Joint Training onEffective Electoral AssistanceEffective Electoral Assistance
UNDP Procurement: The Big PictureMaputo, 23-28 June 2008
Karen HongUNDP/PSO
Procurement Defined
Procurement is the overall process of acquiring goods,
civil works and services which includes all functions from
the identification of needs, selection and solicitation of
sources, preparation and award of contract, and all phases
of contract administration through the end of a services’
contract or the useful life of an asset.contract or the useful life of an asset.
UNDP Procurement Framework
••Focus on more integration between Program and Operations Focus on more integration between Program and Operations
••Decentralised procurementDecentralised procurement
•• Support via Support via -- Procurement Support Office in CopenhagenProcurement Support Office in Copenhagen
Principles of UNDP Procurement
o Best Value for Money
The following general principles must be given due
consideration while executing procurement on behalf
of UNDP:
o Best Value for Moneyo Fairness, Integrity and Transparencyo Effective International Competitiono In the interest of UNDP
Principles of UNDP Procurement
Best Value for MoneyWhat is the actual cost?
PurchasePrice
Acquisition
Installation
Maintenance
Disposal
Principles of UNDP Procurement
Tender Methodology Application Lead time
If Long Term Agreements (LTA) does not exist
RFQ – Request for Quotation
(Goods/Services)
< USD 100,000 1-3 weeks
ITB - Invitation to bid > USD 100,000 10-12 weeks
Effective International Competition:Types and implication on lead time
ITB - Invitation to bid
(Goods)
> USD 100,000 10-12 weeks
RFP – Request for proposal
(Services)
>USD 100,000 12-16 weeks
Where LTA exists
LTA – Long term agreements Where they exist 1 – 4 weeks
Write
Specifications
TOR and SOW
Prepare
Solicitation
Documents
Seek, Clarify
and Close
Choose a Procurement Method
Identify Needs
Procurement Chain
Evaluate Offers & potential Validation Test
and Close
OffersAward Contract
Manage the
Contract
Negotiate the Contract Evaluation
Contracts Review
Committee
Procurement Action Plan
Typical Procurement Action Plan with Timeline
2 weeks: EOI/Pre-qualification
WHAT?WHAT?Defines what will be purchased, how, when, estimated cost, timeline, the Defines what will be purchased, how, when, estimated cost, timeline, the levels of approval required, risk areas, etc.levels of approval required, risk areas, etc.Acts as a road map to the Buyer in specific and the project in generalActs as a road map to the Buyer in specific and the project in general
2 weeks: EOI/Pre-qualification3 weeks: International Tender Exercise 2 weeks: Technical Evaluation1 week: Financial evaluation1 week: Drafting of the CAP submission1 week: CAP review and preparation for the submission to ACP3 weeks: ACP review2 weeks: Negotiation and award of Purchase Order/Contract_________15 weeks3-4 weeks: Delivery into the country
Total 17 - 18 weeks
LEGAL
FRAMEWORK
PLANNING &
IMPLEMENTATION
VERIFICATION
OF RESULTS
POST ELECTION
THE
ELECTORAL
CONSTITUTION
LEGISLATION
ELECTORAL
BODIES
ELECTION CALENDAR
BUDGETING,
FUNDING &
FINANCING
RECRUITMENT &
PROCUREMENT
LOGISTICS & SECURITYTABULATION
OF RESULTS
COMPLAINTS &
APPEALS
OFFICIAL
RESULTS
LEGAL REFORM
AUDITS &
EVALUATIONS
INSTITUTIONAL
STRENGTHENING &
PROFESSIONAL
DEVELOPMENT
ARCHIVING &
RESEARCHVOTERS’ LISTS
UPDATECODES OF
CONDUCT
TRAINING &
EDUCATION
REGISTRATION &
NOMINATIONS
ELECTORAL
CAMPAIGN
VOTING
OPERATIONS &
ELECTION DAY
ELECTORAL
CYCLE OPERATIONAL
TRAINING FOR
ELECTION
OFFICIALS
CIVIC EDUCATION
PARTIES &
CANDIDATES
VOTER
REGISTRATION
OBSERVER
ACCREDITATION
CAMPAIGN
COORDINATIONPARTY
FINANCING
MEDIA
ACCESS
BREACHES &
PENALTIES
VOTING
VOTE
COUNTING
SPECIAL &
EXTERNAL
VOTING
VOTER
INFORMATION
CODES OF
CONDUCT
Constitution & legislation
Electoral System Electoral
Bodies
Staffing
Equipment
Office lease/maintenanceutilities
Warehousing
Verification of Results
Post-
Election
Legal Legal FrameworkFramework
Running Costs Running Costs of EMBof EMB
Tabulation & communication of official results
Complaints & Appeals
Audits & evaluations
Upgrades, updates, training (i.e. BRIDGE) sust. development
Reform
The Electoral
Cycle + its
relation to
consumables
IT equipment/ software/ website
Training
Security Costs
Uniforms
Travel
Conferences
Printing
Voting Operations
and Election Day
Voter Registration
Electoral Campaign
Training and Education
ToT, venues, transport, equipment
Training of civic & voter educators
VR equipm/materials/announcements
Party & Candidate services
Observers & accreditation
Party liaison/Media monitoring
Complaints mechanism
Polling station kits, Ballot boxes, voting screens, ink, lanterns, uniforms, polling station furniture
Embassy voting & out-of-country voting
relation to procurement
activities
Printing of manuals
Training of election officials
Materials/announcements (TV, radio, press)
Data processing, VR list & ID cards
Data Entry Centre, hardware, software
Ballot lottery, design, production, logistics
Polling Forms
Counting Centres
Call Centre/Website
Security
Procurement within an Electoral Cycle
Commonly purchased goods and services by UNDP-PSO
••Training and education: Training and education: Printing services (manuals, posters), training programme, logistics, training kits, venue, Printing services (manuals, posters), training programme, logistics, training kits, venue, hiring of expertshiring of experts
••Voter registration:Voter registration:Printing, purchase of office equipment, ICT, registration kits, logistics, hiring of expertsPrinting, purchase of office equipment, ICT, registration kits, logistics, hiring of experts
••Data Centre Data Centre Hardware, software, training, integration of services, venueHardware, software, training, integration of services, venueHardware, software, training, integration of services, venueHardware, software, training, integration of services, venue
••Electoral campaignElectoral campaignMedia monitoring, printing and venue set up for ballot lottery servicesMedia monitoring, printing and venue set up for ballot lottery services
••Elections dayElections daySecurity & nonSecurity & non--security printing, ballot boxes, polling day kits, voting screens, ink, security printing, ballot boxes, polling day kits, voting screens, ink, lanterns, uniforms, furniture, logisticslanterns, uniforms, furniture, logistics
Procurement within an Electoral Cycle
Roles of Specification/Terms of Reference
PurposePurpose::ToTo provideprovide aa basisbasis forfor obtainingobtaining aa goodgood oror serviceservice toto satisfysatisfy aa particularparticular needneed atat ananeconomicaleconomical costcost
Criteria of good specification:••IdentifyIdentify minimumminimum requirementsrequirements (design(design –– ii..ee.. dimension,dimension, weightweight oror performanceperformance ––whatwhat itit cancan do)do)••Generic,Generic, unbrandedunbranded toto allowallow forfor competitioncompetition••Well balance Well balance -- Not restrictive but also sets limits Not restrictive but also sets limits ••Well balance Well balance -- Not restrictive but also sets limits Not restrictive but also sets limits ••Identify standards in order to test for compliancy and provide quality assurance Identify standards in order to test for compliancy and provide quality assurance (i.e. ISO)(i.e. ISO)
If the Specifications/Terms of Reference are adequate, 50% of the procurement process is already done!
Procurement within an Electoral Cycle
Procurement Oversight
•Key purpose is to mitigate risks
•Provided for in UNDP through the Financial Rules and Regulations and Procurement Manual as part of Internal Control Framework – ‘Checks and Balances’ in action via strong segregation of duties
•Avoid a closed loop circuit – a process does not begin and end with one person or group
In practice?Done in many levels/stages of the procurement chainDone in many levels/stages of the procurement chain
Procurement within an Electoral Cycle
IDENTIFY NEEDS
EOI - SOURCING
PROCUREMENTMETHOD &
SOLICITATION DOCUMENTS
RECEIPT & OPENING
OF OFFERSCONTRACTS
FRR
FRR
FRRGP
GP
Check and balance
Good Practices
Segregation of
Control
Procurement Oversight
GP
OF OFFERSEVALUATION
CONTRACTS REVIEW
COMMITTEE
CONTRACT MANAGEMENT &ADMINISTRATION
DELIVERY
PAYMENTGOODSRECEIPT
END USER MONITORING
FRR
INVOICE CERTIFICATION
AWARD & CONTRACTFINALISATION
FRR
GP
GP
UNDP Procurement
•The volume of UNDP procurement tripled to approximately $2.5 billion over a three-year period • It is no longer a back-office, but rather a mission-critical function
•Procurement having a much larger scope than generally acknowledged!
One Step Back
Procurement Trend (USD Mil)
UNDP Procurement
Formulation of the Support to the 2008-2011 Strategic Plan of the National Election Commission in Rwanda
2008 Total Budget: US$ 19 million equal to 34% of overall 2008-2011 budget
Procurement related activities: US$ 11.7 equal to 61 % of total 2008
Case no: 1
Procurement related activities: US$ 11.7 equal to 61 % of total 2008 expenditure
(here of 36% for procurement of electoral material and logistics, adding up with tendering for training, civic education, EMB core running costs such as comms services, stationary, maintenance, car rental etc.)
UNDP Procurement
Formulation of the Support to the Zambian Electoral Cycle 2008-2011
Total Budget: US$ 17 million
Currently allocated procurement activities: US$ 8 million equal to 47 % of total expenditure
Case no: 2
(these 47% covers only procurement of civic & voter registration material, IT equipment, and contracts for various services but excluding E-Day material and logistics, hiring of international and national experts, EMB core running costs etc.)
Cost of Registration and Elections
Different issues involved – like-to-like comparison among countries unlikely
When cost is discussed it could involved:
• The direct procurement cost• The diffuse cost – difficult to quantify, will not be budgeted for in the ProDoc
Other issues to be considered:Other issues to be considered:
• Integrity cost – related to voter & ballot security. Crucial in emerging and post conflict countries, linked to public trust
• Core cost - election-based activities i.e. voter registration, polling day, counting etc. incurred independent of the integrity cost
So how much does an election actually cost?
Comparative DataCost of Registration & Elections
Stable Democracies: $1-3Chile $1.2Costa Rica $1.8Brazil $2.3Botswana $2.7India $1.0
Transitional Democracies: $3-8Mexico $5.9El Salvador $4.1Paraguay $3.7Lesotho $6.9Uganda $3.7
Post Conflict Elections in Peace Keeping Environment $8-45
Angola 1992 $22.0
Cambodia 1993 $45.5
Mozambique 1994 $10.2
Afghanistan 2004 $20.0
Haiti 2005 $11.0
UNDP Procurement
Case Study – VR Costing
Voter Registration kits with ID and photo for 2500-3000 Voters – Cost estimation (in USD)
Option 1: Low-tech voter registration kit
Option 2: OMR Forms registration kit
Option 3: Digital registration kit
Total price per Kit US$21.20 Total price per
KitUS$1,166 Total price per
KitUS$4,015
Total price per
VoterUS$ 0.71-0.85 Total price per
VoterUS$ 0.39-0.47 Total price per
VoterUS$1.34-1.67
OMR
Machine
US$60,000
Hidden cost -
Logistics
10%-25% of
contract cost
10%-25% of
contract cost
10%-25% of
contract cost
Elections Procurement Elections Procurement –– Risks and ChallengesRisks and Challenges
Structural Arrangements in placeStructural Arrangements in place-- Independent EMB (is it?)Independent EMB (is it?)-- EMB with a EMB with a permanentpermanent structure or is it a shell?structure or is it a shell?-- Human Resources in EMB and UNDP (bodies or technical experts?)Human Resources in EMB and UNDP (bodies or technical experts?)-- Procurement Structure in EMB and UNDP (low/high capacity?)Procurement Structure in EMB and UNDP (low/high capacity?)
The most commonly experienced risks in electoral procurement are:The most commonly experienced risks in electoral procurement are:
Supply Market DistortionSupply Market Distortion- Political lobbying lead to prejudicial outcome of the tender process, market distortion- Some commodities are very simple but limited specialized suppliers - Affects cost, best technical solution, undermined the procurement entity
Insufficient Budget- Lead to sub-optimal goods and services being purchased- Several ad hoc procurement exercise as patch work solution
Elections Procurement Elections Procurement –– Risks and ChallengesRisks and Challenges
Inflexible deadlines- Often use by critical stakeholders as a tool to exert pressure on the procurement agent - Cause serious value for money predicaments i.e. need to airfreight, create artificial single source situation
Incomplete or Late Technical Specifications and ToR/Request Technical Specifications and ToR/Request for assistancefor assistance- Creates small margin for error, remedy action limited - Creates ambiguity, a situation suppliers can manipulate and difficult for - Creates ambiguity, a situation suppliers can manipulate and difficult for procurement agent to disqualify- Can result in the wrong supplier being selected
National ownership, capacity and infrastructureownership, capacity and infrastructure- EMB may not be ready, not created yet or simply lack capacity- Capacity is not just a one-off training- Does policy frameworks, systems & tools, procedures, understanding of budget exist?policy frameworks, systems & tools, procedures, understanding of budget exist?- Leadership? - Some developing countries are challenged logistically i.e. DRC, G-Bissau
Elections Procurement Elections Procurement –– Risks and ChallengesRisks and Challenges
Reputational risk- To EMB, UNDP and the donor community- The media and certain stakeholders may misrepresent the procurement actions
Unrealistic Expectations-- By stakeholders on the Procurement Rules & Regulations to deliver By stakeholders on the Procurement Rules & Regulations to deliver -- IllIll--informed of the market response time and structureinformed of the market response time and structure-- IllIll--informed of the market response time and structureinformed of the market response time and structure
Technological Innovations and Sustainability- Over-focus on traditional products i.e. poloroid cameras, silver nitrate ink- Innovation in the market place was not embraced
Cost of high-tech solutions and sustainability- Cost of VR without logistics factored in could go up to US$1.78 Cost of VR without logistics factored in could go up to US$1.78 -- Could createCould create unrealistic benchmark for some countries-- Creates negative perception if this is not repeated in subsequent electionsCreates negative perception if this is not repeated in subsequent elections-- Could be a oneCould be a one--time event with little synergies into a wider institutional plantime event with little synergies into a wider institutional plan
Elections Procurement Elections Procurement –– SolutionsSolutions
Seek advice early- First and foremost – be aware that emergency ambulance is available! - Make informed decision
Integrate procurement into project formulation- Include procurement opinion/s into project formulation- Create a role for Procurement Officer in the PMU
Procurement tools + InnovationProcurement tools + Innovation- Procurement plans to establish realistic timeline- Long Term Agreement (LTA) to create efficient procurement, expedite delivery,
control unrealistic price/build economy of scale- Explore innovative options i.e. better/new products, leasing options, total
outsource, synergize with other civil activities
Respect for code of conduct- Play fair – suppliers and EMB
Be realistic with the budget- Tools available via the EC Methodological Guide and CORE guideline