8/10/2019 Leadcom Galooli Demo Marthaderoldos
1/14
1
Guayaquil,Julio 28, 2014
GALOOLI SITE MONITORSYSTEM
DEMO: MARTHA DE
ROLDOS
-
8/10/2019 Leadcom Galooli Demo Marthaderoldos
2/14
2
Antecedentes - Objetivo
Ante solicitud de Claro, se plantea la instalacin del sistema de monitoreo Galooli con el
requerimiento indicado para tener un control en tiempo real de ciertos eventos y existamayor seguridad sobre los sistemas de bateras abiertos y generador AC.
-
8/10/2019 Leadcom Galooli Demo Marthaderoldos
3/14
3
Battery voltageBattery Temp
CCTV
AC Energy meter
Esquema general del sistema
Triton / Corona
GPS
InternetExternal Users
ZON Control
Server
-
8/10/2019 Leadcom Galooli Demo Marthaderoldos
4/14
4
Triton inserted on Corona
Esquema general del sistema
Triton inserted on Corona
ZON Control
Triton programmer SerVision Multiclient
-
8/10/2019 Leadcom Galooli Demo Marthaderoldos
5/14
5
Requerimiento
-
8/10/2019 Leadcom Galooli Demo Marthaderoldos
6/14
6
Requerimiento
-
8/10/2019 Leadcom Galooli Demo Marthaderoldos
7/14
7
Energa AC
Requerimiento General
(General Requirement)
Requerimiento Especifico
(Specific Requirement)YES / NO (comply) / Pending confirmation NOTES
Energa AC
(AC Energy)
Registro de voltaje AC
(AC voltage register) YES EM-24 istalled with 2 CT rings.
Registro de corriente AC
(AC current register)YES EM-24 istalled with 2 CT rings.
Registro factor de potencia
(Power factor register)To be confirmed EM-24 istalled with 2 CT rings.
Registro consumo Ah
(AmpereHour consumption
register)
YES EM-24 istalled with 2 CT rings.
-
8/10/2019 Leadcom Galooli Demo Marthaderoldos
8/14
8
Energa DC
La solucin no cumple con este requerimiento
Requerimiento General
(General Requirement)
Requerimiento Especifico
(Specific Requirement)YES / NO (comply) / Pending confirmation NOTES
Energa DC
(DC Energy)
Gestin y monitoreo de planta
de rectificacin
(Monitoring and management of
Power Plant (ELTEK))
NO
ELTEK Power Plant provides SmartPackAdvanced functions with SNMP
compatibility. They want to be able to use
these functions to monitor and manage the
equipment remotely.
Our solution does not offer any connection
through Power Eltek Advanced functions.
DC meter not required.
-
8/10/2019 Leadcom Galooli Demo Marthaderoldos
9/14
9
Bateras estacionarias
Requerimiento General
(General Requirement)
Requerimiento Especifico
(Specific Requirement)
YES / NO (comply) / Pending
confirmationNOTES
Bateras estacionarias
(stationary batteries)
Registro de estado de las bateras
en tiempo real. Implica conocer
parmetros de conductancia o
admitancia de las bateras deforma individual.
(Real Time monitoring of battery
state. Conductance, admittance, or
resistor based methods to monitor
per battery state)
YES / PENDING
Must monitor at least battery voltage per
battery remotely. Conductance /Admittance measurement is a very desired
feature.
Our solution does not offer conductance /
admittance register.
At moment with Galooli solution we have 1
battery temp and 1 battery voltage.
-
8/10/2019 Leadcom Galooli Demo Marthaderoldos
10/14
10
Generador
Requerimiento General(General Requirement)
Requerimiento Especifico(Specific Requirement)
YES / NO (comply) / Pending confirmation NOTES
Generador
(Generator)
Gestin y monitoreo de la planta
generatriz
(Monitor and management of
GENSet)
NO
GENSets on Claros network have specific
GENSet controlling cards
They wish to monitor and manage remotely
all parameters captured by controlling
cards. They also want to able to turn the
Generator ON remotely and program
exercise test periodically remotely.
Our solutions does not access the
controlling card information to monitor and
manage GENSet.
Customer informed that Fuel Level is no
required and should only be considered as
an optional feature. LLS not required.
La solucin no cumple con este requerimiento
-
8/10/2019 Leadcom Galooli Demo Marthaderoldos
11/14
11
Video vigilancia
Requerimiento General
(General Requirement)
Requerimiento Especifico
(Specific Requirement)YES / NO (comply) / Pending confirmation NOTES
Video camara
En cada sitio debern existir al menos 2 cmaras
de video, una interna en el cuarto de equipos y otraexterna.(On each site the must exist at least 2 cameras to
monitor equipment room and access)
YES2 outdoor cameras are available. Newcoax cable will be required since providedlength is not enough.
La resolucin de las cmaras debe permitir la
identificacin clara de las personas que han
ingresado a la radiobase.
(Camera resolution should be good enough to
identify clearly the person accessing site).
YES
Cameras have ok resolution for most of
he covered area, in case client requires
better resolution, new camera must be
accuired.
Las cmaras deben tener la funcionalidad de iniciar
la grabacin al detectar movimiento en su zona deoperacin.
(Cameras must have feature that enables it to
record when it has detected movement in its viewing
range).
YES OK
La grabacin deber ser enviada al sistema de
almacenamiento central con un eficiente uso del
ancho de banda asignado
(All recording should be sent to a centralized server
located in customer premises utilizing bandwithefficiently).
PENDING
Customer wishes to protect privacy and
secure their information and govern their
own equipment.
I believe SerVision does have a
centralized solution. as is now, recording
is done on SerVision gateway on site in
MicroSD and portions of selected videocan be downloaded to centralized location
or live streaming can be seen through
SerVision Multiclient app.
El medio de transmisin entre la Radiobase y el
sistema de almacenamiento central ser provisto
por Conecel.
(The means of transmission of data between site
and centralized location will be provided by
Conecel(Customer)).
YES / PENDING IMPLEMENTATION
Customer offers to provide some means
of transmission of data depending on the
specifications of our product. Our product
uses 3G data card, no need for other
means of transmission.
3G is a bit slow, but for demo purposes is
ok.
3G is not the most reliable connection
means, for demo purposes OK, betterransmission method must be defined in
he future.
-
8/10/2019 Leadcom Galooli Demo Marthaderoldos
12/14
-
8/10/2019 Leadcom Galooli Demo Marthaderoldos
13/14
13
Conclusiones
Solucin parcial, se debe realizar un desarrollo para cumplir al 100% de los
requerimientos.
La solucin de video es independiente al sistema de monitoreo Galooli, no existe
integracin entre ambos sistemas.
Existen fallas en ZON Control que han sido resueltas y mejoras que ha implementado
Galooli poco a poco, a destiempo considerando el demo presentado a Claro.
El medio de TX de la solucion es travs de la red 3G de Claro lo que lo hace un poco lento
(especialmente la solucion de video) el cliente requiere sea Ethernet.
PREGUNTAS y COMENTARIOS.
-
8/10/2019 Leadcom Galooli Demo Marthaderoldos
14/14
14
Gracias