis Input in delay

103

Hamzeh Performance

Emmanuel

I.Daniel,Daniel

Garcia,Ramesh

Marasini,Shaba

Kolo,and Olalekan

Oshodi

Improving

Construction

Management Practice

in the Gibraltor

Construction Industry page 3 paragraph

2 LPS Agreed

Alaa Daramis,Karim

Faour,Lyn Richa

Abdel Ahad,Ghadeer

Salami,and Farouk

Hamza

A Lean-Governance

Approach to Mitigate

Corruption within

official Processess in

the Construction

Industry

Page 6 paragraph

2 ERP Agreed

Ankur Paresh Desai

and Tariq Sami

Abdelhamid

Exploring Crew

Behavior During

Uncertain Jobsite

Conditions

2/paragraph 5

and page 6

paragraph 3

Delay,(LPS and

5S) Agreed

Page 104: Lean Construction and Delay Analysis Input in delay

104

Appendix III

INTRA-RATER RELIABILITY TEST, Coefficient=0.74

Author Literature Page/Line Code Agreement

Iris. D Tommelein

Parade Game: impact of workflow

Variability On succeed trade Performance

Page 3/paragraph 1

Dependency Agreed

I-Tung Yang

Stochastic Analysis On

Project Duration Under

The requirement of

continuous resource utilization

Page 2paragraph2

Buffer, Float, delay, CPM Agreed

Masanobu Sakamoto

A study of the relationship

Between buffers and

performance in construction

page3,paragraph 2

Delay ,lead time, inventory

Disagreed, Agreed

Iris. D Tommelein

More Just-In-Time

page 2 paragraph 2

JIT,TPS Agreed,

Disagreed

Bob Huber, Paul Reiser

The marriage of CPM and

Lean Construction

page 2 paragraph 2

CPM Agreed

Glenn Ballard

Integrating Design

Planning, Scheduling,and

control with Deplan

page 8,paragraph 3

Workflow, Lookahead, CPM

Agreed, Disagreed

Huseyin Erol

A Construction Delay Analysis

Approach Based On

Lean Principles

Page 2,Paragraph 1

Workflow, LPS,CPM Agreed,

Disagreed

Vaidyanathan

Value of visibility and planning in

engineering -to-order

Environement

Page 7 paragraph 3

CPM, Procurement Agreed,

Disagreed

Shen Li Jun

Distributed schedule with

integrated production scheduler

Page 2 paragraph 1

Delay,(LPS and 5S) Agreed

Page 105: Lean Construction and Delay Analysis Input in delay

105

Declaration of Authorship

I hereby declare that the attached Master‟s thesis was completed independently and

without the prohibited assistance of third parties, and that no sources or assistance

were used other than those listed. All passages whose content or wording originates

from another publication have been marked as such. Neither this thesis nor any variant

of it has previously been submitted to an examining authority or published.

Date Signature of the student

Page 106: Lean Construction and Delay Analysis Input in delay

106

References

AACE® International Recommended Practices. (2011). AACE. AACE® International,

Inc.

A.Ghio, V. (1997). Development Of Construction Work Methods And Detailed

Production Planning For On-Site Productivity Improvement. IGLC, 8.

Abdelhamid, T. S. (2003). Six-sigma in lean construction systems:. IGLC, 19.

Alarcón, L. F., Diethelmand, S., & Rojo, O. (2002). Collaborative Implementation of

Lean Planning Systems in Chilean Construction Companies. IGLC, 11.

AlSehaimi, A., & Koskela, L. (2008). What can be learned from studies on delay in

construction ? IGLC, 12.

Alves, T. C., & Tsao, C. C. (2007). Lean Construction – 2000 to 2006. Lean

Construction Journal, 25.

Ansell, M., Holmes, M., Evans, R., Pasquire, C., & Price, A. (2007). Lean Construction

Trial On a Highways Mainenance Project. IGLC, 10.

Ballard, G. (2000). The Last Planner System of Production Control (PHD dissertation).

Birmingham: University of Bimingham.

Ballard, G. (2008). The Lean Project Delivery System: An Update. Lean Construction

Journal, 19.

Ballard, G., & Howell, G. A. (2003). An Update on Last Planner. IGLC, 13.

Ballard, G., & Tommelein, I. (2016). Current Process Benchmark for the Last Planner

System. Berkeley: p2sl.berkeley.edu.

Bob Huber, P. R. (2003). The Marriage of CPM and Lean Construction. IGLC, 9.

Caletka, A. F., & Keane, J. P. (2015). Delay Analysis in Construction Contracts. United

Kingdom: Wiley Blackwell.

Chang, S. C. (2009). Identifying Root Causes of Long Review Times for Engineering

shop drawings. IGLC, 16.

Damaj, O., Fakhreddine, M., Lahoud , M., & Hamzeh, F. (2016). Implementing

ergonomics in construction to improve work performance. IGLC, 10.

David K.H, C. (2009). A framework for construction requirements based planning

utilizing constraints logic programming. IGLC, 10.

Page 107: Lean Construction and Delay Analysis Input in delay

107

Davis, S. R. (2009). An Algorithme for creating Master Schedules that minimizes

schedule reorganization resulting from adverse risk events. IGLC, 10.

Dedoose. (2020, January 2). Dedoose . Retrieved from

Dedoose.com Dedoose Great Research Made Easy :

https://www.dedoose.com/?gclid=Cj0KCQiAxrbwBRCoARIsABEc9sireSAGEh0_

wCUNu5XONcjrlHUJYpAu1K-ZhjQbqviftJ57NOhd2xwaAuIeEALw_wcB

Deschamps, R. R., Esteves, R. R., Rossetto, R., Tomazi, L. F., & Pereira Da Silva, G.

G. (2015). The impact of variability in workflow. IGLC, 10.

Elo, S., & Kyngas, H. (2008). The qualitative content analysis process. Journal of

Advanced Nursing, 10.

Frandson, A., Berghede, K., & Tommelein, I. D. (2014). Takt-time planning and the last.

IGLC, 10.

González Vicente, L. F. (2006). Design Of Work In Process Buffers In repetitive Building

Projects :A case Study. IGLC, 12.

Hammond, J., Choo, H. J., Austin, S., Tommelein, I. D., & Ballard, G. (2000). Integrating

Design Planning,Scheduling,and Control With Deplan. IGLC, 11.

Hegazy, S. (2012). Delay Analysis Methodology in UAE construction projects:Delay

claims,Literature review. PM World Journal, 21.

Huber, B., & Reiser, P. (2003). The Marriage of CPM and Lean Construction. IGLC, 9.

Huseyin , E., Irem, D., & Talat, B. M. (2017). A Construction Delay Analysis Approach

based on Lean Principles. IGLC, 9.

Izquierdo, J. L., & Arbulu, R. (2008). Application of Production Management In Industrial

EPC and Projects In Peru. IGLC, 8.

Joao Matias, N. C. (2010). Evaluating the Potential Benefits and Challenges of LC

Adoption in the Portugese Construction Industry:A Survey Study. IGLC, 11.

Jun, S. L., Chua, D. K., & Hwee, B. S. (2000). Distributed Scheduling with Integrated

Production Scheduler. IGLC, 11.

Koskela, L. (1992). Application for the New Production Philosophy To Construction.

Stanford: Center For Integrated Facility Engineering.

Page 108: Lean Construction and Delay Analysis Input in delay

108

Koskela, L., Kraemer, K., Henrich, G., & Kagioglou, M. (2007, 03 26).

https://www.irbnet.de/daten/iconda/CIB16363.pdf. Retrieved 10 22, 2018, from

www.irbnet.de: https://www.irbnet.de/daten/iconda/CIB16363.pdf

Kpamma, Z. E., & Adjei-Kumi, T. (2013). Construction Permits and Flow of Projects

within the Sunyani Municipality,Ghana. IGLC, 10.

Krippendorff, K. (2004). Content Analysis (An Introduction to its Methodology).

Thousand Oaks,London,New Delhi: SAGE Publications.

Lauri Koskela, A. K. (2015). Suggestions to improve lean construction planning. IGLC,

10.

Lauri Koskela, G. H. (2014). If cpm is so bad,why have we been using it so long? iglc,

11.

Liker, J. K. (2004). The Toyota Way: 14 Management Principles from the World's

Greatest Manufacturer. New York: McGraw-Hill.

Marcus P.Sterzi, E. L. (2007). Integrating Strategic Project Supply Chain Members In

Production Planning and Control. IGLC, 11.

Mary Ansell, M. H. (2007). Lean Construction Trial on a Highways Maintenance Project.

IGLC, 10.

Matias, J., & Cachadinh, N. (2010). Evaluating the potential benefits and Challenges of

LC adoption in the Portuguese construction industry:A survy study. IGLC, 11.

Mosanobu Sakamoto, M. J. (2002). A Study of The Real Relationship Between Buffers

and Performance In Construction. IGLC, 13.

Neale, R. H., Neale, D. E., & Stephenson, P. (2016). Construction Planning. London:

ICE Publishing.

Olivieri , H., Olli, S., & Granja, A. D. (2018). Improving workflow and resource usage in

Construction schedules through location-based management system(LBMS).

Construction Management and Economics, 17.

Patrick T.I.Lam, M. M. (2001). The Mulltiple roles of Specifications in Lean Construction.

IGLC, 11.

Photios G.Loannou, C. S. (2007). The Investigation of Lead-Time Buffering Under

Uncertainty Using Simulation and Cost Optimization. IGLC, 10.

Page 109: Lean Construction and Delay Analysis Input in delay

109

Pingbo Tang, D. G. (2014). Workflow stabilization with fine-grained work packaging and

near real-time progressing monitoring. IGLC, 12.

PMBOK. (2000). A Guide to Projet Management Body of Knowledge. USA: Project

Management Institute,Inc.

Russell Kenley, T. H. (2015). Removing waiting hidden time in critical path schedules :A

location-based approach to avoiding waste. IGLC, 8.

S.Mohammad, H. L. (2012). Possibility of applying lean in post-disaster

reconstruction:An evaluation study. IGLC, 10.

Sakamoto, M., Horman, M. J., & Thomas , H. R. (2002). A Study of the Relationship

between Buffers and Peromance in Construction. IGLC, 13.

Saunders , M., Lewis, P., & Thornhill, A. (2016). Research Methods for Business

Students. Pearsons Eduction Limited.

Senior, B. A. (2009). Critical Path Method Implementation Drawbacks: A Discussion

Using Action Theory.

Seppanen, O. (2012). A production control game for teaching a location-based

management system`s controlling methods. IGLC, 10.

Shen Li Jun, D. K. (2000). Distributed Sheduling With Integrated Production Scheduler.

IGLC, 11.

Sriwuwarnat, C., & Photios, L. G. (2007). The investigation of lead-time buffering under

uncertainty using simulation and cost optimization. IGLC, 10.

Stemler, S. (2001). An overview of content analysis. Practical Assessment, Research &

Evaluation. Retrieved 01 05, 2020, from Semantic Scholar:

https://www.semanticscholar.org/paper/An-Overview-of-Content-Analysis.-

Practical-Research-Stemler/192cd7912e2770f3c725a22822b77a59e4c1d75b

T.S.Abdelhamid, D. S.-G. (2009). Working through unforseen uncertainities using the

OODA Loop:An approach for self-managed Construction teams. IGLC, 10.

Tan, B., Horman, M. J., Messner, J. I., & Riley, D. R. (2003). Increasing the

understanding of Lean Principales with advanced Visualization technologies.

IGLC, 10.

Tommelein Iris.D, M. W. (1999). More Just-In-Time :Location Of Buffers In Structural

Steel Supply and Construction Process. IGLC, 12.

Page 110: Lean Construction and Delay Analysis Input in delay

110

Tommelein, W. M. (1999). More Just in Time:Location of Buffers in structural Steel

Supply and Construction Process. IGLC, 12.

Tung Yang, P. G. (2001). Resources-Driven Scheduling for repetitive Projects:A Pull

System Appraoch. IGLC, 14.

Vaidyanathan, K. (2003). Value of visibility and planning in an enginner-to-order

environment. IGLC, 14.

Williams, M. (2008). The Principles of Project Management. Canada: SitePoint Pty. Ltd.

Womack, J. P., & Jones, D. T. (2003). Lean Thinking:Banish Waste and Create Wealth

in Your Corporation. USA: Free Press.

Yang, I. (2002). Stochastic analysis on project duration under the requirement of

continuous resource utilization. IGLC, 13.