ks3-【v3】operation challenges and solutions of csg 1014(余 … · breaker fault occurred in...

32
Yu jianguo 2014.10 Operation challenges and solutions of CSG

Upload: others

Post on 19-Oct-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

Yu jianguo

2014.10

Operation challenges and solutions of CSG

Page 2: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

Index

31 Introduction of CSG

33 Challenges of CSG

2 Main features of CSG

4 Solutions and Techniques

Page 3: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

Introduction of CSG Typical AC/DC parallel power grid.

Covers transmission, distribution and supplying in 5 provinces

Supplies about 1 million Square kilometers

Serves 230 million people

YunnanYunnan

GuizhouGuizhou

GuangxiGuangxiHainanHainan

GuangdongGuangdong

Page 4: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

Introduction of CSGPower grid structure of CSG by the end of 2002

500kV AC lines

±500kV DC lines

220kV AC lines

HK grid

Power grid structure of CSG by the end of 2012

HK grid

500kV AC lines

±500kV DC lines

220kV AC lines

Page 5: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

NuoZhaDu UHVDC

YunGuang UHVDC

XiLuoDu HVDC

Peak load  136 million kW

8 HVDC and 8 HVAC lines in 2014,  70%  HVDC

63.5 billion kW West‐East, 60% HVDC, 2014

Utilizing  of  DC  transmission about 3000 hours

AC/DC parallel power grid of CSG in 2014

Introduction of CSG

Page 6: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

Index

31 Introduction of CSG

33 Challenges of CSG

2 Main features of CSG

4 Solutions and Techniques

Page 7: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

Main features of CSG

Feature 1:Significant benefits of resource allocation. •80% hydro resources and 96% thermal resources are in the west area. •Over half the loads are located in Guangdong.

Feature 1:Significant benefits of resource allocation. •80% hydro resources and 96% thermal resources are in the west area. •Over half the loads are located in Guangdong.

An increase of nearly 7 times

An increase of nearly 3 times

Page 8: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

Peak load occurs in summer in Guangdong

Peak load occurs in winter in the West

Typical monthly Peak load curve Typical daily load curve in summer

0

10000

20000

30000

40000

50000

60000

70000

80000

9000

10000

11000

12000

13000

14000

15000

16000

广东 广西 贵州 云南

0

10000

20000

30000

40000

50000

60000

70000

4000

6000

8000

10000

12000

14000

16000

广东 广西 贵州 云南

Complementation of load characteristic

Peak load occurs in morning  in Guangdong

Peak load occurs in evening  in the West

Main features of CSG

GD GX GZ YN GD GX GZ YN

Page 9: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

Feature 2:•Complicated structure•Difficult to operate

•Over 30GW power is transferred from West to East. •AC/DC corridor operates close to limit point of the system in flood seasons

Feature 2:•Complicated structure•Difficult to operate

•Over 30GW power is transferred from West to East. •AC/DC corridor operates close to limit point of the system in flood seasons

Main features of CSG

North‐West gridInterregional power 2000MW

North‐East gridInterregional power 12000MW

North China gridInterregional power 11020MW

Central China gridInterregional power 8850MW

East China gridInterregional power 12170MW

CSGInterregional power 30000MW

Page 10: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

Receiving end of San-Guang HVDC

Receiving end of Yun-Guang UHVDC

Receiving end of XiLuoDu HVDC

Receiving end of Tian-Guang HVDC

Receiving end of Gao-Zhao HVDC

Receiving end of NuoZhaDu UHVDC Receiving end of

Xing-An HVDC

Feature 3: •Many HVDC transmission lines. •Concentrated HVDC receiving ends

In 2015, 8 HVDC transmission lines.Receiving ends all in Guangdong.About 1/3 of the maximum load capacity.

Feature 3: •Many HVDC transmission lines. •Concentrated HVDC receiving ends

In 2015, 8 HVDC transmission lines.Receiving ends all in Guangdong.About 1/3 of the maximum load capacity.

Main features of CSG

Page 11: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

Multi-terminal VSC HVDC Submarine cable

Main features of CSGFeature 4:New technology: UHVDC, Multi-terminal VSC HVDC, High voltage submarine cable, controllable TCSC, STATCTOM, etc.

Feature 4:New technology: UHVDC, Multi-terminal VSC HVDC, High voltage submarine cable, controllable TCSC, STATCTOM, etc.

Page 12: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

亚洲首个500kV可控串补

(TCSC )

3.技术先进TCSC in Pingguo Station STATCOM in Dongguan 

Station

Main features of CSG

Page 13: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

Myanmar

Laos

Vietnam

MacaoHK

Feature 5:Connecting HK, Macao, and Southeast Asia. Serves ¼ load of HK, and 90% load of Macao. Some connections with Myanmar, Laos, and Vietnam.

Feature 5:Connecting HK, Macao, and Southeast Asia. Serves ¼ load of HK, and 90% load of Macao. Some connections with Myanmar, Laos, and Vietnam.

Main features of CSG

Page 14: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

Index

31 Introduction of CSG

33 Challenges of CSG

2 Main features of CSG

4 Solutions and Techniques

Page 15: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

Mono-polar blocking of Yun-Guang UHVDC or NuoZhaDu UHVDC

Cause 30-70kV voltage drop at the midpoint of West to East

transmission lines.

Cause 1000MW power oscillation in the 500kV AC transmission line.

Cause power over-limit in relative interfaces.

PMU recording of the voltage drop caused by mono-polar blocking in Yun-Guang UHVDC

Challenges of CSGChallenge 1 : With AC/DC parallel operation, large power transferring caused by DC faults threatens the stability of system.

Statistic of mono‐polar blocking events in CSG

Page 16: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

HVDC bipolar blocking may cause tremendous power transferring to AC sections, hence may cause system instability.

System security depends on proper actions of stability control devices

Challenges of CSG

Statistic of bipolar blocking events in CSG

Page 17: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

(2)On Dec. 15, 2012, breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters.

(1)On Nov. 7, 2010, An AC grounding fault at a 500kv line in Guangdong caused simultaneous commutation failures in 5 HVDC inverters.

石井

Bei-Hua II phase B fault on 4.27 Hua-Bo II phase

AB fault on 4.12

Luo-Bei II phase A fault on 4.25

Xu-Zeng II phase C fault on 4.27

Yan-Hua II phase A fault on 5.2

An-Guan II phase B fault on 5.3

Bei-Shi I fault on 4.25

Zeng-Sui II phase C fault on 8.11

Sui-Shui II phase C fault on 9.4

Zengcheng #2 transformer Phase C fault on 9.7

Typical faults which caused commutation failures in multi HVDCs of CSG in 2012

Challenges of CSGChallenge 2: Multi-infeeded HVDC in Guangdong – AC faults may cause commutation failures in multi HVDCs or even bipolar blockings.

Page 18: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

Long distance, large capacity and long-chain structure transmission lines may cause high risk of low frequency oscillations

Inter-regional low frequency oscillation under a weak system damping

Inner-area low damping oscillations in regional grid may cause the power oscillation in transmission interface

Forced oscillation of generators

Low frequency oscillation of Yunnan-Guangdong in 2003

Forced oscillation of #2 generator, Honghe station in 2008

Challenges of CSGChallenge 3:High risk of low frequency oscillations.

Page 19: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

Freezing Rain

Earthquake

Thunder

Forestry fire

Typhoon

Freezing rain occurred frequently and last for long time which impacts wide area.

Approximately 4-5 typhoons attack east coast area every year including Guangdong, Guangxi and Hainan province.

Earthquake happens frequently in Yunnan. Disasters like forestry fire, thunder, mud-rock flow and

landslide often occurs.

Drought

According to statistics,over one-third multi-loop tripping accidents occurred in CSG are caused by bad weather.

Challenges 4:nature disasters occur frequently

Challenges of CSG

Page 20: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

• In winter of 2008, southern China encountered a severe freezing rain. • The ice-coating of transmission lines reached 118 millimeter, which

caused over 2000 towers fell down and around 900 towers impaired; • During the hazard, Guizhou grid was seriously damaged and forced to

islanding operation.

息烽

鸭溪

兴仁换流

贵阳

鸭溪

福泉施秉 铜仁

青岩

安顺

鸡场

乌当金阳

筑东

南郊

站街

田坝洪家渡

东风

索风营

扎佐

高坡换流

引子渡

两所屯

安顺铝厂

紫云

普定滥坝

双牌铝厂

北郊

水城

野马寨

镇宁

盘县一

盘县二

八河红果

盘南起备

兴义

兴仁

安龙

天生桥二级天生桥一级 枢纽站

盘南

湾塘

大田河

盘脚

开阳

乌江厂

南白

新蒲

遵义

海龙

桐梓习水

黔北金沙

毕节

大花水

剑江

都匀

麻江

凯里 凯里

恒盛

开怀黎平

镇远 青溪

岑巩 玉屏

大龙

大龙

川硐

秀山

贵阳

清镇

纳雍二厂

纳雍一厂

安顺

遵义

瓮安

麻尾

至广东白花洞

至广西至广东北郊

至广东肇庆

至车河

至广西河池

至公坪

至湾潭

至重庆黔江至綦江至黄荆堡

220kV交流

500kV交流

500kV直流

图例

黔西大方

龙里

太平

Guizhou grid separated into 7 small grids 

Challenges of CSG

Impaired tower 

Page 21: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

Index

31 Introduction of CSG

33 Challenges of CSG

2 Main features of CSG

4 Solutions and Techniques

Page 22: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

Asynchronous interconnection of Yunnan and

main power grid

Islanding operation of Yunnan DC

sending system

Configuration optimization of

dynamic reactive power compensation

devices

The possible solutions to stability issues

Large-scale security and

stability control system

Coordination between

generating units and grid

Disaster-prevention

system

Solutions and Techniques

Page 23: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

4 AC line mode for Yunnan-Guangdong UHVDC islanding operation

(Very low SCR: short-circuit ratio is between 1.22 to 1.52 under full load condition )

Typical operation modes for YG UHVDC islanding system

Solution 1:Islanding operation at DC sending  terminal in Yunnan

5 AC line mode for Yunnan-Guangdong UHVDC islanding operation

Solutions and Techniques

Page 24: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

During Sep.11th-19th in 2013, CSG accomplished islanding operation of YG UHVDC, which is the first time to take DC islanding as normal operation.

Islanding operation can be used as a normal operation mode of Yunnan-Guangdong UHVDC.

This first UHVDC islanding operation in the world made a contribution to the development of DC transmission technology.

Solutions and Techniques

Page 25: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

Solution 2:Asynchronous interconnection of Yunnan and main power grid

Implementation schemes of asynchronous interconnection 

A back‐to‐back HVDC project , which includes a 1000MW LCC‐HVDC and a 1000MW VSC‐HVDC in parallel, separates three AC connections.

A long distance HVDC project, which has three connection modes at the receiving end, separates two AC connections.   

A back‐to‐back HVDC project , which includes a 1000MW LCC‐HVDC and a 1000MW VSC‐HVDC in parallel, separates three AC connections.

A long distance HVDC project, which has three connection modes at the receiving end, separates two AC connections.   

Solutions and Techniques

Page 26: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

CSG built 712 sets of Power security and stability control facilities for 110KV and above system, which makes CSG become the largest and most complicated system in the world. 

This system has detected all 166 DC mono‐polar blocking faults and 13 bipolar blocking faults accurately, which protects the system security.

Security and stability control system in CSGSecurity and stability control system in CSG

Solution 3:Large-scale security and stability control system

Solutions and Techniques

Page 27: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

Four  sets  of  ±200Mvar STATCOMs  has  been  installed  in  the multi‐infeeded system  to  improve  system voltage dynamic performance, and  to  improve  the recovery characteristics of HVDC systems.  

Solution 4: Configuration optimization of dynamic reactive powercompensation devices

These  4  sets  of  STATCOMs  have  responded  64  times since  installed,  thus  successfully  enhanced  voltage stability.

Solutions and Techniques

Page 28: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

Focus on dynamic stability  researches  Arrange operation modes reasonably Monitor low frequency oscillation Improve the construction of the grid

Solution 5:coordination between generating units and grid

Make effort on generation PSS configuration  Enhance secondary loop and settings management 

of regulator, exciter, PSS devices. Perform feed‐in test of regulator, exciter, PSS 

devices

Transmission network

Generation

Solutions and Techniques

Page 29: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

Solution 6:Establish effective disaster-prevention system

Established lightning monitor and location system which covers the 

whole CSG area.

Installed On‐line Ice‐coating Monitoring System which covers all lines 

in icy areas.  

Rectified the technique principle of power grid planning, especially 

adapting differential wind‐resistant design for overhead lines near 

coastal area.

Established comprehensive emergency communication system for 

communication during nature disasters, which consists of fiber optic, 

satellite and PLC communication system. 

Solutions and Techniques

Page 30: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

Wind-resistant design of strain tower diagram

Lightning monitor and location system  On‐line Ice‐coating Monitoring System

Comprehensive emergency communication system

Solution 6:Establish effective disaster-prevention system

Solutions and Techniques

Page 31: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

According to “China Southern Power Grid Development and Planning (2013-2020)”published by National Energy Administration, CSG will continue to use HVDC as the main technique to transmit electricity from west to east. Yunnan grid will be a sending network, which is asynchronously connected with the rest CSG system, thus to limit the size of synchronous network. However, there are still lots of research need to be carried out to optimize the size of synchronous system.

Due to the rapid development of new transmission techniques, especially VSC, more attention should be paid on construction schemes for future power grid.

With green energy integrated, including wind and solar power, there will be more pressure on power and frequency regulation, which brings new challenges for system security and stability. Thus it is important to emphasize the balance of system economy and security.

Summary

Page 32: KS3-【v3】Operation challenges and solutions of CSG 1014(余 … · breaker fault occurred in Yandu station which caused simultaneous commutation failures in 3 HVDC inverters. (1)On

Thank you!