Page 1: Lead from the front Texas Nodal  1 Texas Nodal Independent Market Monitoring and Data Collection For Protocol Section 17 Business

http://nodal.ercot.com 1Lead from the front

Texas Nodal

Texas Nodal

Independent Market Monitoring and Data Collection

For Protocol Section 17

Business Requirements Document

Sylvia Shiroyama – October 24, 2006

Page 2: Lead from the front Texas Nodal  1 Texas Nodal Independent Market Monitoring and Data Collection For Protocol Section 17 Business

http://nodal.ercot.com 2Lead from the front

Texas Nodal

Sources of Requirements to EDW

Requirements Through Project Teams

Requirements Due to Changing Source for Existing Reports/Extracts

Independent Market Monitor Protocol 17

Compliance Protocol 8

Page 3: Lead from the front Texas Nodal  1 Texas Nodal Independent Market Monitoring and Data Collection For Protocol Section 17 Business

http://nodal.ercot.com 3Lead from the front

Texas Nodal

Document Contents

• Scope

• Assumptions and Dependencies

• Definitions and Acronyms

• Functional Requirements

• Supplementary Requirements

• Protocol Coverage

Page 4: Lead from the front Texas Nodal  1 Texas Nodal Independent Market Monitoring and Data Collection For Protocol Section 17 Business

http://nodal.ercot.com 4Lead from the front

Texas Nodal

Document Contents

• Introduction

– Scope

– Document Conventions

– Assumptions and Dependencies

– Definitions

• Structure

– Functional Requirements

– Supplemental Requirements

• Functional Requirements

– Requirements from Nodal Protocols

– Requirements from other Binding Documents

Page 5: Lead from the front Texas Nodal  1 Texas Nodal Independent Market Monitoring and Data Collection For Protocol Section 17 Business

http://nodal.ercot.com 5Lead from the front

Texas Nodal

Requirements Specification

• Supplementary Requirements

– Performance Requirements

– Legal and Regulatory Requirements

– System and Communication Requirements

– Back up and Recovery Requirements

– Availability and Redundancy Requirements

– Maintainability Requirements

– Training and Documentation Requirements

– Usability Requirements

• Protocol Coverage

• Sub-Process Coverage

Page 6: Lead from the front Texas Nodal  1 Texas Nodal Independent Market Monitoring and Data Collection For Protocol Section 17 Business

http://nodal.ercot.com 6Lead from the front

Texas Nodal

Scope

The market monitoring data collection is designed to assist the PUCT and WEMM to:

(a) Protect Market Participants and Customers from the exercise of market power and from market manipulations;

(b) Ensure that there is effective and persistent competition for events that are not mitigated;

(c) Ensure that the market design and implementation are efficient;

(d) Guard against inefficiencies in the market and market manipulations;

(e) Ensure a justifiable and reasonable price impact; and

(f) Ensure that data posted on the MIS Public Area fulfills the objective of transparency of market information consistent with Section 1.3, Confidentiality.

Page 7: Lead from the front Texas Nodal  1 Texas Nodal Independent Market Monitoring and Data Collection For Protocol Section 17 Business

http://nodal.ercot.com 7Lead from the front

Texas Nodal

Assumptions and Dependencies

• A1) Auditor will provide recommendations to address potential areas for improvement. (Reference to FR5, FR6, FR7)

• A2) Auditor will be auditing the data repository of required data and processes associated with that data repository. (Reference to FR5, FR6, FR7)

• A3) The Data Archive as stated in the protocols is any data system which retains on-line operational data for 4 years and data in these systems will be maintained for an additional 3 years. (Reference to FR3, FR8)

• A4) The Data Warehouse as stated in the protocols is any data system which retains on-line operational data for 4 years. (Reference to FR3, FR5, FR8)

• D1) Data and process owners will identify the appropriate source system of record for all required and included data to be collected into the EDW. (Reference to FR3, FR8)

• D2) The business owners of each source system are responsible for data validation prior to replication in the EDW. (Reference to FR3)

• D3) The presentation functions of the MIS Public Area will be provided by the Nodal MIS project. (Reference to FR9)

Page 8: Lead from the front Texas Nodal  1 Texas Nodal Independent Market Monitoring and Data Collection For Protocol Section 17 Business

http://nodal.ercot.com 8Lead from the front

Texas Nodal

Definitions and Acronyms

ERCOT data storage systems This phrase is used throughout these requirements and addresses the systems used to provide required data to WEMM and PUCT as defined in FR1

Data Attributes/Attributes

Entities that define properties of data elements.

Data Integrity The accuracy, correctness, and validity of data.

Data Repository Any system which may be used to retain data for consumption.

MTTR Mean Time To Recovery is the average time to return a system to operations after a system failure.

Latency Latency is the time delay between the moment a request for data is initiated, and the moment when the requested data is returned.

MTBF Mean Time Between Failures is the "average" time between failures. Calculations of MTBF assume that a system is "renewed", i.e. fixed, after each failure, and then returned to service immediately after failure.

Performance How fast a business operation performs under defined circumstances.

Reliability The ability of a device or system to perform a required function under stated conditions for a specified period of time.

Role The named set of features defined over a collection of entities (e.g., people, systems, organizations) participating in a particular context.

SLA Service Level Agreement (SLA) – the part of a service contract in which a certain level of service is agreed

Supplementary Requirements Also known as non-functional requirements. Supplementary requirements impose constraints and specify overall characteristics. Examples of supplementary requirements include performance, reliability, availability, security, legal and reusability, etc,

Supportability The ability of technical support personnel to troubleshoot or perform root cause analysis in pursuit of solving a problem with a product/system.

Usability The ease with which people can employ a particular tool or system in order to achieve a particular goal. In user-interface design usability usually refers to the elegance and clarity of the design.

Page 9: Lead from the front Texas Nodal  1 Texas Nodal Independent Market Monitoring and Data Collection For Protocol Section 17 Business

http://nodal.ercot.com 9Lead from the front

Texas Nodal

Functional Requirements

• FR1 - Market Monitoring Data Collection• FR2 - Market Data Collection and Use• FR3 – Data Collection and Retention• FR4 – Data Catalog• FR5 – Accuracy of Data Collection• FR6 – Accuracy of Data Submission• FR7 – Annual Data Accuracy Audit• FR8 – Data Retention• FR9 – Provision of Data to Individual Market Participants• FR10 – Regulatory Reports• FR11 – Evaluation of ERCOT Operations and Market Performance• FR12 – Response to PUCT Data Requests – Substantive Rule

25.362(e)(1)(C)

Page 10: Lead from the front Texas Nodal  1 Texas Nodal Independent Market Monitoring and Data Collection For Protocol Section 17 Business

http://nodal.ercot.com 10Lead from the front

Texas Nodal

Supplementary Requirements

• Data Requirement Specification

• Data Collection Timing Specification

• Data Access Specification

• Data Access Security

• Data Access Performance Requirement

Page 11: Lead from the front Texas Nodal  1 Texas Nodal Independent Market Monitoring and Data Collection For Protocol Section 17 Business

http://nodal.ercot.com 11Lead from the front

Texas Nodal

Protocol Coverage

Protocol Sub-Section # (To the lowest level of granularity as possible) Description

Coverage by Requirements(Full/Partial)

17.1 Marketing Monitoring Data Collection Full (FR1)

17.2 Objective and Scope of Market monitoring Data Collection n/a

17.3 Market Data Collection and Use Full (FR2)

017.3.1 Data Collection and Retention Full (FR3)

17.3.2 Data Catalog Full (FR4)

17.3.3 (1) Accuracy of Data Collection Full (FR5)

17.3.3 (2) Accuracy of Data Submission Full (FR6)

17.3.3 (3) Annual Data Accuracy Audit Full (FR7)

17.3.4 Data Catalog Full (FR4)

17.3.5 Data Retention Full (FR8)

17.4 Provision of Data to Individual Market Participants Full (FR9)

17.5 (1) Regulatory Reports - Nightly Full (FR10)

17.5 (2) Regulatory Reports – Scheduled Full (FR10)

17.6 Evaluate ERCOT Operations and Market Performance Full (FR11)