    Western LRT StudyUPDATE

    National Capital Commission

    June 27, 2013

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    2/30

    2

    Overview

    Background

    What we heard

    Rochester Field Alignment

    Richmond Underground Dominion Station toCleary Station

    Lincoln Fields to Baseline Station

    Next steps

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    3/30

    Federal Interests in the Study AreaTunneys Pasture Station LRT operational 2018

    Bay view

    Proposed Interprovincial Transit CrossingParkway

    Central Experimental FarmDow

    s Lake

    Booth Street Complex

    Lanark (CBC) Site

    Pinecrest Creek

    Capital Arrival along the Queensway

    Airport Link

    O-Train Confederation Station Lands

    3

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    4/30

    What we heard

    Protect Capital Interest

    Protect the Byron Corridor

    Protect the Sir John A MacDonald Parkway Maintain access to the waterfront and

    pathway system

    Noise and Safety Concerns

    4

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    5/30

    Rochester Field

    5

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    6/30

    Rochester Field

    modified

    6

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    7/30

    Cost

    Rochester Field $1.7 B Underground full length

    Rochester Field $1.3 B Trench in Rochester Field, under Richmond Road

    Rochester Field $960M Not Acceptable At-grade in Byron Park

    Richmond Underground $900M At-grade to Cleary, under Richmond Road

    **costing does not include additional mitigation measures

    7

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    8/30

    Preferred Corridor

    Richmond Underground

    8

    Lincoln Fields

    New Orchard

    Cleary

    Dominion

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    9/30

    Modifications

    Skead St. to Cleary Station - Buried

    Natural Ventilation Options

    Dominion Station to Cleary Station

    9

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    10/30

    Dominion to Clearyaerial view

    10

    Cleary Station

    Dominion Station

    Rochester Field

    Sir John A MacDonald Pkwy

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    11/30

    Berm

    11

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    12/30

    Feasibility

    Maintenance of the watermain

    Control of groundwater

    Access to the construction zone

    12

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    13/30

    Feasibility

    Maintenance of the watermain

    Drawings and inspection reports available

    Typical support measures to be used

    Staged daylighting

    Evaluate short term closure

    Typical construction activity

    13

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    14/30

    Feasibility

    Control of groundwater

    Various shoring systems available

    Pumping to manage water and keep sitedry during construction

    Fairly shallow excavation needed

    Typical construction activity

    14

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    15/30

    Feasibility

    Access to the construction zone

    No access from Parkway

    Via Cleary, Transitway & Rochester Field

    Work areas needed for laydown areas

    Areas to be fully restored after construction

    Typical construction activity

    15

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    16/30

    Natural Ventilationoption

    16

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    17/30

    Natural Ventilationview from the pathway looking east

    17

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    18/30

    Improvementsbefore

    18

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    19/30

    Improvementsafter

    19

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    20/30

    20

    Dominion StationToday

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    21/30

    Dominion StationToday

    21

    Sir John A MacDonald Pkwy

    Dominion Station

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    22/30

    Dominion Stationaerial view

    22

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    23/30

    Rochester Field

    Today

    23

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    24/30

    24

    Rochester Fieldproposed

    Richmond Road

    Sir John A MacDonald Pkwy

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    25/30

    Cleary Stationview from the Parkway

    25

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    26/30

    Cleary Stationview from the Continental

    26

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    27/30

    Lincoln Fields to BaselineStage 1

    27

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    28/30

    Lincoln Fields to BaselineStage 2

    28

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    29/30

    Iris Stationpreferred option

    29

    Shallow Trench

  • 7/28/2019 June 27 Wlrtc Ncc Presentation Final

    30/30

    Next Steps

    30

    July 10 Transportation Committee

    July 17 City Council

    Functional Design and EA Documentation

    Decision included in 2013 TMP