King Fahd University of Petroleum and Minerals
CEM 512Value Engineering
Term ProjectTurbine Fuel Gas Heater
Prepared by: Ahmed S. Al ZahraniID# 200295
To: Dr. Sady Assaf
August 8, 2005
OUTLINE
INTRODUCTION
JOB PLAN
Information Phase
Creative Phase
Judicial Phase
Development Phase
Presentation &Implementation Phase
Summary
INTRODUCTION
• In gas compression plant, the compressors are driven by a combustion gas turbine.
• For best turbine performance, the fuel gas temperature should be at certain temperature (120 – 140 deg F).
• Electric Coil heater that provide sufficient heat to fuel gas.
• The objective is to find better heating medium using Value Engineering Technique.
INFORMATION PHASE• The information sources:
– Equipment Manual– Plant Operating Manual– Material Control Group– Planners– Colleagues
Performance Criteria
• Objectives & Desired Criteria:– To give sufficient heat to fuel gas to be in the
acceptable range.– To control and maintain that desired
condition.
• Desired Features & Criteria:– Minimum construction cost.– Easy Control and Operation.– Safe Operation.– Easy Maintenance.
Cost Information
ItemCost,
$
Electric Coil30,000
Wiring & Installation5,000
Instrumentation5,000
Total40,000
Function Identification
• WHAT DOES IT NOW DO?
• WHAT MUST IT DO?
VERBNOUN
SupplyHeat
ControlTemperature
VERBNOUN
SupplyHeat
ControlTemperature
EnhancePerformance
MinimizeMaintenance
Function Identification
To Meet TheRequired Condition
To IncreaseTemperature
Have HeatingMedium
WHY? FUNCTIONHOW?
Beside the Electric Heater:• Steam Jacket.• Exchange Heat Between Hot Lube Oil
and FG.• Exchange Heat Between Process Gas
and FG.• Eliminate the Heater.
CREATIVE PHASE
JUDICIAL PHASE
Goals, Criteria, Functions, FeaturesRaw
ScoreAssignedWeight
A. Construction Cost310
B. Safety27
C. Easy Maintenance13
D. Easy Operation & Control13
BCD
AA-2A-1D-1
BB-1B-1
CC-1
HOW IMPORTANT
3. Major Preference
2. Medium Preference
1. Minor Preference
JUDICIAL PHASE
IDEASCos
tSafet
yMaintenanc
eOperation
TOTAL10733
Proposed Idea:Electric Heater
2322534
1. Steam Jacket4344851
2. Heat Exchange with Lube Oil
4133653
3. Heat Exchange with Process Gas
3123525
4. Eliminate Heater5132722
JUDICIAL PHASE
IDEAADVANTAGESDISADVANTAGESRank
Electric HeaterEasy operationHigh Cost,
Difficult Maintenance
2
Steam JacketLow Cost, Safe, Easy
Maintenance
Difficult Operation
1
Heat Exchanging with Lube Oil
Low Cost, Easy Operation
Not Safe, Difficult Maintenance
3
Heat Exchanging with Process Gas
Low Cost, Easy Operation
Not Safe, Difficult Maintenance
4
Eliminate Heating
No CostNot Reliable,
Affect the turbine Performance
5
DEVELOPMENT PHASE
INTIAL COSTS, $
ELECTRICAL HEATER40,000
STEAM JACKET7,500
SAVINGS32,500
LIFE CYCLE COSTS, $
ELECTRICAL HEATER7,000
STEAM JACKET3,000
SAVINGS4,000
• Will be presented to the operation Manager.
• Decision will be taken by the Manager.
• Implementation will be done by Maintenance Division.
Presentation & Implementation