LS Rail – Learnings from a differentiated

approach to ballast cleaning in the

Hunter Valley

1

Page 2: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

Agenda

1. Overview of LS Rail

2. ARTC Ballast Cleaning Contract

3. Ballast Cleaner Journey

4. First Possession

5. Subsequent Possessions including AMP’s

6. Key learnings

2

Page 3: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

1. Overview of LS Rail

Southern Cross Station Redevelopment – DOT, VIC

3

Page 4: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

Introducing LS Rail

■ Who we are – A JV between Leighton Contractors and Swietelsky

■ Why – Provide high production solutions to deliver optimal track

performance via more flexible and cost effective construction and

maintenance solutions

■ How – 1. Engage with rail clients to understand their needs

2. Customise our approach tapping into the world’s

largest privately owned fleet of high performance track

machines and highly skilled operators

4

Page 5: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

Who are Swietelsky?

■ One of Europe’s leading construction companies with a total of 10,000

staff – 1,700 within it’s rail division

■ World leader in developing and operating high performance, on track

technology and specialised railway equipment

■ Owner of the world’s largest private fleet of on track plant – over 500

high performance machines

■ Highly skilled people who design and patent machines through Plasser

& Theurer for specific client solutions

5

Page 6: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

Differentiators and Benefits

to our Clients

6

■ Access to the world’s largest fleet of high technology machines = WORLD

LEADING

■ Over 98% plant reliability – NO BREAKDOWNS

■ Utilise machines never seen in Australia to construct rail track twice as fast at

premium quality = SPEED IN DELIVERY

■ Customise solutions/machines to meet and exceed our clients requirements =

CLIENT FOCUSSED

■ Enable our clients to operate at maximum capacities and achieve maximum

revenues = ACHIEVING CLIENT BUSINESS GOALS

Page 7: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

Differentiators and Benefits

to our Clients

■ High production/output rates which enable ‘invisible solutions’ to MPM where

there is minimal impact on train operations = NO DISRUPTIONS

■ Achieve high quality construction through high technology plant which will reduce

maintenance cycles = COST EFFECTIVE

■ Highly skilled and trained personnel who are capable of operating in short

durations and consistently maintain the plant = SKILLED PEOPLE

■ A large resource pool to enable our clients people to focus on core business =

CLIENTS KEEP THEIR RESOURCES

■ Less people on site for shorter durations = SAFE

7

Page 8: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

Current LS Rail Plant

09-3X Dynamic Tamper – Hunter Valley Unimat 08 – 275 Tamper – Hunter Valley

SSP 303 Regulator – Hunter Valley

8

H1200 Flash Butt Welder – Maules Creek PK 1-20 – Track Laying RRL Package E

8

RM 80 UHR Ballast Cleaner & 8 MFC Wagons

Page 9: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

2. Ballast Cleaning for ARTC

Richmond Line Alliance – TCA, NSW

9

Page 10: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

The ARTC Contract

■ 2 + 3 Year option Contract with ARTC for ballast cleaning on the Hunter

Valley Network

■ Deliver 92Km of Ballast Cleaning in first 2 years

■ RM80 and 8 MFC Ballast Wagons chose as the best solution for the

contract due to constraints on the network and project budget.

■ First shift commenced on September 30th 2014

10

Page 11: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

Ballast Cleaning Scope

11

Page 12: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

3. Ballast Cleaner’s Journey

Swietelsky – PM1000, Europe

12

Page 13: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

Preparation

■ Modifications were also required to convert the coupling systems to meet Australian standards

■ Upon finalisation of contract negotiations the RM80 & 8 MFC wagons were transferred to Swietelsky’s depot in Fischermand, Austria

■ Structural modification at the MFC main frame to meet Narrow Non Electric Outline for ARTC

13

Page 14: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

Preparation

■ Entire upfront and post machine mapping and survey to confirm plant dimension and meet the ARTC TOC requirements according to the Rolling Stock outline

■ Repainting and branding were also finished prior to boarding the vessel for departure

14

Page 15: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

Leaving Port in Germany

15

Page 16: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

Arriving in Newcastle

16

Page 17: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

Transfer to South Maitland Depot

17

Page 18: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

■ Possession from 06:00 30 Sept to 06:00 3 October 2014

■ Scope – 4,000m

■ Location – Wollar

■ Actual completed – 4,327m

■ 2 cuts, either side of tunnel

■ Topography difficult – high embankments, deep cuttings and the tunnel

■ Mixture of spill to bank and MFC

18

4. First Possession 30th September 2014

Page 19: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

30 September 2014 Possession

Southern Freight Link Alliance – ARTC, NSW

19

Page 20: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

30 September 2014 Possession

Southern Freight Link Alliance – ARTC, NSW

20

Page 21: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

5. Subsequent Possessions including

AMP’s

Post Possession Swietelsky – PM1000, Europe

21

Page 22: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

ULAN to Date

■ Completed 6 x Major Closedowns

■ 26,304 Metres completed

■ 4,250m in 62hr possession in May with 1,600 in 12hr shift

■ Positive feedback from ARTC

Swietelsky – PM1000, Europe

22

Before-Morning of 12/02/15

After-Afternoon of 12/02/15

Page 23: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

February ULAN Pre and Post Shots

Swietelsky – PM1000, Europe

23

Before 10/02/15 After 12/02/15

Page 24: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

AMP Works

■ 24 x AMP shifts completed – record of 613m in 10hr possession

■ 10,278 metres completed

■ Logistical difficulties around various stabling points.

■ Unloading of spoil during the day critical.

Swietelsky – PM1000, Europe

24

RM80 working on the COAL ROADS Condition of DN COAL

Page 25: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

AMP Works

■ Works seriously affected during NSW storms on 20/21 April 15

■ AMPs cancelled due to network closures

■ Further AMPs cancelled due to requirement to keep Coal Rds open

■ AMPs being planned for later in 2015

Swietelsky – PM1000, Europe

25

Completed works post possession

Page 26: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

Ballast Cleaning Process

ULAN March 2015

Page 27: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

6. KEY LEARNINGS

27

■ Early pre-planning to ensure scope fully understood including:

■ Cut depths; and

■ Return rate

■ Importance of the use of SOG charts – time chainage charts but

with physical train lengths included

■ Positive location of cables.

■ Collaborative planning between LS Rail and ARTC staff

Page 28: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

6. KEY LEARNINGS

28

■ Ability for ARTC to utilise tamping plant on other areas during first

shift;

■ Ballast stockpile management and location critical;

■ Associated civils works can be delivered – improvement to access

roads and drainage

■ Strict maintenance regimes on plant.

Page 29: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

6. KEY LEARNINGS FOR THE FUTURE

29

■ Detailed geotechnical assessment of next areas required to enable

detailed planning;

■ Engineering Controls to allow adjacent line working whilst on the

UP Coal

■ Opportunity to work with ATWS as per European working methods

■ Innovative possession management to enable cleaning of track

sections adjacent to complex junctions

■ Better pre-planning with Corridor Managers to maximise beneficial

works

Page 30: Julian Sharp - Leighton Contractors - Learnings from a differentiated approach to ballast cleaning in the Hunter Valley

QUESTIONS