    LAND LAUNCHING

    The purpose of the method statement is to ensure, where safety critical, work is carried out in aparticular sequence with better illustration and description to the erector and worker Where theydo exist they are predominantly for high-risk activities for steel erection / beam launching.

    The land launching works involving total of 8 members of steel girders from Pier 2 to AbutmentA. Two 45 tonne crane was used to erect then pre-fabricated segment girders G1 & G2 on theground. Prior to approve for the launching method statement, the safe working load andlaunching sequence must be submit for review.

    SAFE WORKING LOAD

    Launching Beam(45 Tons Mobile Crane)CASE 1(Launching At Abutment A to Pier 2 and Abutment B to Pier 7 ONLY )Condition With outriggers 7.2m extended 360 deg. Working area

    operating radius -10m (Please show the 6m working radius on the LayoutPlan)Boom Length in meter 17.4mLifitng capacity = 12.45 Ton (from load chart)

    Note :Safety Produre : Reduction of 10% of the capacity due to wind factor / swing effect

    12.45 tons x 10% = 1.245 Tons12.45 1.245 = 11.205 tons11.205 x 2 =22.41 Tons ( For 2 Crane)

    Therefore Total Lifting Capacity = 22.41 Tons

    Total Weight for1st set - Girder G1+G2+Lifting Equipment = 9 +8 +1 = 18tons

    2nd set - Girder G2+G3+Lifting Equipment = 8 +9+1 = 18 tons

    Total Lifting Capacity 22.41 Tons > 18 Tons ---------OK

  • 8/6/2019 Land Launching (Steel Erection)

    2/7

    WORK LAUNCHING SEQUENCE (STAGE 1 ) LAND LAUNCHING

    Plan view

    Cross section view

  • 8/6/2019 Land Launching (Steel Erection)

    3/7

    Elevation View

    Position the crane and the Abutment A and bottom of Pier 1 as per described in the launchingsequence diagram.

  • 8/6/2019 Land Launching (Steel Erection)

    4/7

    Road closure underneath the existing bridge with plastic barriers and signboard.

    Safety toolbox briefed by the KKB Engineerings safety officer to the crane operator and erector before start launching works.

    Shifting the prefabricated G1 & G2 girders to the side of the headstock ready for launching

  • 8/6/2019 Land Launching (Steel Erection)

    5/7

    Hoisting and alignment the position of girders desired position

    Aligned and adjusted the girders by measuring the centerline of girders

  • 8/6/2019 Land Launching (Steel Erection)

    6/7

  • 8/6/2019 Land Launching (Steel Erection)

    7/7

    CHECKING ON GIRDERS STABILITY UNDER ERECTION

    There always be the simplified rules of thumb to assesses the stability of the single girders undererector by the L/b ratio where the, L donates the un-braced length and b is the compressionflange width.

    The rules of thumb for simplified supported girders were as follows;

    1. For girders with L/b less than 60 stability would not be major concern during erection2. For girders with L/b value between 60 and 80, stability is marginal; but further stress

    calculation need to be verified.3. For girders with L/b more than 80, temporary support will be required during erection.

    L/b ratio: Span G1+G2 = ( + )=( + )= 46 +25 = 71

    Therefore 60 < L/b < 80 the Stability is marginal to the stability, further stress calculationrequired.

    A steel girder remains stable without lateral torsional bulking if , which

    is external normal stress cause by banding under self-weight,

    is the resistance factor to flexure,

    is elastic lateral torsional bulking stress

    = =

    =

    =

    The girders added with temporary stiffness to resist the lateral torsion.

    Observation for the combination of girders G1 and G2 during the land launching shown that thegirders were stable and sign of lateral torsional buckling are unlikely to occur.