knox community meeting final - wordpress.com...conceptual design stage focus on overall street...
TRANSCRIPT
Knox Street Complete Streets Project
� Meeting Purpose
� Get community feedback on two conceptual street design options
� www.dallascompletestreets.wordpress.com
Meeting Agenda
� Presentation (20 minutes)
� Project background and schedule
� Summary of preferences from previous workshop
� Overview of conceptual design options
� Break Out Session (1 hour)
� Review/Discuss conceptual design options
� Reporting Out (30 minutes)
� www.dallascompletestreets.wordpress.com
Project Background
� 2012 bond budget: $734,000
� Potential PID funds: ~$ TBD
� Project Limits: Katy Trail to U.S. 75 (4 blocks)
� ROW Width: 62 feet (approx.)
� www.dallascompletestreets.wordpress.com
Interdisciplinary Project Team
� Planning & Neighborhood Vitality
� Strategic Planning
� City Design Studio
� Transportation Planning
� Public Works
� Streets Services
� Storm Water Management (iSWM)
� www.dallascompletestreets.wordpress.com
Project Schedule
� May 2014 - Public workshop #1: Preliminary design priorities
� December 2014 - Public workshop #2: Conceptual design options
Next Steps� Select preferred option� Thoroughfare Plan amendment (if necessary)� Engineering design
� Summer 2015 - Public workshop #3: Preliminary engineering design
Next Steps� Final engineering� Construction contract award� Construction
� www.dallascompletestreets.wordpress.com
Conceptual Design Stage
� Focus on overall street design concept and general location of key design elements
� No specific styles, fixtures or materials selected
� Rough cost estimates to provide a general sense of budget allocation to various design components
� www.dallascompletestreets.wordpress.com
Community Priorities Key Themes From First Public Workshop
� Convert perpendicular parking to angle parking
� Consistent pedestrian improvements throughout the corridor
� Traffic management / traffic calming
� Branding corridor as a unique destination
� www.dallascompletestreets.wordpress.com
Two Conceptual Design Options 4-Lane Option 3-Lane Option
Sidewalk widening: only 1/2 block between Travis and Cole – (5’ approx.)
Sidewalk widening: 2 blocks between Travis and McKinney (10’ approx.)
Limited landscaping (1/2 block) Continuous landscaping (two blocks)
No street repaving/striping Street repaving/re-striping
Angled on-street parking(converted from perpendicular parking)
Angled on-street parking(converted from perpendicular parking)
Mini public plazas (two) Mini public plazas (two)
Decorative paving at intersections Decorative paving at intersections
Repainted crosswalks plus 2 additionalcrosswalks
Repainted crosswalks plus 2 additionalcrosswalks
Pedestrian lighting on south side Pedestrian lighting on south side
Bike racks, benches, trash receptacles at key locations
Bike racks, benches, trash receptacles at key locations
� www.dallascompletestreets.wordpress.com
4-Lane Option
Kn
igh
t
Th
rock
mo
rto
n
� www.dallascompletestreets.wordpress.com
Current ConditionTypical Cross Section
Public Right-Of-Way (62’ approx.)
North SideSouth Side
� www.dallascompletestreets.wordpress.com
4’5’ - 7’
Sidewalk
4-Lane OptionTypical Cross Section
Public Right-Of-Way (62’ approx.)
North SideSouth Side
Maintain existing sidewalk width
Angled parking
� www.dallascompletestreets.wordpress.com
4’
4-Lane Option½ block between Travis and Cole
Public Right-Of-Way (62’ approx.)
North SideSouth Side
Maintain existing sidewalk width
Angled parking
� www.dallascompletestreets.wordpress.com
Landscape buffer and lighting
4’5’
Buffer
5’
Sidewalk
4-Lane Option Cost BreakdownBudget ~$0.7 million
� www.dallascompletestreets.wordpress.com
Mobilization and Traffic Control, $103,000 , 15% Minor Repaving,
Regrading, $27,000 , 4%
Signs (Gateway and Wayfinding),
$20,000 , 3%
Pedestrian Lighting and Conduit, $45,000 , 6%
Furnishings and Bike Racks, $33,000 , 5%
Landscaping, $19,000 , 3%Sidewalks, ADA Ramps, $260,000 , 37%
Crosswalks, $18,000 , 3%
Decorative Paving, $37,000 , 5%
Drainage and Irrigation, $89,000 , 13%
Signals, $41,000 , 6%
Mobilization and Traffic Control
Minor Repaving, Regrading
Signs (Gateway and Wayfinding)
Pedestrian Lighting and Conduit
Furnishings and Bike Racks
Landscaping
Sidewalks, ADA Ramps
Crosswalks
Decorative Paving
Drainage and Irrigation
Signals
3 Lane Option
� www.dallascompletestreets.wordpress.com
Current ConditionTypical Cross Section
Public Right-Of-Way (62’ approx.)
North SideSouth Side
� www.dallascompletestreets.wordpress.com
4’
3-Lane OptionTypical Cross Section
Public Right-Of-Way (62’ approx.)
North SideSouth Side
� www.dallascompletestreets.wordpress.com
4’5’
Buffer
3-Lane Option Cost BreakdownBudget ~1.5 million
� www.dallascompletestreets.wordpress.com
Mobilization and Traffic Control, $103,000 , 7%
Repaving, Regrading, $411,000 , 27%
Signs (Gateway and Wayfinding), $20,000 , 1%
Pedestrian Lighting and Conduit, $45,000 , 3%
Furnishings and Bike Racks, $33,000 , 2%
Landscaping, $89,000 , 6%
Sidewalks, ADA Ramps, $480,000 , 32%
Crosswalks & Lane Markings, $18,000 , 1%
Decorative Paving, $37,000 , 3%
Drainage and Irrigation, $62,000 , 4%
Signals, $206,000 , 14%
Mobilization and TrafficControlRepaving, Regrading
Signs (Gateway andWayfinding)Pedestrian Lighting andConduitFurnishings and Bike Racks
Landscaping
Sidewalks, ADA Ramps
Crosswalks & Lane Markings
Decorative Paving
Drainage and Irrigation
Signals
3-Lane OptionAdditional Considerations
� Road diet option will require:� Thoroughfare Plan amendment – two public
hearings with required property owner notification
� Signal relocation/replacement of at least two signals – SE corners of Travis and McKinney intersections.
� Limited re-grading of street surface in on-street parking area on south side.
� www.dallascompletestreets.wordpress.com
Decorative Pavement Example
Note: This is an example only. No style, material or detailed design choices have been made.
Continental Crosswalk Example
Landscape Buffer Examples
Note: This is an example only. No style, material or detailed design choices have been made.
• City will explore opportunities to reduce storm water run-off using rain gardens in landscaped areas.
Pedestrian Light Examples
Note: This is an example only. No style, material or detailed design choices have been made.
Bike Racks & Trash Receptacles Examples
Note: This is an example only. No style, material or detailed design choices have been made.
Mini Plaza Seating Examples
Note: This is an example only. No style, material or detailed design choices have been made.
Gateway Marker Example
Note: This is an example only. No style, material or detailed design choices have been made.
Pedestrian Way-finding Examples
Note: This is an example only. No style, material or detailed design choices have been made.
On-Street Parking
� Both options include converting existing perpendicular parking to angled parking.
� Angled parking will greatly improve traffic flow.
� Results in a loss of 12 to 15 parking spaces depending on the angle
� www.dallascompletestreets.wordpress.com
Proposed New Crosswalks
� Two New Crosswalks proposed
� At alley between Travis and Cole (near Starbucks )
� At alley between Cole and McKinney
� Solar powered flashing yellow beacons to be installed for pedestrian safety
� www.dallascompletestreets.wordpress.com
PID Involvement
� In both options, City will seek to partner with PID on maintenance of some design elements:� Gateway markers
� Soft landscape
� Bike racks, benches, trash receptacles
� Pedestrian lighting
� 3-Lane option will depend upon capital contribution from PID
� www.dallascompletestreets.wordpress.com
Future Development Opportunities
Break Out Work Session
� Discuss conceptual design options
� Identify preferred conceptual design option
� Prioritize desired improvements
� Report out
� www.dallascompletestreets.wordpress.com