land disturbance permit residential - milton dev... · land disturbance permit package ... all...

50
LAND DISTURBANCE PERMIT RESIDENTIAL NOTE: These forms are in addition to the site plans, construction plans or other outside documentation. If you fail to provide all required documentation, issuance of your permit could be delayed. ADDITIONAL FORMS YOU MAY NEED 1. Variance Application - If your plans fall outside of the limits of the zoning ordinance, you will be asked to submit a Variance Application. CONTACT NUMBERS Community Development Department (678)242-2545 City Plan Review Engineer Jimmy Sanders (678)242-2543 City Storm Water Engineer Jim Seeba (678)242-2513 City Arborist Mark Law (678)242-2552 Traffic Signal Utility Location Matt Fallstrom (678)242-2558 Fulton County Environmental Health Services (404)332-1801 Fulton County Water/Sewer (404)612-7518 Utilities Protection Center (800)282-7411 Fire Flow - Fulton County Department of Public Works Tom Kozak (404)244-0485 NPDES Requirements http://gaswcc.org DOCUMENTS YOU WILL NEED 1. Land Disturbance Permit Package 2. Copy of state contractor license and business license IMPORTANT INFORMATION Fire Flow tests must be performed by Fulton County Department of Public Works. You must provide proof of submittal to all planned utility companies. You must call the Utilities Protection Center not less than 3 working days before digging or blasting.

Upload: phamliem

Post on 21-Jul-2018

229 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

LAND DISTURBANCE PERMIT – RESIDENTIAL

NOTE: These forms are in addition to the site plans, construction plans or other outside documentation.

If you fail to provide all required documentation, issuance of your permit could be delayed.

ADDITIONAL FORMS YOU MAY NEED

1. Variance Application - If your plans fall outside of the limits of the zoning ordinance, you will

be asked to submit a Variance Application.

CONTACT NUMBERS

Community Development Department (678)242-2545

City Plan Review Engineer – Jimmy Sanders (678)242-2543

City Storm Water Engineer – Jim Seeba (678)242-2513

City Arborist – Mark Law (678)242-2552

Traffic Signal Utility Location – Matt Fallstrom (678)242-2558

Fulton County Environmental Health Services (404)332-1801

Fulton County Water/Sewer (404)612-7518

Utilities Protection Center (800)282-7411

Fire Flow - Fulton County Department of Public Works – Tom Kozak (404)244-0485

NPDES Requirements – http://gaswcc.org

DOCUMENTS YOU WILL NEED

1. Land Disturbance Permit Package

2. Copy of state contractor license and

business license

IMPORTANT INFORMATION

Fire Flow tests must be performed by Fulton

County Department of Public Works.

You must provide proof of submittal to all

planned utility companies.

You must call the Utilities Protection Center

not less than 3 working days before digging

or blasting.

Page 2: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 2 of 50

PERMITS MINIMUM SUBMITTAL CHECKLIST FOR LAND DISTURBANCE

Project Name: _____________________________________________ Date: _____________________

Project Number: ___________________________________________ Telephone: ________________

Reviewed By: _____________________________________________ Email: ____________________

Overlay District: _______________________________________________________________________

Provide all items listed below. If not applicable, applicant shall explain herein. Incomplete

application will not be accepted into the review process.

1. One set of plans, bearing the design professional’s seal and signature.

2. Provide project name, project address, owner’s name/address/phone, design firm

name/address/phone, point of contact and contact phone number, north arrow (on all

sheets), acreage, and location map. Indicate scale (1” – 10’ to 1” – 100’), graphic scale.

1” – 60’ for non-overall pages.

3. Submittal fee and completed application.

4. Maximum sheet size shall be 30” x 42” (E).

5. Conditions of Zoning (2 copies).

6. Signed copy of Arborist’s site visit.

7. Engineer’s Storm Water Management Report/Hydrology Report, (2 copies).

8. Flood Study (2 copies if applicable).

9. Plan Set includes: (LDP # on each page) Cover notes site plan

Storm Drainage Pipe calculations and profiles

Sewer Plan and Profile

Water Plan (or joint Utility Plan)

Erosion Control Plan

Landscape Tree Protection Plan details

10. Fire flow test results. Must be performed by Fulton County, contact Tom Kozak/FCDPW

and arrange for the test at (404)224-0485 or by email [email protected] and

pay the $100 fee for the test.

11. Proof of submittal to all planned utility companies as shown on cover page of plan set.

Page 3: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 3 of 50

Letters will be required by utility companies stating that plans will work as submitted,

prior to Milton LDP approval. This is required for all projects – residential and

commercial.

12. Detailed, specific REVISION STATEMENT on plan and/or letter attached to each set of

plans (for permit revisions only).

13. All construction shall conform to the City of Milton and GDOT Standards and

Specifications.

14. Benchmark: The benchmarks used are _____________________________.

15. Contractor is to notify inspector 24 hours prior to commencing constructions.

16. Signing and striping is to be provided by the Contractor and shall be in accordance with

City of Milton Specifications.

17. Notify City of Milton inspector 24 hours before every phase of construction.

18. All revisions to these plans must be submitted to the City of Milton Community

Development Department prior to continuing construction.

19. Call the Utilities Protection Center not less than three (3) working days before any digging

or blasting operations commence. You can contact the Utilities Protection Center at

(800)282-7411 Monday through Friday from 7 am to 7 pm.

20. Provide the City of Milton Encroachment permit for all work within the City’s R.W.W.

Any traffic signal or utility relocations will be the responsibility of the

developer/contractor. Developer/Contactor must contact City of Milton personnel directly

for traffic signal utility locations. Phone (678)242-2558.

21. Site survey was prepared by __________________________________________.

The City of Milton reserves the right to change this checklist and/or any review criteria deemed necessary

at any time.

Page 4: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 4 of 50

!!ATTENTION!!

FULTON COUNTY SANITARY SEWER PERMIT IS REQUIRED

PRIOR TO ANY WORK ON THE SANITARY SEWER SYSTEM. A

FULTON COUNTY WATER PERMIT MAY ALSO BE REQUIRED

DPENDNG ON THE LOCATOIN OF THE PROJECT.

FULTON COUNTY APPROVAL OF THE AS-BUILT SANITARITY

SEWER IS REQUIRED PRIOR TO THE ISSUANCE OF A

CERTIFICATE OF OCCUPANCY.

MAKE SURE YOU CORRDINATE YOUR SEWER APPROVALS

EARLY.

NOTE: A Fulton County LDP does not authorize any land disturbing

activities within the City of Milton. The city of Milton LDP must be

issued prior to any work authorized under the Fulton County permit.

Page 5: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 5 of 50

Inspections Information Package for Land Disturbance Permits

Inspector Assignment Sheet

Erosion and Sediment Control Pre-Construction Notice

Erosion Control Affidavit

Required Inspections

Erosion and Sediment Control Ordinance

Page 6: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 6 of 50

Development Permit Inspection Assignment

Project Name: __________________________________________________________________

Prior to any construction activity contact the City of Milton Community Development

Department at (678) 242-2544 for a pre-construction meeting.

Your inspector is _______________________________________. Please contact him 24 hours

in advance of the meeting.

At the meeting you will be instructed which erosion and sediment control devices must be

installed prior to the final permit sign-off from the inspector.

No construction activity, other than that designated erosion control installation, may begin

on site until the inspector has approved the installation of these measures and has signed

the grading permit. Failure to schedule the pre-construction meeting and the erosion control

inspection may result in a citation and issuance of a stop work order.

A City of Milton Department of Transportation permit is required for any work with the city

right-of-way. Contact Matthew Fallstrom at (678) 242-2558 for more information.

Applicant/Owner’s Name (Please Print): _____________________________________________

Applicant/Owner’s Signature: _______________________________________Date:__________

Page 7: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 7 of 50

EROSION & SEDIMENT CONTROL

PRECONSTRUCTION

NOTICE

Milton, Georgia

Community Development Department

(678) 242- 2500

THIS NOTICE IS TO FAMILIARIZE THE PERMITTEE WITH GENERAL

SEDIMENT CONTROL/STORM WATER REQUIREMENTS.

THIS IS NOT A COMPLETE LIST OF PERMIT CONDITION AND PLAN

REQUIREMENTS. PLEASE REVIEW YOUR PLANS AND PERMIT

THOROUGHLY.

1. INSPECTION REQUREST MUST BE MADE BY CALL (678) 242-2544, NO EXCEPTIONS.

Inspection requests must be made at least 24 hours in advance. You will need the permit number,

premise address, type of inspection requested and a phone number where you can be reached.

2. READ AND FOLLOW THE SEQUENCE OF CONSTRUCTION SHOWN ON THE

APPROVED PLAN(S).

An approved plan modification must be obtained from the department to deviate from the

sequence of construction.

Page 8: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 8 of 50

3. The limits of disturbance must be field marked prior to clearing, installation of sediment control

measures, construction, or other land disturbing activities.

4. The permittee must obtain written approval from the City of Milton inspection, (678) 242-2552,

certifying that the limits of disturbance and tree protection measures are correctly marked and

installed prior to commencing any clearing.

5. After the pre-construction meeting, you may clear only those areas necessary and approved to

install sediment control measures as shown on the approved plan(s). Identify those areas with the

inspector at the pre-construction meeting.

6. Call (678)242-2544 for sediment control installation inspection. You must obtain WRITTEN

approval from the Department before continuing with further grading or site development. A

Stop Work Order will be issued immediately if grading proceeds without written approval from

the inspector.

7. Stabilize sediment control measures with seed and anchored straw mulch within 14 calendar days

of installation.

8. SEDIMENT BASINS AND STORMWATER MANAGEMENT FACILITIES REQUIRE

SPECIFIC, DOCUMENTED INSPECTIONS DURING CONSTRUCTION BY THE

DEPARTMENT’S INSPECTOR AND THE PERMITTEE’S ENGINEER. Confirm these

inspection points and the need for testing and documentation with your inspector. PRIOR to

commencing work.

9. Safety fence must be installed around all sediment control devices that pond water greater than 9

feet in width and 18 inches in depth. Safety fence must be 14 gauge welded wire and openings no

greater than 2” x 4” and be at least 42” high. Support posts must be a maximum of 8 feet apart.

10. Be certain not to go beyond the limits of disturbance on your approved plan. All disturbed areas

not constructed upon for more than 14 calendar days must be stabilized with seed and anchored

straw mulch. A stabilization phasing schedule shall be developed at the pre-construction

meeting, and updated as necessary, with the inspector’s approval.

11. KEEP ALL STREETS CLEAN. Precautions, such as stone construction entrance, must be

installed and maintained. If mud is tracked onto the street, do no wash the mud into storm drains

unless the storm drain is diverted to an approved sediment-trapping device.

12. ALL SEDIMENT CONTROL DEVICES MUST BE MAINTAINED IN GOOD AND

EFFECTIVE CONDITION AT ALL TIMES. YOU ARE REQUIRED TO PROVIDE YOUR

OWN PERIODIC INSPECTIONS AND MAKE NECESSARY REPAIRS PROMPTLY.

Do not wait for the city inspector, as failure to maintain sediment control measures in good

and effective condition will result in the issuance of Criminal citations and/or a Stop Work

Order without prior warning. You must have a person responsible for sediment control on

the site who has successfully completed an Erosion and Sediment Control Certification

Program pursuant to state and local law.

Page 9: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 9 of 50

13. SEDIMENT CONTROL DEVICES MAY NOT BE REMOVED OR MODIFIED WITHOUT

WRITTEN PERMISSION FROM THE SEDIMENT CONTROL INSPECTOR.

14. All official notices, citations, stop work orders, etc., will be issued to the on-site representative of

the permittee designated on the attached form.

15. A sediment control permit does not transfer with ownership. The permittee is required to notify

the Department by certified mail within 48 hours of any change in ownership. The new owner

and lots/parcels affected must be identified.

16. Should you have any questions, please contact your sediment control inspector at the number

provided.

17. Additional comments by the inspector:

_________________________________________________________________________________

_________________________________________________________________________________

_________________________________________________________________________________

Project Name: _____________________________________________________________________

Inspector: _________________________________________________________________________

Received by: ______________________________________________________________________

Printed Name: _____________________________________________________________________

Signature: ______________________________________________________Date:______________

Phone Number: ____________________________________________________________________

Page 10: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 10 of 50

Erosion Control Affidavit

(This affidavit must be completed prior to the pre-construction meeting. The individual

whose name appears on this affidavit is required to attend the pre-construction meeting.)

Project Name:_______________________________________________________________

I, __________________________________________, certify that I am the responsible party

for inspecting the installation and maintenance of all erosion and sediment control measures

identified on the approved plan. I understand that failure to implement or maintain these

measures may result in the issuance of a citation or stop work order.

I have read and understand the City of Milton Erosion and Sediment Control ordinance.

If for any reason I cannot continue my erosion and sediment control responsibilities for this

site, a replacement will be named and the City will be notified in writing. If a suitable

replacement cannot be found, the site will be stabilized and all land disturbing activities will

cease until a replacement can be named.

Print Name: ________________________________________________________________

Signature: __________________________________________________________________

24 Hour Phone: __________________Cell Phone: _________________ Fax:____________

Company Name:_____________________________________________________________

Address: ___________________________________________________________________

GSWCC#:___________________________________________ Date:__________________

Page 11: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 11 of 50

Required Inspections

Notify your inspector 24 hours in advance of all inspections unless otherwise noted. All construction

shall conform to City of Milton, Fulton County or Georgia DOT construction standards. Any

deviation from these specifications without prior written approval may result in the removal and

reconstruction of the deficient items. Inspections and sign-offs are required for the following items:

Preconstruction Meeting: Shall be scheduled and completed prior to any

activity commencing on the site.

For projects under the jurisdiction of an NPDES

permit, a copy of the Notice of Intent shall be

provided to the inspector at this meeting.

Initial Erosion Control Installation: Initial scope of work shall be determined at the

preconstruction meeting. The permit card shall

be protected from the weather and posted in a

clearly visible location.

No other work shall be initiated until the erosion

control installation is completed, inspected and

approved.

After the installation of the E&S measures,

contact the City of Milton inspector for E&S

inspection and final grading permit approval.

Erosion and Sediment Control: For projects under the jurisdiction of an NPDES

permit a copy of the Engineers’ certification

stating the necessary erosion and sediment

control measures have been installed properly

shall be provided to the COM inspector within 7

days of the start of construction activities.

Periodic inspections will be made of the erosion

and sediment control devices without prior

notice. Failure to maintain BMP’s or follow the

approved plan shall constitute a violation and

may be subject immediate enforcement action.

Grading: Contact the Milton inspector 24 hours prior to the

initial grading. Inspector shall make periodic

inspections without prior notification.

Page 12: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 12 of 50

Storm Drainage: Contact the Milton inspector 24 hours prior to the

installation of any storm drainage system.

All pipe joints and junction boxes shall be

inspected after grouting , but prior to replacement

of backfill. DO NOT BACKFILL ANY

STORMDRAIN DRAIN LINES WITHOUT

PRIOR APPROVAL FROM THE MILTON

INSPECTOR.

Curb and Gutter: Contact the COM inspector 24 hours prior to the

installation of concrete.

Detention Point: Contact the COM inspector after the rough

grading has been completed.

Engineer’s certification and as-built drawings are

required for final approval.

Water: Contact the COM inspector 24 hours prior to the

initial installation.

Contact the COM inspector after the backflow

installation. A copy of the BFP testing report

shall be submitted to the COM inspector prior to

the issuance of a certificate of occupancy.

All thrust block shall be inspected by a COM

inspector on the fire lines

All fire mains 6: and larger shall be tested @200

psi for a minimum of 2 hours. All tests shall be

conducted in the presence of a COM inspector.

All water lines that have passed the pressure test

shall be flushed and chlorinated in accordance

with the standard construction specifications.

Bacteria test shall be submitted to the COM

inspector.

Water (continued): A COM inspector shall be present for all aspects

of construction for any water line to be dedicated

to the City of Milton.

Page 13: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 13 of 50

Paving: Contact the COM inspector 48 hours to the

placement of base material to schedule of proof-

roll of the subgrade.

A COM inspector shall be present for the

installation of the base, binder and surface

course.

Road cores shall be submitted for all road

sections, including deceleration lanes. Cores

shall be taken at minimum intervals of 300’ and

shall alternate sides of the road.

Core reports shall indicate the thickness of the

base. The thickness of the asphalt layers and the

level of compaction of the asphalt as a percentage

of the maximum theoretical compaction of the

asphalt.

Sidewalks: Contact the COM inspector after the forms have

been set.

Do not pour concrete until the forms have

been inspected and approved by a COM

inspector.

Contact the COM inspector after the sidewalk has

been poured.

Dumpster Pad: Contact the COM inspector after the forms have

been set.

Do not pour concrete until the forms have

been inspected and approved by a COM

inspector.

Contact the COM inspector after the pad has

been poured.

Striping: All striping within the right-of-way shall be pre-

marked and approved by the COM inspector

prior to final striping.

Contact the COM inspector after the striping has

been completed.

Page 14: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 14 of 50

Driveway Apron: Contact the COM inspector after the forms have

been set.

Do not pour concrete until the forms have

been inspected and approved by a COM

inspector.

Contact the COM inspector after the apron has

been poured.

Retaining Wall: Concrete: Contact the COM inspector 24 hours

prior to the placement of any concrete to inspect

the formwork and steel installation.

Do not pour concrete until the forms have been

inspected and approved by a COM inspector.

Other: Contact the COM inspector 24 hours

prior to the placement of any backfill to inspect

the foundation and tie-back installation.

Contact the COM inspector after the completion

of work.

Utility Cuts: Open cuts in existing paving must have prior

written approval from the City of Milton

Transportation Engineer.

Utility cuts must be backfilled and covered at the

completion of each day’s work.

COM shall inspect the installation and

compaction of the base material and shall be

present when the concrete cap is installed.

Sanitary Sewer: All sanitary sewer inspections are performed and

approved by Fulton County.

Trench: All trench activities must have a specific

trenching permit prior to commencing.

Trench permits shall only be issued to qualified

persons. The Qualified Person must be onsite

at all times when trenching activities are

under way.

A trenching permit may be obtained from the

designated COM inspector.

Page 15: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 15 of 50

DRAINAGE CHECKLIST FOR LAND DISTURBANCE PERMIT

Project Name: _____________________________________________ Date: _____________________

Project Number: ___________________________________________ Telephone: ________________

Reviewed By: _____________________________________________ Email: ____________________

A. General

1. For all permit revisions, submit a letter stating the proposed changes. These changes should be

highlighted on all sheets affected.

2. Minimum culvert size shall be 18”, and maximum velocity shall be 15 ft./sec.

3. Locate catch basins with 600 feet maximum spacing, designed for 10-year storm with a maximum

gutter spread of 8 feet.

4. Show nearest existing catch basin and/or drop inlets that receive water from this development.

5. Provide design calculations for all storm drainage pipes. Storm drainage pipes shall be designed

for 25-year storm frequency.

6. Culverts beneath roads shall be designed to convey the 100-year storm. Show analysis/effects of

100-year storm.

7. Provide design calculations for all ditches and channels. Ditches and channels shall be designed

for 25-year storm frequency. Show sod ditch detail if necessary.

8. Provide back water effect due to constriction of pipes in ditches or swales. Limit backwater to

within the property.

B. Storm Drainage

1. Show existing and proposed contours, clearly distinguishable.

2. Identify drainage structures as existing or proposed.

Page 16: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 16 of 50

3. Show drainage easements drawn with width dimensions specified. Typical D.E. width is 20 ft.

maximum.

4. Delineate and label any flood zone within the site.

5. Show the limits of proposed construction to be permitted.

6. Profile all existing/proposed storm pipes above which land disturbance will occur.

7. Reference all storm drainage structures (i.e. catch basins, drop inlets, headwalls, etc.) to Milton or

GDOT for all work in the ROW. Provide complete detail(s) if an alternate design is used within the

site and is not a public standard.

8. Storm drainage structures are not allowed within the radius of a curb.

9. Provide outlet velocity at outlet structures (i.e. storm drainage profile).

10. Storm drainage structure shall discharge into natural draws or drainage channels/swales.

C. Storm Drainage Pipe Design

1. 30” maximum cross drain pipe draining through standard catch basins or drop inlets. When larger

diameter is required, provide design and detail of all structures.

2. Storm drain cross section

A. Minimum pipe cover:

1. Storm drains: 18: outside roadway, 36” within roadway (see GDOT specs and

details).

2. Berming or trenching is not allowed to achieve minimum or maximum cover.

B. Minimum pipe slopes:

1. Concrete or smooth walled HDPE 0.5%

2. CMP 1.0%

3. All storm crossings under public roadways shall be reinforced concrete pipe, class per GDOT

specs and details.

4. Storm pipe material types, directional changes, slope changes or transitions are permitted only at

drainage structure with surface access (i.e. junction box with manhole, catch basin, etc.). Concrete

collars are not acceptable at transitions.

5. Show size, material type, class or gauge, percent slope, and length of all pipes.

6. Provide invert elevations and top elevations of drainage structures.

7. Anchor collars are required on storm pipes when the slope is greater than 30%.

Page 17: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 17 of 50

D. Ditches and Swales

1. All proposed swales and ditches shall have cross sections, centerline profiles, flow rates, and

velocities shown on plans.

2. If velocity in ditch is greater than 3 ft./sec., ditch invert shall have a no-erodible material.

3. Show drainage area, Q25 and headwater elevation at the inlet of all storm drain structures (include

accumulative areas and Q’s, and longitudinal system).

4. Indicate the type and GDOT standard number for inlet and outlet structures of all pipes.

5. All pre-cast M.H. shall be provided with a minimum of 9 inches clearance on each side of

connecting pipe between all cut-outs or penetrations.

6. Use online catch basins except for cul-de-sac applications in which one foot offset is required.

7. Show concrete spillway at the end of curb and gutter (as per GDOT Standard 9013, type III) where

applicable.

8. Use concrete flared end sections at driveway crossings within the right-of-way and other

applications adjacent to vehicular traffic (Ref. GDOT Standard 1120).

9. Engineer’s seal and signature required on all plans and reports.

E. Hydrology Report (Separate Checklist)

F. Drainage and Earthwork Notes

1. GDOT structures must be used within the ROW.

2. GDOT specifications, standards and details on projects in the City of Milton.

3. All areas to receive structural fill shall be cleared, stripped and free of topsoil, roots, stumps and

all other deleterious material. Structural fill shall be clean from organics and all other deleterious

material. Fill shall be placed in maximum 8” lifts and compacted to at least 95% standard procotor

maximum density and to within =/- 3% of the optimum moisture content, unless otherwise specified

in the project geotechnical report or by the project geotechnical engineer. All fill soils are to be

placed under the observation of the project geotechnical engineer. Documentation of compaction

testing shall be provided to the Land Disturbance Activity Inspector for all roadway construction in

the right-of-way (including deceleration lane). Contact Land Disturbance Activity Inspector prior to

construction for further testing requirements.

Page 18: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 18 of 50

4. Failure of the contractor to perform the prescribed erosion control practices shall result in the

immediate issuance of a stop work order for the project site, pursuant to Section 5-103 (B) of the City

Code.

5. Maintenance of all soil erosion and sedimentation control practices, whether temporary or

permanent, shall be the responsibility of the contractor.

6. All disturbed areas must be vegetated within 14 days of final grade.

7. All fill slopes shall have silt fence at the toe of slope.

8. The escape of sediment from the site shall be prevented by the installation of erosion and sediment

control measures and practices prior to, or concurrent with, land-disturbing activities.

9. Erosion control measures will be maintained at all times. If full implementation of the approved

plan does provide for effective erosion control, additional erosion and sediment control measures

shall be implemented to control or treat sediment source.

10. The contractor shall remove the sediment once it has accumulated to one-half the original height

of the silt fence used for erosion control.

11. Maximum cut or fill slopes are 2 (horizontal) and 1(vertical).

12. Any disturbed area left exposed for 14 days shall be temporarily stabilized with seed or mulch.

13. All silt fencing shall be Type C.

14. The construction exit shall be maintained in a condition, which will prevent tracking or flow of

mud onto public right-of-way. This may require periodic top-dressing with stone, as conditions

demand. (All materials spilled, drop washed, or tracked from vehicle or site onto roadway or into

storm drain system must be removed immediately by sweeping).

15. All storm drains and drop inlets will have 4” permanent pollution prevention markers installed

prior to inspection. Markers are available at City of Milton Public Works Department.

16. The contractor shall maintain storm water runoff controls at all times. Additional controls will be

installed if deemed necessary by City inspection.

17. Erosion control matting shall be installed on all slopes steeper than 3:1.

18. This site does not contain any state waters or wetlands.

19. On site burial is not allowed.

20. Mulch storage must comply with the following section of the standard fire prevention code

section 502.3.1: No person shall store in any building or upon any premise in excess of 2,500 cubic

Page 19: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 19 of 50

feet gross volume of combustible empty packing cases, boxes, barrels, or similar containers, or rubber

tires, rubber or cork or similarly combustible materials with a permit.

21. Two copies of the NPDES Notice of Intent must be provided to the Land Disturbance Inspector

prior to initiating construction for sites over 1 acre disturbed area.

22. Irrigation systems are not allowed within the public right-of-way.

Page 20: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 20 of 50

LANDSCAPE AND TREE PROTECTION CHECKLIST

Project Name: _____________________________________ Date: ___________________________

Project Number: ___________________________________ Tax ID #: ________________________

Reviewed By: _____________________________________ Telephone: _______________________

Overlay District: ___________________________________ Show compliance.

Zoning: __________________________________________

Zoning Case # (As applicable): ________________________

Initial Arborist Site Visit Requirement

Applicant may be required to meet with the Community Development Department Arborist to

perform an on-site evaluation prior to submitting plans for LDP review. To schedule an on-site

evaluation, call (678)242-2552.

Per Article 34.4.1.d of the City of Milton Zoning Ordinance, Show a Separate Sheet Dedicated to a

Tree Protection and Landscape Plan

A Tree Protection Plan may be submitted either as part of the landscape plan or as a separate

drawing. Refer to the City of Milton Tree Preservation Ordinance Chapter 14, Article 8 for

guidance.

Please address all items marked with an “X”

Landscape Plan Requirements

1. Include all required undisturbed buffers, landscape strips, and parking islands with the

required dimensions. These requirements must be drawn and dimensioned on all sheets

submitted for a permit.

2. Include planting list with proposed plant material names (common and botanical), quantity,

size, and any special planting notes.

3. Include planting detail.

Page 21: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 21 of 50

4. Include location of any proposed irrigation systems, if applicable. Drawings for irrigation

systems must show the locations of the lines, spray radius, shut off valves, timers, and a 24-

hour emergency contact number. Spray heads or other above ground irrigation equipment

must not be located in the rights-of-way.

5. All required landscape strips must be planted at a density so as to provide at least 60%

spatial coverage in trees and shrubs, with no more than 40% grass, so, or other ground

cover. Show the calculations on the plan.

6. All required buffers must be planted or replanted to buffer standards unless existing

conditions meet or exceed these standards.

7. Detention Pond Requirements: A 20-foot wide landscape strip planted to buffer standards

shall be provided around the exterior of all detention areas adjacent to and outside of the

required 10-foot wide access easement, or as may be approved by the City of Milton

Arborist (Zoning Resolution 34.5.4).

8. Parking Islands must be provided as required by conditional zoning or section 4.23.2 of the

Zoning Resolution. Parking islands must be planted with 2” caliper shade trees as

approved by the City Arborist. Parking islands must be a minimum of 10 feet wide.

9. Permanent structures cannot be permitted in landscape strips, parking islands, improvement

setbacks or buffers, including but not limited to walls, fences, headwalls, drop inlets, catch

basins, riprap, light fixtures, phone booths, etc. Monument signs, drainage structures, and

sidewalks may be allowed with pre-approval in landscape strips only.

10. Curb stops must be used to prevent vehicle overhang into required landscape and parking

islands. One curb stop per parking stall is required.

Tree Protection Plan Requirements

1. Include all tree protection zones and label all tree save areas (even in ROW, adjacent to

sidewalk) and show areas of re-vegetation.

2. Indicate exact location of all specimen trees onsite as verified by a field run survey. On the

site plan, include the size of each specimen tree and indicate whether the specimen tree is

to be saved or removed.

3. Healthy specimen trees impacted by land disturbance will have to be recompensed with a

tree unit value that is equal to the value of the tree being removed. Replacement trees shall

be 4” caliper or 2” caliper unit. Unit value of a 2” caliper recompense tree is .35, exactly ½

that of a 4” tree. In addition, recompense trees have to be paid to the City of Milton Tree

Fund prior to the issuance of a Land Disturbance Permit. (LDP)

4. Include limits of clearing and land disturbance such as grading, trenching, etc., where these

disturbances may affect tree protection zones.

Page 22: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 22 of 50

5. Indicate the proposed locations of all underground utilities. Tree save areas cannot be

considered in utility easements.

6. Methods of tree protection shall be indicated for all tree protection zones, including tree

fencing, erosion control, retaining walls, tunneling for utilities, aeration systems,

transplanting, staking, signage, etc. Show detail of tree protection.

7. This plan should indicate staging areas for parking, materials storage, concrete washout,

and debris burn and burial holes because these areas might affect tree protection.

8. The required site tree density factor must be satisfied. Compliance shall be demonstrated

on the tree protection plan. Existing trees or stands of trees used in the density calculation

must be indicated on the drawing. Flowering ornamental replacement trees may not be

used in density calculations. If enough existing trees are not saved in order to meet density,

the replacement tree cost must be paid to the City of Milton Tree Fund prior to issuance of

the LDP.

9. Replacement trees used in density calculations must be ecologically compatible with the

intended growing site.

Include These Notes on the Tree Protection/Landscape Plans

1. Provisions for tree protection on the site shall be, as a minimum, in conformance with the

requirements of the latest edition of the City of Milton tree preservation ordinance and

administrative guidelines pertaining to tree protection.

2. If the landscape design and plant material are changed from the permitted plan, you shall submit

three (3) sets of revised plans to the City of Milton arborist’s office for approval, prior to any

landscape installation.

3. All landscaping for each phase of development shall be completed prior to the recording of the

final plat for that phase, prior to the issuance of Certificate of Occupancy for that phase, or prior

to connection of permanent power for that phase. Contact the City of Milton Arborist at

(678)242-2552 for site inspection upon completion of landscape installation.

Include These Notes on BOTH the Tree Protection/Landscape Plan and the Grading Sheet

1. Contact the City of Milton Arborist at (678)242-2552 to determine if a pre-construction meeting

prior to any land disturbance is required. All required tree fence must be installed prior to this

meeting.

2. Undisturbed buffers shall be planted to buffer standards where sparsely vegetated or where

disturbed due to approved utility crossings. Replanting is subject to city arborist approval. (Do

not plant trees within the sanitary sewer easement).

Page 23: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 23 of 50

Stream Buffer Projection Standards

All State Waters (as defined by O.C.G.A. 12-7) require a minimum undisturbed vegetative buffer

fifty (50) feet wide and an impervious setback of twenty-five (25) feet measured from the top of

the bank of both sides of the stream or edge of water (i.e. lake/pond). The Director of

Community Development or their designee shall make the determination as to whether or not a

feature is considered state waters.

Page 24: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 24 of 50

HYDROLOGY CHECKLIST FOR LAND DISTURBANCE PERMITS

Project Name: _________________________________________________________________________

Project Number: ________________________________________ Date: _______________________

Reviewed By: __________________________________________ Telephone: ___________________

Email: _______________________________________________________________________________

Address all items marked with an “X”

Minimum Submittal Requirements

1. Conceptual Review Approval

2. Engineer’s Stormwater Management Report/Hydrologic Analysis (2 copies bound)

3. Construction plans bearing details of all stormwater management facilities and plans and profiles of

proposed storm sewer. (2 sets)

Stormwater Management Report Contents

1. Existing Conditions Analysis

A. Provide topographic map of existing conditions. Show the following on the map:

i. Delineate drainage boundaries (including offsite areas draining onto site) and

label/name each drainage area the same as each basin is labeled/named in

calculations and tabulations appearing elsewhere in the report.

ii. Indicate acreage of each delineated drainage area.

iii. Indicate CN for each delineated drainage area.

iv. Indicate tc for each delineated drainage area.

v. Indicate runoff travel path and correlate to calculations determining tc for each

drainage area.

vi. Indicate land cover condition for each drainage area.

Page 25: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 25 of 50

vii. Map shall have border, project name, narrow, scale and title (minimum size 11 x 17).

B. Provide summary table of peak rates of runoff from each delineated drainage area for 1, 2, 5,

10, 25, 50 and 100 year storm events. Include in summary table for each drainage area the

following data: label/name of drainage area, acreage, CN, tc, gross rainfall amount for each

storm event, and peak flow rate for each storm event (cfs).

C. Provide time of concentration determination calculations for each drainage area.

2. Post Development Conditions Analysis

A. Provide topographic map of developed conditions. Show the following on the map:

i. Delineate drainage boundaries (including offsite areas draining onto site) and

label/name each drainage area the same as each basin is labeled/named in

calculations and tabulations appearing elsewhere in the report.

ii. Indicate acreage of each delineated drainage area.

iii. Indicate CN for each delineated drainage area.

iv. Indicate tc for each delineated drainage area.

v. Indicate runoff travel path and correlate to calculations determining tc for each

drainage area.

vi. Indicate land cover condition for each drainage area.

vii. Delineate and label/name each stormwater management facility.

viii. Indicate all outflow locations for each stormwater management facility.

ix. Maps shall have border, project name, narrow, scale and title (minimum size 11 x

17).

B. Provide a summary table of peak rates of runoff from each delineated drainage area for 1, 2,

5, 10, 25, 50 and 100 year storm events. Include in summary table for each drainage area the

following data: label/name of drainage area, acreage, CN, tc, gross rainfall amount for each

storm event, and peak flow rate for each storm event (cfs).

C. Provide a summary table of developed peak rates of runoff vs. existing peak rates of runoff

for each drainage area. Demonstrate no increase in peak rates of runoff for 1, 2, 5, 10, or 25,

50 and 100 year events for each drainage area.

D. Provide tabular hydrograph output for drainage area(s) draining to each stormwater

management facility for the 1, 2,5, 10, 25,50 and 100 year events.

Page 26: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 26 of 50

E. Provide tabular hydrograph output for outflow (routing) of each stormwater management

facility for the 1, 2, 5, 10, 25 and 100 year events.

F. For any bypass area hydrograph that is combined with a stormwater management facility

outflow hydrograph, provide the tabular hydrograph output for the bypass area for the 1, 2, 5,

10, 25 and 100 year events. Provide the tabular hydrograph output for each combined

hydrograph.

G. Provide time of concentration determination calculations for each drainage area.

H. For each stormwater management facility provide Stage/Storage/Outflow tabulation and

outlet configuration data used for routing each stormwater management facility.

I. Provide Water Quality Volume (WQV) calculations in accordance with the Georgia

Stormwater Management Manual (GSMM). Orifice shall be to the nearest inch.

J. Provide Channel Protection Volume (CPV) calculations in accordance with the Georgia

Stormwater Management Manual (GSMM). Orifice shall be to the nearest inch.

K. Provide 48 hour extended detention orifice sizing calculation.

L. Provide details for outlet control structures/devices for each stormwater management facility

on plans and in stormwater management report. Ensure details on plans agree with details in

report. Label structures so plans and details in report and on plan can be easily correlated.

3. Post Development Downstream Analysis

A. Provide analysis of downstream conditions at each point or area along project boundary at

which runoff will exit the property.

B. Extend analysis of downstream conditions to include all portions of the downstream

conveyances between the site and the point where the site area is 10 % of the total basin area.

C. Compare capacity vs. designed flows for each downstream conveyance between site and 10%

point.

4. Minimum Hydrology Design Parameters

A. Existing condition, previous vegetated areas minimum CN = 55 (for >5ac use SCS Method

or C = 0.3 if <5 ac). Use rational method.

B. Existing condition time of concentration determination shall be in accordance with Section

2.1.5.6 in the Georgia Stormwater Management Manual (GSMM). Sheet/ Overland flow

lengths less than 100 feet used in GSMM equation 2.1.9 shall be justified in stormwater

management report. Use of exiting time of concentrations greater than calculated in

accordance with GSMM 2.1.5.6 is acceptable.

C. Minimum freeboard for above ground earthen stormwater management facility dams is 2 feet.

Page 27: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 27 of 50

D. Minimum freeboard for concrete stormwater management containment facility is 1 foot.

5. Hydrology and Drainage Items

A. Show a 20 ft., graded (max 16% slope) and stabilized access easement to all stormwater

management facilities from a location of public vehicle access.

B. Provide a 20 ft. landscape strip as required by the City Arborist around the exterior of all

detention areas adjacent to and outside the required 10 ft. access easement.

C. Show a six foot high security fence with a 10 ft. access gate outside the ten foot access

easement around each detention pond. Show the location of the access gate.

D. Provide Standard 908 Detail for Earth Fill for Detention Ponds or other detail that meets the

minimum standards inherent in standard 908.

E. State the Water Quality Volume, the Channel Protection Volume, the 25-year volume, and

the 100- year volume on the plans. State the Water Quality elevation, the Channel Protection

elevation, the 25-year Elevation and the 100-year elevation on the plans.

F. Eliminate proposed concentrated discharge from site where existing condition is sheet flow.

G. When serving more than three lots, detention ponds shall be located on a separate parcel

where no home can be constructed.

H. Provide design engineer’s profession seal and signature on plans and report.

6. Inspection and Maintenance Agreement (Milton Zoning Ordinance Chapter 20)

A. An Inspection and Maintenance Agreement for all stormwater management facilities must be

approved by the Community Development Department before permitting.

B. State name and official title of person(s) responsible for carrying out inspection and

maintenance.

C. Responsibility shall remain with property owner and shall pass to any successor owner.

D. Include schedule for when and how often routine inspection and maintenance will occur.

E. Include plans for annual inspections and include remedies for default.

F. Agreement shall be recorded before final plat approval for residential developments, and

before certification of occupancy for other developments.

4E. Proprietary Water Quality Devices

Page 28: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 28 of 50

Require third party data backup and proof submitted to City. This must meet 3.3.10.2 of

the Blue Book.

Require LDP engineer sizing calculation according to Blue Book Chapter 3.

Commercial use only at this point in time. Proof of maintenance contract provider

required to be kept current with the City.

5I. TSS Excel Chart

The Use of the TSS Chart is required to be submitted at this point in time. Staff

understands that certain Milton specific locations may be difficult to get using 80% using

this urban-situation developed chart. Staff will take interpretive decisions based upon the

intent of the Blue Book stormwater practices.

4G. Bypass

Bypass must be detained if it leaves the site.

Location within the drainage basin will be considered on a site by site analysis. It is

understood by Staff that Milton has some unique topography limitations not completely

covered in the Blue Book.

4F. Individual Lots

For new subdivisions greater than 3 lots, detention is required on a separate lot (AG

zoning)

For small “minor” subdivisions, onsite BMP’s are acceptable.

BMP’s which require maintenance (other than mowing) and are located on an individual

lot are required to have a maintenance program included on the deed of the lot. Proof of

deed encumbrance is required. Otherwise BMP’s are not acceptable on individual lots.

4D. Detention Ponds

Residential Detention Ponds may not have (precast) walls without special application. A

more natural look is desired for these settings.

Commercial Detention Ponds with greater than 50% perimeter precast concrete wall

ponds are unacceptable. For this level of urban look, underground detention is required.

6G. O&M Manual is required to be recorded with the HOA agreement.

Page 29: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 29 of 50

FLOOD PLAIN CHECKLIST

Project Name: __________________________________________ Tax ID #: _________________

Project Number: ________________________________________ Date: _____________________

Reviewed By: __________________________________________ Telephone: ________________

Please address all items marked with an “X”

_____ 1. General (all projects)

A. Provide F.E.M.A. Flood Insurance Rate Map (F.I.R.M.) excerpt on the cover sheet

for the subject site development plans on which the site is delineated.

B. Provide statement below F.E.M.A. F.I.R.M. excerpt on cover sheet of plans:

“This site [is/is not] located within a zone [A, AE, shaded zone X] as defined by

F.I.R.M. Community Panel Number(s) ________________ for unincorporated

Fulton County, GA (Use September 18, 2013 map).”

_____ 2. Flood Zone AE within site:

A. Clearly delineate flood zone extents and both the existing and proposed 100 year

flood elevations on plans.

B. Provide project benchmark with elevation, tied to Milton or Fulton County G.I.S.

monument. Use N.G.V.D. or Mean Sea Level Datum.

C. If the proposed work encroaches within Zone AE, the following is required:

1. Professional Engineer’s certification that the proposed work will not:

a. Raise the base flood elevation outside the property limits

b. Reduce the flood storage capacity in the flood plain (fill placed

within flood plain must be compensated and all cut areas must

gravity drain to watercourse)

c. Impede the movements of flood waters

d. Create hazardous or erosion-producing velocities

Page 30: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 30 of 50

2. Flood study, prepared by Professional Engineer, substantiating the

certification.

3. At the request of Milton, application to F.E.M.A. for a conditional F.I.R.M.

revision to be submitted to F.E.M.A. through Milton.

D. Provide a RECORDED copy of the Milton Flood Plain Indemnification Agreement.

_____ 3. If Flood Zone A and/or shaded Zone X exists within site:

A. Clearly delineate flood zone extents and both the existing and proposed 100 year

flood elevations on plans.

B. Provide project benchmark with elevation, tied to Milton or Fulton County G.I.S.

monument. Use N.G.V.D. or Mean Sea Level Datum.

C. Provide flood study prepared by a Professional Engineer that determines both the

existing and proposed extents and elevations of the flood zone.

D. Locate all flood study sections on the plans and state the existing and proposed flood

elevations at each section.

E. If the proposed work encroaches within Zone A or shaded Zone X, the following is

required:

1. Professional Engineer’s Certification that the proposed work will not:

a. Raise the base flood elevation outside of the property limits

b. Reduce the flood storage capacity in the flood plain (fill placed

within flood plain must be compensated and all cut areas must

gravity drain to watercourse)

c. Impede the movement of flood waters

d. Change the flow characteristics of the flood waters

e. Create hazardous or erosion-producing velocities

F. Provide a RECORDED copy of the Milton Flood Plain Indemnification Agreement.

_____ 4. State the “lowest floor elevation”, including basement and attached garage for each lot affected

by the flood plain.

_____ 5. Per article 4.24.9G of the Zoning Ordinance, certify and submit calculated areas to demonstrate

that no lot area has less than 50% of the minimum lot area (as established by the applicable

zoning district regulations) above the base flood elevation, and/or no less than 70% of the

buildable land area of any lot lies above the base flood elevation by a minimum of one foot.

Page 31: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 31 of 50

_____ 6. Show the following NOTES on the construction plans:

A. The flood zone(s) __________ shown hereon are based on the Fulton County

Community Panels 9F.I.R.M.) [Numbers/Numbers] __________.

B. The base flood (I.R.F.) elevations shown heron are based on the flood elevation study

by ______________________, etc.

OR

The base flood (I.R.F.) elevations shown hereon are based on the flood insurance

studies for unincorporated Fulton County.

C. All construction including grading and filling within the flood plain shown hereon

shall be in conformance with the Milton Zoning Ordinance Article 4, Section 24.

D. All cut and fill within the flood plain shall be field verified and certified by a

Professional Engineer.

E. All intermediate regional flood plain shall be field located and staked prior to

encroachment within them. Such location shall be maintained clear and visible

throughout construction and final approval.

F. When utility (storm drains, sewers, etc.) construction is within a flood plain:

1. The contractor shall restore the flood plain to the original condition and

grade immediately upon completion.

2. Upon completion of restoration, a Professional Engineer shall certify in

writing to the Community Development Department that all work is

complete and the flood plain is restored.

G. The lowest floor elevation includes basement and attached garage.

_____ 7. Show the limits of construction and the quantities of cut/fill proposed within the flood plain

on the construction plans. Show a grading plan with quantities and proposed contours for the

area where the compensating cut is to be made. When fill or cut is proposed within a flood

plain, a plan and profile based on field run cross section shall be submitted as part of the land

disturbance permit. The horizontal and vertical scales shall be such that the contractor can

clearly determine the extent and amount of work and such as to facilitate the engineer in

submitting the required certification.

_____ 8. Disturbance of 50 foot Milton Stream Buffer requires a City of Milton – Board of Zoning

Appeals variance.

_____ 9. Disturbance of the 25 foot State of Georgia buffer requires a variance from the GA DNR –

Environmental Protection Division. Obtain prior to submitting to the Milton Board of Zoning

Appeals.

Page 32: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 32 of 50

TRANPORTATION CHECKLIST FOR LAND DISTURBANCE PERMITS

Project Name:_____________________________________ Date: ___________________________

Permit Number: ___________________________________ Telephone: _______________________

Reviewed By: _____________________________________ Email: __________________________

Overlay District: _______________________________________________________________________

Note: The Following abbreviations are used in the checklist:

MUTCD – Manual of Uniform Traffic Control Devices. A signing and striping reference document

produced by the Federal Highway Administration.

AASHTO – A Policy on Geometric Design of Highways and Streets, by American Association of State

Highway Transportation Officials.

R/W – Right of Way

GDOT – Georgia Department of Transportation

Please address all items marked with an “X”

GDOT Driveway Permit Number: ________________________________.

This development accesses on a road maintained by GDOT and/or a City road with a currently

programmed state improvement project. Provide GDOT driveway permit number and approval. No

Land Disturbance Permit will be issued showing roadway improvements until GDOT plans and

approval are presented to Milton Department of Community Development.

GDOT R/W Dedication and Reservation

Plans must show GDOT mandated R/W dedications and reservations for all projects adjacent to any

road maintained by GDOT and/or any City road with a currently programmed state improvement

project.

Page 33: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 33 of 50

Traffic Control Plan

A separate sheet dedicated to a Traffic Control Plan should be submitted with the Land Disturbance

Permit approval drawings if the improvements associated with the development will create the need

for supplemental road improvement, signing, or striping of a City road which will either be accessed

on or dedicated by the development. The plan should be at a scale of between 1: = 20’ and 1” = 60’,

contain a location map and north arrow. It must include all warning devices, barricades, signage, and

operational changes to all affected roads, including any necessary detour routes. All work zone

signage and marking must conform to the MUTCD. An 8 x 11 copy of this plan is required when

ROW Encroachment Permit is filed by the Contractor.

AASHTO COMPLIANCE

All road designs shall conform to AASHTO and these checklist items as a minimum. Revise plans to

conform to AASHTO requirements noted in the review.

Plan Conventions. All plans must include a north arrow (oriented to the top or right of the sheet),

location map, and scale of between 1: = 20’ and 1” = 60’.

A. Curb Cuts

1. Show all existing and proposed curb cuts which are within 300 feet of proposed

driveway(s) along property frontage.

2. Dimension distance from centerline of project curb cuts to existing and/or proposed curb

cuts.

3. Show angle of incidence of centerline of driveway and entrance, with centerline of road.

4. Show width of driveway entrance from back of curb to back of burb. Driveway widths

must conform to Milton Driveway Manual and Standard Details.

5. Show concrete apron per Milton Standard Details. For private residential street entrances

and commercial and industrial entrances; add this detail to your plans.

6. Show right-/right-out only curb cut design per Milton Standard Details; add this detail to

your plans. Provide inset detail with dimensions and at least one coordinate for stake-

out.

7. Show any proposed walls and/or fences along the property frontage. No portion of the

fence or wall may be closer than 3’ to the R/W line. If the fence is located within the

R/W reservation, an agreement must be filed, before LDP issuance, that the fence will be

removed at no cost to the City at any future time that the City may purchase the

reservation. Such agreement must be filed with the City Clerk and the Department of

Public Works and tied to the property deed.

8. Show separate dimensioned entrance detail for all gated entrances. Provide gate permit

application.

Page 34: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 34 of 50

B. Roadway Construction/Drainage

1. Show proposed improvement(s) on City roads dimensioned from legal centerline of road.

Include deceleration, left turn lanes, road widening, and other improvements as required

by Milton Driveway Manual. All improvements must conform to Milton Standard

Details.

2. Show how the proposed road improvement(s) will be tied into the existing conditions, on

the City road at the limits of the property frontage with the adjacent parcel(s).

3. Show Milton Standard Details, for pavement.

4. Show typical Milton standard cross-section as required.

5. Subdivision mass grading is not acceptable. Redesign to show road clearing only. Lots

require individual site plans.

C. Signing/Striping

1. Show legal centerline of all existing and proposed City roads. Show speed limits for all

roads (existing and proposed); locate any adjacent speed limit signs; label proposed as

future public or private.

2. Show deceleration land(s) striping and signage, if required. Show signing and striping on

the plans per Milton Standard Details and the MUTCD.

3. Show left turn land(s) striping and signage, if required. Show signing and striping on the

plans per Milton Standard Details and the MUTCD.

4. Show striping plan for frontage resurfacing. Show signing and striping on the plans per

Milton Standard Details.

D. Sight Distance

1. Intersection Sight Distance Profile

Show intersection sight distance (not to be confused with stopping sigh distance) of each

proposed intersection entrance, street or driveway.

Intersection sight distance is determined with an assumed height of driver’s eye of 3.5

feet and an assumed height of object of 3.5 feet when measuring in the vertical plan.

When measuring in the horizontal plane, the intersection sight distance is determined

with an assumed driver’s eye location from a point 4’ offset from the centerline and 15’

from the edge of closest travel lane to a point along the centerline of the closest

oncoming travel lane. When measuring in either plane, the line of sight must remain in

the proposed standard dedicated ROW and may not be obstructed by monuments, walls

fences, trees, hedges, or other visual impediments/obstructions.

Page 35: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 35 of 50

2. Show Sight Triangles shown on tree plans and site plan. Show proposed wall and sign

locations outside the sight triangle.

E. Right of Way / Utilities

1. Show proposed R/W dedication and reservation, dimension from centerline.

2. Show a 10.5 foot R/W shoulder dimensioned from the back of curb of all road

improvements, if the road improvement plus 10.5 feet will be greater than the proposed

R/W dedication.

3. Show R/W miter at external street intersections of at least 20 feet radius. Ensure

intersection site distance, free of obstructions, is provided.

4. All utility locations must conform to Milton Standard Details; add this detail to your

plans. Specify which trench detail (based on site utility needs) on utility plan.

5. Show R/W widths for all proposed streets and cul-de-sacs per Milton Standard Details,

Subdivision Regulations, and Driveway Manual.

F. Vertical Alignment (for internal streets)

1. Minor street (44’ ROW) = 15% maximum grade

All grades exceeding 12% shall not exceed a length of 250 feet.

Minimum: K > 12 sag

K > 16 rest

2. Show minimum centerline profile and longitudinal gutter slopes with grade of at least 1

percent when used as a tangent.

3. Show minimum Vertical curve lengths, per Milton Subdivision Regulations.

4. Show compliance with Milton Subdivision Regulations for leveling course design at

approaches to an intersection.

5. Show 4% max break at side road intersections with mainline for a minimum distance of

50 feet.

G. Horizontal Alignment (for internal streets)

1. Show minimum horizontal centerline curve radius, per Milton Subdivision Regulations.

2. Show minimum tangent lengths between reverse horizontal curves of 100 feet, per

Subdivision Regulations.

Page 36: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 36 of 50

3. Show desired ninety degree angle of incidence between intersections, per Subdivision

Regulations.

H. Traffic Report

See separate checklist.

I. Signal Permit

See separate checklist

J. Notes: Show the following notes on the plans prior to approval:

1. GDOT structures required in the Right-of-Way. All pavement work shall be saw cut.

2. GDOT specifications, standards, and details on projects in the City of Milton.

3. New pavement/surfacing is required across all property frontages to existing centerline,

to be installed per Milton Standard Details or as additionally directed by Milton Traffic

Engineer.

4. Striping (white and yellow) and arrow marking shall be applied using GDOT standards

for thermoplastic striping for all work in the ROW. Work within the site may be traffic

paint.

5. When necessary, existing striping shall be removed by grinding, unless specified by

Milton Traffic Engineer.

6. All final signage must be installed concurrently with the performance of the striping

work.

7. Separate R/W permit is required for construction and signage.

8. HC detectable warning devices must be either tile or paver type. Stamped warnings are

not acceptable.

9. Engineering Testing is required for sub-base, base, and asphalt/concrete. Include

Engineering Testing Guidelines.

10. Notify City Engineer and City Inspector 24 hours prior to every phase of construction.

11. Off-street parking shall be provided and maintained throughout construction.

12. Upon completion of construction, the project engineer shall submit to Community

Development Department and as-built set of plans and certification.

13. All radi and pavement widths are measured back of curb unless otherwise noted.

Page 37: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 37 of 50

14. If signs, striping and modifications to traffic control are required as part of this

development, control must be complete and approved by City Traffic Engineer prior to

occupancy.

15. Road on lane closure is not permitted during the hours of 7 am – 9 pm and 4pm – 7 pm

(or other hours as directed by the Community Development Department).

16. All water meters shall be relocated outside of sidewalk.

17. All standard highway signs shall be fabricated and erected in accordance with the details

shown in the plans, the manual on uniform traffic control devices, current edition, and the

Georgia standard specifications, supplemental specifications, and/or special provisions.

18. Sign erection locations are approximate and may be adjusted to meet field conditions

where necessary, but shall be within the limitation set forth in the manual on uniform

traffic control devices, current edition, no sign location shall be changed by the

contractor or by the project engineer without prior approval from the office of traffic

operations.

19. All standard highway signs shall be erected at a height of 7 feet above the normal edge of

pavement to the bottom of the sign or assembly.

20. Horizontal clearance for standard signs on all other roadways shall be 6 fee from the edge

of paved shoulder or 12 feet from the normal edge of pavement to the nearer edge of the

signs, whichever is greater, the horizontal clearance in non-mountable curb sections shall

be at least 2 feet from the curb face to the nearer edge of the signs.

21. Type III (encapsulated lens) reflective sheeting shall be used for all standard highway

signs requiring reflectorized backgrounds except as specified below or specified

otherwise in the plans. Either class 1 or class 2 adhesive backing is permissible.

22. Type VI (wide angle prismatic) reflective sheeting shall be used for all red series signs

(R1-1, R1-2, R1-3A, R1-4A, R5-1)

NOTE:

All water meters, water valves, fire hydrants, and sanitary

sewer manholes are to be adjusted to grade unless

otherwise noted.

Page 38: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 38 of 50

STORMWATER MANAGEMENT/BMP

FACILITIES COVENANT

City of Milton, GA

Community Development Department

(678) 642-2500

THIS INSTRUMENT, made and entered into this ________ day of ________________, 20____,

by and between (Insert Full Name of Owner) _______________________________________

hereinafter called the “Landowner”, and the City of Milton, Georgia, hereinafter called the “City”.

WITNESSETH, that

WHEREAS, the Landowner is the owner of certain real property described as (Fulton County Tax

Map/Parcel Identification Number) ___________________________________________________ as

recorded by deed in the land records of Fulton County, Georgia, Deed Book __________, Page

___________, hereinafter called the “Property”; and

WHEREAS the Landowner is proceeding to build on and develop the property; and

WHEREAS, the Site Plan/Subdivision Plan known as _______________________________ (Name of Plan/Development)

hereinafter called the “Plan”, which is expressly made a part hereof, as approved or to be approved by the

City, provides for the treatment and/or detention of stormwater within the confines of the property; and

WHEREAS, the City and the Landowner, its successors and assigns, including any homeowners

association agree that the health, safety and welfare of the residents of the City of Milton, Georgia,

require that on-site stormwater management/BMP facilities be constructed and adequately maintained on

the Property; and

WHEREAS, The City requires that onsite stormwater management/BMP facilities as shown on the Plan

be constructed and adequately maintained by the Landowner, its successors and assigns, including any

homeowners association; and

WHEREAS, Landowner, its successors and assigns, understand the execution and adherence to the

provisions of this Instrument is a condition precedent to the City’s permitting of the contemplated

development;

Page 39: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 39 of 50

NOW, THEREFORE, in consideration of the foregoing premises, the mutual covenants contained

herein, and the following terms and conditions, the parties hereto agree as follows:

1. The on-site stormwater management/BMP facilities shall be constructed and operated by the

Landowner, its successors and assigns, in accordance with the plans and specifications identified in

the Plan.

2. The Landowner, its successors and assigns, including any homeowners association, shall adequately

maintain the stormwater management/BMP facilities. This includes all pipes and channels built to

convey stormwater to the facility, as well as all structures, improvements, and vegetation provided to

control the quantity and quality of the stormwater. Adequate maintenance is herein defined as good

working condition so that these facilities are performing their design functions.

3. The Landowner, its successors and assigns, shall inspect the stormwater management /BMP facility

and submit an inspection report annually. The purpose of the inspection is to assure safe and proper

functioning of the facilities. The inspections shall cover the entire facilities, berms outlet structure,

pond area, access roads, etc. Deficiencies shall be noted in the inspection report.

4. The Landowner, its successors and assigns, hereby grant permission to the City, its authorized agents

and employees, to enter upon the Property and to inspect the stormwater management/BMP facilities

whenever the City deems necessary. The purpose of inspection is to follow-up on reported

deficiencies and/or to respond to citizen complaints. The City shall provide the Landowner, its

successors and assigns, copies of the inspection findings and a directive to commence with the repairs

if necessary.

5. In the event the Landowner, its successors and assigns, fails to maintain the stormwater

management/BMP facilities in good working condition acceptable to the City, the City may enter

upon the Property and take what steps are necessary to correct deficiencies identified in the inspection

report and to charge the costs of such repairs to the Landowner, its successor and assigns. This

provision shall not be construed to allow the City to erect any structure of permanent nature on the

land of the Landowner outside of the easement for the stormwater management/BMP facilities. It is

expressly understood and agreed that the City is under no obligation to routinely maintain or repair

said facilities, and in no event shall this Instrument be construed to impose any such obligation on the

City.

6. The Landowner, its successors and assigns, will perform the work necessary to keep these facilities in

good working order ad appropriate. In the event a maintenance schedule for the stormwater

management/BMP facilities (including sediment removal) is outlined on the approved plans, the

schedule will be followed.

7. In the event the City pursuant to this Instrument, performs work of any nature, or expends any funds in

performance of said work for labor, use of equipment, supplies, materials, and the like, the

Landowner, its successors and assigns, shall reimburse the City upon demand, within thirty (30) days

of receipt thereof for all actual costs incurred by the City hereunder.

Page 40: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 40 of 50

8. This Instrument imposes no liability of any kind whatsoever on the City and the Land owner agrees to

hold the City harmless from any liability in the event the stormwater management/BMP facilities fail

to operate properly.

9. This Instrument shall be recorded among the land records of Fulton County, Georgia, and shall

constitute a covenant running with the land, and shall be binding on the Landowner, its

administrators, executors, assigns, heirs and any other successors in interests, including any

homeowners association

WITNESS the following signatures and seals:

____________________________________________

Company/Corporation/Partnership Name (Seal)

By: _______________________________________________ (Signature)

_______________________________________________ (Type Name)

________________________________________________ (Type Title)

STATE OF ___________________

COUNTY OF _________________

The foregoing instrument was acknowledged before me this ____________ day of

____________________,20______, by________________________________________________.

_________________________________________ (Seal)

NOTARY PUBLIC

My Commission Expires: _________________________

Page 41: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 41 of 50

Attachment A

Responsible Person

As required by Section 20-287 of the City of Milton Code of Ordinances, identify the responsible person

or position that shall ensure the inspection and maintenance of the stormwater facility is accomplished

according to the Inspection and Maintenance Schedule prepared by the engineer of record for this facility.

_________________________________________________________________ Address or Name of Facility

Results of those inspections shall be submitted annually to the City of Milton. Inspection reports shall be

submitted to:

City of Milton

Community Development

13000 Deerfield Parkway, Suite 107F

Milton, Georgia 30004

Attn: Plan Review Engineer

If the responsible entity or contact person changes, the City of Milton shall be notified in writing of the

change. Failure to meet the requirements of the inspection and maintenance agreement shall constitute a

violation of Chapter 20, Article IV of the City of Milton Code of Ordinances and shall be punishable

under Section 20-264 of said code.

____________________________________________________________________ Responsible Entity

_____________________________________________________________________________________________

Contact Person’s Name

_____________________________________________________________________________________________

Signature

_____________________________________________________________________________________________

Address

______________________________________________________________________________________________

City, State, Zip Code

______________________________________________________________________________________________

Phone Number

Page 42: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 42 of 50

Attachment B

Required Inspection and Maintenance Schedule

Attach an inspection and maintenance schedule. Refer to Chapter 3, of the

“Georgia Stormwater Management Manual”, Latest Edition for minimum

recommended inspection and maintenance requirements.

Attach stormwater facility detail sheets (8 ½” x 11” or 11”x17”)

Page 43: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 43 of 50

OWNER'S INDEMNIFICATION AND MAINTENANCE AGREEMENT

FOR DETENTION PONDS (Plats)

THIS AGREEMENT is made and entered into as of this _________day of ________________, _______ Date Month Year

by and between ______________________________________________________________________

(hereinafter referred to as "Owner"), and the City of Milton.

WHEREAS, Owner holds title to certain real property located in __________________________

Subdivision, __________ Land Lots, ________District, __________ City of Milton,

Georgia, more particularly described on the Final Plat (hereinafter referred to as the "Property"); and

WHEREAS, Owner has applied for a Final Subdivision plat approval from the City of Milton,

in accordance with plans and specifications submitted to the City of Milton in order to

construct a detention pond upon said Property in connection with such approval (the "Detention Facility")

and;

WHEREAS, the City of Milton is willing to grant such approval upon the terms and

conditions set forth herein below:

It is HEREBY AGREED as follows:

1. Owner, at its sole cost and expense, hereby agrees to maintain the Detention Facility in a

structurally sound condition so that it satisfies the drainage function for which it was intended, to

maintain the Detention Facility in a clean and safe condition so as not to constitute a hazard of nuisance to the

public, and to maintain the Detention Facility in accordance with all rules, standards, and regulations

applicable thereto as may from time to time be enacted by and governmental agency or authority,

including the City of Milton. Maintenance of the Detention Facility shall include inspection and

maintenance performed at least as frequently as biannually. Owner shall keep records detailing

inspection and maintenance activity and these records shall be made available to Milton upon

request. The City of Milton is hereby relieved of all responsibility for the maintenance of the

Page 44: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 44 of 50

Detention Facility for the term of this agreement.

2. During and throughout the term hereof, the Owner hereby agrees to indemnify and hold

The City of Milton, its officers, agents, and employees, harmless from all damages, liability,

claims, demands, attorney’s fees, and legal cost, relating to or arising from; (A) the drainage function of

the Detention Facility and including the construction, maintenance, operation, and use thereof and (B)

the increase of the flow of water or diversion of the flow of water resulting from the Detention Facility.

3. The Owner hereby authorizes the City of Milton to enter upon the premises for

purposes of inspection, but written notice of the City of Milton’s intention to so enter

must be given to Owner at least twenty-four (24) hours in advance of said entry. Except, however, in the

event of an emergency threatening loss of life or valuable property right, Milton is hereby

granted immediate access to Detention Pond and the right, but not the obligation, to perform any

required maintenance, the cost of which is to be paid by Owner, as provided in Paragraph 4 herein

below.

4. In the event that the required maintenance is not performed by the Owner after thirty (30)

day’s written notice to the Owner from the City of Milton, the City of Milton shall have

the right (but not the obligation) to enter the Property for the purpose of performing such maintenance.

The costs of such performance shall be billed to the Owner and the Owner shall promptly reimburse

The City of Milton for such costs within thirty (30) days after receipt of such billing. Failing such

reimbursement, the City of Milton shall be entitled to a lien upon the Property for the full amount

of such costs.

5. Upon the execution of this agreement by ________________________________________,

the City of Milton shall approve the Final Subdivision Plat and Detention Facility in accordance

with plans and specifications approved by the City of Milton. Specifically, Owner is prohibited

from the importation of fill into the Detention Facility and any modification to the approved outlet

structure without the City of Milton’s approval. Further, Owner is to keep a maintenance log

concerning activities within the pond to be made available to the City of Milton upon written

request.

Page 45: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 45 of 50

3. The terms of this agreement shall take effect upon the date hereof and shall continue in

effect for as long as the Detention Facility is in existence.

4. All notices provided for are permitted to be given pursuant to this agreement must be in

writing and shall be deemed to have been properly given or served by deposition in the United States

Mail.

For the City of Milton: City of Milton

13000 Deerfield Parkway Suite 107F

Milton, Georgia 30004

For the Owner: _____________________________________________________

Address _____________________________________________________

City/State/Zip Code ______________________________________________

Telephone Number ______________________________________________

5. This agreement shall be binding upon and insure to the benefit of the parties hereto and

their respective executors, administrators, heirs, successors, and successors-in-title,

whether voluntary by action of the parties or involuntary by operation of law. IT IS HEREBY

STIPULATED AND AGREED that this agreement constitutes a covenant running with the land herein

described.

IN WITNESS WHEREOF, the parties have caused this agreement to be executed under seal

as of the date of acceptance by Owner.

Page 46: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 46 of 50

OWNER:

_________________________________________________

_________________________________________________

Sworn to and subscribed to before me this _________ day of_______________, _______

Date Month Year

________________________________________ ____________________________________

NOTARY PUBLIC SIGNATURE & SEAL UNOFFICIAL WITTNESS SIGNATURE

Attach Schedule

Page 47: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 47 of 50

TRENCHING PERMIT

Permit Number: ______________________________

This permit must be posted on site in a visible location.

This permit is valid only for the individual listed as the competent person for this project. The competent

person must be present at all times when trenching and excavation activities covered by this permit are

occurring.

Project Name:_________________________________________________________________________

Competent Person: _____________________________________________________________________

Office: __________________ Pager: ___________________ Cell Phone: ______________________

24 Hour Emergency Number: ___________________________________________________________

Certifying Agency: _____________________________________________________________________

Inspector Signature: __________________________________ Issue Date: _______________________

Conditions:

1. Issuance of this permit authorizes the holder of the permit to conduct trenching and excavation activities

only on the project site identified above.

2. All activities shall be performed in accordance with the City of Milton specification and OSHA standards

1926.650, 1926.651, 1926.652.

3. Violations of this ordinance may result in the revocation or suspension of this permit.

4. Failure to abide by a written notification of deficiency may result in the suspension or revocation of

building permits, land disturbance permits or any other permit issued by the City of Milton.

I certify that I have received and understand the safety requirements associated with trenching and

excavation activities from a qualified instructor. I understand the conditions associated with this permit as

stated hereon and in the ordinance. I also certify that I am the competent person holding a valid certificate

for trenching and excavation activities on this site.

Printed Name: ________________________________________________________________________

Signature: ________________________________________________________ ____ Date: ______________

Page 48: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 48 of 50

DESIGN REVIEW BOARD APPLICATION

MEETING DATE: ________________________________________________________________

TYPE OF REVIEW: FINAL _____ COURTESY _____ CASE # _________________________

PROJECT INFORMATION

PROJECT NAME:___________________________________________________________________

PROJECT ADDRESS: _______________________________________________________________

OVERLAY/FORM BASED CODE: ____________________________________________________

HAS LDP/BUILDING PERMIT BEEN SUBMITTED FOR REVIEW? YES ____ NO______

PROJECT TYPE (CHECK ONE): SITE/LANDSCAPE ___________ BUILDING ___________ SALES TRAILER _________ DEMOLITION ________ ZONING/USE PERMIT/VARIANCE ___________ OTHER (EXPLAIN) _________________________

PROJECT DESCRIPTION: ___________________________________________________________ ___________________________________________________________________________________ ___________________________________________________________________________________

APPLICANT/REPRESENTATIVE INFORMATION

CONTACT PERSON NAME: _________________________________________________________

COMPANY:________________________________________________________________________

ADDRESS: ________________________________________________________________________

PHONE: ___________________________________ FAX: _________________________________

EMAIL: ___________________________________________________________________________

APPLICANT’S SIGNATURE: To the best of my knowledge, this application is correct and complete. I understand that I, or my representative should be in attendance at the Design Review Board meeting on ________________________, at 6:00pm, to present this project. To the best of my knowledge, I have met all applicable Overlay/Form Based Code conditions (Hwy 9/Deerfield, Birmingham, Crabapple, Northwest Fulton.)

Applicant: __ __ Date

Page 49: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 49 of 50

DESIGN REVIEW BOARD SUBMITTAL REQUIREMENTS

Please see the list below for materials required according to the type of review. All site plans and building plans shall be drawn to scale. Incomplete submittals will not be accepted for review. Mounted drawings and sample boards showing materials, colors, etc. may be brought to the meeting for your presentation. Please collate and fold all drawings down to 81/2 by 11 size. If you have any questions, please contact Angela Rambeau at 678 242 2539.

SITE PLAN/LANDSCAPE PLAN REVIEW—9 sets

Construction drawings, as required for LDP, including, but not limited to: Site location map(atlas map) Aerial map (Google) Acreage, density, adjacent zonings Zoning conditions (if any) Building footprint, square footage Grading, storm water plan, detention/retention areas Location of streams, stream buffers Roadways, parking areas, driveways, sidewalks, bike paths, pedestrian paths Dumpster location Landscape plan showing location, size and type of specimen and recompense trees, as well as

other plantings Site lighting with photometric drawings , lighting fixture details Retaining wall(s) location and material details Fencing location and details Bike rack location and details Mail kiosk location (If applicable)

BUILDING REVIEW—9 sets Site location map(atlas map) Aerial map (Google) Site plan Colored renderings of all facades Line drawings of all elevations with heights, and materials labled Locations of roof top equipment, satellite dishes, antennas,vents,exhausts (as applicable) Site line study showing that rooftop units are not visible from adjoining roads (if applicable) Location, details of lighting fixtures Dumpster enclosure details (If applicable) Mail kiosk details (If applicable) Sample board showing materials, colors, etc. (Bring to the meeting)

SALES TRAILER—9 sets Site location map(atlas map) Aerial map (Google) Site plan showing location of sales trailer, setbacks, parking, etc. Landscape plan Picture and/or construction details of trailer

DEMOLITION REVIEW—9 sets Site location map(atlas map)

Page 50: LAND DISTURBANCE PERMIT RESIDENTIAL - Milton dev... · Land Disturbance Permit Package ... All construction shall conform to the City of Milton and GDOT Standards and ... Any traffic

Land Disturbance Permit Package

Page 50 of 50

Aerial map (Google) Site plan, indicating structure(s) to be demolished and the location of specimen trees, erosion

control, tree save fencing Pictures of structure(s) to be demolished

VARIANCE/USE PEMIT/REZONING—9 sets Site location map(atlas map) Aerial map (Google) Acreage, density, existing site conditions Conceptual site plan showing location of buildings, detention areas, streams/stream buffers,

specimen trees, roads, parking, driveways, sidewalks, etc. For commercial/multifamily/townhome uses: conceptual renderings of buildings, square

footages For sign variance: site line study showing view of signs from adjacent roads For stream buffer variance: mitigation plan