lane coburn & assocs., seattle specifying generators · s tandby generators are a key component...
TRANSCRIPT
Standby generators are a key component of anymission-critical facility. There are many issues thatneed to be addressed when selecting and design thestandby generator system. This article will cover three
of the main issues: proper sizing, the fuel supply system,and proper grounding.
PROPER SIZINGWhen sizing a standby generator, the engineer must considerthe total output in real power, the required compensation forharmonic content in the electrical distribution system, andlarge-motor startup requirements.
Generators are typically specifi ed with a kW rating andan associated power factor. Together, these values indicatethe maximum kW (real power) and kVA (apparent power).An engineer must consider both the engine and generator—individually, and as a system. Engines produce the realpower, or horsepower, and control frequency. Generatorschange this mechanical energy into electrical energy (kVA)and must satisfy magnetization current (kVAR) within anelectrical system.
In a purely inductive load, the current lags the voltageby 90 deg (see Figure 1). Power alternates equally betweencycles of positive and negative. This means that power isbeing alternately absorbed and returned to the source. Ifthe system is a mechanical generator, it would take practi-cally no net mechanical energy to turn the shaft because nopower would be used by the load.
Often, a more critical generator sizing parameter is themaximum starting kVA (skVA) and maximum starting kW(skW) allowed. The skVA depends on the maximum allow-able voltage drop during starting and will be lower for moresensitive critical loads, or where lower maximum voltagedrops are required by code.
It is common for a system stating kVA and maximumallowable voltage drop to drive the size of the generator. Mo-tors can draw six times the full load amperes during startup.
High effi ciency motors can draw 10 times the full load cur-rent or more. This means that motor starting can dramati-cally affect the skVA required and may exceed the maximumskVA of a generator that would otherwise be large enough toserve the steady state load. This could require an oversizedgenerator based solely on the motor-starting requirements.
Staggering the starting of large motors and/or providingsoft starters or variable frequency drives (VFDs) can mitigatethe voltage drop problem by reducing the inrush currentand kVA. Staggering the starting of large motors can reducethe peak starting kVA to within limits of a smaller genera-tor. When providing steps between loads, the designer mustbe aware of all codes and maximum allowable starting timedelays for life safety and legally required standby loads.
Soft starters or VFDs can reduce the starting inrush cur-rent and kVA to half of that of an across-the-line starter.On the downside, these devices also use silicon-controlledrectifi ers to chop up the ac sine wave, resulting in a non-linear waveform. This nonlinear waveform, also known asharmonics, causes voltage distortion across the reactance ofthe generator and can cause unacceptable transient perfor-mance. Consequently, the results of harmonics will adverselyaffect the performance of the entire system. Voltage dropand voltage distortion will be much higher when a facility isunder generator power than when on utility power. Typicalgenerators have 15% to 20% internal reactive impedance,whereas utility transformers typically have between 2% and5% internal reactive impedance.
UPS rectifi ers usually do not draw a sine wave currentfrom the power source. The more the current waveform devi-ates from a sine wave, the more total harmonic distortion(THD) the current waveform contains. Harmonic distortioncan cause excessive heating at the generator and excessivevoltage distortion across the entire system.
An engineer must be familiar with the various methodsUPS and generator manufacturers use to make their UPSsystems more user-friendly to generator systems. Thesemethods include the use of:
UPS with12-pulse rectifi ers in lieu of 6-pulse rectifi ersUPS with passive fi ltersUPS with step loading or “walk-in” featuresPermanent-magnet generators with digital excitationcontrolsUPS that reduce maximum input current.
specifying generators8
www.csemag.com
PU
RE
PO
WE
R//
SP
RIN
G 2
011
Engineers must consider size, fuel capacity,
and grounding when designing mission-critical
standby power systems.
Specifying generatorsfor mission-critical environments
By Keith Lane, PE, RCDD/NTS, LC, LEED AP,Lane Coburn & Assocs., Seattle
CSEPP1103_FMCF.indd 8 2/26/2011 1:48:52 PM
9
www.csemag.com
PU
RE
PO
WE
R// S
PR
ING
2011
A 6-pulse rectifi er typically has about 30% THD, richin 5th and 7th harmonics. A 12-pulse rectifi er has lessthan half of the THD than that of a 6-pulse rectifi er,and is rich in 11th and 13th harmonics.
UPS manufacturers can provide passive fi lters to re-duce the THD seen by the generator. At low UPS load-ing, the static fi lter can provide an excessive capacitivecomponent that is sent back to the generator. Unlikea utility source, a generator cannot absorb the voltagerise caused by the capacitance in the system. Theoreti-cally, the generator’s voltage regulator can lose controland raise the output voltage to the UPS. The UPSrectifi er may turn off when it sees the rise in voltage.This disconnecting of the UPS rectifi er will remove theadditional capacitance in the system, which will allowthe generator’s voltage regulator to operate properly.This cycle can continue and the UPS will be unable topick up the load under generator power.
This problem can be eliminated by evaluating the systemto provide a smaller fi lter, which should be sized to provideno excitation at the lowest possible load. In addition, the fi l-ter can be completely removed under generator power withcontrol circuitry. Strategically providing reactive loads in thesystem and connecting them to the generator prior to theUPS will allow these loads to absorb the capacitive compo-nent, which essentially redirects the capacitive componentaway from the generator.
A 100% step-loading of the UPS system to the generator inthe case of a loss of utility power will cause sudden fl uctua-tions in both frequency and voltage of a standby generator.Many manufacturers will offer a “walk-in” function. Duringa utility power outage, the load served through the inverteroutput from the utility source via the rectifi ers will immedi-ately switch to the UPS batteries. Once the generator is upto speed (voltage and frequency), the total load on the UPSsystem’s batteries can be slowly applied to the generator.Typically, this can be programmed to occur over a 30-secperiod. The walk-in feature greatly reduces the frequency
specifying generators
Figure 1. This illustration shows the relationship between generator voltage, cur-
rent, and power. The current lags the voltage by 90 deg in a purely inductive load.
Courtesy: Lane Coburn & Assocs.
Figure 2. This illustration shows a portion of a one line diagram for a large high-rise building with multiple automatic transfer switches. These transfer
switches include life safety, legally required standby, and optional branches. Courtesy: Lane Coburn & Assocs.
Voltage
Power
Current
90 deg
180 deg
270 deg
360 degV L
Phase relationships
One-line diagram showing multiple ATSs
C
E
70
1,600 A
84L
N E
L
N E
L
N E
L
N
71 85 1
M M M M
FP-1100 hp
FPC-1100 hp
FPC-2100 hp
JPC-15 hp
JPC-25 hp
FP-2100 hp
JP-15 hp
JP-25 hp
225A
4
800A
4 60C
4
175A
3
175A
3
15C
3
15C
3
400A
4
600A
4
225A
4
225A
4
800A
4
175A
4
175A
4
175A
3
175A
3
15C
3
15C
3
400/
3
600/
3
225/
3
225/
3
800/
3
250/
3
250/
3
20/3
20/3
800/
3
800/
3
50/3
50/3
SPARE SPARE
ATS-1225 A4-POLE
TO SOUTH/WESTTOWER ATS-3
TO WESTTOWER ATS-4
TO SOUTHTOWER ATS-5
Fire pump controllerand transfer switchby fi re protectionsystems installer(TYP 2)
For continuation,see south/westtower one-line
EG11,000 kW
Emergencygenerator
G
1E17.01
ATS-2800 A4-POLE
C
N GND
CSEPP1103_FMCF.indd 9 2/26/2011 1:49:38 PM
and voltage fl uctuation on the genera-tor output.
UPS harmonics can cause voltagewaveform distortion at the generator.Permanent magnet generators thatderive their own excitation can helpto mitigate this problem. In addition,digital voltage regulators and digitalexcitation controls can further provideimmunity to the harmonic effect ofnonlinear loads.
Many UPSs allow the operator toset the maximum input current. Afterrestoration of ac power, the rectifi er/battery charger will power the inverter
and simultaneously charge the bat-teries. The maximum possible inputcurrent to the UPS must be consid-ered when sizing the generator. Ifan operator reduces the maximuminput current, the total load on thegenerator is reduced, but the time torecharge the batteries is increased.
Waveform notching can be detri-mental to solid-state timing devicesthat rely on zero crossing switches.To compensate for the voltage dis-tortion from nonlinear loads, a largergenerator with reduced impedancecan reduce the effects caused by thenonlinear load.
The design engineer must beaware of the intended use of theon-site generator. Depending on theload factor, typical application, typi-cal peak loading, and typical hoursper year, the generator will requireeither a standby rating, a primerating, or a continuous rating. Inaddition, code issues will drive therequired rating of an on-site genera-tor. Operating a generator beyond itsrating will result in a shorter life andmore expensive operating costs. It isimportant to reference a generator’sintended use to the manufacturer’swarrantee restrictions in regard torun time per year.
When specifying a standby gen-erator for a data center or mission-critical facility, I recommend asubtransient reactance of 12% orless. The lower, the better.
Stepping the loads on a gen-erator is a method used during the
design process to reduce the requiredsize of the generator. If all the loadsare stepped on at the same time, thegenerator will be greatly oversized.Providing multiple automatic transferswitches and timing the transitionseveral seconds apart is one method ofensuring a multistage start of the gen-erator. Another method is to programa UPS system walk-in to ensure theentire load of the UPS is not slammedinto the generator.
Most large data centers will usestandby generators to serve the
“optional” data center loads. Thesegenerators will not mix life safety,legally required standby, and optionalload. But for small data centers withinan offi ce building, the same genera-tor that is used for the life safety andlegally required standby loads can alsoserve the optional load.
In these cases, there are threebranches of automatic transfer switch-es that can provide convenient loadstepping during generator startup (seeFigure 2). This will typically reducethe required size of the generator. Thetransfer switches can be timed per theNational Electrical Code (NEC) to startthe life safety loads within 10 sec (NEC700.12) and the standby loads within60 sec (NEC 701.11).
Conservatively oversizing a genera-tor because one does not clearly un-derstand sizing requirements will notonly add undo expense to a project,but it can also adversely affect systemreliability. Most manufacturers recom-mend that diesel engines should notbe run at less than10% of rated loadfor extended periods, and in generalrecommend that loads do not dropbelow 30% of the generator rating.Check manufacturer recommendationsfor specifi c installations.
THE FUEL SUPPLY SYSTEMThe engineer must also be awareof the minimum amount of on-sitefuel supply required for an internalcombustion prime mover serving as apower source for emergency systems.
The fuel supply system is a criticalcomponent of the standby generatorsystem in a mission-critical facility.We typically see requirements rang-ing from 24 hours to 72 hours of fuelrequired. On the design side, a goodrule-of-thumb when sizing the fuelsupply is to assume 0.07 G/kW/hr.
For example, a 2,000 kW generatorrequires approximately 140 G/hr at fulloperation.
2,000 kW x 0.07 = 140 G/hr atfull load
For large generators, the minimumamount of on-site fuel supply can
specifying generators10
www.csemag.com
PU
RE
PO
WE
R//
SP
RIN
G 2
011
Table 1:Generator ratings highlightingsubtransient reactance
GENERATOR RATINGS
PMG stator 2.1
410.1a No load exciter fi eld Ampsat 480 V Line-to-Line 0.79 A dc
420.1a Short circuit ratio 0.617
421.1a Xd synchronous reactance 2.25 pu0.319
422.1a X2 negative sequence 0.212 pureactance 0.03
423.1a X0 zero sequence reactance 0.063 pu0.009
425.1a X’d transient reactance 0.163 pu0.023
426.1a X”d subtransient reactance 0.119 pu0.017
-- Xq quadrature 1.1 pusynch reactance 0.156
427.1a T’d transient short- 0.162circuit time constant sec
428.1a T”d subtransient short- 0.011circuit time constant sec
430.1a T’do transient open- 2.55circuit time constant sec
432.1a Ta short-circuit time 0.027constant of armature winding sec
Subtransient reactance should be 12% or less.
This table represents a subtransient reactance
of 11.9%. Courtesy: MTU
CSEPP1103_FMCF.indd 10 2/26/2011 1:50:22 PM
PU
RE
PO
WE
R//
SP
RIN
G 2
011
exceed the limits set by building and/or fi re codes, and canlead to additional system requirements. These additionalsystem requirements include separate fuel supply systems;Class H, Div. 3 occupancies; or UL 2085 tanks with integralsecondary containment.
Another consideration is the type of fuel tank. Single-walltanks are UL-142 labeled and designed for storing fl ammableand combustible liquids. A UL 2085 tank may be required forsituations when large amounts of fuel are necessary.
PROPER GROUNDINGGenerator system grounding is an important criterion that mustbe understood to ensure proper operation of the critical systems.
The generator system can use either 3- or 4-pole transferswitches (see Figures 3 and 4). There are potential groundfault issues when using a 3-pole automatic transfer switch(ATS). The NEC requires a GFI breaker on the generatorif the breaker is 1,000 A or more, and 480 V. If this is anoptional generator, the generator breaker is required to tripduring a ground fault. A generator serving a life-safety loadhas the options of alarm only and no tripping. One methodof grounding a generator with a GFI is to bond the neutraland ground together at the generator, treat the generator as aseparately derived source, and provide a 4-pole ATS.
Consider a GFI breaker on the main service and on thestandby generator. In this example, the generator is not treatedas a separately derived system, and a 3-pole ATS is used. Thereis a possibility under generator operation and a ground faultthat the main breaker GFI could trip in addition to the generatorGFI breaker. Under this circumstance, when the normal utilityreturns, the main breaker in the service could potentially trip,not allowing the utility to serve the facility.
A Modifi ed Differential Ground Fault (MDGF) systemcan add signifi cant complexity to a standby electricaldistribution system. An MDGF system is required when thereare multisource systems with 3-pole transformer switches.In some situations, additional source grounding cannot becontrolled. An MDGF can provide ground fault selectivityeven on very complex systems.
ABOUT THE AUTHOR
Lane, PE, RCDD/NTS, LC, LEED AP is president and CEOof Lane Coburn & Assocs. LLC. and a member of theConsulting-Specifying Engineer Editorial Advisory Board.
Table 2:UL 2085 tank properties
UL 2085 TANK TEST REQUIREMENTS
Test Withstand ratings
Prolonged fi re test Two hours at 2,000 F Maximum average temp. = 280 F
Hose stream test Five minutes, 45 psig water stream after fi re test
Bullet resistance Five rounds, 150 grain, Caliber test 0.30, M2 Ballammunition, 2,700 ft/sec impact velocity
Vehicle impact 12,000 lb applied over 1 sq ft @ 10 MPH
Leakage test After successful completion of the above tests, leakagetest is performed using 5.0 psig air; tank to hold air for1 hr without leaking.
This table lists some of the UL 2085 tank properties.Courtesy: Underwriters Laboratories
Utility transformer(480/277 V, 3 phase, 4W)
Service entrance
4-pole ATSStandby generator
Conduit
GG
G
NN
G G
G N
GND
G
Separately derived source
Utility transformer(480/277 V, 3 phase, 4W)
Main breaker
3-pole ATS
Standby generator
ConduitService entrance
Not a separately derived source
Figure 3. When the generator is considered a separately derived
source, the neutral and ground are tied together at the generator and a
4-pole transfer switch must be used. Courtesy: Lane Coburn & Assocs.
Figure 4. When the generator is not considered a separately derived
source, the neutral and ground are not tied together at the generator and
a 3-pole transfer switch must be used. Courtesy: Lane Coburn & Assocs.
specifying generators12
CSEPP1103_FMCF.indd 12 2/26/2011 1:50:41 PM