krishna machine.pptx
TRANSCRIPT
-
8/10/2019 Krishna Machine.pptx
1/13
Machine Utilization at
Krishna Ltd.
Submitted By:-
Roll No: 1401061to 1401080
PGDIE 44th
SECTION- B
-
8/10/2019 Krishna Machine.pptx
2/13
OBJECTIVE OF STUDY:
1. Evaluation of current machine utilization and improvement
2. Future capacity requirements (In view of increase in production)
3. Measures for 2 month stock
-
8/10/2019 Krishna Machine.pptx
3/13
Question: 01
Objectives of the study were met by the
consultant, i.e. (i) The current M/C
utilization, (ii) Improvement suggestions,
(iii) Suggestion for future capacity
requirements & 2 month stock, All are
addressed.
However the study DOES NOT considersome of the important aspects*.
* Same will be discussed in next sections.
-
8/10/2019 Krishna Machine.pptx
4/13
Question: 02(Improvement of Shop Supervision)
Provision can be made, so that all lines receive equal supervision.
(With due consideration to most underutilized line)
Dedicated supervision for each area.
Surprise/Periodic supervision by shop in-charge
Whether supervisors are overloaded ? Needs to be analyzed.
Only improved supervision may not increase the machine utilization.
Human factors for operators, such as motivation etc. need to be
analyzed.
-
8/10/2019 Krishna Machine.pptx
5/13
Question: 02(Improvement of Shop Supervision)
Study
Shop
Supervision
Adequate ?
Study of
probable
reasons
Adequate no. of
supervisor as per
standard ?
Supervisor busy
with other work ?
Dedicated
supervisor foreach area ?
Area is too large
for the supervisor
to handle ?
Higher level
involvement needed.
No. of supervisor
needs to be increased
Target to be given
to supervisors
related to m/c
utilization
Supervisor s are
excessive friendly
with operators ?
Departmental
supervision needed
YES
NO
YESNO
YES
NO
YES
NO
YES
NO
YES
NO
Proper
training to
be given
-
8/10/2019 Krishna Machine.pptx
6/13
Question: 03(Weakness in work sampling study)
Individual machine wise study was not done. Grouped machines were
studied. Which does not give a clear picture about the individual
machine utilization.
Idle due to operator has been given as one of the highest
contributing factor for machine idle time, but break up for the same
was not given.
Standards for machine utilization of similar shops were not
considered.
-
8/10/2019 Krishna Machine.pptx
7/13
Question: 04(Capacity Determination: Option 01)
Annual Demand 2 Month Stock Group I Group II Group III Group IV
Speedometers 203000 33833.33333 62 2097.67 66 2233 82 2774.33 0
Pressure Gauges 212700 35450 24.4 864.98 91 3225.95 0 17.3 613.285
Temperature Gauges 118560 19760 0 0 85 1679.6 0 8.5 167.96
Tachographs/ Speed indicators 20000 3333.333333 151 503.333 150 500 133.7 445.667 21.8 72.6667
Faremeters 4500 750 7.1 5.325 67 50.25 11.7 8.775 0
Cables 300000 50000 66 3300 7 350 0 0
Hub drive 10000 1666.666667 42.6 71 11.2 18.6667 26.4 44 13.6 22.6667
Warning lamp 82560 13760 15 206.4 5.3 72.928 0 5.1 70.176
Total 7048.71Total 8130.39Total 3272.78Total 946.754
Hours / Week 135.552 156.354 62.938 18.2068
No. of Machines 10 13 6 3
OT/Machine/Week 13.5552 12.0272 10.4897 6.06894
-
8/10/2019 Krishna Machine.pptx
8/13
Question: 04(Capacity Determination: Option 02)
Introduction of 3rdShiftAssumptions:
Working Hours = 8 Hrs
Break = 1 Hr (Considering Night Shift)
No. of
working
days
Daily
working
Hrs
Total
working
Hrs
300 7 2100
Group 1 Group 2 Group 3 Group 4
10 13 6 3
21000 27300 12600 6300
Extra working Hours
Total No. of Machines required
Target time for 2 month inventory (In months)
GroupMachine Hrs Required Available M/C Hrs/Year/Machine 2 4 6 8 10 12
I 7048.705 2100 20 10 7 5 4 3
II 8130.394667 2100 23 12 8 6 5 4
III 3272.775 2100 9 5 3 2 2 2
IV 946.7543333 2100 3 1 1 1 1 1
TOTAL MACHINES 55 28 18 14 11 10
TOTAL OPERATORS 28 18 14 11 10
WAGES (400/Day) Rupees NOTFEASIBLE 1344000 1296000 1344000 1320000 1440000
-
8/10/2019 Krishna Machine.pptx
9/13
Question: 04(Capacity Determination: Option 02)
Introduction of 3rdShiftComparison of OT and 3rdShift
Month Required GR 1 GR 2 GR 3 GR 4 Total CostOT Cost (2 times of
Normal wage)
4 10 12 5 1 1344000
1939862.9
6 7 8 3 1 1296000
8 5 6 2 1 1344000
10 4 5 2 1 1320000
12 3 4 2 1 1440000
Over time 7048.7 8130.4 3272.8 946.75
-
8/10/2019 Krishna Machine.pptx
10/13
ANNUAL DEMAND CALCULATION
Annual Demand Group I Group II Group III Group IV
Speedometers 203000 62 12586 66 13398 82 16646 0
Pressure Gauges 212700 24.4 5189.88 91 19355.7 0 17.3 3679.71
Temperature Gauges 118560 0 0 85 10077.6 0 8.5 1007.76
Tachographs/ Speed indicators 20000 151 3020 150 3000 133.7 2674 21.8 436
Faremeters 4500 7.1 31.95 67 301.5 11.7 52.65 0
Cables 300000 66 19800 7 2100 0 0
Hub drive 10000 42.6 426 11.2 112 26.4 264 13.6 136
Warning lamp 82560 15 1238.4 5.3 437.568 0 5.1 421.056
Total 42292.2 Total 48782.4 Total 19636.7 Total 5680.53
Total Available Hrs/Mc/Yr 4500 4500 4500 4500
No. of Machines 10 13 6 3
OT/Machine/Week 45000 58500 27000 13500
Allowance 0.16 0.22 0.2 0.15
Available Time 37800 45630 21600 11475
Shortage 4492.23 3152.37 -1963.4 -5794.5
Annual Demand
-
8/10/2019 Krishna Machine.pptx
11/13
Total No. of Machines required
Target time for 2 month inventory (In months)
Group
Machine HrsRequired for 2
month stock
Shortage for
annual demand
Net M/C hrs
requiredAvailable M/C Hrs/Year/Machine 2 4 6 8 10 12
I 7049 4492 11541 2100 33 16 11 8 7 5
II 8130 3152 11283 2100 32 16 11 8 6 5
III 3273 -1963 1309 2100 4 2 1 1 1 1
IV 947 -5794 -4848 2100 0 0 0 0 0 0
TOTAL MACHINES 69 34 23 17 14 11
TOTAL OPERATORS 17 14 11
WAGES (400/Day) Rupees NOT FEASIBLENOT FEASIBLE NOT FEASIBLE 1632000 16800001584000
Month
RequiredGR 1 GR 2 GR 3 GR 4 Total Cost
OT Cost (2 times
of Normal wage)
4 0 0 0 0 NA 2413200
6 0 0 0 0 NA 2413200
8 5 6 2 1 1632000 2413200
10 4 5 2 1 1680000 2403200
12 3 4 2 1 1584000 241320011541 11282 1309 0
Total cost comparison (Considering all demand)
-
8/10/2019 Krishna Machine.pptx
12/13
Question: 05Scheduling
Backward scheduling
Determining a production schedule by working backwards from
the due date (or time) to the start date (or time).
Simultaneously computing the materials and time required at
every operation or stage.
Different heuristics like branch and bound technique can be used.
As per the target date set by the sales departments, the job
priorities will be set wrt the manufacturing lead time and the
penalties associated with it.
-
8/10/2019 Krishna Machine.pptx
13/13
Question: 06Trivial and Useful Suggestion
Following recommendations were found to be trivial:-
Shop supervision to be improved. (Because, strict supervision may not
always contribute to higher utilization. And can cause union problem.)
Gear up maintenance effort. (Instead of increasing maintenance activities,
change the maintenance system. Can deploy TPM, preventive maintenance.)
Piece rate incentive scheme. (It is not considered as a fair method as it is
directly output depended. All the jobs do not have equal cycle time. Better
alternatives are available like a) Halsey plan b) Rowan plan c) Emerson plan)
Useful solutions:-
1. Dedicated PPC department.
2. Maintaining buffer stock.
3. Use of lead time cards.