julian sharp - leighton contractors - learnings from a differentiated approach to ballast cleaning...
TRANSCRIPT
LS Rail – Learnings from a differentiated
approach to ballast cleaning in the
Hunter Valley
1
Agenda
1. Overview of LS Rail
2. ARTC Ballast Cleaning Contract
3. Ballast Cleaner Journey
4. First Possession
5. Subsequent Possessions including AMP’s
6. Key learnings
2
1. Overview of LS Rail
Southern Cross Station Redevelopment – DOT, VIC
3
Introducing LS Rail
■ Who we are – A JV between Leighton Contractors and Swietelsky
■ Why – Provide high production solutions to deliver optimal track
performance via more flexible and cost effective construction and
maintenance solutions
■ How – 1. Engage with rail clients to understand their needs
2. Customise our approach tapping into the world’s
largest privately owned fleet of high performance track
machines and highly skilled operators
4
Who are Swietelsky?
■ One of Europe’s leading construction companies with a total of 10,000
staff – 1,700 within it’s rail division
■ World leader in developing and operating high performance, on track
technology and specialised railway equipment
■ Owner of the world’s largest private fleet of on track plant – over 500
high performance machines
■ Highly skilled people who design and patent machines through Plasser
& Theurer for specific client solutions
5
Differentiators and Benefits
to our Clients
6
■ Access to the world’s largest fleet of high technology machines = WORLD
LEADING
■ Over 98% plant reliability – NO BREAKDOWNS
■ Utilise machines never seen in Australia to construct rail track twice as fast at
premium quality = SPEED IN DELIVERY
■ Customise solutions/machines to meet and exceed our clients requirements =
CLIENT FOCUSSED
■ Enable our clients to operate at maximum capacities and achieve maximum
revenues = ACHIEVING CLIENT BUSINESS GOALS
Differentiators and Benefits
to our Clients
■ High production/output rates which enable ‘invisible solutions’ to MPM where
there is minimal impact on train operations = NO DISRUPTIONS
■ Achieve high quality construction through high technology plant which will reduce
maintenance cycles = COST EFFECTIVE
■ Highly skilled and trained personnel who are capable of operating in short
durations and consistently maintain the plant = SKILLED PEOPLE
■ A large resource pool to enable our clients people to focus on core business =
CLIENTS KEEP THEIR RESOURCES
■ Less people on site for shorter durations = SAFE
7
Current LS Rail Plant
09-3X Dynamic Tamper – Hunter Valley Unimat 08 – 275 Tamper – Hunter Valley
SSP 303 Regulator – Hunter Valley
8
H1200 Flash Butt Welder – Maules Creek PK 1-20 – Track Laying RRL Package E
8
RM 80 UHR Ballast Cleaner & 8 MFC Wagons
2. Ballast Cleaning for ARTC
Richmond Line Alliance – TCA, NSW
9
The ARTC Contract
■ 2 + 3 Year option Contract with ARTC for ballast cleaning on the Hunter
Valley Network
■ Deliver 92Km of Ballast Cleaning in first 2 years
■ RM80 and 8 MFC Ballast Wagons chose as the best solution for the
contract due to constraints on the network and project budget.
■ First shift commenced on September 30th 2014
10
Ballast Cleaning Scope
11
3. Ballast Cleaner’s Journey
Swietelsky – PM1000, Europe
12
Preparation
■ Modifications were also required to convert the coupling systems to meet Australian standards
■ Upon finalisation of contract negotiations the RM80 & 8 MFC wagons were transferred to Swietelsky’s depot in Fischermand, Austria
■ Structural modification at the MFC main frame to meet Narrow Non Electric Outline for ARTC
13
Preparation
■ Entire upfront and post machine mapping and survey to confirm plant dimension and meet the ARTC TOC requirements according to the Rolling Stock outline
■ Repainting and branding were also finished prior to boarding the vessel for departure
14
Leaving Port in Germany
15
Arriving in Newcastle
16
Transfer to South Maitland Depot
17
■ Possession from 06:00 30 Sept to 06:00 3 October 2014
■ Scope – 4,000m
■ Location – Wollar
■ Actual completed – 4,327m
■ 2 cuts, either side of tunnel
■ Topography difficult – high embankments, deep cuttings and the tunnel
■ Mixture of spill to bank and MFC
18
4. First Possession 30th September 2014
30 September 2014 Possession
Southern Freight Link Alliance – ARTC, NSW
19
30 September 2014 Possession
Southern Freight Link Alliance – ARTC, NSW
20
5. Subsequent Possessions including
AMP’s
Post Possession Swietelsky – PM1000, Europe
21
ULAN to Date
■ Completed 6 x Major Closedowns
■ 26,304 Metres completed
■ 4,250m in 62hr possession in May with 1,600 in 12hr shift
■ Positive feedback from ARTC
Swietelsky – PM1000, Europe
22
Before-Morning of 12/02/15
After-Afternoon of 12/02/15
February ULAN Pre and Post Shots
Swietelsky – PM1000, Europe
23
Before 10/02/15 After 12/02/15
AMP Works
■ 24 x AMP shifts completed – record of 613m in 10hr possession
■ 10,278 metres completed
■ Logistical difficulties around various stabling points.
■ Unloading of spoil during the day critical.
Swietelsky – PM1000, Europe
24
RM80 working on the COAL ROADS Condition of DN COAL
AMP Works
■ Works seriously affected during NSW storms on 20/21 April 15
■ AMPs cancelled due to network closures
■ Further AMPs cancelled due to requirement to keep Coal Rds open
■ AMPs being planned for later in 2015
Swietelsky – PM1000, Europe
25
Completed works post possession
Ballast Cleaning Process
ULAN March 2015
6. KEY LEARNINGS
27
■ Early pre-planning to ensure scope fully understood including:
■ Cut depths; and
■ Return rate
■ Importance of the use of SOG charts – time chainage charts but
with physical train lengths included
■ Positive location of cables.
■ Collaborative planning between LS Rail and ARTC staff
6. KEY LEARNINGS
28
■ Ability for ARTC to utilise tamping plant on other areas during first
shift;
■ Ballast stockpile management and location critical;
■ Associated civils works can be delivered – improvement to access
roads and drainage
■ Strict maintenance regimes on plant.
6. KEY LEARNINGS FOR THE FUTURE
29
■ Detailed geotechnical assessment of next areas required to enable
detailed planning;
■ Engineering Controls to allow adjacent line working whilst on the
UP Coal
■ Opportunity to work with ATWS as per European working methods
■ Innovative possession management to enable cleaning of track
sections adjacent to complex junctions
■ Better pre-planning with Corridor Managers to maximise beneficial
works
QUESTIONS