  • 8/10/2019 Krishna Machine.pptx

    1/13

    Machine Utilization at

    Krishna Ltd.

    Submitted By:-

    Roll No: 1401061to 1401080

    PGDIE 44th

    SECTION- B

  • 8/10/2019 Krishna Machine.pptx

    2/13

    OBJECTIVE OF STUDY:

    1. Evaluation of current machine utilization and improvement

    2. Future capacity requirements (In view of increase in production)

    3. Measures for 2 month stock

  • 8/10/2019 Krishna Machine.pptx

    3/13

    Question: 01

    Objectives of the study were met by the

    consultant, i.e. (i) The current M/C

    utilization, (ii) Improvement suggestions,

    (iii) Suggestion for future capacity

    requirements & 2 month stock, All are

    addressed.

    However the study DOES NOT considersome of the important aspects*.

    * Same will be discussed in next sections.

  • 8/10/2019 Krishna Machine.pptx

    4/13

    Question: 02(Improvement of Shop Supervision)

    Provision can be made, so that all lines receive equal supervision.

    (With due consideration to most underutilized line)

    Dedicated supervision for each area.

    Surprise/Periodic supervision by shop in-charge

    Whether supervisors are overloaded ? Needs to be analyzed.

    Only improved supervision may not increase the machine utilization.

    Human factors for operators, such as motivation etc. need to be

    analyzed.

  • 8/10/2019 Krishna Machine.pptx

    5/13

    Question: 02(Improvement of Shop Supervision)

    Study

    Shop

    Supervision

    Adequate ?

    Study of

    probable

    reasons

    Adequate no. of

    supervisor as per

    standard ?

    Supervisor busy

    with other work ?

    Dedicated

    supervisor foreach area ?

    Area is too large

    for the supervisor

    to handle ?

    Higher level

    involvement needed.

    No. of supervisor

    needs to be increased

    Target to be given

    to supervisors

    related to m/c

    utilization

    Supervisor s are

    excessive friendly

    with operators ?

    Departmental

    supervision needed

    YES

    NO

    YESNO

    YES

    NO

    YES

    NO

    YES

    NO

    YES

    NO

    Proper

    training to

    be given

  • 8/10/2019 Krishna Machine.pptx

    6/13

    Question: 03(Weakness in work sampling study)

    Individual machine wise study was not done. Grouped machines were

    studied. Which does not give a clear picture about the individual

    machine utilization.

    Idle due to operator has been given as one of the highest

    contributing factor for machine idle time, but break up for the same

    was not given.

    Standards for machine utilization of similar shops were not

    considered.

  • 8/10/2019 Krishna Machine.pptx

    7/13

    Question: 04(Capacity Determination: Option 01)

    Annual Demand 2 Month Stock Group I Group II Group III Group IV

    Speedometers 203000 33833.33333 62 2097.67 66 2233 82 2774.33 0

    Pressure Gauges 212700 35450 24.4 864.98 91 3225.95 0 17.3 613.285

    Temperature Gauges 118560 19760 0 0 85 1679.6 0 8.5 167.96

    Tachographs/ Speed indicators 20000 3333.333333 151 503.333 150 500 133.7 445.667 21.8 72.6667

    Faremeters 4500 750 7.1 5.325 67 50.25 11.7 8.775 0

    Cables 300000 50000 66 3300 7 350 0 0

    Hub drive 10000 1666.666667 42.6 71 11.2 18.6667 26.4 44 13.6 22.6667

    Warning lamp 82560 13760 15 206.4 5.3 72.928 0 5.1 70.176

    Total 7048.71Total 8130.39Total 3272.78Total 946.754

    Hours / Week 135.552 156.354 62.938 18.2068

    No. of Machines 10 13 6 3

    OT/Machine/Week 13.5552 12.0272 10.4897 6.06894

  • 8/10/2019 Krishna Machine.pptx

    8/13

    Question: 04(Capacity Determination: Option 02)

    Introduction of 3rdShiftAssumptions:

    Working Hours = 8 Hrs

    Break = 1 Hr (Considering Night Shift)

    No. of

    working

    days

    Daily

    working

    Hrs

    Total

    working

    Hrs

    300 7 2100

    Group 1 Group 2 Group 3 Group 4

    10 13 6 3

    21000 27300 12600 6300

    Extra working Hours

    Total No. of Machines required

    Target time for 2 month inventory (In months)

    GroupMachine Hrs Required Available M/C Hrs/Year/Machine 2 4 6 8 10 12

    I 7048.705 2100 20 10 7 5 4 3

    II 8130.394667 2100 23 12 8 6 5 4

    III 3272.775 2100 9 5 3 2 2 2

    IV 946.7543333 2100 3 1 1 1 1 1

    TOTAL MACHINES 55 28 18 14 11 10

    TOTAL OPERATORS 28 18 14 11 10

    WAGES (400/Day) Rupees NOTFEASIBLE 1344000 1296000 1344000 1320000 1440000

  • 8/10/2019 Krishna Machine.pptx

    9/13

    Question: 04(Capacity Determination: Option 02)

    Introduction of 3rdShiftComparison of OT and 3rdShift

    Month Required GR 1 GR 2 GR 3 GR 4 Total CostOT Cost (2 times of

    Normal wage)

    4 10 12 5 1 1344000

    1939862.9

    6 7 8 3 1 1296000

    8 5 6 2 1 1344000

    10 4 5 2 1 1320000

    12 3 4 2 1 1440000

    Over time 7048.7 8130.4 3272.8 946.75

  • 8/10/2019 Krishna Machine.pptx

    10/13

    ANNUAL DEMAND CALCULATION

    Annual Demand Group I Group II Group III Group IV

    Speedometers 203000 62 12586 66 13398 82 16646 0

    Pressure Gauges 212700 24.4 5189.88 91 19355.7 0 17.3 3679.71

    Temperature Gauges 118560 0 0 85 10077.6 0 8.5 1007.76

    Tachographs/ Speed indicators 20000 151 3020 150 3000 133.7 2674 21.8 436

    Faremeters 4500 7.1 31.95 67 301.5 11.7 52.65 0

    Cables 300000 66 19800 7 2100 0 0

    Hub drive 10000 42.6 426 11.2 112 26.4 264 13.6 136

    Warning lamp 82560 15 1238.4 5.3 437.568 0 5.1 421.056

    Total 42292.2 Total 48782.4 Total 19636.7 Total 5680.53

    Total Available Hrs/Mc/Yr 4500 4500 4500 4500

    No. of Machines 10 13 6 3

    OT/Machine/Week 45000 58500 27000 13500

    Allowance 0.16 0.22 0.2 0.15

    Available Time 37800 45630 21600 11475

    Shortage 4492.23 3152.37 -1963.4 -5794.5

    Annual Demand

  • 8/10/2019 Krishna Machine.pptx

    11/13

    Total No. of Machines required

    Target time for 2 month inventory (In months)

    Group

    Machine HrsRequired for 2

    month stock

    Shortage for

    annual demand

    Net M/C hrs

    requiredAvailable M/C Hrs/Year/Machine 2 4 6 8 10 12

    I 7049 4492 11541 2100 33 16 11 8 7 5

    II 8130 3152 11283 2100 32 16 11 8 6 5

    III 3273 -1963 1309 2100 4 2 1 1 1 1

    IV 947 -5794 -4848 2100 0 0 0 0 0 0

    TOTAL MACHINES 69 34 23 17 14 11

    TOTAL OPERATORS 17 14 11

    WAGES (400/Day) Rupees NOT FEASIBLENOT FEASIBLE NOT FEASIBLE 1632000 16800001584000

    Month

    RequiredGR 1 GR 2 GR 3 GR 4 Total Cost

    OT Cost (2 times

    of Normal wage)

    4 0 0 0 0 NA 2413200

    6 0 0 0 0 NA 2413200

    8 5 6 2 1 1632000 2413200

    10 4 5 2 1 1680000 2403200

    12 3 4 2 1 1584000 241320011541 11282 1309 0

    Total cost comparison (Considering all demand)

  • 8/10/2019 Krishna Machine.pptx

    12/13

    Question: 05Scheduling

    Backward scheduling

    Determining a production schedule by working backwards from

    the due date (or time) to the start date (or time).

    Simultaneously computing the materials and time required at

    every operation or stage.

    Different heuristics like branch and bound technique can be used.

    As per the target date set by the sales departments, the job

    priorities will be set wrt the manufacturing lead time and the

    penalties associated with it.

  • 8/10/2019 Krishna Machine.pptx

    13/13

    Question: 06Trivial and Useful Suggestion

    Following recommendations were found to be trivial:-

    Shop supervision to be improved. (Because, strict supervision may not

    always contribute to higher utilization. And can cause union problem.)

    Gear up maintenance effort. (Instead of increasing maintenance activities,

    change the maintenance system. Can deploy TPM, preventive maintenance.)

    Piece rate incentive scheme. (It is not considered as a fair method as it is

    directly output depended. All the jobs do not have equal cycle time. Better

    alternatives are available like a) Halsey plan b) Rowan plan c) Emerson plan)

    Useful solutions:-

    1. Dedicated PPC department.

    2. Maintaining buffer stock.

    3. Use of lead time cards.