leakage of miv

Upload: sienlangphioo

Post on 08-Aug-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/22/2019 Leakage of MIV

    1/8

    LEAKAGES OF MIV

    Unit-3 & Unit-4 machines were re-commissioned on 21st October 2002 and

    17th Jan 2003 respectively after R & M works by Toshiba & Mitsui & Co, Ltd, Japan.

    The MIV of Unit -1 & 2 were replaced by new one but for Unit -3 & 4, the old MIV

    were overhauled by M/S Toshiba, Japan during R & M works in 2001-02. Subsequently

    it was found that some leakages appeared in the MIV of Unit -3 & 4, whereas MIV in

    unit -1 & 2 were performing properly till date. It was observed that these leakages of

    Unit 3 & 4 kept on increasing day by day and at present leaking heavily at the rate of

    0.4 Cubic metres/sec (400 litres/sec).During the recent inspection, it was found that the leakages have increased for

    Unit-3 & 4 to a great extent that it is not possible to enter the spiral casing for closer

    inspection as shown in Exhibit -1, while it was also found that there were no leakages

    for Unit -2 as shown in Exhibit -2. When the machine was idle, it was observed from the

    Discharge meter located in the Draft Tube that the reading was 0.4 cubic metres / sec

    i.e. the wastage of water. Based on this discharge meter reading, the calculation was

    prepared which ultimately shows the actual loss in Rupees per year at Rs 1.68 cr as per

    annex--I.

    It is therefore very much necessary that the above two MIVs be also replaced by

    the new Horizontal Thru Flow Type complete with Servomotor, Coupling Bolts & Nuts,Flanges, Installation materials, Mounting materials, Oil piping, etc except Bypass

    Valve which have already been replaced during R&M. Since the Power Station was

    built and renovated by M/S TOSHIBA Ltd, Japan, the original manufacturer, so it is

    proposed that the above MIVs be procured from M/S Toshiba, Ltd, Japan.

  • 8/22/2019 Leakage of MIV

    2/8

    1

    It was seen that, if the MIV were replaced, the total cost will be recovered

    within three years time and it will also save the Turbines, etc from further damages.

    AnnexI

    CALCULATION OF DISCHARGE

    P = 9.8 x Q x H (as per annexII)

    Where

    P = power in kw

    Q = discharge in cubic metre per sec.

    H = effective head in metre.

    Here

    P = unknown

    Q = 0.4 cubic metre/sec (as per the present reading in the meter)

    H = (h max + h min)/2 = (169+130)/2 = 149.50 m (as per annexV)

    Therefore,

    P = 9.8 x0.4 x 149.5 kw

    = 586.04 kw

    Taking

    1.The average idle condition of the machine = 15.75 hrs/day (as perannexure-III)

    2.Cost of energy per unit = Rs 2.494 P (as per annex-IV)3.Number of machine (i.e leakages) = 2

    Therefore Loss in Rupees for one year

    = Rs (586.04 x 15.75 x 2.494 x 2 x 365)

    = Rs 16804559.28

    (Say) = Rs 1.68 crores.

    (Rupees one point six eight crores.)

    N.B. Amount of Leakages were considered during idle hours only.

  • 8/22/2019 Leakage of MIV

    3/8

    2

    Idle Hours of Unit-3 & Unit-4 machines wef Jan-06 upto Jul-06 ofStage-I

    Month/Year

    Unit-3 Unit-4No.of

    daysTotal

    AvailableHours

    RunningHours

    IdleHours

    TotalAvailable

    Hours

    RunningHours

    IdleHours

    Jan-06 744:00:00 151:48:00 592:12:00 744:00:00 545:07:00 198:53:00 31

    Feb-06 672:00:00 24:45:00 647:15:00 672:00:00 404:06:00 267:54:00 28

    Mar-06 744:00:00 62:47:00 681:13:00 744:00:00 375:59:00 368:01:00 31

    Apr-06 720:00:00 63:39:00 656:21:00 720:00:00 252:24:00 467:36:00 30

    May-06 744:00:00 72:19:00 671:41:00 744:00:00 237:02:00 506:58:00 31

    Jun-06 720:00:00 226:21:00 493:39:00 720:00:00 580:43:00 139:17:00 30

    Jul-06 744:00:00 93:49:00 650:11:00 744:00:00 404:43:00 339:17:00 31

    Total 5088:00:00 695:28:00 4392:32:00 5088:00:00 2800:04:00 2287:56:00 212

    Average Idle Hours per day = (4392:32 + 2287:56) / 2 x 212

    = 15:45:21 Hrs

    = 15.75 Hours (say)

  • 8/22/2019 Leakage of MIV

    4/8

    3

    EXHIBIT: 1

    VIEW OF MIV LEAKAGES IN CLOSED CONDITION AS SEEN FROM THE MANHOLE

    FIG.1: UNIT-4

    FIG. 2: UNIT-3

  • 8/22/2019 Leakage of MIV

    5/8

    4

    EXHIBIT: 2

    VIEW OF MIV LEAKAGES IN CLOSED CONDITION AS SEEN FROM

    THE MANHOLE:

    FIG. 3: UNIT-2

    FIG. 4: UNIT-2

    VIEW OF MIV IN CLOSED CONDITION AS SEEN FROM INSIDE THE SPIRAL

    CASING / DOWNSTREAM SIDE.

  • 8/22/2019 Leakage of MIV

    6/8

    5

    EXHIBIT: 3

    FIGURE SHOWING THE LOCATION OF MIV (MAIN INLET VALVE) WITH RESPECT TO

    PENSTOCK & TURBINE OF THE POWER PLANT.

  • 8/22/2019 Leakage of MIV

    7/8

    6

    EXHIBIT: 4

    FIG: 1. MIV IN FULLY CLOSED POSITION.

    FIG:2. MIV IN FULLY OPENED POSITION.

  • 8/22/2019 Leakage of MIV

    8/8

    7

    CONCLUSION

    The loss due to the leakages of the MIVs in Unit 3 & 4 is quite

    significant which cannot easily be ignored. In fact if both the MIVs are

    replaced as early as possibly the whole expenditure including the cost of newMIV, Servomotor, plus taxes, interest, etc could be recovered within two

    years from the date of re-commissioning of the Unit.

    If the MIVs of Unit-3 & 4 are not immediately replaced, then the loss

    will definitely increase, thereby causing more loses than projected at present.

    At present also with so much leakages in the MIV, then the question of

    attending or inspection of the Turbine section including Guide Vanes

    adjustment, runner blades, draft tubes, etc is out of question.

    Since the inspection/repair of the above parts are of vital importance

    for the running of the Hydel Power Station, I would very much like to

    recommend for complete replacement of the above MIV at the earliest in

    order to avoid any further loss and damages to the turbines and last but not

    the least for the safety of all the personnel in the power station.