Vogtle Units 3 & 4 Nuclear DevelopmentEarly Site Construction Progression

Mike Jordan

New Nuclear Projects-Engineering/Construction

May 1, 2013

Page 2: K.2 vogtle units 3 and 4 nuclear development early site construction progression

2

Vogtle Plant – Units 3 & 4

FAST FACTS• Two Nuclear Generating Units

• Capacity – 1117 MW Per Unit

• Operator – Southern Nuclear

• Technology - Westinghouse AP1000

• Constructor – CBI (formerly Shaw)

• Located in Burke County Near

Waynesboro, Ga.

• Size – Approximately 1800 Acres

Page 3: K.2 vogtle units 3 and 4 nuclear development early site construction progression

3

Vogtle 3 & 4 Timeline

Page 4: K.2 vogtle units 3 and 4 nuclear development early site construction progression

4

Vogtle 3 & 4 – Initial Site WorkJULY 2009

Page 5: K.2 vogtle units 3 and 4 nuclear development early site construction progression

5

Vogtle 3 & 4 Site Layout

•Lay down & Storage area

Modular Assembly Building

•Containment Vessel FAB Area

•Units 3 & 4 Nuclear Islands

•Cooling Towers Foundations

•Fabrication & Laydown Area

•Parking & Offices

•Units 1 & 2

January 2013

Page 6: K.2 vogtle units 3 and 4 nuclear development early site construction progression

6

Initial Construction Activities

• Clearing, grubbing, excavation, backfill, grading, and dewatering

• Install temporary and permanent access roads and drainage features

• Install temporary facilities – office trailers, change shacks, underground electrical, water, fiber, laydown areas, and concrete batch plant

• Set up site security – guard houses, fences, access gates, badging facilities, etc.

• Build warehouses, offices, and Training/Simulator Building

• Relocate 500 kv transmission line interferences

Page 7: K.2 vogtle units 3 and 4 nuclear development early site construction progression

7

Plant Area Earthwork Progress

October 2009

Page 8: K.2 vogtle units 3 and 4 nuclear development early site construction progression

8

Plant Area Earthwork Progress

October 2009

Page 9: K.2 vogtle units 3 and 4 nuclear development early site construction progression

9

Plant Area Earthwork Progress January 2010

Page 10: K.2 vogtle units 3 and 4 nuclear development early site construction progression

10

Plant Area Earthwork Progress

March 2010

Page 11: K.2 vogtle units 3 and 4 nuclear development early site construction progression

11

Plant Area Earthwork Progress

March 2010

Page 12: K.2 vogtle units 3 and 4 nuclear development early site construction progression

12

Plant Area Earthwork Progress

December 2010

Page 13: K.2 vogtle units 3 and 4 nuclear development early site construction progression

13

Early Plant Major Construction Activities

• Complete Mechanically Stabilized Earth (MSE) wall, mud

mat, and concrete basemat for the Nuclear Island

• Install 10 ft diameter Circulating Water Piping

• Install Turbine Building foundations

• Erect 13 story Modular Assembly Building

• Install foundations for and erect 1M Ton O Crane

• Fabricate 140 ft diameter Containment Vessel bottom head

• Install foundations for 560 ft tall Cooling Towers

Page 14: K.2 vogtle units 3 and 4 nuclear development early site construction progression

14

Plant Area Progress

March 2011

Page 15: K.2 vogtle units 3 and 4 nuclear development early site construction progression

15

Plant Area Progress

March 2011

Page 16: K.2 vogtle units 3 and 4 nuclear development early site construction progression

16

Plant Area Progress

March 2011

Page 17: K.2 vogtle units 3 and 4 nuclear development early site construction progression

17

Key Components/Facilities Progress

July 2011

Page 18: K.2 vogtle units 3 and 4 nuclear development early site construction progression

18

July 2011Key Components/Facilities Progress

Page 19: K.2 vogtle units 3 and 4 nuclear development early site construction progression

19

Key Components/Facilities Progress

July 2011

Page 20: K.2 vogtle units 3 and 4 nuclear development early site construction progression

20

Aerial Photo - Plant Area

August 2011

Page 21: K.2 vogtle units 3 and 4 nuclear development early site construction progression

21

January 2012

Key Components Progress

Page 22: K.2 vogtle units 3 and 4 nuclear development early site construction progression

22

January 2012Key Components Progress

Page 23: K.2 vogtle units 3 and 4 nuclear development early site construction progression

23

Key Components Progress

January 2012

Page 24: K.2 vogtle units 3 and 4 nuclear development early site construction progression

24

Key Components Progress July 2012

Page 25: K.2 vogtle units 3 and 4 nuclear development early site construction progression

25

Key Components Progress

July 2012

Page 26: K.2 vogtle units 3 and 4 nuclear development early site construction progression

26

Key Components Progress

July 2012

Page 27: K.2 vogtle units 3 and 4 nuclear development early site construction progression

27

Key Components Progress January 2013

Page 28: K.2 vogtle units 3 and 4 nuclear development early site construction progression

28

Key Components Progress January 2013

Page 29: K.2 vogtle units 3 and 4 nuclear development early site construction progression

29

Key Components Progress January 2013

Page 30: K.2 vogtle units 3 and 4 nuclear development early site construction progression

30

1ST Nuclear Concrete

• Nuclear Island Basemat is the foundation for the Reactor Containment Building and the Reactor Auxiliary Building and is the first safety related concrete placement

• Nuclear Island Basemat is six (6) foot thick and contains over 6800 cubic yards of concrete

• This placement of concrete was rehearsed during a 1/6 size “mock-up” in September 2012 to ensure a successful continuous pour

• The actual placement was delayed several months due to rebar discrepancies in the design and final resolution with the NRC

• In March 2013 the full size Nuclear Island Basemat was placed successfully in approximately 51 hours

Page 31: K.2 vogtle units 3 and 4 nuclear development early site construction progression

31

1st Nuclear Concrete Major Milestone

Unit 3 Nuclear Island Basemat Placement March 2013

Page 32: K.2 vogtle units 3 and 4 nuclear development early site construction progression

32

Some of the Facts

• Over 22 million cubic yards of earth were moved during excavation and backfill while preparing the site for construction

• The Nuclear Island area was excavated to a depth of approximately 80 ft to remove unsuitable marl material and replaced with Class I backfill

• The 70,000 square foot Simulator/Training Center took 1 year to complete and currently houses all operator training activities

• The 13 story Modular Assembly Building is over 300 ft long and is where structural modules are assembled and loaded on heavy haul transporters for moving to the appropriate plant location

• There are 23,000 tons of steel, 16M feet of cable, and 546,00 ft of piping associated with the two units

• There are currently over 2200 workers on site and the peak workforce will be around 5000

Page 33: K.2 vogtle units 3 and 4 nuclear development early site construction progression

33

Vogtle 3 & 4 Site Layout

•Lay down & Storage area

Modular Assembly Building

•Containment Vessel FAB Area

•Units 3 & 4 Nuclear Islands

•Cooling Towers Foundations

•Fabrication & Laydown Area

•Parking & Offices

•Units 1 & 2

January 2013

Page 34: K.2 vogtle units 3 and 4 nuclear development early site construction progression

34

Any Questions