kern county solar projects spreadsheets and maps

8
03/14/2013 Name Case Number Consultant Acreage MW Location Application Deemed Complete Approved Substation Desert/Valley Chevron Energy Solutions Company by URS Corporation CUP 24, Map 103-7 NA 18 2 former Chevron Bakersfield Refinery N/A 03/09/2009 on-site valley Meadows Field Solar Project CUP 53, Map 102 NA 9 0.75 Meadow Field Airport N/A 04/28/2008 on-site valley GE Energy LLC by URS Corp CUP 36, Map 167 NA 337 40 13681 Chantico Rd N/A 06/19/2009 Tehachapi n/a LADWP CUP 5, Map 150 NA 75 10 Jawbone Canyon Rd N/A 12/16/2009 Pinetree n/a Vaquero Energy CUP 15, Map 125 NA 10 1 N/A On-Site valley Cenergy Power by McIntosh & Assoc. CUP 18, Map 55 NA 2 0.5 N/A On-Site valley Renewable Technology Development CUP 17, Map 57 NA 2 0.5 Driver Road, South of Kimberlina N/A 11/11/2010 unknown valley Rosamond Solar Project by SGS Antelope Valley LLC GPA 16, ZCC 33, CUP 27, Map 232 ESA 960 120 Rosamond N/A 11/11/2010 Whirlwind desert Lost Hills Solar by NextLight GPA 6, CUP 11, Map 28 ICF 307 33 East of Hwy 46 and Hwy 33 N/A 10/26/2010 Blackwell valley Cenergy Power CUP 10, Map 29 160 1.5 GP Rd, NW of Lost Hills N/A 12/09/2010 Copus valley Maricopa Sun Solar Complex Project by Maricopa Sun LLC GPA 5, CUP 5, Map 158/ GPA 1, CUP 7, Map 159 ICF 6,046 700 West of I-5 and east of Taft N/A 03/29/2011 Copus Road and Lakeview valley SKIC Development Inc CUP 6, 7 & 8, Map 158 NA 321 20 South Kern Industrial Center N/A 12/07/2010 Copus valley Kern County General Services Dept - Lerdo Detention Facility CUP 47-Map 81 NA 14 2 17801 Industrial Farm Road - Lerdo Detention Facility N/A 04/14/2011 on-site valley RE Distributed Solar Projects (RE Barren Ridge 1) CUP 1, Map 151 588 74 North of Philips Road N/A 12/06/2011 no gen-tie desert RE Distributed Solar Projects (RE Rosamond One) SPA 1, ZCC 1, CUP 3, Map 231- 03 320 20 NW Favorito and 60th N/A 12/06/2011 no gen-tie desert RE Distributed Solar Projects (RE Rosamond Two) CUP 4, Map 231-03 160 20 Willow Springs N/A 12/06/2011 no gen-tie desert RE Distributed Solar Projects (RE Columbia One) ZCC 46, CUP 31, Map 196 165 20 Mojave N/A 12/06/2011 no gen-tie desert RE Distributed Solar Projects (RE Columbia Two) CUP 32, Map 196 132 20 Purdy west of Hwy 14 N/A 12/06/2011 no gen-tie desert RE Distributed Solar Projects (RE Columbia Three) CUP 33, Map 196 68 10 Purdy west of Hwy 14 N/A 12/06/2011 no gen-tie desert RE Distributed Solar Projects (RE Great Lakes) ZCC 118, CUP 34, Map 230 40 5 NE of Sierra Hwy and Avenue A N/A 12/06/2011 no gen-tie desert RE Distributed Solar Projects (RE Rio Grande) CUP 30, Map 196 47 5 Mojave 03/19/2010 no gen-tie desert Elk Hills Solar by enXco CUP 16, Map 139 47 7 Highway 119 east of Valley West Road N/A 12/08/2011 Elk Hills valley Goose Lake Solar by enXco CUP 7, Map 53 94 15 Corcoran Rd and Carmel Rd N/A 12/08/2011 Gooselake valley Smyrna Solar by enXco CUP 5, Map 7 125 12 Intersection of Pond Rd and Peterson Rd N/A 12/08/2011 Smyrna valley Antelope Valley Solar Project by Renewable Resources GPA 17, ZCC 34, CUP 28, Map 232; GPA 3, ZCC 13, CUP 8, Map 233 ESA 5,698 650 Rosamond N/A 02/04/2010 Whirlwind desert Cenergy Power by McIntosh & Associates CUP 11, Map 29 NA 29 3 North of G.P. Road adjacent to the California Acquaduct N/A 12/09/2010 Copus valley KERN COUNTY SOLAR PROJECTS Approved Projects Single EIR ICF Single EIR ESA

Upload: others

Post on 03-Feb-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

03/14/2013

Name Case Number Consultant Acreage MW Location

Application

Deemed

Complete

Approved Substation Desert/Valley

Chevron Energy Solutions Company by URS

CorporationCUP 24, Map 103-7 NA 18 2

former Chevron Bakersfield

Refinery

N/A

03/09/2009 on-site valley

Meadows Field Solar Project CUP 53, Map 102 NA 9 0.75 Meadow Field AirportN/A

04/28/2008 on-site valley

GE Energy LLC by URS Corp CUP 36, Map 167 NA 337 40 13681 Chantico Rd N/A 06/19/2009 Tehachapi n/a

LADWP CUP 5, Map 150 NA 75 10 Jawbone Canyon Rd N/A 12/16/2009 Pinetree n/a

Vaquero Energy CUP 15, Map 125 NA 10 1 N/A On-Site valley

Cenergy Power by McIntosh & Assoc. CUP 18, Map 55 NA 2 0.5 N/A On-Site valley

Renewable Technology Development CUP 17, Map 57 NA 2 0.5 Driver Road, South of Kimberlina N/A 11/11/2010 unknownvalley

Rosamond Solar Project by SGS Antelope Valley

LLC

GPA 16, ZCC 33, CUP 27, Map

232ESA 960 120 Rosamond

N/A11/11/2010 Whirlwind desert

Lost Hills Solar by NextLight GPA 6, CUP 11, Map 28 ICF 307 33 East of Hwy 46 and Hwy 33 N/A 10/26/2010 Blackwell valley

Cenergy Power CUP 10, Map 29 160 1.5 GP Rd, NW of Lost Hills N/A 12/09/2010 Copus valley

Maricopa Sun Solar Complex Project by Maricopa

Sun LLC

GPA 5, CUP 5, Map 158/ GPA 1,

CUP 7, Map 159ICF 6,046 700 West of I-5 and east of Taft

N/A03/29/2011

Copus Road and

Lakeview valley

SKIC Development Inc CUP 6, 7 & 8, Map 158 NA 321 20 South Kern Industrial Center N/A 12/07/2010 Copus valley

Kern County General Services Dept - Lerdo

Detention FacilityCUP 47-Map 81 NA 14 2

17801 Industrial Farm Road - Lerdo

Detention FacilityN/A

04/14/2011 on-site valley

RE Distributed Solar Projects (RE Barren Ridge 1) CUP 1, Map 151 588 74 North of Philips RoadN/A

12/06/2011 no gen-tie desert

RE Distributed Solar Projects (RE Rosamond

One)

SPA 1, ZCC 1, CUP 3, Map 231-

03320 20 NW Favorito and 60th

N/A12/06/2011 no gen-tie desert

RE Distributed Solar Projects (RE Rosamond

Two)CUP 4, Map 231-03 160 20 Willow Springs

N/A12/06/2011 no gen-tie desert

RE Distributed Solar Projects (RE Columbia One) ZCC 46, CUP 31, Map 196 165 20 MojaveN/A

12/06/2011 no gen-tie desert

RE Distributed Solar Projects (RE Columbia Two) CUP 32, Map 196 132 20 Purdy west of Hwy 14N/A

12/06/2011 no gen-tie desert

RE Distributed Solar Projects (RE Columbia

Three)CUP 33, Map 196 68 10 Purdy west of Hwy 14

N/A12/06/2011 no gen-tie desert

RE Distributed Solar Projects (RE Great Lakes) ZCC 118, CUP 34, Map 230 40 5 NE of Sierra Hwy and Avenue AN/A

12/06/2011 no gen-tie desert

RE Distributed Solar Projects (RE Rio Grande) CUP 30, Map 196 47 5 Mojave 03/19/2010 no gen-tie desert

Elk Hills Solar by enXco CUP 16, Map 139 47 7Highway 119 east of Valley West

Road N/A12/08/2011 Elk Hills valley

Goose Lake Solar by enXco CUP 7, Map 53 94 15 Corcoran Rd and Carmel Rd N/A 12/08/2011 Gooselake valley

Smyrna Solar by enXco CUP 5, Map 7 125 12Intersection of Pond Rd and

Peterson Rd N/A12/08/2011 Smyrna valley

Antelope Valley Solar Project by Renewable

Resources

GPA 17, ZCC 34, CUP 28, Map

232; GPA 3, ZCC 13, CUP 8,

Map 233

ESA 5,698 650 Rosamond

N/A

02/04/2010 Whirlwind desert

Cenergy Power by McIntosh & Associates CUP 11, Map 29 NA 29 3North of G.P. Road adjacent to the

California Acquaduct N/A 12/09/2010 Copus valley

KERN COUNTY SOLAR PROJECTS

Approved Projects

Single EIR ICF

Single EIR ESA

03/14/2013

Catalina (Enxco)ZCC 8, Map 215; ZCC 8,

Map 215RBF 1,223 150

West of Tehachapi-Willow Springs

Rd, north of Rosamond Blvd.

N/A

12/06/2011 Whirlwind desert

Beacon Solar by Nextera CUP 11, Map 152 ESA 2320 250 Sections 3, 4, 8, 9; T31S, R37E 08/10/2011 10/01/3012

LADWP Barren

Ridge desert

Old River One by RE Old River One LLC CUP 63, Map 142 Single EIR ICF 105 16 Old River Rd 03/26/2010 11/13/2012 Old River valley

Adobe Rd and Wheeler Ridge Rd 05/09/2011 Wheeler Ridgevalley

GPA 5/CUP 16, Map 125 810 75

Sec 22 & 27, T30S, R29E, on the

south side of Hermosa Road, west

side of Comanche Drive, 07/26/2011 Wheeler Ridge

valley

Pioneer Green Energy Solar (3 sites: Wildwood,

Pumpjack & Rio Bravo)

CUP 5, Map 97; CUP 5, Map 30;

CUP 6, Map 97Single EIR

ESA 480 125 N of Lokern, S of D7th Standard Rd 03/20/2011

Tremblor &

Midwayvalley

acres 20872

TOTAL MW APPROVED 2428.25

FRV Valley Solar Project (2sites: Regulus, Adobe)GPA 3/ CUP 24, Map 161

Single EIR ICF160 20

03/14/2013

Name Case Number Consultant Acreage MW Location

Application

Deemed

Complete

Approved Substation Desert/Valley

FRV Mojave Solar Project by FRV Mojave Solar,

LP

SPA 24, ZCC 56, CUP 62, Map

213 ICF 174 20

APN 431-010-02 & 431-030-02

SEC of Sierra Highway & Sopp

Road 04/12/2011 Windhub desert

Monte Vista Solar Array by First SolarGPA 24, ZCC 45, CUP 29, Map

196ESA 1,040 126 Southeast of Mojave 08/25/2009 Windhub desert

Rosamond Solar Array by First SolarGPA 14, ZCC 31, CUP 25, Map

232ESA 1,177 155 West of Rosamond 12/29/2009 Whirlwind desert

Willow Springs Solar Array by First SolarGPA 15, ZCC 32, CUP 26, Map

232ESA 1,402 160 Northwest of Rosamond 12/29/2009 Whirlwind desert

High Desert Solar by Element Power CUP 34, Map 196 154 18 NW United Street and Purdy Ave 10/21/2010 unknown desert

Orion Solar by Fotowatio Renewable VenturesGPA 2, Map 162; CUP 6, Map

162; WA Cancellation 11-9; LLA

36-11

ICF 265 20 Herring Rd and S. Edision Rd 10/06/2011

unknown

valley

FS Weldon1 Solar - Foresight Solar-

ZCC/CUP , Map 43/CUP Map

43 EIR ICF 538 20 Kelso Valley Road, south of SR 178 12/19/2011 Weldon mountain

Wasco-Charca Solar by Solar Land Partners CUP 14, Map 56 EIR ICF 72 8

Hwy 46, less than ¼ mile east of

Hwy 43 and on the border of

Wasco’s city limits 03/12/2012

Wasco &

Charca valley

Fremont Valley Preservation Water Bank & Solar

Project

ZCC 3/CUP 1 Map 114; ZCC

13/CUP 13, Map 133; CUP 4,

Map 134; CUP 12, Map 152;

GPA 2 Map 114; GPA 3, map

133; GPA 2, map 134; GPA 3,

Map 152 EIR ESA 4,806 1008

north of SR 58 and east of SR 14, in

the Cantil/Rancho Seco area of

eastern Kern 03/23/2012

LADWP Barren

Ridge, Yeager,

Kramer desert

Kern Solar Ranch

GPA 3/CUP 2, Map 50

GPA 3/CUP 7 Map 51

GPA 1/CUP 1, Map 73

GPA 2/CUP 6, Map 74

GPA 3/CUP 2, Map 50; GPA

3/CUP 7, Map 51; GPA 1/CUP

1, Map 73; GPA 2/CUP 6, Map

74 EIR ICF 6,100 1,000 south of SR 46 and west of SR 33

new off-site

PG&E

substation valley

SLP Solar (Sunlight Partners, LLC)

CUP, Map 230-21; ZCC/CUP,

Map 231; ZCC/CUP Map 231-

14; ZCC/CUP Map 231-17;

ZCC/CUP Map 231-19;

ZCC/CUP Map 231-20 Single EIR ESA 139.88 12-12.5

Near Rosamond Blvd. from Sierra

Hwy west to 90th Street West 08/28/2012 Unknown Desert

RE Astoria Solar by RE Astoria LLC (Recurrent). CUP 10, Map 233 Single EIR ICF 1,501 175

Astoria Dr, 180th

St, Ave A, and

205th

Str, Willow Springs area 01/25/2013

FRV EAFB Solar Holdings LLC (Oro Verde Solar) Franchise agreement Single EIR ESA Edwards AFB unknown

Kingbird Solar by FirstSolar SPA 3/ZCC 16 /CUP 9 Map 233 EIR ESA 324 40

NW Corner of 170th Street West

and Avenue A 01/25/2012 Whirlwind desert

RE Columbia and RE Colubmia 2 by Recurrent

CUP 31/CUP 32, Map 196

MODIFICATION addendum NA 476 40

Southeast of Purdy Avenue and Holt

Street, South of Mojave 03/02/2013

Projects deemed complete for processing by Staff

03/14/2013

Rosamond Solar by SGS addendum NA 230 40

Oak Creek Rd, Sect 13 & 29 of

T.11N, R.13W SBB&M 03/15/2013

Blackwells Solar Park

GPA.CUP Map 51, CUP Map 51-

6 ICF 476 20 SR 33 south of SR 46 11/30/2012 Blackwell

FRV EAFB Solar Holdings LLC (Oro Verde Solar) Franchise agreement Edwards AFB unknown

acres15,868 2850

Total MW Pending

03/14/2013

Name Case Number Consultant Acreage MW LocationApplication

Deemed Approved Substation Desert/Valley

Avenida Del Sol Solar Project CUP, Map 46 37 5 Inyokern on-site desert

Aeromen Solar by Aeromen LLC 237 35

APN #237-562-12, 35, 37, 40, 41

and 42 unknown desert

Gettysburg Solar by WDG SPP, ZCC, CUP, Map 213 120 20 unknown desert

Chaparral Solar by Aurora Solar (Iberdrola) CUP Map 160 172 30 old River Rd north of Copus Rd Copus valley

Gateway Solar Project by East Kern Properties,

LLCCUP, Map 194 3,066 350

NWC Hwy 58 and California City

Blvd unknowndesert

Browning Rd Solar by Integrated Resources

Development CUP, Map 33-1 28 4.5 Browning Rd, McFarland unknown valley

Twisselman Solar by Gestamp CUP, Map 33-1 103 17

S/S of Twisselman Rd, betwn

Holloway Rd and West Side Hwy unknown valley

Calwest Energy by Jonathan Bender CUP 196 29 APN 236-360-64 & 12 unknown desert

Champagne Road Solar PV Project by Aurora

Solar, LLC (Iberdrola Renewables) CUP 214 320 40

APN 346-032-05 6970 Tehachapi

Willow Springs Road unknown desert

CA Solar LLC CUP Map 139 37 3

SR 119, 5 mi east of Taft- Dustin

Acres area unknown valley

Axio Power w/ TRC Solutions CUP Map 98 McFarland-Delano SLF unknown valley

Axio Power w/ TRC Solutions CUP Map 98 Buttonwillow SLF unknown valley

Pond-Poso Solar by SolarGEN CUP Map 54 35 5

intersection of Wedel Avenue and

Jackson Avenue, 2 miles south of

SR 46 11 miles west of Wasco Semitropic valley

Paso Robles Solar by SolarGen

CUP Map 30

80 10

intersection of McCombs Road and

Highway 46, west of Corcoran Road Gooselake valley

Thermopylae Solar by WDG Captial Partners

CUP Map 237/CUP Map 237-

33/CUP 8, Ma 237 MOD 94 20

Frazier Mountain Park Road, 1 mile

west of LeBec Road and 1.5 miles

west of I-5. unknown mountain

Borax Solar Project by Valos Solar Ventures, LCC CUP 192 320 20

Gephart Road, north of SR 58, 3

miles northeast of North Edwards

(232-051-12) unknown

desert

CUP, Map 124-14 45Oswell Solar Section 14, T30S,

R28E, off of South Oswell

CUP Map 126 40

Bena Solar T30S, R30E, off Bena

Road

Harris ZCC/CUP Map 166-25 40 1.5 Tehachapi Blvd & Gemstone desert

SEPV Mojave West ZCC/CUP/CUP Map 197 230 40 Oak Creek Rd desert

Springbok Solar by 8 Minute Energy Rewables (3

sites)

ZCC/CUP Maps 133, 134, 152,

153 Single EIR unknown 500

Sects: 26 & 27 T.30S, R.37E

MDB&M; 32 & 33 T.30S, R.38E;

12 T.31S, R.37E desert

Prewoznik Solar Project CUP Map 193 unknown unknown

frontage road of SR 58West, ½

mile west of North Edwards desert

4,768

Single EIR

Application submitted by applicant, but deemed incomplete for processing by Staff

Single EIR

Ignite solar valley

03/14/2013

Name Case NumberDecision

Making Body Acreage MW Location

RE Distributed Solar Projects (RE Tehachapi

Solar One)CUP 75, Map 164 160 20 Tehachapi

RE Distributed Solar Projects (RE Tehachapi

Solar Two)CUP 76, Map 164 157 20 Tehachapi

Name Case Number Consultant Acreage MW Location

Application

Deemed

Complete

Approved Substation Desert/Valley

7th Standard Rd Solar by FirstSolar CUP , Map 100 188 20

7th Standard Road, between Enos

Lane and Superior Road

Enos Rd

substation valley

Sherwood Av Solar CUP, Map 35 4 1

34556 Sherwood Ave, 1 mile west

of Hwy 65

existing

transmission line valley

North Muroc Solar by Sepctrum EnergyZCC 9, CUP 7, Map 194 73 9 North of Edwards Air Force Base 03/20/2010

unknowndesert

Nautilus Cantil Solar by Spectrum EnergyZCC 12, CUP 12, Map 133 77 9 Cantil 03/19/2010

unknowndesert

Sunshine Solar by CongentrixSPA 25, ZCC 146, CUP 104,

Map 231319 40

East of 100th Street West and

Gaskell Road09/08/2010 unknown desert

Pham Solar Project by Sunlight Partners, LLC CUP 231 29

APN 252-332-20 NWC of West

Rosamond Blvd & 83rd Street West unknown desert

Reck Solar Project by Sunlight Partners, LLC CUP 231 19

APN 374-250-08 North of Elder

Ave, between 90th Street West &

85th Street West unknown desert

Old River Two by RE Old River Two LLC CUP 64, Map 143 110 17 Old River Rd 03/26/2010 Old River valley

Weldon Solar Project by Renewable ResourcesZCC 3, CUP 1, Map 42-13; ZCC

1, CUP 1, Map 42-24ICF 300 60

North & South of Hwy 178;

between Fay Ranch Rd & Bonkell

St.

02/08/2010 Weldon Mountain

EnXco Development Corp CUP 5, Map 162 43 6

San Bernard. David Road, east of

Edison Rd

FRV Valley- Rigel Site GPA 3/CUP 25, Map 161 158 20 David Rd

SunGen Solar by La Paloma CUP 5 Map 118 ICF 398 31 East of McKittrick 04/08/2011 McKittrickvalley

Interstate Ministorage by Duane DeBlauw CUP 230 10

Apn 258-090-27 Adjacent to 2463

15th Street West unknown desert

PROJECTS DENIED

Single EIR

Single EIRPlanning

Commision

PROJECTS WITHDRAWN / TERMINATED

Kern County Valley Solar Projects

Blackwell Solar Park

Ignite Solar FS Weldon 1 Solar

Wasco Charca Solar

- Approved Project

- Proposed Project

FRV

Kern Solar Ranch

Oro Verde

Kingbird

Champagne

Gettysburg

Gateway

North Muroc

Borax

Cal West

Catalina Solar

FRV Mojave

High Desert

south

Kern County—Desert Solar Projects

(Nautilus)

(Nautilus)

Solar Electric Solutions

Proposed Projects

Approved Projects

Denied Projects

Electrical Substations

Whirlwind Substation

Windhub Substation

Harris

Fremont Valley Preservation

Tenaska Solar

Springbok Solar

Beacon Solar

Prezwoznik

RE Astoria

SEPV Mojave West