joint review panel for the enbridge northern gateway project · joint review panel for the enbridge...
TRANSCRIPT
JOINT REVIEW PANEL FOR THE ENBRIDGE
NORTHERN GATEWAY PROJECT
COMMISSION D’EXAMEN CONJOINT DU PROJET
ENBRIDGE NORTHERN GATEWAY
Hearing Order OH-4-2011
Ordonnance d’audience OH-4-2011
Northern Gateway Pipelines Inc.
Enbridge Northern Gateway Project
Application of 27 May 2010
Demande de Northern Gateway Pipelines Inc.
du 27 mai 2010 relative au projet
Enbridge Northern Gateway
VOLUME 89
Hearing held at
Audience tenue à
Columbus Community Centre
7201 Domano Blvd.
Prince George, British Columbia
October 13, 2012
Le 13 octobre 2012
International Reporting Inc.
Ottawa, Ontario
(613) 748-6043
© Her Majesty the Queen in Right of Canada 2012
as represented by the Minister of the Environment
and the National Energy Board
© Sa Majesté du Chef du Canada 2012
représentée par le Ministre de l’Environnement et
l’Office national de l’énergie
This publication is the recorded verbatim transcript
and, as such, is taped and transcribed in either of the
official languages, depending on the languages
spoken by the participant at the public hearing.
Cette publication est un compte rendu textuel des
délibérations et, en tant que tel, est enregistrée et
transcrite dans l’une ou l’autre des deux langues
officielles, compte tenu de la langue utilisée par le
participant à l’audience publique.
Printed in Canada Imprimé au Canada
Transcript Hearing Order OH-4-2011
HEARING /AUDIENCE
OH-4-2011
IN THE MATTER OF an application filed by the Northern Gateway Pipelines
Limited Partnership for a Certificate of Public Convenience and Necessity
pursuant to section 52 of the National Energy Board Act, for authorization
to construct and operate the Enbridge Northern Gateway Project.
HEARING LOCATION/LIEU DE L'AUDIENCE
Hearing held in Prince George (British Columbia), Saturday, October 13, 2012
Audience tenue à Prince George (Colombie-Britannique), samedi, le 13 octobre 2012
JOINT REVIEW PANEL/LA COMMISSION D’EXAMEN CONJOINT
S. Leggett Chairperson/Présidente
K. Bateman Member/Membre
H. Matthews Member/Membre
Transcript Hearing Order OH-4-2011
APPEARANCES/COMPARUTIONS (i)
APPLICANT/DEMANDEUR Northern Gateway Pipelines Inc. - Mr. Richard A. Neufeld, Q.C. - Mr. Ken MacDonald - Mr. Bernie Roth - Ms. Laura Estep - Ms. Kathleen Shannon - Mr. Dennis Langen - Mr. Douglas Crowther INTERVENORS/INTERVENANTS Alberta Federation of Labour - Ms. Leanne Chahley Alberta Lands Ltd. - Mr. Darryl Carter Alexander First Nation - Ms. Caroline O’Driscoll BC Nature and Nature Canada - Mr. Chris Tollefson - Mr. Mark Haddock Doug Beckett Province of British Columbia - Ms. Elizabeth Graff - Mr. Christopher R. Jones Nathan Cullen C.J. Peter Associates Engineering - Mr. Chris Peter Canadian Association of Petroleum Producers (CAPP) - Mr. Keith Bergner - Mr. Lewis L. Manning Cenovus Energy Inc., Nexen Inc., Suncor Energy Marketing Inc., Total E&P Canada Ltd. - Mr. Don Davies Coastal First Nations - Ms. Brenda Gaertner Council of the Haida Nation - Ms. G.L. Terri-Lynn Williams-Davidson
Transcript Hearing Order OH-4-2011
APPEARANCES/COMPARUTIONS (Continued/Suite)
(ii) INTERVENORS/INTERVENANTS Daiya-Mattess Keyoh - Mr. Kenny Sam Douglas Channel Watch - Mr. Murray Minchin - Ms. Cheryl Brown - Mr. Kelly Marsh - Mr. Manny Arruda Driftpile Cree Nation - Mr. Amyn F. Lalji Enoch Cree Nation, Ermineskin Cree Nation and Samson Cree Nation - Mr. G. Rangi Jeerakathil - Mr. Sean Fairhust - Mr. Brock Roe ForestEthics Advocacy, Living Oceans Society and Raincoast Conservation Foundation - “The Coalition” - Mr. Barry Robinson - Mr. Tim Leadem, Q.C. - Ms. Sasha Russell - Ms. Karen Campbell Fort St. James, District of - Mr. Kevin Crook Fort St. James Sustainability Group - Mr. Lawrence Shute - Ms. Brenda Gouglas - Ms. Candace Kerr Friends of Morice-Bulkley - Ms. Dawn Remington Gitxaala Nation - Ms. Rosanne M. Kyle - Mr. Robert Janes Government of Alberta - Mr. Ron Kruhlak Government of Canada - Mr. Kirk Lambrecht
Transcript Hearing Order OH-4-2011
APPEARANCES/COMPARUTIONS (Continued/Suite)
(iii) INTERVENORS/INTERVENANTS Haisla Nation - Ms. Jennifer Griffith - Ms. Hana Boye - Mr. Jesse McCormick - Mr. Allan Donovan Kelly Izzard Kitimat Valley Naturalists - Mr. Walter Thorne - Mr. Dennis Horwood - Ms. April MacLeod MEG Energy Corp. - Mr. Loyola Keough - Mr. David A. McGillivray Northwest Institute of Bioregional Research - Ms. Patricia Moss Office of the Wet'suwet'en - Mr. Mike Ridsdale Swan River First Nation - Mr. Jay Nelson - Ms. Dominique Nouvet United Fishermen and Allied Workers' Union - Ms. Joy Thorkelson - Mr. Hugh Kerr Terry Vulcano Josette Wier National Energy Board/Office national de l’énergie - Mr. Andrew Hudson - Ms. Carol Hales - Ms. Rebecca Brown - Mr. Asad Chaudhary
Transcript Hearing Order OH-4-2011
ERRATA
(i)
Wednesday, October 10, 2012 - Volume 86
Paragraph No.: Should read:
6226:
“A four-hour…rate would be 200,000 metres “A four-hour…rate would be 200
…looking at about 800,000 metres…” metres…looking at about 800 metres…”
Friday, October 12, 2012 - Volume 88
Paragraph No.: Should read:
8087:
"In this paragraph…total of the bored "In this paragraph…total of the bored
crossing was 19…” crossings was 19…”
8162:
“You know, the choice of having a remote “You know, the choice of having a remote
empowerment is independent of seismic impoundment is independent of seismic
activity.” activity.”
8164:
“So in this case, due to the site situation, “So in this case, due to the site situation,
remove empowerment system…” remove impoundment system…”
8167:
“…seismicity in this area if we look at peek “…seismicity in this area if we look at peak
ground acceleration as a…” ground acceleration as a…”
8168:
“…15 percent for hard ground at the rock.” “…15 percent for hard ground or soft rock.”
8169:
“…Mr. Malhotra’s questions that we were “…Mr. Malhotra’s questions. That we were
not going to consider. We were not going not going to consider --- We are not going to
to use…that we were going to follow the use…that we are going to generally follow
structural provisions of the Canadian Code…” the structural provisions of the Canadian
Code…”
8171:
“And just define g, we’ve used it a couple “And just to define g, we’ve used it a couple
of days now…” of days now…”
Transcript Hearing Order OH-4-2011
ERRATA
(ii)
Friday, October 12, 2012 - Volume 88
Paragraph No.: Should read:
8291:
“…previous testimony, how many of “…previous testimony, for many of these
these hazards…” hazards…”
8292:
“…where geohazards of various location “…where geohazards at various locations
-- of types exist.” and types exist.”
8293:
“…continuous hazard along the function is “…continuous hazard along the pipeline is
the hazard of seismic shaking.” the hazard of seismic shaking.”
8294:
“…liquefaction, failure of ground movement, “…liquefaction, failure due to ground
just the pipeline…” movement, just the pipeline…”
8335:
“…that’s our peak ground acceleration…” “…that’s a peak ground acceleration…”
8454:
“You have to de-aggregate the results.” “You have to deaggregate the results.”
8456:
“And so we can disaggregate to look at “And so we can deaggregate to look at what
what the probability…” the probability…”
8456:
“That’s called “de-aggregation of the seismic “That’s called “deaggregation of the seismic
data”…” data”…”
8457:
“…numbers that are used for design as per “…numbers that are used for design as per
the building code.” the Building Code.”
8458:
“…results of Ms. Atkinson’s study can be “…results of Ms. Atkinson’s study can be
de-aggregated, has the de-aggregation been deaggregated, has the deaggregation been
performed…” performed…”
Transcript Hearing Order OH-4-2011
ERRATA
(iii)
Friday, October 12, 2012 - Volume 88
Paragraph No.: Should read:
8560:
“Some manufacturers produced hydro “Some manufacturers produced hyper-
sensitized steels...” sensitized steels...”
8573:
“…to be what we call “jigs” or “holidays” “…to be what we call “jeeps” or holidays in
in coating.” coating.”
8597:
“…the number of remotely-operable blocked “…the number of remotely-operable block
valves.” valves.”
8710:
“I think we’ve acknowledged…seeing in our “I think we’ve acknowledged…seeing in our
Kitimat Valley design, construction, and Kitimat Valley Design, Construction, and
operations report that that is a possibility.” Operations Report that that is a possibility.”
8711:
“…focus of the Kitimat Valley Design, “…focus of the Kitimat Valley Design,
Construction, and Operations Point Report Construction, and Operations Report points
to try …” to try …”
8721:
“In terms or the sensitivity of the “In terms of the sensitivity of the
environment…” environment…”
8864:
“…covered really larger zones and we’ve “…covered really large zones and we’ve
taken those zones…” taken those zones…”
8894:
“…approximately 5 kilometres across the “…approximately 5 kilometres across the
water from Kitimat Village within…” water from Kitimaat Village within…”
8928:
“Features such as evulsion were more confined “Features such as avulsion were more
than what we were…” confined than what we were…”
Transcript Hearing Order OH-4-2011
ERRATA
(iv)
Friday, October 12, 2012 - Volume 88
Paragraph No.: Should read:
9057:
“…representation indicating the potential “representation indicating the potential
volume or releases…” volume of releases…”
9166:
“MR. RAY DOERING: ...” “MR. JIM MIHELL: ...”
9272:
“For NGTL to provide an updated version “For NGP to provide an updated version of a
of a map…” map…”
9296:
“There’s a very extensive provincial park “There’s a very extensive Provincial Park
running along the river valley farther south.” running along the river valley farther south.”
Transcript Hearing Order OH-4-2011
TABLE OF CONTENTS/TABLE DES MATIÈRES
(i)
Description Paragraph No./No. de paragraphe
Opening remarks by the Chairperson 9464
Preliminary matters brought forward by Ms. Shannon 9467
Enbridge Northern Gateway Panel 2
Mr. Ray Doering
Mr. Peter Acton
Mr. Barry Callele
Mr. Drummond Cavers
Mr. Tom Fiddler
Mr. Shane Kelly
Mr. Clive MacKay
Mr. James Mihell
Mr. Peter Wong
- Examination by Dr. Kerr 9482
- Examination by Mr. Beckett 9920
- Examination by Mr. Vulcano 10139
- Examination by Dr. Wier 10391
Transcript Hearing Order OH-4-2011
LIST OF EXHIBITS/LISTE DES PIÈCES
(i)
No. Description Paragraph No./No. de paragraphe
AQ26-A United Fishermen Allied Workers’ Union - CVN
schematics test results prepared by Mr. Hugh Kerr. 9590
AQ27-A Doug Beckett – Article – Stream network modeling
using LiDAR and photogrammetric digital elevation
models: a comparison and filed verification by
Paul N.C., Murphy, Jae Ogilvie, Fran-Rui Meng
and Paul Arp. 10132
B140 Enbridge Northern Gateway’s Response to
Undertaking U-32 10709
Transcript Hearing Order OH-4-2011
RULINGS/DÉCISIONS
(i)
Description Paragraph No./No. de paragraphe
Transcript Hearing Order OH-4-2011
UNDERTAKINGS/ENGAGEMENTS
No. Description Paragraph No./No. de paragraphe
Preliminary matters
Transcript Hearing Order OH-4-2011
--- Upon commencing at 8:28 a.m./L’audience débute à 8h28
9464. THE CHAIRPERSON: Good morning, everybody. Wasn’t it a
lovely sunrise this morning? We all got to see it, I think.
9465. Before we get under way with further questions of this panel, are there
any preliminary matters that parties would like to raise?
9466. Ms. Shannon?
9467. MS. SHANNON: Mr. Callele and Mr. Mihell have very brief
preliminary matters. Thank you.
RAY DOERING: Resumed
PETER ACTON: Resumed
BARRY CALLELE: Resumed
DRUMMOND CAVERS: Resumed
TOM FIDDLER: Resumed
SHANE KELLY: Resumed
CLIVE MacKAY: Resumed
JAMES MIHELL: Resumed
PETER WONG: Resumed
9468. MR. BARRY CALLELE: Good morning.
9469. Could I take you to yesterday's transcript, Volume 88, paragraph
8520? Thank you, Madam Clerk.
9470. We were being asked whether or not we're doing real time monitoring
of cathodic protection and I told them that I would -- the Haisla counsel that I'd
get back to them later in the day. It took us a little bit longer -- actually, we found
the IR itself.
9471. If we -- it was actually Exhibit B93-3, Adobe page 97. The answer to
the question is in letter C of it, so it'd be 126C, I guess.
9472. And the remaining questions regarding cathodic protection, we'll defer
to the integrity -- oh sorry, to the Operations Panel. But basically C states that
Enbridge does incorporate remote monitoring equipment on some of its pipeline
systems designed to capture induced DC or AC voltage fluctuations in real time
Preliminary matters
Transcript Hearing Order OH-4-2011
with immediate notification transmission of other range readings.
9473. Basically, what we're saying there is that we're ensuring that we're not
overcharging the systems and getting it to the state where the coding might
disbond.
9474. So I just wanted to bring that to everybody's attention. Thank you
very much.
9475. THE CHAIRPERSON: Thank you, Mr. Callele.
9476. MR. JAMES MIHELL: And good morning.
9477. I have one item as well. On paragraph 8283, the transcript reads:
“So typically, longer pipelines have greater failure events
during the course of a year than shorter events all other things
being equal.”
9478. And that doesn't make much sense. It should read:
“So typically, longer pipelines have greater failure events
during the course of a year than shorter pipelines, all other
things being equal.”
9479. Thank you.
9480. THE CHAIRPERSON: Thank you, Mr. Mihell.
9481. Seeing no other preliminary matters, Dr. Kerr, I think we left off with
you yesterday afternoon and you were going to begin your questions on behalf of
the Union of this panel.
--- EXAMINATION BY/INTERROGATOIRE PAR DR. KERR:
9482. DR. KERR: Thank you, Madam Chair.
9483. The first think I want to talk about is to get some perspective on the
size of a spill where there is spill. So I want first to go to Table 4.1.
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9484. So we see from this table that the oil pipeline capacity -- the
theoretical design capacity is 583,000 barrels per day. Is that right, Mr. Doering?
9485. MR. RAY DOERING: Yes, that would be the maximum design
capacity of the oil pipeline.
9486. DR. KERR: And that’s in Phase 1; right?
9487. MR. RAY DOERING: That is the facility that we've described here
in the application, the facility that we're seeking approval for.
9488. DR. KERR: So we don’t talk about Phase 4 here.
9489. MR. RAY DOERING: No, we're not seeking an application for any
capacity beyond the maximum design rate indicated here.
9490. DR. KERR: Okay. So if we look at that number, 583,000, that’s per
day. So per hour we divide that by 24; correct?
9491. MR. RAY DOERING: Yes, you could do that.
9492. DR. KERR: And per minute, we'd divide again by 60.
9493. MR. RAY DOERING: That would work.
9494. DR. KERR: And your response time is 13 minutes. Is that right?
9495. MR. RAY DOERING: We have described a maximum response
time to a full bore rupture event of 13 minutes. That is 10 minutes to identify and
determine the situation and three minutes then to isolate the system, so that’s the
three minutes. That’s a very conservative estimate of a response time under a full
bore rupture scenario.
9496. I think Mr. Callele could probably describe how a full bore rupture
scenario would result in a multiple of -- a multitude of signals from
instrumentation along the pipeline that would likely cause a shutdown much
sooner than 10 minutes.
9497. DR. KERR: So I can use 13 minutes as a basis for my calculation?
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9498. MR. RAY DOERING: That’s what we've been using ---
9499. DR. KERR: Okay, thank you.
9500. MR. RAY DOERING: --- from a conservative perspective, yes.
9501. DR. KERR: So according to my calculation, when I do all of those
mathematical operations, I end up with 5,261 barrels being spilled in 13 minutes.
--- (A short pause/Courte pause)
9502. MR. RAY DOERING: We're just checking the math here for you.
9503. DR. KERR: Thank you. Professors make mistakes.
9504. MR. BARRY CALLELE: Sorry; what was your barrels per minute?
9505. DR. KERR: Barrels per minute, 404.86.
9506. MR. BARRY CALLELE: So -- oh, you're using maximum design
capacity.
9507. DR. KERR: That’s right; 583,000.
9508. MR. BARRY CALLELE: Oh, yeah, I was using 525. Sorry, I'll ---
9509. DR. KERR: Can someone confirm my number?
9510. MR. BARRY CALLELE: Five thousand two hundred and sixty-
three (5,263), is that what you got?
9511. DR. KERR: That’s -- yeah, close enough. Okay. Now, a barrel ---
9512. MR. RAY DOERING: I was just going to comment here ---
9513. DR. KERR: Sure.
9514. MR. RAY DOERING: --- Mr. Kerr.
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9515. The -- when we do this calculation, the valve will be fully closed in
three minutes. But we use, actually, an average of that flow rate over that three-
minute period, so we're actually calculating a full -- assuming about a full flow
rate for about one and a half minutes of that three minutes because, actually, your
flow rate is dramatically reduced very quickly as you start to close the valve, so
it's not -- it's not a linear relationship, necessarily.
9516. So for our purposes, we typically assume that within one and a half
minutes, you're essentially getting to zero flow on an average basis.
9517. DR. KERR: So you're saying the 13 minutes doesn’t mean much;
that you want to use 1.5 minutes? Is that what you're saying?
9518. MR. RAY DOERING: Thirteen (13) minutes does mean a lot. I'm
just trying to indicate to you that our calculation would be slightly different than
the one you're using here.
9519. DR. KERR: So how different would it be?
9520. MR. RAY DOERING: It would be different by about one and a half
minutes.
9521. DR. KERR: In other words, I reduce it by 30 percent, approximately,
33 percent?
9522. MR. RAY DOERING: You would reduce the -- you would do the
calculation based on 11 and a half minutes versus 13 minutes.
9523. DR. KERR: Okay. So that’s about a 15 percent decrease, something
like that?
9524. MR. RAY DOERING: More or less.
9525. DR. KERR: Or 10 percent. All right.
9526. So anyway, a barrel is .159 metres cubed. Is that correct?
9527. MR. RAY DOERING: That sounds close.
9528. DR. KERR: Close enough.
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9529. So using my 13 minutes, I calculate that the spill would be about 837
cubic metres. You with me? Is that right?
9530. MR. BARRY CALLELE: I think it's closer to 740, myself, from my
calculations.
9531. DR. KERR: You used 525 or 583?
9532. MR. BARRY CALLELE: Five eighty three (583) times 11 and a
half minutes gets you 740 ---
9533. DR. KERR: Okay.
9534. MR. BARRY CALLELE: --- .23.
9535. DR. KERR: Seven hundred and forty (740).
9536. MR. BARRY CALLELE: Yeah.
9537. DR. KERR: Okay, that’s fine.
9538. MR. BARRY CALLELE: Which works out to 4655 or 4656 barrels.
9539. DR. KERR: Now, Mr. Doering, have you ever seen salmon spawn?
9540. MR. RAY DOERING: Yes.
9541. DR. KERR: So you know that they swim up very small rivers, small
streams to spawn.
9542. MR. RAY DOERING: Yes, that’s certainly possible.
9543. DR. KERR: I'm a member of the Squamish Stream Keepers. I
moved to B.C. four years ago from Waterloo, and one of my jobs is to count the
fish that go up a certain creek. And in fact, they're starting about this time of
year. They also bring the eagles to Squamish and we have bears who
occasionally walk across my front yard.
9544. So I know that salmon can swim up a very small creek, but let's, for
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
simplicity, think about a stream that’s one metre wide and one metre deep. Okay,
you got that?
9545. So that cross-sectional area is one square metre.
9546. MR. RAY DOERING: Yeah, sure, I understand that.
9547. DR. KERR: So your spill is how long?
9548. MR. RAY DOERING: I responded to some similar comments
yesterday.
9549. It's fully dependent on where the spill occurs ---
9550. DR. KERR: Well, according to the calculations we've just made, how
long is it?
9551. THE CHAIRPERSON: Excuse me, Dr. Kerr, would you let the
witness please answer the question?
9552. DR. KERR: Okay, sorry.
9553. MR. RAY DOERING: I guess, yeah, just to continue, it's entirely
dependent on where that leak occurs relative to that watercourse.
9554. So it may not occur directly into the watercourse. It -- we've
developed scenarios that have identified the maximum full bore rupture potential
along each kilometre of the pipeline and that often does not correspond with --
directly with the watercourse. It could be elsewhere along the pipeline.
9555. And in that case, there would have to be some mechanism to allow that
product then to ultimately migrate to a watercourse so you're not necessarily
going to get the full quantity that you're describing here directly into that
watercourse, just so we understand that that's the -- could be the -- one of the
scenarios that we're -- have modeled.
9556. DR. KERR: But one of the scenarios could be that all of it goes into a
stream?
9557. MR. RAY DOERING: That could be a scenario.
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9558. DR. KERR: And how long would that spill then be?
9559. MR. RAY DOERING: It depends on the stream velocity, entirely, to
determine, ultimately, how far that could potentially go downstream.
9560. There's also other characteristics of the stream that can slow the
movement of product if it were to get into a stream. Really, it depends on the
characteristics of each stream.
9561. DR. KERR: But would you agree that the minimum length that, if it
all went in the river -- forgetting for the moment the flow velocity, which would,
in fact, make it longer -- the minimum length would be, what, 740 metres?
9562. Is that right?
9563. MR. LANGEN: Madam Chair, I don't -- I'm struggling with the line
of cross.
9564. I understand Dr. Kerr is presenting a scenario, a hypothetical, to the
Panel. The difficulty, I think, with the hypothetical is he's delivering it to the
Panel and it involves more than few assumptions that haven't been provided to the
Panel, and they've already done the math on the fly here.
9565. And if he wants to outline the assumptions that he's built into his
hypothetical to help the Panel respond, that would be helpful.
9566. But, as Mr. Doering has already indicated, there are a number of
factors that will affect how far oil will travel on any channel and Dr. Kerr is
saying it's going to be a certain amount, but he hasn't outlined the assumptions
he's built into his calculation.
9567. THE CHAIRPERSON: Dr. Kerr, are you completed with this line of
questioning or did you ---
9568. DR. KERR: I'll just make a comment, or am I allowed to make a
comment?
9569. THE CHAIRPERSON: Hard to pre-judge what your comment is.
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9570. Your opportunity here is to question this Panel to test the evidence,
and if you have any comments on the answers that you've received back, those
comments are saved for final argument.
9571. DR. KERR: Okay.
9572. Well, were it all to go into the -- I agree that we could discuss that
length what the actual length of the spill would be in a stream like that but there's
a lot of oil into that spill under those -- under the scenario that we've discussed.
9573. It's many hundreds of metres long and, any salmon, would they be able
to swim through that; do you think?
9574. MR. RAY DOERING: Perhaps I'll respond to the first part.
9575. I think we've acknowledged from some of the spill trajectory mapping
that has been provided to the JRP, we've indicated that, yes, under these extreme
scenarios that have been described here -- these full bore rupture scenarios -- that
there -- the spill extent within these watercourses can be quite extensive; so
hundreds of metres, yes, that's entirely possible.
9576. In terms of this salmon habitat and their -- how they respond,
potentially, to a spill within those watercourses, that's probably best left to be
addressed through our Environment Panel who will have fisheries experts on that
panel with lots of experience that could describe the behaviour of fish in those
sorts of circumstances.
9577. DR KERR: Okay. Thank you.
9578. I'd like to turn to some of the discussion that Mr. Peter began a couple
of days ago on toughness of the pipe and he had an aid to questions, I think it's
number 24-C.
9579. Madam Clerk, if you could bring that up?
9580. Oh, sorry, it's the wrong one. AQ24-E.
9581. So just to remind us on a Saturday morning before 9 o'clock -- yeah,
stick with that one. That's good.
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9582. Here, we have a schematic of the results of a Charpy V-notch series of
tests carried out over a range of temperatures schematically going from minus 50
to plus 50 -- you might not go as high as plus 50, you might only go to 25, room
temperature -- and I believe that Mr. Mihell agreed that this is typical of the sort
of result that one gets, that you have an upper shelf energy, you have a lower shelf
energy and you have a gradual curve over a transition region.
9583. Is that correct?
9584. MR. JAMES MIHELL: Yes, that's correct.
9585. DR. KERR: Now, I think you also agreed that the values of
toughness at the upper shelf level and the lower shelf energy -- lower shelf level
are both subject to many variables.
9586. Is that correct?
9587. MR. JAMES MIHELL: Yes, that's true.
9588. DR. KERR: So let's go -- I've prepared another slide as an aid to
questions.
9589. THE CHAIRPERSON: Just while we're going there, could we get a
number for the Union's aid to questioning, please?
9590. THE REGULATORY OFFICER: That will be AQ26.
--- AID TO CROSS-EXAMINATION NO./AIDE AU CONTRE-
INTERROGATOIRE No. AQ26:
United Fishermen Allied Workers’ Union - CVN schematics test results
prepared by Mr. Hugh Kerr.
9591. MR. LANGEN: Madam Chair, it's my understanding that this aid to
cross, the witnesses have not seen it. We certainly, at counsel table, haven't seen
it.
9592. So if we can give the witnesses some time to review it and then they
can confirm when they're ready to take a question?
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9593. THE CHAIRPERSON: So is this correct that the witnesses have not
yet seen this aid to questioning?
9594. MR. JAMES MIHELL: That's correct. This is the first time I'm
seeing this right now.
9595. THE CHAIRPERSON: Okay.
9596. So then why don't we take a break and you tell us when you're ready to
resume?
9597. Dr. Kerr, it's not fair to the witnesses to put something in front of them
that they haven't had the opportunity to study so ---
9598. DR. KERR: Sorry. I'd given it to ---
9599. THE CHAIRPERSON: --- we'll need to take a break.
9600. DR. KERR: --- Madam Clerk, yesterday, but I didn't realize that's as
far as it went.
9601. THE CHAIRPERSON: Okay.
9602. So we'll take a break and we'll let the witness panel let us know when
they're ready to come back.
9603. MR. JAMES MIHELL: Madam Chair, it's a very straightforward
diagram. I think we can work through it in the interests of saving time.
9604. We'll try to accommodate the -- the proceeding forthwith on this.
9605. THE CHAIRPERSON: Let's proceed on that basis, then. Thank
you.
9606. DR. KERR: Thank you.
9607. So here we see that there could be test results, for example, at 25
degrees C, at normal room temperature, and at minus 5 degrees C.
9608. We don't know what the Enbridge specifications are for tests, but
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
they've asked that we consider the design temperature be minus 5 degrees.
9609. Is that correct?
9610. MR. JAMES MIHELL: I think, in actual fact, while there was some
discussion regarding the fact that the exact pipe specification and pipe purchase
requirements have yet to be fully landed at this point, we did point out that --
excuse me. I’m worried about that; I once spilled a cup of tea on my computer
and it made for a very bad day.
--- (Laughter/Rires)
9611. MR. JAMES MIHELL: So, nevertheless, where was I?
9612. DR. KERR: Talking about design temperature, I think.
9613. MR. JAMES MIHELL: Okay, no, actually, pipe purchase
specifications.
9614. I think Enbridge has given itself some latitude with the understanding
that there may be -- they made order Category 2 pipe for certain circumstances or
for the entire length of the pipe. However, CSAZ662 make provision for the use
of Category 1 pipe for oil pipelines.
9615. And so with that understanding, you know, it’s perfectly within code
to use Category 1 pipe in oil pipelines.
9616. And I think I was trying to describe the rationale for that in that
Category 2 pipe, under CSAZ662, is -- has notch-toughness and fracture
appearance properties specifically to guard against fracture propagation.
9617. And you would agree, I think, that fracture propagation in an oil
pipeline doesn’t present a realistic threat.
9618. DR. KERR: We could debate that one all day.
9619. We could also debate correlation between Charpy V-notch results and
fracture toughness. There’s a lot of stuff in the literature about that but I won’t
belabour that. It’s too complicated for this Panel and the audience I believe.
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9620. But anyway, would you agree that if one took the results at 25 degrees
plus 25 and minus 5, only those results that -- and then extrapolated them, that
one would get the straight line that one sees here?
9621. MR. JAMES MIHELL: Just before I address that, I think in your
preamble you left the suggestion that fracture propagation events, long-distance
fracture propagation events in oil pipelines were, in fact, a real possibility and I
would like to take issue with that.
9622. DR. KERR: No, I’m sorry I wasn’t suggesting that. I wasn’t talking
about crack propagation.
9623. MR. JAMES MIHELL: Okay, then, if you -- if that’s the case, then,
perhaps you could restate the question then.
9624. DR. KERR: Would you agree that if you took the results at plus 25
and minus 5 and extrapolated them, you would get the straight line that’s shown
there as extrapolated?
9625. MR. JAMES MIHELL: Yes, that’s what you’ve done with that
straight line.
9626. DR. KERR: And is it possible that the actual Charpy V-notch results
are the curved line with the lower shelf energy as shown there?
9627. MR. JAMES MIHELL: Yes, that’s what your diagram shows.
9628. DR. KERR: And does that seem like a feasible scenario?
9629. MR. JAMES MIHELL: I think, if -- yeah, I think anybody can see
that if you extrapolate from those two points on that curve that the red line is
above the black line in the region of minus 25 to minus 50.
9630. DR. KERR: And do you agree that Category 1 pipe, which has
unproven toughness -- so we don’t worry about the lower shelf energy -- could in
fact have a Charpy V set of results that is similar to what’s shown here?
9631. MR. JAMES MIHELL: Well, I guess we’re debating a meaningless
debate if we aren’t actually taking Charpy tests on Category 1 -- and we’re not by
definition -- then, you know, you can make up whatever values you wish.
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9632. DR. KERR: Are you disagreeing that it could be like this?
--- (A short pause/Courte pause)
9633. MR. JAMES MIHELL: So I’ve just been advised that, in actual
practice, even with Category 1 pipe, when performing welding qualification tests
and performing the Charpy tests that are associated with that, what in actual
practice tends to happen is that we’re still well on the upper shelf at minus 25.
9634. Although, in your hypothetical, theoretical chart, I’m not disagreeing
that you’ve created a chart that has two lines and has a transition temperature
somewhere between minus 25 and minus oh -- perhaps, -25 and 0 and that if
under these circumstances in your hypothetical chart using hypothetical material,
that you would get this sort of behaviour.
9635. DR. KERR: Thank you.
9636. Now, this might be the Charpy results for the base metal, the pipe
material. The pipe gets welded; do you know what influence -- that, if you test
the weld metal, the welding process might have, for example, on the upper shelf
energy?
9637. MR. JAMES MIHELL: In fact, I think we know very well exactly
what sort of fracture toughness we have in the weld region because it is
Enbridge’s practice to use CTOD testing as part of the qualification of the
welding procedures.
9638. And rather than using a crude test that doesn’t do a good job of
measuring fracture initiation resistance such as the Charpy test, they use CTOD
tests which accurately reflect the quasi-static nature of fracture initiation events
whereas the Charpy test, which is a dynamic test -- let me back off here because
I’m using jargon and I don’t want to cause this point to be missed.
9639. So let me explain what a Charpy test is. First of all, it’s called a
“dynamic fracture test” where you take a piece of steel, typically 10 millimetres
by 10 millimetres in cross section, and you put a 2 millimetre notch in it and you
chill that piece of steel to a certain temperature and you whack it with a pendulum
and that pendulum is travelling at a high velocity when it hits the back of the
Charpy specimen and you break the specimen open.
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9640. And you are, therefore, measuring a number of things. You’re
measuring, in part -- part of that energy that you’re measuring when you break the
specimen open is the energy required to initiate a fracture but you’re also
measuring some deformation energy sometimes because these steels tend to be so
tough that they don’t always break all the way through.
9641. You tend to measure the energy sometimes that’s required to drag the
specimen through the anvil because, again, complete fracture of a lot of these
specimens isn’t often achieved and you also measure the resistance to dynamic
fracture propagation.
9642. So dynamic fracture propagation occurs in fracture propagation events.
That’s one type of fracture event that, yes, you want to measure energy resistance
for, is the energy to guard against dynamic fracture propagation.
9643. That’s one type of fracture event. The thing that we want to get a
handle on to guard against fracture initiation is not a rapid fracture event like you
would test in a Charpy specimen because, in fracture initiation, fracture initiates
in what’s called “quasi-static mode”.
9644. It’s a situation where you have a defect which may be at one moment
just subcritical and then suddenly causes a fracture; and it might be a crack, it
might be a corrosion defect, it might be a variety of things but it isn’t a rapid
propagating fracture event, it is a quasi-static event.
9645. And I think using a Charpy specimen to measure resistance against
that type of event which is quasi-static in nature is perhaps using the wrong tool to
get a measure of the thing that you’re trying to get at.
9646. Instead of using a Charpy specimen to measure fracture toughness,
you would be much better to use other fracture mechanics tests such as what I’ve
indicated here earlier on CTOD tests, which are Crack Tip Opening Displacement
tests or J Integral tests which are another form of fracture mechanics based tests.
9647. Nevertheless, it is Enbridge’s practice to do CTOD tests in the weld
zone. It’s -- the CTOD specimen is oriented in a number of different orientations
such that the fatigued pre-cracked tip of the CTOD specimen is catching a variety
of local regions within the weld including the base metal, including the heat-
affected zone, including the weld metal centre line, including the hardest
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
microstructure that could be observed and a number of these CTOD tests are done
in the weld zone.
9648. That CTOD testing is a much better and more representative measure
of fracture initiation resistance than I think what is being advocated here using a
crude but cheap and simple and fast test such as the Charpy test. So in answer to
your question, yes, we have a very good idea of the fracture toughness in the heat-
affected zone and in the weld metal.
9649. DR. KERR: Thank you for your very complete answer.
9650. Is the Charpy V test in your specifications for the base metal?
9651. MR. JAMES MIHELL: Are you talking about pipe purchase
specifications?
9652. DR. KERR: Yes.
9653. MR. JAMES MIHELL: So it depends on what type of pipe one
would be ordering. When one was ordering Category 1 pipe, which I said is the
standard type of pipe which in Canada is -- is ordered for oil pipelines by virtue of
the performance characteristics of oil pipelines, then you probably would not
order any Charpy testing. It would be deemed not necessary. And that’s standard
practice.
9654. That’s what most oil transmission pipeline operators would adhere to.
It’s in complete compliance with the Code. If you were, however, ordering
Category 2 or Category 3 pipe, then you would be ordering weld metal -- sorry,
base metal tests.
9655. DR. KERR: I don’t know if Madam Clerk is ready for this because I
didn’t expect to have to do this, but can we go back to the Enbridge pipe
specification which Mr. Peter was talking about Thursday and we see some of the
redacted parts. Do you think you can bring that up?
9656. THE CHAIRPERSON: Do you have an exhibit number for her?
9657. DR. KERR: B49. Someone’s whispering in my ear; sorry. No, Mr.
Peter -- B49-9. You don’t have it? There is no B49-9. B42-9?
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9658. THE CHAIRPERSON: It’s starting to sound like bingo.
--- (Laughter/Rires)
9659. DR. KERR: Yeah.
9660. Do you recall the redacted engineering -- Enbridge engineering
standard?
9661. MR. JAMES MIHELL: You can proceed. We’ll -- we’ll see where
we get.
9662. DR. KERR: Do you remember that there are headings that say
Charpy V?
9663. MR. JAMES MIHELL: Yeah, and I think we went there the other
day because of the nature of the -- of the specification. It again adopts CSA
Z245.1 as the base standard. And as I tried to explain to Mr. Peter because I think
there was some misunderstanding associated with -- with how the specification
works, the specification works by using the same clause numbering sequence that
is contained in Z245.1 and where the minimum requirements of Z245.1 are to be
adhered to without change.
9664. The -- the protocol in that standard is to either be silent on that clause
or to say something like "accepted". And if, in fact, more stringent requirements
are needed, then it -- the specification will have those more stringent requirements
associated with that clause.
9665. DR. KERR: So if I interpret your comments correctly. you’re saying
that if your standard says the Charpy V-notch tests are accepted that you will,
indeed, carry out such tests or you will replace them and not tell us that you’re
replacing them with CTOD tests. Is that what you’re saying?
9666. MR. JAMES MIHELL: No. I don’t know where to begin with that
one, but ---
9667. DR. KERR: Well, let me -- let me break it into two simple questions.
9668. Does your standard include C -- sorry, Charpy V tests? It says
"applicable", I believe.
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9669. MR. JAMES MIHELL: Okay. As -- as I indicated before, the
Z245.1 code does not require Charpy V-notch testing for Category 1 pipe.
9670. DR. KERR: So the fact that it says "applicable", it doesn’t really
apply. Is that what I’m to take?
9671. MR. LANGEN: Madam Chair, perhaps we can find the exhibit. I
think that would be helpful.
9672. THE CHAIRPERSON: Thank you. That would be very helpful to
the Panel.
9673. MR. LANGEN: Thank you.
9674. MR. JAMES MIHELL: And just to clarify, I think your question
was the fact that it says "applicable", it means that it doesn’t really apply. That, in
fact, is the exact opposite of what it means.
9675. Where it says "applicable", it means the requirements of Z245.1 do
apply. Only where the -- the clause has been embellished by further wording or
discussion or additional -- addition of requirements are more restrictive
requirements over and above those which are required by Z245.1 needed.
9676. DR. KERR: Okay. So I stand corrected.
9677. You’ve replaced the Charpy V testing, but you have argued that
Charpy Vs are not applicable anyway because they’re a dynamic type of test
rather than the slow strain type of test that one has in CTOD.
9678. MR. JAMES MIHELL: I don’t know if I’ve -- I’ve said that --
there’s a role for Charpy V testing and there’s a role for CTOD testing. You
would perform Charpy V testing in -- such that the fracture face is oriented in --
along the pipe access to address things such as fracture propagation events. You
would perform CTOD tests with the fatigue pre-notch oriented in a hoop direction
to address the potential for girth weld defects.
9679. DR. KERR: Would you agree that a seismic event can be quite
dynamic?
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9680. MR. JAMES MIHELL: Yes.
9681. DR. KERR: And that, under those conditions, a Charpy V type
testing might be applicable?
9682. MR. JAMES MIHELL: No, I wouldn’t agree with that. I think we
discussed this yesterday. I personally can’t think of any occasion anywhere
where shaking due to a seismic event has precipitated a brittle fracture in a -- in a
piece of pipe absent sorts of steel cast iron pipes that were characteristic of the
'30s.
9683. The shaking is not the thing that might present a threat to a pipeline in
the event of a seismic event. The real threat, and perhaps Mr. Cavers can speak a
little bit further to that, in the event of a seismic event is if you happen to be
located on unstable ground, especially on grounds that are associated or prone to
soil liquefaction and might, therefore, cause large scale strain-based failures of --
of the pipe. But not the shaking per se. That’s not the threat.
9684. MR. DRUMMOND CAVERS: Yeah, we’ve -- we’ve discussed that
in previous evidence, including IRs. We were just looking for the reference here,
if it’s of interest.
9685. DR. KERR: During construction, does the pipe sit out in the open?
9686. MR. TOM FIDDLER: Yes.
9687. DR. KERR: And might it reach, say, minus 25 or minus 40?
9688. MR. TOM FIDDLER: Absolutely.
9689. DR. KERR: Has it ever been known that a piece of pipe is hit by a
backhoe?
9690. MR. TOM FIDDLER: Sure. There can be incidents like that. There
can be pipe dropped as it’s being lifted; those types of events.
9691. DR. KERR: Do any of the workers ever have a hammer in their
presence?
9692. MR. TOM FIDDLER: Yes.
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9693. DR. KERR: Is it possible that one of them could hit the pipe with a
hammer trying to get it aligned properly?
9694. MR. TOM FIDDLER: Absolutely, yes.
9695. DR. KERR: Thank you.
9696. MR. TOM FIDDLER: Yeah. If I could, please, I think there’s some
confusion and -- and more as a layperson practitioner, if you will, of pipeline
construction.
9697. I wanted to see if I can clarify something here. As much as we talked
extensively about pipe material specifications and the -- there being a -- not a
requirement for Charpy V testing as a protocol of manufacturer and qualifications
of Category 1 pipe, what my colleague was explaining is that, in fact, as we do
our welding procedure development, we do, in fact, undertake CTOD testing
which, inherent to that work, provides us toughness characteristics of the material,
the parent pipe, the heat-affected zone and the weld metal.
9698. MR. TOM FIDDLER: And, Dr. Kerr, just to inject a piece of reality
into this whole hypothetical situation of hitting pipes with hammers or back hoes,
you could have asked one more questions perhaps in that string of questions to
which we said “yes”.
9699. If you had asked: Has there ever been an occasion, where as a result
of any of these events, of a piece of pipe being struck by a backhoe or a hammer
sitting up on skids in cold weather has broken in a brittle fashion, like a piece of
glass? I would say the answer to that is “No”.
9700. DR. KERR: Thank you.
9701. MR. TOM FIDDLER: And If I could, I absolutely have to echo that
in the modern micro-alloyed high strength steels for pipeline construction have --
have no characteristics similar to some of the other older vintages of steel pipe or
cast iron as my colleague has elaborated on previously.
9702. DR. KERR: So if we turn our attention to CTOD, I didn’t intend to --
in fact, to ask about those but since you’ve opened up that discussion, I will.
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9703. You do CTOD tests on base metal. You do them on gas metal arc
welds presumably using the sort of welding procedures that you would normally
use to make the automated welds that you make for most of the welds; is that
correct?
9704. MR. TOM FIDDLER: That’s correct.
9705. MR. KERR: When it comes to tie-in welds, joining long lengths of
pipe to already-welded pipelines, my understanding is that a lot of those are done
using manual arc welding, shielded metal arc welding; at least for the route passes
and also the subsequent passes.
9706. Is that correct?
9707. MR. TOM FIDDLER: Often they are, yes.
9708. DR. KERR: So how do you prepare the specimens for CTOD tests
done by manual arc welding?
9709. MR. JAMES MIHELL: So, Dr. Kerr, I guess that requires a certain
base understanding of pipeline practices and code requirements.
9710. However, the CTOD testing is done for the purposes of establishing
weld defect zone, defect acceptance criteria, based on fracture mechanics
approach for mechanized girth welds.
9711. And the code enables you to do that for mechanized girth welds but for
manual welds, because of the high variability in the geometry and in the welding
parameters that are associated with manual welds, we don’t do defect acceptance
through fracture mechanics based analysis on those welds.
9712. So we don’t -- although, obviously, the CTOD testing that’s performed
for the mechanized welds have notch orientations or fatigue pre-crack orientations
such that they catch portions of the base metal and, therefore, those results are
representative of anything that might be welded with a manual process.
9713. We don’t look at CTOD testing per se for manual welds. However, I
think Mr. Fiddler will add to what sort of testing is done to address manual welds.
--- (A short pause/Courte pause)
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9714. MR. TOM FIDDLER: Yes, as part of our standard process for
qualification of our detailed welding procedure specifications, we’ll complete
Charpys on those.
9715. DR. KERR: So you use Charpy tests, do you, for the manual welds?
9716. MR. TOM FIDDLER: Yes, we do.
9717. DR. KERR: Now, manual welds in the field are rather difficult.
9718. Would you agree that the tie-in welds are, in fact, the most critical
welds?
9719. MR. TOM FIDDLER: I don’t know that I would characterize them
that way.
9720. It really depends on many variables in terms of the circumstances.
They can be very challenging welds, I acknowledge that.
9721. DR. KERR: And you have, in a tie-in weld, new variables that you
don’t really have for the automated welds in terms of fit-up.
9722. Is that correct?
9723. MR. TOM FIDDLER: That is often the case.
9724. DR. KERR: So that, instead of the almost perfect fit-up that you have
for the gas metal arc welds, at the root, you can have gaps -- what sort of range of
gaps would you say might occur?
9725. Would it be up to an eighth of an inch? A quarter of an inch?
9726. MR. TOM FIDDLER: Are you referring to a maximum high-low
type of situation, like, differential in wall thickness, alignment ---
9727. DR. KERR: Well, maybe you -- maybe you should explain to all of
us what you mean by “maximum high-low”.
9728. MR. TOM FIDDLER: So a maximum in our specification -- and it’s
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
actually lesser than code -- for our situation, code would allow 2.4mm maximum
wall thickness and/or ovality difference, when you fit up with pipe joint.
9729. We apply 1.6 mm as a standard and we inspect to that.
9730. MR. KERR: And nobody ever hits those with a hammer, I guess,
when they’re trying to fit it into place?
9731. I’m joking. Relax.
9732. So you might have a variation of .16 mm and -- what would it be? It
would be just about zero, would it, for the gas metal arc welds?
--- (A short pause/Courte pause)
9733. MR. TOM FIDDLER: That -- that very much would depend on the
exact welding procedures.
9734. We qualify the welding procedures when it comes to metal -- gas
metal arc welding procedures, based on the mechanized welding equipment
vendor and our work with them.
9735. And we do that work ourselves. We don’t rely on the contractors or
others. And we’ll develop and accept the welding procedures. Within that, we’ll
define critical variables in terms of fit-up.
9736. My colleague is just looking for an example of one of the more
prevalent mechanized welding service providers but if it may help, Dr. Kerr, we
filed a very significant response to a recent JRP IR 9 -- sorry, 11.5C was a filing
recently, with regards to our welding procedure specifications, our NDT
procedures and policies and so on.
9737. So if you want to get into that, we can certainly call that up or ---
9738. MR. KERR: Well I’m ---
9739. MR. TOM FIDDLER: --- and refer to that. And if you want to have
follow-on conversation in the future we’re certainly willing to do so.
9740. MR. KERR: I’m -- I’ve looked at that briefly but I’m most concerned
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
actually with the tie-in welds because they’re the most difficult.
9741. And you’ve already told me that you don’t do J integral -- or sorry you
don’t do CTOD tests on those. You rely essentially on the capabilities of the
individual manual welders to ---
9742. MR. TOM FIDDLER: But as far -- sorry. Go ahead.
9743. MR. KERR: --- to make up for the fact that the fit-up is not as good
for the gas metal arc welds.
9744. You’ve got four welders do you typically welding at the same time?
9745. MR. LANGEN: Madam Chair, I don’t mean to be difficult but I
think Dr. Kerr’s question is a little unfair.
9746. He’s built a bunch of presumptions into the question that I didn’t hear
the witnesses say and he’s attributed to the witnesses. I would ask that he be very
careful in what he’s saying. Unless I’ve missed something I don’t think that the
witnesses have said what he -- what he just said and he’s implied that they have.
9747. So I’d ask him to reframe his question.
9748. DR. KERR: How many welders normally are welding
simultaneously for the shielded metal arc welds?
9749. MR. TOM FIDDLER: It varies by pipe size and the complexity of
---
9750. DR. KERR: For the 36-inch pipes we're discussing here.
9751. MR. TOM FIDDLER: It definitely would be three and could be
four.
9752. DR. KERR: And so each of those has to make a very good weld.
They each have to be concerned about the start/stop situations where they start an
electrode and then they finish an electrode. Is that correct?
9753. MR. TOM FIDDLER: Yes, that's correct. They're very
interdependent.
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9754. And not to jump ahead of you here, but acknowledging that -- as I did
earlier, that tie-ins can be some of the most challenging welds, we implement
additional layers of quality assurance and control on those tie-ins.
9755. So as an example, and going back to your conversation point around
alignment and fit-up, if the wall thickness differences in the design are greater
than 1.6 millimetre, then we will actually require a counterbore and taper to
equalize the wall thicknesses. And then more on the follow-on procedures, we'll
have delayed NDT. So we'll wait a minimum of 18 hours and follow on with
NDT inspection to assure that there's been no latent hydrogen-assisted cracking or
stress-related cracking on that weld.
9756. DR. KERR: Do you maintain a post-weld temperature during those
18 hours or you allow it to cool down to room temperature?
9757. MR. TOM FIDDLER: We have controlled cooling with the use of
insulated blankets at colder temperatures as a standard requirement, and we allow
the weld to cool before we do the NDT, the delayed NDT.
9758. DR. KERR: So do you have an estimate of how long it takes to cool?
9759. MR. TOM FIDDLER: We've done some work on heat decay rates in
welds, and it's very, very much dependent on ambient weather conditions
following removal of blanket. We have a minimum temperature when the blanket
can be removed from the weld.
9760. DR. KERR: Just for the sake of the audience here, the concern is that
with shielded metal arc welds, especially with the route passes, you use normally
an electrode -- and people from Enbridge can correct me if my assumptions are
not correct. Well, I'll just ask the question.
9761. In the route passes, do you normally use a high hydrogen electrode, a
cellulosic type electrode?
9762. MR. TOM FIDDLER: Yes.
9763. DR. KERR: A 70:10, something like that?
9764. So you acknowledge that's got a relatively high hydrogen content.
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9765. MR. TOM FIDDLER: Relative to low-hydrogen rod, yes.
9766. DR. KERR: Right. So the concern -- the reason for your post-weld
temperature is to try and get that hydrogen to diffuse away from the weld. Is that
correct?
9767. MR. TOM FIDDLER: Can you repeat the question, please?
9768. DR. KERR: Do you maintain a temperature after welding for a
certain length of time?
9769. MR. TOM FIDDLER: We control the cooling ---
9770. DR. KERR: Right. Okay.
9771. MR. TOM FIDDLER: --- and allow it not to be -- the heat decay rate
to be enhanced by weather conditions is what we're trying to mitigate.
9772. DR. KERR: And why are you worried about that cooling rate?
9773. MR. TOM FIDDLER: The -- a byproduct of the cellulosic welding
procedure as you've talked about is that there is -- and it is a very small potential
of latent hydrogen gas within the weld deposit itself and, therefore, you're
wanting that gas to diffuse through the weld metal. And it's atomic hydrogen.
9774. DR. KERR: And so you're dependent on the diffusion of the
hydrogen within the solid metal to get that hydrogen out of the region right
around the weld.
9775. MR. TOM FIDDLER: Well, understanding that the process
continues with your hot passes and your fill passes and the like so you're
continually applying heat until you're completing a weld.
9776. DR. KERR: So you have some welders that make the route pass and
then you have other welders that complete the weld, is what you're saying. Is that
correct?
9777. MR. TOM FIDDLER: Typically, there would be welders that do the
route pass and there'd be more than one on a 36-inch pipe joint. And similarly,
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
there'd be fill and hot pass welders and maybe -- and they'll cap out the weld.
9778. DR. KERR: Right. So the ---
9779. MR. TOM FIDDLER: Through the course of that welding
procedure, it's very important as part of the specification in the welding procedure
qualification, there's a minimum preheat and maintenance of temperature that has
to occur.
9780. DR. KERR: Right. And the intention is to allow the hydrogen to
diffuse away from the route passes so that the maximum amount of hydrogen
remaining is relative low. Is that correct?
9781. MR. TOM FIDDLER: Yes.
9782. DR. KERR: I don't know whether to test your memory on terms of
how far things can diffuse in a certain time knowing the diffusion coefficient, but
there's a simple calculation.
9783. MR. TOM FIDDLER: As I indicated earlier, I'm more of a
practitioner and applicator ---
9784. DR. KERR: Right.
9785. MR. TOM FIDDLER: --- and my colleague here is certainly the
metallurgical engineer. But I've done enough work with very respected
metallurgical engineers including, as I mentioned, studies on heat decay rates of
welds and migration and diffusion of hydrogen that I understand the concept and
the principles.
9786. DR. KERR: But we rely on the people on the job to actually do it
correctly.
9787. You sign off -- who signs off on the weld procedure specifications?
9788. MR. TOM FIDDLER: We employ third-party metallurgical
consultants to assist us with the assessment and the implementation of the weld
and acceptance of the welding procedures, whether we develop them or they're
proposed to us by a contractor.
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9789. DR. KERR: But doesn't someone within Enbridge take responsibility
for that, WPS?
9790. MR. TOM FIDDLER: Yes, ultimately -- ultimately, we have a team
of metallurgical engineers that do a final review.
9791. DR. KERR: And who, ultimately, decides that they're correct and
takes responsibility?
9792. MR. TOM FIDDLER: I'm not sure if you're looking for an
individual. Certainly that can vary, but it's a responsible metallurgical
professional.
9793. DR. KERR: But according to engineering standards, you're making
an engineering decision. There must be an engineer, a qualified engineer, who is
willing to sign off on that. Is that correct?
9794. MR. TOM FIDDLER: The detailed Welding Procedures
Specifications and the acceptance and assessment of them with our metallurgic
consultants, their work is all signed and stamped for us.
9795. DR. KERR: So in fact, the consultants make the final decision?
9796. MR. TOM FIDDLER: Ultimately, we have a team internally of
professional engineers that also do a further review and final acceptance before
we implement them.
9797. DR. KERR: So if there were a large spill which happened to be from
one of these tie-in welds, who would get sued; the consultant? Would the Stream
Keepers, for example, very angry at a stream being mucked up, would we just sue
Enbridge, would we sue individuals within Enbridge, would we sue the
consultants? Who should we sue?
9798. THE CHAIRPERSON: I believe Mr. Langen had something he
wanted to say.
9799. MR. LANGEN: I did. I let it run its course, but I now have
something to say.
9800. I'm questioning the relevance of -- I'm questioning the relevance of Dr.
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
Kerr's last question. He's -- again, I don't mean to be difficult, but I don't see any
value in asking this panel a hypothetical question as to who should be sued with
respect to a hypothetical failure.
9801. Firstly, it's all hypothetical. Secondly, it's not within the area of
expertise of these individuals. He's asking a legal question. It's an improper
question to this panel. In fact, it's an improper question, probably, to most of the
panels, and so I'd ask him to move along.
9802. THE CHAIRPERSON: Dr. Kerr, you are, from the Panel's
perspective, raising a legal question and this isn't the appropriate time or place to
be doing that. So perhaps you can move on to your next line of questioning.
9803. DR. KERR: Sorry. Are you aware that an engineer who was
working for TransCanada Pipeline has made a complaint to Professional
Engineers of Alberta about people not following Welding Procedures
Specifications?
9804. MR. TOM FIDDLER: I'm aware of what I've read in that regard.
I'm not certain of the facts.
9805. DR. KERR: No, I agree these are allegations, but it's certainly very
serious allegations and very sad situation as far as professional engineers. It's not
good at all for our reputation.
9806. Now, coming back to -- if we can see that funny-looking slide again,
the one with the curve on it.
9807. I believe I started to ask about factors which influence the upper shelf
energy, et cetera, and Mr. Mihell diverted us onto CTOD testing. Let me come
back to my question on upper shelf energy.
9808. This might be the curve for the base metal, then that base metal gets
welded. The composition of the filler metal is different, generally. Is that
correct?
9809. MR. JAMES MIHELL: That’s correct.
9810. DR. KERR: And so the redacted specifications, in fact, do not refer
to the filler metal compositions. Is that correct?
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9811. MR. JAMES MIHELL: I’m sorry; could you please repeat your
question?
9812. DR. KERR: The redacted specifications on the pipe do not include
the filler metal composition specifications.
9813. MR. JAMES MIHELL: You're talking about for the seam weld of
the pipe rather than for the girth welds.
9814. DR. KERR: No, I'm talking about the girth welds.
9815. MR. JAMES MIHELL: Well, there never are any girth weld
specification requirements, ever, in pipe purchase specifications.
9816. DR. KERR: But you do use filler metal that you buy from a third
party, which does have specifications on it. Is that correct?
9817. MR. JAMES MIHELL: That’s correct. One of the things that I
didn’t make mention of is that every heat of filler metal has to be requalified with
the battery of CTOD tests that I described earlier.
9818. DR. KERR: Would you agree that the compositions are somewhat
different from the pipe material compositions?
9819. MR. JAMES MIHELL: Yes, they are.
9820. DR. KERR: And consequently they can be, for example, higher in
carbon content than the base metal?
9821. MR. JAMES MIHELL: They can -- I'll just say the compositions are
different from the base metal.
9822. DR. KERR: Consequently, the properties of the weld that -- can be
quite different from the properties of the base metal.
9823. MR. JAMES MIHELL: Yes, sir.
9824. DR. KERR: And would you say that the properties of the weld metal
typically have a higher upper shelf energy or lower? Do you know that?
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9825. MR. JAMES MIHELL: You know, when people do these CTOD
tests, they do them at the minimum design temperature and they tend not to do
full transition curves on them. However, there is such a number of individual
tests that are required that any -- any scatter that might exist that might result from
being close to the transition would manifest itself and cause you to fail the -- fail
the test, I think.
9826. DR. KERR: But we've already heard that you don’t do CTOD tests
on shielded metal arc welds.
9827. MR. JAMES MIHELL: So -- yes. For -- just to reiterate, rather than
doing CTOD tests on the weld metal and the heat affected zone of manual test --
manual welds, Charpy tests are done.
9828. DR. KERR: So to reiterate my question, would the upper shelf
energy from those Charpy tests normally be the same as, higher than or lower
than? Can you give us an indication of what sort of comparison you might
expect?
9829. MR. JAMES MIHELL: I will give you that they are going to be
different, typically. I would hate to venture a guess as to what -- what you would
get, depending upon the welding process and so on.
9830. DR. KERR: The fracture mechanism of the upper shelf energy is
what fracture mechanism? Would you say it's brittle, ductile?
9831. MR. JAMES MIHELL: It's ductile.
9832. DR. KERR: So in ductile fracture, we have initiation of voids and
those then link? Is that correct?
9833. MR. JAMES MIHELL: Yes, you have plastic collapse precipitated
by microvoid coalescence. That’s right.
--- (A short pause/Courte pause)
9834. DR. KERR: Ready for the next question?
9835. MR. JAMES MIHELL: Yes, you may proceed.
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9836. DR. KERR: So if it's initiated by microvoids, what initiates those
microvoids, do you know, in general, in the weld metal?
9837. MR. JAMES MIHELL: It's typically very small -- I guess small
particles that lock -- dislocations, I believe. You're getting back several years for
me now since I last spent a whole time -- a whole lot of time looking at this.
9838. DR. KERR: Well, a weld metal generally -- specially shielded metal
arc welds contain a lot of inclusions; would you agree?
9839. MR. JAMES MIHELL: Yes.
9840. DR. KERR: And those inclusions, in fact, can be rather larger than
the original hard particles that one has in base metal; would you agree?
9841. MR. JAMES MIHELL: Yes, okay. I'll go with that.
9842. DR. KERR: And depending on shielding metal composition, the gas
used, et cetera, there can be a large number of those inclusions, and consequently
-- and they can be relatively large compared to the base metal, which has
relatively few inclusions.
9843. That means that -- would you agree that that means that they might
initiate microvoids at relatively low strains?
9844. MR. JAMES MIHELL: So you're talking about shielded metal arc
welding here.
9845. DR. KERR: Yes.
9846. MR. JAMES MIHELL: So therefore, we're talking about
mechanized welding systems which are, as I iterated earlier a couple of times, a
battery of ---
9847. DR. KERR: No, I'm sorry, we're not talking about automated. We're
talking about manual shielded metal arc welds.
9848. MR. JAMES MIHELL: Well, we don’t do that in this industry.
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9849. DR. KERR: You do with tie-in welds. We just heard that.
9850. MR. JAMES MIHELL: We don’t use manual gas metal arc
welding.
9851. DR. KERR: I didn’t mean gas metal arc; I meant manual shielded
metal arc. I believe that’s what I said.
9852. MR. JAMES MIHELL: Okay, I took you to say that you were
talking about gas metal arc welding.
9853. So we're talking about shielded metal arc welding now.
9854. DR. KERR: And we have been for some time. We're talking about
tie-in welds.
9855. MR. JAMES MIHELL: Okay. I think you had a question. Perhaps
you could ask that question again, please.
9856. DR. KERR: The question was, would you agree that there's a
relatively high number of oxide particles in shielded metal arc welds compared to
the base metal?
9857. MR. JAMES MIHELL: Yes, I would agree.
9858. THE CHAIRPERSON: Dr. Kerr, we have to get you to move your
microphone a little bit further back or you ---
9859. DR. KERR: Back?
9860. THE CHAIRPERSON: --- further back. We can't ---
9861. DR. KERR: All right, okay.
9862. THE CHAIRPERSON: --- catch the words for the transcript.
9863. So perhaps you could repeat that question for us, please?
9864. DR. KERR: I asked whether Mr. Mihell would agree that there's a
relatively high number of oxide particles in the weld metal.
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
9865. MR. JAMES MIHELL: And I agreed.
9866. DR. KERR: And that they, in turn, during ductile fracture, initiate
microvoids.
9867. MR. JAMES MIHELL: And I'll agree to that, too.
9868. DR. KERR: And the larger ones will initiate microvoids at lower
strengths. That then implies what to you?
9869. Would you agree that the strain -- the failure strain is less in shielded
metal arc welds than it would be for the base metal?
9870. MR. JAMES MIHELL: Well, up until now we've been talking about
fracture tests and I guess now we're talking about failure strain. And so one of the
things that we haven’t talked about is the fact that there's tensile test requirements
across the base metal and through the weld metal as part of every welding
procedure ---
9871. DR. KERR: No, sorry, I'm still talking about Charpy tests and the
ductile region of the Charpy tests, which is what I started to talk about.
9872. MR. JAMES MIHELL: Right. However, if you're talking about
ductile microvoid coalescence and the potential for lower failure strains, then that
certainly -- it seems to me it would be well identified by a tensile test that goes
through the weld metal zone and one of the test requirements is that the failure
cannot occur in the weld metal zone when performing that test.
9873. DR. KERR: But if you do a Charpy of the weld metal then it does go
through the weld metal which is what I’m talking about; the Charpy V properties
of weld metal.
9874. MR. JAMES MIHELL: I’ll -- I’ll wait for your question.
9875. DR. KERR: Well, because the strain, what happens is that those
small inclusions nucleate, microvoids at low strain, therefore, the fracture strain is
less than it would be in the base metal.
9876. Therefore, since the energy is the fracture strain times the stress at
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
which it occurs, the energy is less in the weld metal, of shielded metal arc welds,
than it would be without the presence of all those inclusions. So that upper shelf
energy goes down.
9877. You don’t seem to know that but I’m telling you that’s what happens
since you can’t seem to ---
9878. THE CHAIRPERSON: Dr. Kerr, you’re here to test the evidence as
opposed to ---
9879. DR. KERR: Okay.
9880. THE CHAIRPERSON: --- provide -- would you, please, frame a
question for the witnesses and allow them to answer it?
9881. DR. KERR: If the fracture strain in the weld metal is decreased,
would you agree that it might be less in the weld metal than in the base metal
because of the presence of inclusions?
9882. MR. JAMES MIHELL: So you’re asking if the -- the strain
tolerance of the weld metal is less than the base metal or that’s the premise of
your question; is that correct?
9883. DR. KERR: Yes.
9884. MR. JAMES MIHELL: Okay, in a -- if that’s the case, we’re talking
about critical strain at failure.
9885. I can again indicate that, when we perform Tensile tests, we are able
therefore to identify the critical strain at failure through that test and one of the
criteria for the Tensile tests is that the failure must occur outside of the weld zone.
9886. DR. KERR: I’m sorry, I’m talking about Charpy tests of weld metal.
9887. MR. JAMES MIHELL: Perhaps, Dr. Kerr, if you ask a direct
question?
9888. You’re asking a number of leading questions.
9889. DR. KERR: I’m asking whether the fracture strain in a Charpy V test
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
of weld metal would be less than the fracture strain of the base metal.
9890. MR. JAMES MIHELL: Okay, so -- so let’s -- let’s acknowledge
that.
9891. DR. KERR: And would you then agree that the fracture energy in the
weld metal would be less than the fracture energy in the base metal?
9892. MR. JAMES MIHELL: Yes.
9893. DR. KERR: Thank you.
9894. So therefore, the upper shelf energy in the weld metal is less than that
in the base metal.
9895. MR. JAMES MIHELL: Are you asking a question?
9896. DR. KERR: Would you agree?
9897. MR. JAMES MIHELL: Under those circumstances, yes.
9898. But, Dr. Kerr, we are doing Charpy tests in the weld metal.
9899. DR. KERR: Not for shielded metal arc welds, apparently.
9900. MR. JAMES MIHELL: No, I guess you misunderstood us.
9901. We said maybe about a half an hour ago that we do Charpy tests in the
weld metal of shielded metal arc welds.
9902. DR. KERR: Then I’m surprised that nobody could answer my
question about relative values that I -- it’s taken us this long because I basically
was asking whether or not the upper shelf energy in the weld metal was less than
that of the base metal and no one was willing to answer that question. So I had to
come back and ask it very slowly, sorry.
9903. So it’s important that one realizes that it doesn’t take much energy to,
in a Charpy-type situation and a dynamic-type situation, to break the weld.
9904. MR. JAMES MIHELL: Well, the whole purpose of performing
Enbridge Northern Gateway Panel 2
Examination by Dr. Kerr
Transcript Hearing Order OH-4-2011
Charpy tests in the weld metal of a shielded metal arc weld is to ensure that it
does take sufficient energy to break the weld.
9905. DR. KERR: And the values of energy at which that occurs are less
than in the base metal.
9906. So it -- it becomes very important to control the filler metal
compositions and, at the same time, monitor the properties and it’s very
frustrating when things start to break because people don’t properly do that.
9907. In the case of X80, I guess you’re not going to use X80. We’ve
determined that already.
9908. Is that correct?
9909. MR. TOM FIDDLER: That's correct.
9910. DR. KERR: Okay, well I’ll hold on questions because I hear that
people have been trying to weld X80 with shielded metal arc and are having great
difficulty but I’ll hold off on those questions.
9911. MR. JAMES MIHELL: Dr. Kerr, just in -- in defence of the industry
as a whole, we’ve been, as an industry, welding X80 successfully for decades.
9912. DR. KERR: Thank you.
9913. MS. THORKELSON: That concludes our questions.
9914. THE CHAIRPERSON: Are those the questions of the Union?
9915. MS. THORKELSON: Yes.
9916. THE CHAIRPERSON: Thank you very much to both of you for
participating in this process.
9917. I’m going to call Mr. Beckett next.
--- (A short pause/Courte pause)
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
9918. THE CHAIRPERSON: Good morning, Mr. Beckett. Thank you for
being here.
9919. Please proceed with your questions of this witness panel when you’re
ready.
--- EXAMINATION BY/INTERROGATOIRE PAR MR. BECKETT:
9920. MR. BECKETT: Good morning, Madam Chair.
9921. I must say it felt great driving my Weiss Electric Truck into town this
morning. It’s wonderful to see a little bit of blue sky out there and thank you for
giving me this opportunity to pose some questions.
9922. I’m speaking or questioning as a member of the public. I’d like to be
clear with that.
9923. I would like to begin with questioning the Proponent’s expert with
respect to LiDAR and I was wondering if the proponent would please confirm
who that would be?
9924. MR. DRUMMOND CAVERS: Well, you can address the questions
to the Panel and the best person will -- will respond. You can probably start with
me but it’ll depend on the question.
9925. MR. BECKETT: Okay, I had understood it would be yourself, Mr.
Cavers. Thank you.
9926. So I would like to bring up Exhibit I believe it’s B90-18. It’s your CV
and the CV suggests that you’ve done a lot of work to assist companies with their
projects.
9927. Is that correct?
9928. MR. DRUMMOND CAVERS: Yes, I’m a consultant.
9929. MR. BECKETT: Electronic page 11 of the CV suggests you’ve
given seminars to companies and to government organizations.
9930. What proportion of your working time as outlined in the CV has been
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
devoted to government organizations clients?
9931. MR. DRUMMOND CAVERS: Well, in recent years, probably zero.
9932. MR. BECKETT: Your CV makes no mention of environmental non-
government organizations, NGOs.
9933. What proportion of your working time as outlined in the CV has been
devoted to NGO clients?
9934. MR. DRUMMOND CAVERS: I don’t -- I don’t recall any NGO
clients at -- at this point.
9935. MR. BECKETT: Thank you.
9936. Are any of the publications listed on electronic pages 11 and 12 of the
CV, are any of them peer-reviewed journal articles on the use of LiDAR in the
part of B.C. where this pipeline is proposed?
9937. MR. DRUMMOND CAVERS: No, they are not.
9938. MR. BECKETT: Thank you.
9939. I would now like to question the Proponent’s expert with respect to the
likelihood and risk of landslides. Would the Proponent please confirm who that
would be?
9940. MR. DRUMMOND CAVERS: Well, again, you can start with me
but we are a panel and we do work together.
9941. MR. BECKETT: And so, similar question, electronic pages 11 and
12 of the CV, the peer-reviewed journal articles.
9942. Are any of them on -- are any of those peer-reviewed journal articles
on methods of identifying landslides or assessing the likelihood and risk of
landslides in the part of B.C where this pipeline is proposed?
9943. MR. DRUMMOND CAVERS: No, they are not but you seem to be
questioning my qualifications to use LiDAR.
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
9944. I can assure you that I have been using LiDAR as a tool -- not writing
academic papers about it -- but as a tool for at least 10 years to look at landslides,
to look at geohazard issues and for other uses not only in the part of the province
that we’re talking about but throughout B.C, Alberta and across Canada as well as
in parts of the United States.
9945. So I think, from a practical point of view, that I have used LiDAR as --
probably as long as anybody in the industry has been using it.
9946. MR. BECKETT: Very good. Thank you.
9947. With that experience, have you personally identified landslides
utilizing LiDAR in areas where conventional assessment approaches have failed
to identify the landslide?
9948. MR. DRUMMONED CAVERS: Well, certainly, LiDAR is a very
useful tool.
9949. It lets us strip off the vegetation as it were; it lets us construct hill
shade images which can assist by varying the light source, assist greatly in finding
small features that we can’t otherwise detect.
9950. So, yes, LiDAR is a very useful tool for finding features that we may
not be able to find, depending on circumstances on, say, conventional air
photography and, indeed, sometimes we can find features that we have difficulty
seeing on the ground when they’re very small and the vegetation is heavy.
9951. One of the advantages, again, that we can strip off the vegetation as it
were and have a look at a bigger area. So LiDAR is a very useful tool in what we
do.
9952. MR. BECKETT: I agree.
9953. So have you personally identified landslides, using LiDAR, in areas
where traditional assessment approaches have failed to identify the landslide?
9954. MR. DRUMMOND CAVERS: Well, I’d have to qualify what you
mean by “traditional approaches”.
9955. Certainly, we’ve identified numerous slides in areas where air
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
photographs have not identified them.
9956. When we get right down on the ground and crawl along on our hands
and knees, I would say that the -- that it’s -- usually, we find the same features
that are in LiDAR.
9957. So the answer to your question with respect to, say, conventional air
photography, orthoimages, and so on would be “yes”.
9958. I would have to say that walking on the ground and really grinding
across the topography and we get right down on our hands and knees and look for
tiny little cracks in the soil and so on, if we do that then the -- then we’re probably
about one-to-one with the LiDAR.
9959. But one of the big advantages of LiDAR is it takes a long time to
cover an area on your hands and knees.
9960. MR. BECKETT: And I take that as a “qualified no”.
9961. Have you received guidance and training from landslide experts who
do have this experience and expertise then in this process for the terrain hazard
assessment and everything?
9962. MR. DRUMMOND CAVERS: I would consider myself to be an
expert.
9963. MR. BECKETT: So you haven’t gained that additional expertise
then?
9964. MR. DRUMMOND CAVERS: I have used LiDAR as long as
anybody has and I would consider myself to be an expert and capable of -- and I
do train others in its use in my company, with my clients. And so, no, I haven’t
taken any formal training courses but I would consider myself to be an expert.
9965. Somebody has to start at ground zero and I’m one of the guys who
started at ground zero with this stuff.
9966. MR. BECKETT: I believe there are others too.
9967. From the October 9th
transcript, line 4944 -- oh, October 9th
transcript,
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
line 4944. That was the number anyways on the left-hand side when I was
reading through them.
9968. And, I’m sorry, I didn’t give Madam Clerk much notice. I provided
her my list this morning not yesterday or earlier as I had been requested. I’m
sorry about that.
“In areas where we need …”
9969. It states:
“In areas where we need a wider width of LIDAR along the
route to pick up areas that may be subject to natural hazards
that could affect the pipeline route, we will widen the corridor
out and, in other areas, we will typically be looking at a 2-
kilometre minimum width.”
9970. Which I recognize was subsequently corrected to be a 1-kilometre
minimum width.
9971. Recognizing that on electronic page 2 of a 2011 paper titled “Pipeline
Routing in Landslide Prone Terrain” by Dr. Marten Geertsema -- it’s a published
paper that assesses landslides in the portion of B.C where this proposed pipeline is
being considered -- and this paper suggests landslides can travel 2, 3 and even 4
kilometres from the point of initiation.
9972. A referred 2009 paper by Dr. Marten Geertsema that is already on the
record also supports the observation that landslides can travel long distances.
9973. I’d like to know on what basis has a 1-kilometre minimum width -- a
width of 500 metres on each side of the proposed pipeline -- then derived?
9974. MR. DRUMMOND CAVERS: My colleague is pulling up some of
the references to past responses to information requests. I believe this area has
been discussed extensively in the past. We discussed it the other day as well.
9975. This 1-kilometre width is in areas -- as this testimony from the other
day says, is in areas where we don’t have this issue where slides may travel into
the right-of-way from long distances outside.
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
9976. As we’ve indicated, where there’s hazards that may affect the pipeline
back to the height of land or for longer distances, we do widen out the LiDAR
coverage.
9977. And secondly, in the testimony the other day, we did indicate that
these 2 to 4-kilometre long slides that are referenced, I believe, in Dr.
Geertsema’s paper, were -- including the rock avalanches along the PNG route in
the Limonite Creek and Copper River areas, these are slides I’ve worked on and
we don’t have that kind of terrain. We’ve discussed that in previous testimony.
9978. And if we could pull up B47-28, page 37?
--- (A short pause/Courte pause)
9979. MR. DRUMMOND CAVERS: This -- while we’re waiting for
Madam Clerk to bring it up, this is an IR that discusses a response to exactly the
same issues which is on the record. The information request was from the
Province of British Columbia.
9980. So I believe that we’re well-covered in this issue where we do need a
wider coverage. We either have it or are going to get it. We have looked
extensively at the geology, extensively at the failure mechanisms. We do not --
we are simply not in areas where we're going to get a four-kilometre long rock
avalanche.
9981. The reference to the one-kilometre width is basically out in the
Prairies, very flat terrain. Those are the areas principally -- and areas of similar
terrain where there is really no chance of a hazard travelling, say, two, four
kilometres that we're going to go with minimum width.
9982. Where we have higher topography and where there is a chance for
such failures to come into the right-of-way, we are going to err on the cautious
side. We'll acquire the additional right-of-way -- additional LiDAR and -- so that
we have the opportunity to make those analyses.
9983. And in the province of British Columbia, B47-28, page 39, just -- I'd
like to read a paragraph into the -- into the record. We said that note -- the --
starting in the middle of the paragraph:
“The proposed strategies presented in the overview level [of
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
this paper] (Geertsema and Clague, 2011) publication to
reduce landslide risks to pipelines are consistent with the basic
outline of industry defined principles presented by (Rizkalla,
2008) and with the work carried out on the Project.”
9984. So we are consistent with the methodologies outlined here. I would
note:
“It must be noted, however, that (Rizkalla 2008) includes a
more comprehensive discussion of geohazards management
strategies and terrain analysis systems used in common
pipeline geohazards practice in Canada today and is noted to
have been prepared by [...] Canadian industry practice leaders
in the subject of geohazards assessment for [the] pipelines.”
9985. And as I'm sure you're aware, we've used the general methodology
outlined in that report as part of our SQRA.
9986. So I think that the methods that we are using here are very defensible.
They're methods that have been evolved over a period of tens of years of looking
at geohazard -- looking at geohazards, looking for geohazards and mitigating
those geohazards so that they do not pose undue hazard to the pipeline.
9987. So the simple -- the simple matter is that where we need more LiDAR,
we will get more LiDAR.
9988. MR. BECKETT: Once you're out of the flatter terrain at the Peace as
you're entering British Columbia from there through where you have the more
extreme terrain, more beautiful terrain in British Columbia from all of Canada,
what sort of minimum width are you looking at in that sort of terrain?
9989. MR. DRUMMOND CAVERS: Well, certainly the argument of
beauty is a judgment factor and there's probably people from the Peace country
who would also argue that that’s a very beautiful part of the world and a part of
the world that we want to take very good care of as well as the -- as well as all the
-- as all the geography along the pipeline right-of-way, which has its own beauty
and its own wonderful environment.
9990. In terms of what we're going to do as we come in to higher terrain --
and this would include, incidentally, the valleys and so on farther east in what we
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
might consider to be the Prairies where we have terrain where we need to look
wider for geohazards either in terms of the hazard reaching the pipeline or to
understand the geohazard, the LiDAR width will be widened out.
9991. MR. BECKETT: So I think you would agree that obtaining high
resolution LiDAR, wider swaths will benefit you by obtaining more information
on all the hazards that may impact the pipeline and there is more information to
obtain by getting the wider swaths of LiDAR.
9992. MR. DRUMMOND CAVERS: That’s entirely correct. My
colleagues joke about the size of my computer, the size of my hard drives and the
size of my power supply and it's because I like LiDAR data and I like having it all
with me so that I can work with it on an ongoing basis while we're looking at the
geohazards on the pipeline.
9993. I certainly view LiDAR as a very important advance that's given us a
wonderful tool, one of a number of tools that we use in assessment of geohazards.
And I'm a tremendous advocate for LiDAR. I agree 100 percent with you that
LiDAR is a very, very good tool, but one of a number of tools that we use for that
hazard assessment.
9994. MR. BECKETT: Yeah, I agree it has to be used as part of a package
on top of what we've done in the past. In that way, it's a wonderful advantage.
9995. Recognizing there are many reasons you may find it beneficial to
change the route being planned for the proposed pipeline, for example, to meet
community interests, wouldn’t an even wider corridor of quality information
provide greater clarity and certainty in the new route that the new route selected
will work and will not require further changes?
9996. So to provide just a little more comfort to the communities that what's
being discussed is fully informed and there's not constantly changes unnecessarily
because we don’t have good information.
9997. MR. DRUMMOND CAVERS: Well, you're certainly -- you're
certainly correct in that it's always nice to have more LiDAR and it's always -- it's
always an advantage to have that at hand. But sometimes our reroutes may be
quite considerable.
9998. We just looked at the Morice reroute, for example, here, which is
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
about seven or eight, I think, kilometres away from the original route in places.
9999. We have in the past rerouted tens of kilometres sideways from where
we are. And so it's really a -- it's really a bit of a trade-off between saying, well,
let's -- it would be really nice to say let's acquire a 100-kilometre wide swath right
across the whole project. But the cost and the -- and also the time to do that
because, especially in the west here, we run into flying problems and so on. And
so we might be sticking at one end trying to get a very wide swath when it would
be to our advantage to get through -- get as much data as we can.
10000. So there's trade-offs in this is, as there always is, and on occasion we
will -- or we may have to route outside where we have LiDAR. And in those
kinds of cases, ultimately we -- we typically go back and acquire additional
LiDAR in those areas. If it's a small swath and there's no snow on the ground, we
may be able to reroute a plane that’s already flying for another contract.
10001. So it's a -- these things are always trade-offs. There's always trade-offs
in life over these things. And I think -- I guess, ultimately, 20 or 30 years from
now when the younger engineers are sitting on this panel or a similar panel they
may have 20-centimetre LiDAR for the whole province at their fingertips just the
way we have air photographs now.
10002. Right now, we do have to -- we do have to compromise from the point
of view of practicality in terms of what we get, especially in areas where we don’t
know about a reroute right now. But we do try and be proactive as much as we
can. If we know we're going to look at an area, we'll widen out. We may have to
go back on occasion and acquire more in some areas, so it's one of life's trade-
offs, unfortunately.
10003. MR. BECKETT: So LiDAR not only improves the ability to assess
the likelihood and risk of landslides and mass wasting as we've been talking
about, but also improves the ability to locate small streams and ephemeral streams
as shown in a journal article that I provided this morning, "Stream Network
Modeling Using LiDAR and Photogrammetic Digital Elevation Models, A
Comparison In Field Verification".
10004. I understand there may be hard copies still at the back to -- for
anybody in the audience who would like to take a look at the article as well.
10005. Without going through the complete paper and looking at Table 1 on
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
the top of page 1751, would you agree, Mr. Cavers, that assessment methods that
include high resolution LiDAR will likely provide a better representation of small
streams and ephemeral streams than conventional methods without high-
resolution LiDAR?
10006. MR. DRUMMOND CAVERS: Yes, yes it will.
10007. This is just -- this is just another part of the whole advantage of
LiDAR which is -- one of them is to be able to look at subtle features.
10008. I would note that -- that, typically, these very small streams are not
fish-bearing but they are important to us from the point of view of assessing
erosion, assessing terrain conditions such as seepage.
10009. We often use LiDAR now even during clean-up when we’re setting
the locations of cross-berms, we’ll look at where the small drainages are because
one of the principles of water management -- of surface water management, from
my point of view which is to keep erosion to a minimum on the fresh right-of-
way, to keep water where we want water to be, is that we like to keep the water in
the streams, in the little water rills. We like to have the water come on one side of
the water -- right-of-way, flow across and go out and stay in the same stream it
was or in the same small drainage as it was.
10010. And so, yeah, you’re quite right, we use LiDAR now at the clean-up
stage often to assess where those little depressions are, the water was flowing in
before and we try to align our cross-berms at least in part with those. It depends
on the characteristics of the right-of-way and so on but we certainly use it as a
tool from that point of view as well to try and restore the terrain and to keep the
water where the water should be at the end of clean-up which is one of the
principles of reducing the sedimentation at the end of -- at the end of pipeline
construction, which we are very concerned about.
10011. MR. BECKETT: I would hope that you also use it to assess that, if
there is a leak from the pipeline or when there are leaks from the pipeline, assess
what downstream, down water channel risks values are at risk and incorporate
that into your Terrain Hazard Assessment that you have done.
10012. Have you done that?
10013. MR. DRUMMOND CAVERS: Well, that -- that’s more part of the
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
next panel.
10014. I believe it’s the next panel in terms of the spill response but, certainly,
LiDAR provides us the opportunity to look at those small features of terrain that
can be important in those circumstances.
10015. MR. BECKETT: Recognizing you already have some LiDAR
coverage for small portions of the area being looked at for this proposed pipeline,
have you done any comparisons of how assessments which incorporate high-
resolution LiDAR compared to conventional assessment methods do not
incorporate high-resolution LiDAR to see what extent the conventional method
are missing landslide risk areas and missing small and ephemeral streams?
--- (A short pause/Courte pause)
10016. MR. DRUMMOND CAVERS: Yeah, that’s been -- that’s been
covered in a previous IR but we are practical people and you noted that I haven’t
got LiDAR in any of my papers. It’s because I’m too busy using it rather than
writing papers that some of my academic friends are more interested in writing.
10017. So it’s not -- we prefer not to do studies. We prefer to take all the
different inputs we can get, that includes air photographs, orthoimages,
topography, TRIM, LiDAR, visual observations in the field, ground observations
in the field, survey, input from local residents who may often see things that
happened in the past and valuable source of information. There’s a huge suite of
information that we want to access and use in our assessments. We don’t usually
spend the time looking at: “Well, this one’s more efficient than that.” We usually
try and take advantage of everything we can get.
10018. Just to correct my previous testimony, we discussed those differences
in previous testimony. There wasn’t a specific IR on it.
10019. MR. BECKETT: As a member of the public trying to understand
your proposal and the consequence to the values that I cherish and the values that
many other people cherish, I was looking for some information of that sort that
would help me understand, you know, are you missing 3 percent of those
landslides? Are you missing 90 percent of the landslides? Are you -- so what
quality of information are we getting at this point to review?
10020. I haven’t seen that. Is there some of that that I’ve missed?
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
--- (A short pause/Courte pause)
10021. MR. DRUMMOND CAVERS: We -- as we’ve discussed
previously, we have a process here by which we’re moving forward continuously
and so our endeavour is not to miss anything significant.
10022. So doing a study to determine what we’ve missed, I’m not sure what
the point of it is. We want to find everything.
10023. MR. BECKETT: I think you’ve recognized that information
supported by high-resolution LiDAR has the potential of being more reflective of
what’s on the ground than information that doesn’t -- that’s not supported by
high-resolution LiDAR.
10024. A lot of the identification of values that’s been communicated to the
public has been based on information not supported by high-resolution LiDAR.
10025. We’d like to have a sense of the quality where we’re missing the high-
resolution LiDAR in relation to where you have it so that we know what type of
differences we might see down the road when you finally provide all the terrain
hazard information fully supported by high-definition LiDAR.
10026. MR. DRUMMOND CAVERS: We’re in a process going forward
with respect to the geohazards.
10027. I think it’s a process, as I said before, that we can be very proud of. It
certainly includes high-definition LiDAR and many of the areas -- in fact, most of
the areas where we have significant topographic issues, where we are expecting to
maybe see issues, we already have LiDAR in most of these areas.
10028. We will be acquiring more LiDAR, wider areas of LiDAR in some
areas, more extensive areas of LiDAR and continuous LiDAR coverage along the
entire pipeline route.
10029. This is all part of the process as we refine these geohazards and so I
don’t think you can say at one point in the process: “What are you missing?”
10030. We know that as we move forward and continue to refine our
geohazards inventory, to continue to refine our mitigation methods while there’s
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
little reroutes, changes in the pipeline, we have a process which is ongoing and we
don’t want to miss anything. And I think that we can be very proud of that
process but to say, in the middle of the process “You haven’t got everything”, we
know we don’t have everything. We are endeavouring to get everything and we
are confident that we will have everything significant as we finalize our design.
10031. MR. BECKETT: So, Mr. Cavers, I assume you would also agree
other attributes including the identification of active faults and unstable terrain
would be improved when high-resolution LiDAR is incorporated into the
assessment methods?
10032. MR. DRUMMOND CAVERS: We’ve talked about both of these in
the past, unstable terrain, yes, we’re not aware of any active faults in -- that cross
the right-of-way that are at the ground surface, but the answer to that is “yes” as
well.
10033. MR. BECKETT: Thank you very much.
10034. From the October 9th
transcript, line 5437, it states:
“We do recognize that, as we get more LiDAR, more detailed
LiDAR, as we look further at it -- as we get additional sources
of information, that we may well identify additional
geotechnical hazards. We expect to.”
10035. Without the benefit of high-resolution LiDAR for the entire proposed
pipeline route, how can the public be confident that the Joint Panel Review’s (sic)
decision is fully informed, to feel comfortable that all of the information they
should have is being provided, that all of the values placed at risk are being
identified and quantified and that the public and other stakeholders have had full
opportunity to review and comment on that material?
10036. MR. DRUMMOND CAVERS: I’m sorry; could you just repeat your
question?
10037. MR. BECKETT: Just the question portion, or do you want the
transcript portion as well?
10038. MR. DRUMMOND CAVERS: Well, just maybe give me the whole
thing again. I’m sorry; I was talking to my colleague here.
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
10039. MR. BECKETT: From the October 9th transcript, line 5437, it states:
“We do recognize that, as we get more LiDAR, more detailed
LiDAR, as we look further at it -- as we get additional sources
of information, that we may well identify additional
geotechnical hazards. We expect to.”
10040. “We expect to”, so that’s the statement.
10041. So my question, then, is without the benefit of high resolution LiDAR
for the entire proposed pipeline route, how can the public be confident that the
Joint Review Panel’s decision is fully informed, to feel comfortable that all the
information they should have is being provided, that all of the values being placed
at risk are being identified and quantified and that the public has had full
opportunity to review and comment and reflect on that information?
10042. MR. DRUMMOND CAVERS: I think -- first of all, I stand by my
testimony in line 5437 here. We have a process that we have talked about a lot
here. It includes the SQRA, which is -- has been filed. That’s a living document.
10043. That process is continuing to go forward. It’s continuing to go
forward as we speak in terms of engineers working in the field, looking at
geomorphic processes, looking at geohazards, looking at LiDAR, looking at all
the other sources of information that we have.
10044. It’s a process that’s going forward. It uses a huge amount of
information and it does incorporate, ultimately, high resolution LiDAR for the
complete route. And I think we can -- as I said before, I think we can be very
proud of what we’re doing.
10045. We are confident that we will identify everything that’s of material
importance relative to geohazards and these -- this information, as we go forward,
there will be, I’m sure -- and I can’t to speak to this in detail, but typically in these
processes there are ways for the public to interact with the design team.
10046. We are certainly interested in any interest the public has concerning
instability in their neck of the woods. I’ve said before this is something that we
view with interest because I’ve had situations, for example, not on this route, but
input from Native Elders to say that their grandfather had observed the slide at a
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
particular location. It was very useful because that location was now eroded by
the river, but it told us something about mechanisms of slides.
10047. So we are interested in all these sources of information. We are very
confident that we will identify the geohazards that are of -- important to the
design and safe operation of the pipeline.
10048. MR. BECKETT: And that will be prior to the Joint Review Panel’s
making of a decision?
10049. MR. RAY DOERING: Mr. Beckett, perhaps I can just help you a
little bit to understand that -- or to give you some assurances that Northern
Gateway is going to live up to the commitments we’re making here through this
testimony.
10050. There are a number of commitments that have been made in the
application during the hearings and all sorts of documentation that’s been now
filed as part of the regulatory process. These commitments that we’re making, we
track these.
10051. We manage a database that will measure to ensure that we are actually
delivering on these commitments that we’re making, so that’s something that we
do. And certainly the Joint Review Panel and the National Energy Board, they
have very detailed and comprehensive processes that they use to ensure that we
are complying with the commitments that we’ve made through processes just like
the ones you’ve heard here today.
10052. So when a certificate is issued for the project, it will certainly contain
conditions that will hold us to that to ensure that we are complying with
commitments and tracking those and reporting on those. And so I fully expect
that that will be a requirement of any certificate, that we live up to the things that
we’re saying here and that you’re hearing from Mr. Cavers today.
10053. MR. BECKETT: And excuse me if I’ve missed these details, but
what are the specifications you propose to use for this more detailed LiDAR in
comparison to the LiDAR that you currently possess? That’s again in reference to
the last October 9th
transcript, line 5437 statement.
10054. Were you committing to getting more LiDAR and more detailed
LiDAR?
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
10055. MR. DRUMMOND CAVERS: We will have complete LiDAR
coverage of the route which is suitable for our uses.
10056. MR. BECKETT: Can you give me a hint of sort of what resolution,
what specs you’re looking at there?
10057. MR. DRUMMOND CAVERS: Well, typically it’s sub one metre. It
depends a bit on where we are. We have had some problems getting really high
resolution out in a very few limited areas out west, but typically LiDAR these
days is sub one metre.
10058. MR. BECKETT: A little bit of change in questions here.
10059. Have you read papers where forest fires, logging or insect killed
forests, which often affect the hydrological cycle, have resulted in debris flows or
unstable terrain?
10060. MR. DRUMMOND CAVERS: Yes.
10061. MR. BECKETT: Have these potential causes of landslides been
factored into the terrain hazard assessment that you’ve completed so far?
10062. MR. DRUMMOND CAVERS: Our testimony, I think, is very clear
on this. What you’re referring to you are -- we would call triggers to landslides
and we look at whether the landslide can occur. If the landslide can occur, we
mitigate for it.
10063. MR. BECKETT: Do you believe climate change is occurring?
10064. MR. LANGEN: Madam Chair, I question the relevance of the
question. Whether the witnesses believe climate change is occurring is -- they
may have a personal view. I don’t think their professional view is relevant, nor is
their personal view, but I don’t think the question is relevant to this panel and I
don’t think it’s necessarily a fair question at the same time.
10065. THE CHAIRPERSON: Mr. Beckett, we’re here to hear your
questions to test the evidence of this panel with respect to the design aspects of
the proposed project and perhaps you want to continue your questions in that line
in order to be able to get the answers to questions that you are posing.
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
10066. MR. BECKETT: I think an answer to this question would put the
next question into better perspective, but I will continue to the next question if
you'd prefer.
10067. How have you modified your assessment of likelihood and risk of
landslides in light of changes brought on by climate change?
--- (A short pause/Courte pause)
10068. MR. DRUMMOND CAVERS: We’re just -- we have responded to
similar questions in a previous IR from the province of B.C. We’re just trying to
find that IR.
--- (A short pause/Courte pause)
10069. MR. DRUMMOND CAVERS: We replied to this question in
Exhibit B47-28, which was a response to the province of B.C. IR Number 2, and
we're on page 38 and it's point (a).
10070. So we -- what we say in there is that: “Ongoing management...”
“[...] geohazards assessment forms part of an overall integrity-
based risk management framework, [...] geohazards will be
actively managed throughout the life of the Project. Ongoing
management allows for updating predictive models based on
[...] long-term conditions, such as potential future climate
affects, [...] allow for ongoing adjustments to the defined
geohazard [...] areas, [and the] predicted occurrence, and
mitigation strategies, as required.”
10071. And further to that comment -- I think your question in part relates to
how we're assessing it right now. And we are -- we are cognizant that there -- that
certainly weather can be variable, climate can be variable and we are allowing for
this in our assessment . But we're not allowing for it on the triggering point of
view because, as I've said before, we assume that the landslides, if they can occur,
will be triggered and so we're mitigating them on that assumption. We're not --
we're not looking at the chance they might be triggered; we are assuming that they
will be triggered.
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
10072. MR. BECKETT: Thank you very much.
10073. What happens to the pipeline pipe and the welds when the landslide
characteristics exceed what the pipeline can handle?
10074. MR. DRUMMOND CAVERS: Well, this is -- this is conjecture and
I don’t think it's appropriate because our -- we are not proposing what's called a
“strain-based design” at this juncture. We are looking to mitigate -- either avoid
the landslides wherever we can or, where we cannot, to mitigate those slides so
that they don’t affect the pipe. And we've discussed those mitigation measures
previously.
10075. MR. BECKETT: But it's very likely that there's going to be
landslides along stretches that you did not predict would have landslides and the
pipe's going to be affected. It also assesses the -- it factors into which landslides
you consider a hazard versus the ones that don’t. I understand that you're digging
your pipe down deeper where you think landslides are going to be. That’s good.
The depth is relevant to the landslide. Your assessment of all that has to do with
the landslide.
10076. You surely must know what factors of a landslide you have to consider
are a threat to the pipeline.
10077. MR. LANGEN: Madam Chair, sorry, I just want to caution -- and all
due respect to Mr. Beckett. I realized he's not legally trained.
10078. A couple of his preambles -- they're -- more than a couple. They're
fairly lengthy and he includes assertions in them that I think if he wants to put
those assertions to the witnesses, it would be fair to do so in a single question.
10079. So in the last preamble that he just delivered, he said there are very
likely to be landslides along the pipeline route and then he went on in his
preamble quite -- quite a ways and then he ended with a question. And earlier, he
put another preamble to the witnesses where he said "you have a small amount of
LiDAR" and then he went on and asked the question.
10080. And I do mean no disrespect to you, sir, recognizing that this isn’t
what you do for a living, so I appreciate that. But I am concerned that there are
nested assertions in the preambles that may, at a later date, be taken for agreement
because the witnesses didn’t necessarily deal with them up front.
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
10081. So with that cautionary note, I would ask, Mr. Beckett, if you could try
to break your questions up if you have a long preamble. I think that would be
helpful, if that’s okay, Madam Chair.
10082. THE CHAIRPERSON: Mr. Beckett, you've obviously spent a great
deal of time preparing -- or at least that’s the impression you're leaving with me --
and it may be that you need to slow down just a little bit so that we can keep up
with you.
10083. It's -- I'm not sure how much longer you plan to be. We do like to take
a break in the morning at some point. So you know, within the next 10 minutes or
so maybe you could let us know when a good time to take a break is, recognizing,
again, that I've already interrupted you at this point.
10084. I don’t know if you want to continue on and perhaps break your series
of questions down that you just asked, get the answers to those and then maybe
take a break? I'll be in your hands as to what's most appropriate for you.
10085. MR. BECKETT: I take your advice and I'll try to heed forth from
now.
10086. I'm just at the top of page 7 of basically seven pages of questioning.
So I think it's easy enough to finish, but it's your call.
10087. THE CHAIRPERSON: Thank you for letting us know. The Panel
thinks it would be a great idea if we just continued on and finished.
10088. So having said that, maybe we could roll back to the series of
questions that you posed and just put those to the panel in more bite-size chunks,
please.
10089. MR. BECKETT: Will do. So I'll start at the first question on the top
which had the long preamble; sorry.
10090. What happens to the pipeline pipe and the welds when the landslide
characteristics exceed what the pipeline can handle?
10091. MR. DRUMMOND CAVERS: That’s a hypothetical question and I
can't -- I can't answer it. I do repeat that our objective is not to have the pipeline
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
in landslides.
10092. MR. BECKETT: Hypothetical. So my -- would it be fair to say that
the pipeline would probably start leaking, would rupture if it was faced to that
hypothetical situation?
10093. MR. DRUMMOND CAVERS: Well, you've -- I think what you're --
I think what you're trying to say here is if the pipeline's in some hypothetical giant
landslide and it exceeds the strength of the pipeline that it would fail. And the
answer is yes to that hypothetical situation. That’s what we are spending
enormous time to avoid having -- having occur.
10094. MR. BECKETT: I appreciate that, especially considering what
happens to the pipeline contents when the pipeline ruptures. And that’s a
question.
10095. MR. DRUMMOND CAVERS: Sorry; I didn’t understand the
question.
10096. MR. BECKETT: What happens to the pipeline contents when the
pipeline ruptures?
10097. MR. RAY DOERING: There are a number of variables, I guess, that
would determine what would happen to the contents. The size of the rupture
certainly is -- would be an important determination. The time to detect that
rupture; the time to isolate the pipeline system; the time to respond to that location
in that situation.
10098. So there's a number of variables. It's -- it could be anything from a
very minor event immediately locally contained in the vicinity of the pipeline to
something -- to something bigger than that, so it's -- there's really an infinite
number of scenarios.
10099. We have described at great length how we go about determining not
only safe design practices and identification and mitigation for potential
geohazards, but as prevention methods -- of course, there's all sorts of other
ongoing prevention methods that can detect over time whether -- whether subtle
shifts in the land are occurring.
10100. My colleague will be able to describe that and maybe he should,
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
actually, just to -- so that you understand.
10101. But really, reducing the potential consequences of an event like that
are why we spend a lot of time determining where to most effectively place
isolation valves and where to most effectively locate response personnel and
equipment. These are all important considerations, so it's much more complex
than I could just give you a simple answer to.
10102. MR. BECKETT: So if you can honour me with the hypothetical
situations still, could you explain the characteristics that a landslide needs to have
to begin causing damage to a pipeline?
10103. I’m trying to get a sense of which landslides we worry about and
which ones we don’t.
10104. MR. DRUMMOND CAVERS: Perhaps -- perhaps you could
rephrase the question to get rid of the hypothetical landslide and just ask it more
directly.
10105. I’m not -- we could either build a textbook or maybe just get the
question tighter around where you’d like to go.
10106. MR. BECKETT: Could you explain the characteristics that a
landslide needs to have to begin causing damage to a pipeline?
10107. MR. DRUMMOND CAVERS: Well, I’ll take it that what you’re
asking is: What kind of landslides are we maybe concerned about relative to the
pipeline?
10108. And the -- of course, our -- what we’re ultimately concerned about
with respect to a landslide is soil pipeline interaction. The degree of soil pipeline
interaction that occurs in a slide.
10109. Our objective with mitigating the slides -- and you referred earlier to
digging under slides, we very seldom, actually, dig under a slide because we can’t
get deep enough but our -- what we endeavour to do is to have no soil interaction
with the pipe.
10110. But the degree of loading in a hypothetical landslide depends on the
soil interaction with the pipeline.
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
10111. MR. BECKETT: And trusting you have -- even though you haven’t
answered that part, you know it, so are these landslide characteristics that you’re
describing or referring to -- trust me, you know, we have -- specific -- so are the
landslide characteristics that you’ve described based on the specific pipeline
design and material qualities that will be used if this proposed pipeline is
constructed?
10112. MR. DRUMMOND CAVERS: No, let me make it clear, we are not
relying on the pipeline strength.
10113. We are not primarily relying on the pipeline’s strength to resist failure
in a landslide. We don’t want the pipeline to be in landslides that could damage
it. We are not relying on the material strength of the pipeline to resist failure in a
slide. Our design -- that is not the basis of our geotechnical design.
--- (A short pause/Courte pause)
10114. MR. BECKETT: So I heard some earlier questioning that was
talking about the welds on a pipe and there’s the PHFS -- PHMSA, the Pipeline
Hazardous Material Safety Administration, and they have some standards for
notch toughness.
10115. Assuming CAT1 pipe and welding techniques, all of that irrelevant
and unnecessary with respect to pipeline landslide considerations then?
10116. MR. JAMES MIHELL: So, again, we’re in -- very deep into the
realm of the hypothetical here but, with respect to large-scale strain events such as
landslides, materials, should you expose them to large-scale strain events, don’t
fail in a manner that would be characterised best by the Charpy toughness test that
we’re talking about earlier. It’s basically simply what’s called “plastic collapse”.
10117. You’re -- you would -- in large-scale strain, material fails on the basis
of its overriding flow stress capability; its ability to sustain stress.
10118. You referenced welds there and it brought into question the welds,
whether or not they would form, perhaps, the weak link in the chain.
10119. In actual fact, the whole point of performing tensile strength -- sorry,
tensile tests on welds as part of the welding procedure qualification is to ensure
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
the weld isn’t the weak link in the chain, that the weld material is stronger than
the surrounding base metal.
10120. And I know there’s been some discussion about Enbridge’s pipe spec
but Enbridge’s pipe spec is written in such a way to ensure that that is the case.
10121. MR. BECKETT: And with those last answers, have your answers
assumed all welds are stress relieved?
10122. MR. JAMES MIHELL: Stress relief actually has no bearing on
material strength. It -- that’s not why some -- under some construction projects,
stress relief is performed.
10123. Stress relief isn’t undertaken on pipelines. It’s not something that is
characteristically done in the pipeline industry.
10124. MR. BECKETT: I’ll thank all of you for taking time to answer my
many questions.
10125. And thank you, Madam Chair, for guiding me through this process.
10126. And thank you, Madam Clerk, for presenting the referred materials,
especially on such short notice.
10127. THE CHAIRPERSON: Thank you, Mr. Beckett.
10128. You -- you know, you indicated that you’ve stepped forward as a
member of the public and, obviously, as I said before, you’ve spent a lot of time
being ready to ask your questions and I just want you to know that the Panel
really appreciates your participation and the questions that you’ve posed to be
able to understand the evidence of this witness panel better.
10129. So thank you very much for taking the time to be here.
10130. We also know that you’re not here during work hours as you brought
forward in your preliminary matter.
10131. So the only thing we need to do is just have Ms. Niro give us an AQ
number for the paper that you referenced during your questioning.
Enbridge Northern Gateway Panel 2
Examination by Mr. Beckett
Transcript Hearing Order OH-4-2011
10132. MS. NIRO: That will be AQ27.
--- AID TO CROSS-EXAMINATION NO./AIDE AU CONTRE-
INTERROGATOIRE No. AQ27-A:
Doug Beckett – Article – Stream Network Modeling using LiDAR and
Photogrammetric Digital Elevation Models: A comparison and filed
verification by Paul N.C., Murphy, Jae Ogilvie, Fran-Rui Meng and Paul Arp
10133. THE CHAIRPERSON: So thank you, Mr. Beckett.
10134. We’ll take a 15 minute break now. We’ll come back at five after
eleven and the next person who will ask questions is Mr. Vulcano.
10135. Thank you very much.
--- Upon recessing at 10:46 a.m./L’audience est suspendue à 10h46
--- Upon resuming at 11:10 a.m./L'audience est reprise à 11h10
10136. THE CHAIRPERSON: I believe we’re ready to get underway again.
Thank you.
RAY DOERING: Resumed
PETER ACTON: Resumed
BARRY CALLELE: Resumed
DRUMMOND CAVERS: Resumed
TOM FIDDLER: Resumed
SHANE KELLY: Resumed
CLIVE MacKAY: Resumed
JAMES MIHELL: Resumed
PETER WONG: Resumed
10137. THE CHAIRPERSON: Good morning Mr. Vulcano. Nice to see
you again.
10138. Would you please proceed with your questions of this witness panel?
Enbridge Northern Gateway Panel 2
Examination by Mr. Vulcano
Transcript Hearing Order OH-4-2011
--- EXAMINATION BY/INTERROGATOIRE PAR MR. VULCANO:
10139. MR. VULCANO: Good morning Madam Chair, Panel, NEB Staff,
Enbridge Personnel and other participants. I’d like to acknowledge being on the
traditional territory of the Lheidli T’enneh.
10140. My questions are going to mostly be about the spreads. So more of a
macro perspective than the micro on cracks and welds.
10141. If we could start with Exhibit B82, Adobe page 74. That’s from
Volume 6E, Section 4.4, page 4.4-60
10142. I was wondering if the Proponent could elaborate on the rationale for
the 12 spreads and in the order that they’re being done?
10143. I’ve asked for a map that could be put up, if that’ll help, 6.1 from
Volume 8 of 10.
10144. I’ve deduced that the spreads start from Bruderheim and then go west,
1 through 12; would that be correct?
10145. MR. RAY DOERING: Hello, Mr. Vulcano. I’ll start.
10146. First of all, no, it’s not quite correct that the spreads will go to -- from
Bruderheim to Kitimat. It is more complex than that.
10147. We start with trying to understand, basically, what a Mainline pipeline
construction contractor -- what kind of productivity they could get in any given
season and we look at, typically, two seasons of potential pipeline construction be
it the summer season, probably a four month period through the summer season
and there would be, similarly, a three or four month period through winter season
where a contractor can productively work.
10148. And in between there are -- for example, in the spring, there are a lot
of things that -- reasons why you wouldn’t be constructing through the spring, just
through the spring breakup and migratory bird sensitivities, things like that. So
there’s certain times of the year where you don’t want to be doing your Mainline
construction activities.
10149. Similarly in the fall, typically winter construction spreads are
Enbridge Northern Gateway Panel 2
Examination by Mr. Vulcano
Transcript Hearing Order OH-4-2011
undertaken where you might have wetter conditions, perhaps muskegs involved,
that sort of that where you actually want frozen ground conditions. So you need
that ground to actually freeze before the contractor would move into that area and
begin construction.
10150. So maybe I’ll try and use these figures that you have up. The one
that’s shown up -- projected now ---
10151. MR. VULCANO: Sorry, I just wanted clarification just on the spread
numbering, like the numbering, number 1 is closest to Edmonton and number 2
beside it and number 3 beside it?
10152. MR. RAY DOERING: No, it’s not that simple.
10153. MR. VULCANO: No. It’s -- okay so ---
10154. MR. RAY DOERING: It’s -- we have broken up the work, in this
case -- in this example that we’ve undertaken here for the assessment purposes --
into four different construction seasons. There are two winters and two summers.
So that’s identified by what we call “Summer 1” and “Summer 2”. We didn’t put
years on it because, you know, there’s some uncertainty in terms of what is the
actual start date going to be so we just sort of indicate it by season rather than by
year.
10155. But there will be -- as we’ve indicated I think in previous IR responses
and in information that’s been filed, we are anticipating potentially three pipeline
construction contractors -- Mainline pipeline construction contractors working
simultaneously in different areas along the route. So not just starting in the east
and working towards the west, they will be starting in different areas.
10156. And I think we have -- so those three construction contractors will
have three construction spreads in different locations in Summer 1, three
construction spreads that they’ll be doing in the first winter season and then,
similarly, in the second summer and the second winter. But they’re not
consecutive starting from east and going west. I think maybe that will help.
10157. But I just wanted to just to give you a little bit more context on this
before you move on maybe to your next question. Figure 6-2 in what you’re
showing up here, that area, basically from the Bruderheim area to around the
Whitecourt area, the first 200 km of the pipeline, this would be typically
Enbridge Northern Gateway Panel 2
Examination by Mr. Vulcano
Transcript Hearing Order OH-4-2011
cultivated farmland.
10158. This is the agricultural area. This is -- in Alberta, they call it “The
White Zone”. It’s been undergoing -- the land’s being used for agricultural
purposes for many years. In these areas where you have valuable topsoils, for
example, you want to do that work in the summer because you want to be able to
properly take care of that topsoil and remove it from the right-of-way, store it on
the edge of the right of way, undertake your work and then replace that topsoil
and that’s best done in summer conditions. You don’t want to have any sort of
topsoil, subsoil mixing concerns.
10159. So that area in the first 200 km would be typical what we call “summer
construction”. As you move west, beyond Whitecourt ---
10160. MR. VULCANO: Sorry, can you tell me what spread that would be
then if it’s not number 1?
10161. MR. RAY DOERING: Well, it’s not -- I can’t really -- unless, Tom,
you want to.
10162. We haven’t really defined here in this information which exactly is the
first summer spread. I don’t think that’s actually contained in the filing material,
unless I’m mistaken.
10163. MR. VULCANO: Could -- Ms. Niro, could you go back to the chart,
please?
10164. MR. TOM FIDDLER: Mr. Vulcano, maybe I can help and we
haven’t met along the way but I have certainly recognized your interest in the
logistics of pipeline construction and we’ve taken -- applied significant effort to
fielding some questions from not only yourself but others in associated
communities along the right-of-way who are legitimately interested in not just the
logistics but opportunities to be participants in the project.
10165. In some of the documentation -- and like this table here -- the
numerical numbering is literally the beginning of a logistical plan for how we can
identify an associated, specific segment of work, if you will.
10166. It doesn’t mean that that’s sequential in any way, as Mr. Doering
indicated and ---
Enbridge Northern Gateway Panel 2
Examination by Mr. Vulcano
Transcript Hearing Order OH-4-2011
10167. MR. VULCANO: Sorry, does it mean it’s not sequential?
10168. MR. TOM FIDDLER: It doesn’t mean that it’s sequentially, going
to be built step 1 through 12.
10169. MR. VULCANO: I understand that and that’s what this chart is.
10170. So you’re going to go, like, the first contractors intended will go
spread 3, spread 1, spread 2, spread 6?
10171. MR. TOM FIDDLER: Yes.
10172. MR. VULCANO: That -- so that sequence is on,
10173. MR. TOM FIDDLER: Now, that was based on this schedule which
was 2014-15.
10174. We talked early in this hearing about completion of the work, now,
conceptually it would be in mid-summer or the end of the winter of 17-18 leading
up to in-service at the end of 18.
10175. MR. VULCANO: Sure.
10176. And I’m not so interested in the years as the scheduling and I’m trying
to get a sense of where these spreads are.
10177. If they’re not sequential, can you show -- is there a map, for instance,
that shows where spread 3 is, where spread 1 is, where spread 2 -- where all 12
spreads are?
--- (A short pause/Courte pause)
10178. MR. TOM FIDDLER: So there is a table 10-3 in Volume 3, B1-5
table, Adobe page 92, thank you.
10179. MR. VULCANO: Louise is working her magic there.
10180. MR. TOM FIDDLER: Yes, I acknowledge she does a great job too.
Enbridge Northern Gateway Panel 2
Examination by Mr. Vulcano
Transcript Hearing Order OH-4-2011
10181. MR. VULCANO: Yes.
10182. MR. TOM FIDDLER: So, really, the delineation of spreads is by
kilometre posts and, going back to what Mr. Doering was talking about earlier,
that’s largely driven by some initial planning based on productivity expectations
within a certain window of time whether it be winter condition or summer
condition.
10183. We refer to it as “summer”, it often extends greatly into the fall given
restricted activity periods around migratory birds and the like but ---
10184. MR. VULCANO: Could we just refer to this for a moment?
10185. If I’m looking at those kilometre posts it looks like it’s pretty
straightforward. Spread 1 starts in the east and then spread 2 is right beside it,
spread 3 right, beside it, all the way to 12 before going to Kitimat.
10186. MR. TOM FIDDLER: Correct.
10187. But that’s a numerical sequencing just for logistical planning basics, if
you will. It’s not how the construction execution will ultimately happen.
10188. MR. VULCANO: Right and that’s why ---
10189. MR. TOM FIDDLER: Yeah.
10190. MR. VULCANO: --- I brought up the first table.
10191. MR. TOM FIDDLER: You bet.
10192. MR. VULCANO: So you’re going to go with spread 3 which is
Kilometre Posts 279 to 372; correct?
10193. MR. TOM FIDDLER: Yes.
10194. MR. VULCANO: For construction group 1.
10195. And then, Ray -- if I may use your first name -- was saying that, you
know, there’s logistic reasons. I can appreciate that, that you want to be -- it’s
going to be the winter, so spread 3 and then you’re going to move to -- that
Enbridge Northern Gateway Panel 2
Examination by Mr. Vulcano
Transcript Hearing Order OH-4-2011
particular crew will move to spread 1 then spread 2.
10196. MR. TOM FIDDLER: Correct.
10197. MR. VULCANO: So for logistic reasons, you know, the farmland
thing, you want to be doing that farmland spread 1 in the summer.
10198. MR. TOM FIDDLER: Yes.
10199. And I would add to that that an element of this is also the camps that
are forecast and that’s still a work in progress and, at some communities, we’ve
obviously got consultation to complete with them on existing accommodations,
competing businesses for space in community facilities so …
10200. And then, beyond that, we get into travel time for crews and the safety
of the public in terms of the transportation of work force and those types of
things.
10201. So there’s many factors that go into deciding where these spread
breaks are and the logistics that come into play around attracting contractors to
the work and then being efficient and doing the right things.
10202. MR. VULCANO: And as I’m trying to get behind some of the logic
---
10203. MR. TOM FIDDLER: Yup.
10204. MR. VULCANO: --- the -- so spread 3 is the start. So you’ll have a
crew that you’ll hire or the contractor will hire for that.
10205. Where will those personnel come from?
10206. MR. TOM FIDDLER: I’m not sure what you mean by the question.
10207. Certainly, the contractors will bring to bear in their proposals to us a
resource management plan and, within that, they’ll identify -- so let’s talk
specifically that -- and we have had preliminary discussions with the Pipeline
Contractors Association of Canada about this project given its magnitude. They
would propose to us and say: “Well, we expect that at that particular timing that
50 percent of our workforce will come from our union halls locally in Alberta”.
Enbridge Northern Gateway Panel 2
Examination by Mr. Vulcano
Transcript Hearing Order OH-4-2011
10208. We've got an additional expectation of our contractor community to
employ a minimum of 15 percent Aboriginal workforce in the construction.
10209. So we'll be defining to them, within their resource planning proposals,
the communities we expect them to consult with and have opportunity for
engagement. Then, they will identify potential gaps from local union halls and,
obviously, then it extends out and there's a protocol relative to that.
10210. MR. VULCANO: Now, spread 3 from the map, it kind of looks like
it would start around Whitecourt ?
10211. Ms. Niro, if you might go to the map there, around 6.3?
10212. Will it be starting and moving west or will it be starting on the west
part and coming east when you're working on Spread 3?
10213. MR. TOM FIDDLER: Direction of travel, as we refer to it when
we're building, is typically east to west on this project.
10214. Predominantly and our intention, other than there may be some
geotechnical-driven situations or the like, the intention is to construct the 36-inch
first in the right-of-way and the 20-inch adjacent to it.
10215. MR. VULCANO: And so when the contractor is finished Spread 3,
he's going to move to -- near Bruderheim and start Spread 1? That's ---
10216. MR. TOM FIDDLER: That's correct.
10217. MR. VULCANO: And is he likely to take most of his crew with him
then?
10218. MR. TOM FIDDLER: Yes, absolutely.
10219. MR. VULCANO: So the benefits for hiring, there's going to be
people near Whitecourt initially then?
10220. MR. TOM FIDDLER: Yes.
10221. MR. VULCANO: Okay.
Enbridge Northern Gateway Panel 2
Examination by Mr. Vulcano
Transcript Hearing Order OH-4-2011
10222. And one of the advantages of having the same crews then they're
going to start doing a better job?
10223. MR. TOM FIDDLER: There's inherently efficiency and whether
you talk productivity or you talk quality, safety management, environmental
compliance and the like.
10224. Not that we don't have safeguards and practices that oversee those
aspects of the project; it becomes a far smoother operation to have continuity of
work and continuity of the workforce to the extent we can.
10225. MR. VULCANO: Good, that -- well, that makes sense to me.
10226. MR. TOM FIDDLER: Yeah.
10227. MR. VULCANO: Glad I’ve figured that out or came to that same
conclusion.
10228. So you're going to have camps for the crew in Spread 3 but, when they
go to Edmonton, they're expected to find their own housing in Edmonton?
10229. MR. TOM FIDDLER: Well, they aren't on their own as individuals,
whether they be PLCAC contractors -- so the Pipe Line Contractors Association
of Canada contractors -- or CLAC contractors -- Christian Labour Association of
Canada -- or a non-union contractor that may be pre-qualified, the contractors
management take a very paternalistic approach to accommodations and we work
with them on accommodations planning, given the potential issues with attraction
and retention of the workforce as well as the safety of their travel and
transportation.
10230. So it's not something where everybody is left on their own. There is,
in the pipeline industry, more circumstances in summer conditions where
individuals like to bring their family along and utilize campgrounds, to be honest
with you, or farmyards they may have been acquainted with and negotiate a
situation to pull their fifth-wheel trailer in or those types of things and we don't
interfere with that and, typically, the contractors don't either.
10231. MR. VULCANO: Okay.
Enbridge Northern Gateway Panel 2
Examination by Mr. Vulcano
Transcript Hearing Order OH-4-2011
10232. Moving then -- okay, so after they've done Spread 1, Spread 2 just
follows logically. They it jumps to, according to the chart, Spread 6.
10233. So that goes into B.C. What is the logic for going to Spread 6?
10234. Ms. Niro, perhaps you'd like to go back to the chart?
10235. MR. TOM FIDDLER: I apologize, I do have a vision problem going
with a retina detachment that I'm recently recovering from. So I honestly -- I'm
struggling to see the screen.
10236. MR. VULCANO: Okay, yeah, you do want to get that retina
attached.
10237. MR. TOM FIDDLER: It's attached.
10238. MR. VULCANO: Okay.
10239. MR. TOM FIDDLER: The vision is not that good.
--- (A short pause/Courte pause)
10240. MR. RAY DOERING: So, Tom, if I can help.
10241. MR. TOM FIDDLER: Yeah.
10242. MR. RAY DOERING: Just move that back.
10243. Spread 6 was indicated as the second summer for that particular
contractor and, in the initial filing, we indicated that was around -- between
Kilometre Posts approximately 560 and 630, which would be in the Rocky
Mountain area.
10244. So over the height of land on either east and west side of the Rocky
Mountains.
10245. So this is sort of the next adjacent summer spread following from the
Alberta side as you go west. Summer construction through that area and that's
essentially to deal with the climatic conditions. So in the winter, you've got a lot
of snow in that area that can accumulate so you want to do that construction
Enbridge Northern Gateway Panel 2
Examination by Mr. Vulcano
Transcript Hearing Order OH-4-2011
through summer, through the summer months.
10246. So that would have been a description for Spread 6, if that helps.
10247. MR. VULCANO: I just wanted -- because you're going to have a
crew that's pretty versant in working in the Prairies and then they're going to jump
-- the contractor is going to be in the Mountains.
10248. MR. TOM FIDDLER: The contractor community have, although not
of recent, built mountain pipelines -- they certainly have especially across
Southern British Columbia -- ad one of the advantages we're going to realize as a
project is that there's a significant amount of large bore pipeline activity in British
Columbia and elsewhere in different terrain than more recently.
10249. So we feel that's going to be a significant benefit to some of the aspect
that we've talked about in terms of quality and compliance and safety and the like.
10250. MR. VULCANO: Let's move to Contract 2 there.
10251. I can see some logic, there's going to be similar terrain, minimal
logistics, Spreads 9 to 10, and then 8 to 7.
10252. Contract 3, you've got starting in Spread 4 going to Spread 11. That
seems to me that's going to be quite a jump for all the crews and the contractor
and moving the equipment.
10253. MR. TOM FIDDLER: I think that's a fair observation.
10254. I'm sorry, I don't understand what maybe the question is.
10255. MR. VULCANO: Well, what's your justification from going from 4
to 11?
10256. MR. TOM FIDDLER: The -- so we start off with a concept in this
plan of three contractors, each of them with a Winter 1 assignment, if you will,
scope of work. Then they -- you know, the Summer 1, Winter 2, Summer 2
assignment -- and, inherently, just mathematically with three spreads and 12 -- or
sorry, 12 spreads and three contractors, you end up having to leapfrog with at
least one of them.
Enbridge Northern Gateway Panel 2
Examination by Mr. Vulcano
Transcript Hearing Order OH-4-2011
10257. And with that -- you know, some previous comments, one of the things
we want to do is have sequential work, not -- and I don't mean sequential
necessarily in the same communities or the same geographic region but
continuous work to retain the workforce and the contractors and attract the best
skilled labour and the best contractors.
10258. MR. VULCANO: I think that's a great principle.
10259. MR. TOM FIDDLER: Yeah.
10260. MR. VULCANO: I support taking that approach both for the
steadiness and the consistency, going for the quality work.
10261. So a question I have is along that line: Because you're going to have
less and less impacts by having the same crews, why not just have one contractor
doing all 12 spreads and then you won't need the leapfrogging?
10262. You'll have the best of the skilled people to work with, minimize
impacts on the communities and the environment.
10263. MR. TOM FIDDLER: The consequences of that scenario -- and it's
not that it's not doable, if you will -- but the reality is we would need multiple
years.
10264. Again, if you consider each spread as taking half a year, including
breaks for things like road bends and break-up and so on, and then late in the year
you're waiting for freeze up for the winter work, you end up with -- it would
essentially take, depending on the contractor, 12 years to build -- or sorry, six
years to build.
10265. The reality is in Canada right now. There is only one large bore
contractor with two pipeline spreads capability and it ebbs and flows but currently
are -- and it is a critical aspect of the industry that we forecast and we spend effort
working with that side of the industry.
10266. There currently is an estimation of roughly 10 large bore pipeline
spreads in Canada and that’s not to preclude that others may invest and develop
pipeline contractor spreads but they are major capital investments in terms of the
size of equipment, both rolling stock and heavy equipment, that are involved in
getting into the business and it is a cyclical business, traditionally.
Enbridge Northern Gateway Panel 2
Examination by Mr. Vulcano
Transcript Hearing Order OH-4-2011
10267. MR. VULCANO: And there’s a question I have further down is
about the capital stock.
10268. Wouldn’t that be more efficient then if it was just one contractor
having to get one set of equipment rather than three contractors getting three sets
of equipment?
10269. MR. TOM FIDDLER: Well, the marketplace takes care of that itself
in that the contractors are in -- obviously in the business for a purpose and end
means of their business objectives and they invest in their equipment and survive
the test of time based on their objectives.
10270. In our case, as I mentioned, we don’t have a reasonable expectation or
could we tolerate a six-year construction window and I’m not sure that it would
be in the interest of the public at large either, in terms of completion of the
project.
10271. MR. VULCANO: Could you elaborate on that?
10272. Why wouldn’t it be in the interest of the public?
10273. MR. TOM FIDDLER: Well, the project would be -- progress very
slow in comparison.
10274. You -- the pipeline business is a competitive business on the contractor
side as well as in ours and there are -- there’s a particular type of person that is
willing to live basically on the road and work away from home for these
protracted periods of time.
10275. It’s not like an industrial site such as some of those we compete with
in Fort McMurray and elsewhere, where the workforce knows where they’re
going every day. It’s a defined environment, controlled environment in terms of a
workplace setting and you can basically set up home.
10276. A pipeline construction project is very much like a linear assembly
line and it’s very difficult as -- and very much an element of the industry that the
work force enjoys there two or three months break in between pipeline spreads to
regroup with their families and do other -- take care of their other social needs
versus working continually for, you know, in the hypothetical case, for six years
Enbridge Northern Gateway Panel 2
Examination by Mr. Vulcano
Transcript Hearing Order OH-4-2011
continuously on a travelling assembly line, as I describe it.
10277. MR. VULCANO: So, if I understand correctly, they’re willing to do
it for two years but not six years; is basically it?
10278. MR. TOM FIDDLER: Well, and with the breaks in between.
10279. The reality is in between those seasons. Then, there’s equipment
servicing, there’s many folks that continue to work. Others take a break and get
an opportunity but everybody ultimately gets an opportunity for a vacation, if you
will, in between.
10280. MR. VULCANO: But wouldn’t they have that whether it was a two-
year or a six-year term?
10281. MR. TOM FIDDLER: Just more difficult to retain the work force
for steady, continuous, six-year cycle and, again, on a single project competing in
the marketplace, we believe there would also be additional risks to that retention.
10282. We currently see a window of opportunity when Northern Gateway
goes to construction here in terms of competing market demands for the limited
number of pipeline spreads, as I elaborated on earlier.
10283. MR. VULCANO: Sorry, limited number of pipeline?
10284. MR. TOM FIDDLER: Spreads.
10285. MR. VULCANO: Spreads?
10286. MR. TOM FIDDLER: Yes.
10287. So again, going back to there being 10 or thereabouts and that does
ebb and flow, there -- the period that we’re looking at construction here and how
we’re looking at getting out ahead in the marketplace gives us confidence that we
can secure the three pipeline contractors and their spreads that we are going to
need to execute the project.
10288. MR. VULCANO: Okay, I’m trying to appreciate that perspective.
10289. I would have thought the same as -- it’s better for consistency to have
Enbridge Northern Gateway Panel 2
Examination by Mr. Vulcano
Transcript Hearing Order OH-4-2011
a group moving from the first four spreads, that they’d be happier to work on all
12 spreads.
10290. There seems to be some line in there that you’re saying that two years
is better than three months but two years is also better than six years.
10291. MR. TOM FIDDLER: Mr. Doering’s indicating he wants to try and
help me with some of the rationale as well and has some additional comments to
layer on.
10292. MR. RAY DOERING: Yeah and really, a little bit more from a
commercial perspective and you may have heard from our first Panel in
Edmonton about some of these matters. But I mentioned here this week that our
in-service date is anticipated to be 2018 and I think Mr. Fiddler has mentioned
that again.
10293. And there are commercial drivers to achieve that date. There are
needs to deliver that incremental production that’s expected from the Western
Canadian Sedimentary Basin by that time frame and so we really can’t have a
project that will take six years to construct.
10294. That just won’t meet the needs, the commercial needs of the project as
well. So, that’s a very important consideration that I think that really is -- needs
to be considered as well.
10295. MR. VULCANO: Okay.
10296. And I don’t want to belabour this aspect, so that brings me -- the point
I wanted to make was: You’re weighing against minimal impacts versus needs of
the project to have it done on time?
10297. MR. TOM FIDDLER: If I could, Mr. Vulcano, there’s also another
aspect to this that’s subtle but important. I mentioned it earlier but we’ve made
commitments to the Aboriginals as well as the local communities along the way.
10298. So part of the logistics creates also greater opportunity for local
businesses and local employment and for the First Nations along the route that we
want to assure some opportunity for participation.
10299. So, you know, using the concept of a single contractor going one end
Enbridge Northern Gateway Panel 2
Examination by Mr. Vulcano
Transcript Hearing Order OH-4-2011
to the other, that would certainly be problematic to some of those other
dimensions of our objectives.
10300. MR. VULCANO: In so much as they wouldn’t want to wait so long
or that because you made a commitment to one group then they may feel that they
can have that commitment when you move along; is that it?
10301. MR. TOM FIDDLER: Well, literally, what we would be doing is
compelling the contractor to change out a proportion of his work force as he went
down the line.
10302. And, alternatively, and albeit we’ve got some skips here that are going
to do that in the one leap frog scenario, it’s not effecting all 12 spreads where they
have to change out the workforce because of the geographic region that they’re
moving into.
10303. MR. VULCANO: Okay, thank you.
10304. I just want to check where I am on my questioning.
--- (A short pause/Courte pause)
10305. MR. VULCANO: You’d mentioned the dates changed, will the
Enbridge plan to draw on LNG pipeline personnel?
10306. Does it hope that the lines will be completed so you’ll have that
expertise to make use of?
10307. MR. TOM FIDDLER: Current forecasts for some of the projects and
a number of them aren’t underway yet, so we can only take into consideration in
our detailed execution planning what we know is in the public domain or, you
know, promotional material and the like.
10308. There is opportunity, as I mentioned earlier, to benefit from other
projects not only of the industry but our own in Western Canada over the next few
years leading up to this construction.
10309. I think that relates to your question.
10310. MR. VULCANO: Okay, what proportion of females are expected to
Enbridge Northern Gateway Panel 2
Examination by Mr. Vulcano
Transcript Hearing Order OH-4-2011
be employed?
10311. You make mention that, you know, there’s opportunities for them.
10312. MR. TOM FIDDLER: Absolutely.
10313. I’m not aware of any percentage or any targets of that nature. We
work with the pipeline contractors and them with their -- if they do, in fact, have
represented labour or organized labour units such as the pipeline contractor
unions, there’s four of those.
10314. Christian Labour Association of Canada in each province have their
own association and organized labour objectives.
10315. At this stage we don’t interfere with their objectives or their methods
of recruitment and attraction. I know that -- I know, specifically, the pipeline
unions have an effort underway to attract Aboriginal and female gender workers
to the workforce.
10316. Other than that, I can't comment.
10317. MR. VULCANO: So you're leaving it up to the contractors?
10318. MR. TOM FIDDLER: In those regards, yes.
10319. MR. VULCANO: Are you aware that female equipment operators
are less hard on equipment?
10320. MR. TOM FIDDLER: I've heard that, I don’t know that that’s not
anything more than anecdotal but ---
10321. MR. VULCANO: Well, it would seem to me that that’s worth
pursuing; if you think it's only anecdotal, that you can talk to the companies that
---
10322. MR. TOM FIDDLER: Yeah.
10323. MR. VULCANO: --- hire them.
10324. I'm just thinking in terms of you want to minimize impacts and you
Enbridge Northern Gateway Panel 2
Examination by Mr. Vulcano
Transcript Hearing Order OH-4-2011
want to do a good job that maybe one of your strategies could be more female
operators. And I'm wondering if you've got anything in your plans that are sort of
showing there's some action behind your notion? You say: Yeah, we want to,
you know, benefit females.
10325. For instance, there's a group in Grande Prairie that specializes in
assisting women getting in the workforce and, you know, have you done anything
to support them?
10326. MR. TOM FIDDLER: I'm not aware of any initiatives with that
specific focus by Enbridge.
10327. As I mentioned, I know the contractors unions have that focus in terms
of recruitment into the trades.
10328. And I've got to comment that our objective is to define with -- and the
unions do it themselves -- in terms of defining journeymen and apprentices and
provide opportunities to all sectors of the workforce and are trying to grow the
industry, in particular, on the pipeline side as we speak; they're doing extensive
work on recruitment.
10329. And on the Northern Gateway team, we've got some folks that are
working on training and recruitment with the communities along the pipeline
corridor as well and I can't speak on their behalf, they'll be in another forum later
on; I believe in Prince Rupert but I'm not sure of the setting for them.
10330. MR. VULCANO: My line of questioning on the two aspects of
female equipment operators and having fewer contractors is just to go with your --
I'll use the term “buzz phrase” that “you're trying to minimize impacts”.
10331. And I'm wondering if that’s just not a word that you're using because
it's a nice word to include?
10332. MR. TOM FIDDLER: You'd have to give me some context that
you're referring to the buzz word “minimize impacts.”
10333. We talk about impacts in various ways. There's environmental and
other risk mitigation impacts. There's impacts if we're talking about
accommodations and the impacts on an adjacent community and their
infrastructure and their services.
Enbridge Northern Gateway Panel 2
Examination by Mr. Vulcano
Transcript Hearing Order OH-4-2011
10334. So I'm just missing a context and ---
10335. MR. VULCANO: It was, in my mind, more on the communities --
impact on the communities that you don’t have a lot going on at the same time.
10336. MR. TOM FIDDLER: Could you repeat the question again, please,
or was it a statement?
10337. MR. VULCANO: It's just minimize -- you were asking the context.
10338. MR. TOM FIDDLER: Yes.
10339. MR. VULCANO: It was to minimize the impact on communities is
the thrust of my query.
10340. MR. TOM FIDDLER: Well, in minimizing -- in the case that you
might be referring to it suggests a negative.
10341. Many of the communities along the corridor are looking for
opportunity so they're looking at it positive, obviously.
10342. And we've had discussions with various communities about additional
industrial travel on the roadways, communications that we have to evolve with
first responders, whether it be the -- those of a medical nature or those of -- I
guess other first responder nature.
10343. But, ultimately, it's subjective whether, you know, you put a spin on it
whether it's negative or positive. We hope to work with the communities and
stakeholders -- and key stakeholders to minimize any -- and mitigate any negative
impacts and have positive experiences and impacts.
10344. MR. VULCANO: Well, I would think the benefits are going to be
there whether it's -- I'll use a six-year or a two-year construction -- it's just a
matter of when it arrives to the community.
10345. But the impacts, because there's so much going on at once, are going
to be more cumulative and I'm suggesting you could minimize those impacts but,
as you already mentioned, you're weighing it against the other factors by having
just one contractor.
Enbridge Northern Gateway Panel 2
Examination by Mr. Vulcano
Transcript Hearing Order OH-4-2011
10346. MR. TOM FIDDLER: That’s your assertion, yes.
10347. MR. VULCANO: Well, I think it's supported by what you've said
near the beginning, that there's, you know, the crews get better, they're more
efficient, there's less impact when they're moving from one spread to the other.
I'm just trying to take that logically then if you did that with all 12 spreads.
10348. I'm not denying that there's other factors in consideration, I’m just
going there and trying to answer your question when I'm talking about by having
---
10349. MR. TOM FIDDLER: Yeah.
10350. MR. VULCANO: --- less impacts.
10351. MR. TOM FIDDLER: Okay.
10352. MR. VULCANO: And I will have more questions under the
socioeconomic component on that; I mean we're bordering on that.
10353. So if I may, I'll thank everybody for allowing me to ask my questions.
10354. THE CHAIRPERSON: Thank you very much, Mr. Vulcano.
10355. Dr. Wier is the next person who's going to pose questions of this
witness panel and I understand she's joining us remotely so we'll just get that
infrastructure in place.
10356. DR. WIER: Hello?
10357. THE CHAIRPERSON: Hello, Dr. Wier, this is Sheila Leggett.
10358. DR. WIER: Hello? I can barely hear you, hello?
10359. THE CHAIRPERSON: Hello, Dr. Wier, this is Sheila Leggett.
10360. Can you hear me?
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
10361. DR. WIER: Yeah, that’s better.
10362. THE CHAIRPERSON: Oh great.
10363. DR. WIER: Thank you very much.
10364. Am I heard properly as well?
10365. THE CHAIRPERSON: Yes, yeah, we're able to hear you were
clearly in the hearing room, thank you.
10366. DR. WIER: Very good.
10367. First, I want to thank the Panel for allowing me to participate long
distance, it's -- I'm very grateful for that. I apologize for registering so late.
10368. Hello?
10369. THE CHAIRPERSON: Yes, you're still with us, yup.
10370. DR. WIER: Okay.
10371. I apologize for registering so late with this Panel because we had a
glitch in the email communication with Mr. Neufeld and I learned yesterday that I
would be on this Panel so …
10372. I want also to say that I was not able to listen to the hearing ---
10373. THE CHAIRPERSON: Sorry, Dr. Wier, we just need to stop you for
a moment, you're fading on us.
10374. We'll just have to get the technology rolling so that we're able to hear
you clearly.
10375. You didn’t switch to a speakerphone or something like that?
10376. DR. WIER: No, I'm ---
10377. THE CHAIRPERSON: Oh, you're back loud and clear now. So ---
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
10378. DR. WIER: I'm -- I'm -- okay, I put it ---
10379. THE CHAIRPERSON: Yes, so you had said that you were grateful
to be participating remotely and we're glad that the technology appears to be able
to work so that we're able to accommodate that.
10380. DR. WIER: Okay.
10381. THE CHAIRPERSON: And maybe you could carry on from there,
please?
10382. DR. WIER: Yeah, and I -- I was delayed for my registration from a
glitch in communication with Mr. Neufeld.
10383. In any case, I was not able to listen -- hello?
10384. THE CHAIRPERSON: Yes.
10385. DR. WIER: Hello?
10386. THE CHAIRPERSON: We're still hearing you.
10387. DR. WIER: I have an echo.
10388. So I was not able to listen to the hearing yesterday and the transcript is
not available. So if I repeat a question that was asked yesterday, I’m sure you will
know how to mention it to me.
10389. THE CHAIRPERSON: Thank you, Dr. Wier.
10390. Again, you're fading so we're -- we heard what you said for that last
sentence but I wouldn’t want you to proceed further. Let's try you -- let's try
again and see, Dr. Wier, if you can hear?
--- EXAMINATION BY/INTERROGATOIRE PAR DR. WIER:
10391. DR. WIER: Okay.
10392. The gist of my questions are about the Semi-Quantitative Risk
Assessment and if Louise could pull the B75-2, page 18, and you'll have to let me
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
know when it's on the screen, please.
10393. THE CHAIRPERSON: Dr. Wier, we again hear you -- are you
staying consistently the same place ---
10394. DR. WIER: Yeah.
10395. THE CHAIRPERSON: --- with your telephone?
10396. There, you're back now.
10397. DR. WIER: Yeah.
10398. THE CHAIRPERSON: Yeah.
10399. DR. WIER: I'm going to try my -- another phone, so let's try this.
10400. Was this better?
10401. THE CHAIRPERSON: Can you speak a little more, please?
10402. DR. WIER: Is this better?
10403. THE CHAIRPERSON: No, it's not, I'm sorry to say.
10404. Can we go back to the other phone?
10405. DR. WIER: We're back on the other phone.
10406. THE CHAIRPERSON: That’s much clearer, thank you, Dr. Wier.
10407. DR. WIER: I wonder if I should position myself maybe differently.
10408. How is this now?
10409. THE CHAIRPERSON: This is perfect the way you are right now.
10410. DR. WIER: Okay.
10411. So, okay, my first question is regarding the Semi-Quantitative Risk
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
Assessment and if Louise could put B75-2, page 18?
10412. Ad please let me know when it’s on the screen.
10413. THE CHAIRPERSON: It’s on the screen now, Dr. Wier.
10414. DR. WIER: Okay, so regarding the analog ILI, the following factors
at the end under “Summary of Methods” were examined: water content ---
10415. THE CHAIRPERSON: I’m sorry, Dr. Wier, we’re losing you again.
10416. It’s just that you fade. We’re able to still hear your voice but it’s not
nearly as clear as other times when you’re speaking.
10417. DR. WIER: I don’t know how to solve this. I -- nothing is ---
10418. THE CHAIRPERSON: Nothing is changing; is it?
10419. DR. WIER: No.
10420. THE CHAIRPERSON: We can hear you again.
10421. So let’s try again and I know that our sound technician in the back will
be working on a full-time basis here trying to make sure that we can get the
volume consistent so that we can have this conversation without anybody not
being able to hear the full conversation.
10422. So you -- we’re on page 18 and you were speaking with reference to
the ILI data?
10423. DR. WIER: Yes, looking at the factors that were examined and
maybe I will not read them but they do not include the nature of the fuel
transported and I want to ask the question: Why was the nature of the fuel
transported not mentioned?
10424. MR. JAMES MIHELL: I believe we had an IR on that, Dr. Wier.
10425. In fact, I believe it was in response to your IR number 8, B97-2,
Adobe page 19.
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
10426. DR. WIER: Of course, I don’t have the ability to pull it but ---
10427. MR. JAMES MIHELL: I understand.
10428. We’ll try to perhaps convey what we’re seeing on the screen here
because that must be ---
10429. DR. WIER: Okay.
10430. MR. JAMES MIHELL: --- you don’t have the benefit that we have
here in this room.
10431. DR. WIER: Can you repeat the -- I’m pretty good, actually, B98?
10432. What is it?
10433. MR. JAMES MIHELL: Hang on, it’s B97-2 and we can hang on
while you get that up.
10434. DR. WIER: Yep, I have it.
10435. MR. JAMES MIHELL: Okay, and if you go to Adobe page 19.
10436. DR. WIER: Okay.
10437. MR. JAMES MIHELL: Just to refresh your memory, you had asked
a question about the content of or the product composition ---
10438. DR. WIER: Yeah.
10439. MR. JAMES MIHELL: --- that was being transported through the
what we’re calling the “analog pipeline”, the 36-inch line 4.
10440. And so the table that’s provided there on, I guess it’s Adobe page 19,
provides a product stream breakdown for that pipeline.
10441. DR. WIER: I see that. My apologies, so this was answered.
10442. Are the others aware of the uncertainties about the safety of
transporting dilbit as I submitted in my first evidence -- written evidence, B217-
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
18-1 -- which is the US Pipeline Safety Regulatory Certainty and Job Creation
Act amendment of last December?
10443. THE CHAIRPERSON: Dr. Wier, it’s Sheila again. I’m just going
to ask you to slow down a little bit when you’re speaking so that we can follow
you.
10444. DR. WIER: Thanks. Sorry.
10445. Are the -- (sound problems) -- in the amendment of the US Pipeline
Safety Regulatory Certainty and Job Creation Act of 2011 with this amendment
that requests a review of the safety of transportation of dilbit?
10446. MR. JAMES MIHELL: Dr. Wier, I think you’re referring to a
document and, unfortunately, it’s a little bit garbled but is this an aid to cross that
we would have in hand that we could refer to just so that we could be really clear
as to which document you’re referring to?
10447. DR. WIER: No, this was my written evidence B17-18-1.
10448. THE CHAIRPERSON: Ms. Niro, were you able to hear that?
--- (A short pause/Courte pause)
10449. THE CHAIRPERSON: So, Dr. Wier, we have your written evidence
on the screen and perhaps from there you could -- now that we’ve got this in front
of us, you could pose your question that you wanted to ask to the witness panel?
10450. DR. WIER: So the question is: Are the others aware -- I have an ech
-- are the others aware of the uncertainty regarding the safety of the transportation
of dilbit?
10451. THE CHAIRPERSON: Dr. Wier, we lost you again.
10452. Do you have the web broadcast playing in the background by any
possibility?
10453. DR. WIER: No.
10454. THE CHAIRPERSON: You’re just on the phone; are you?
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
10455. DR. WIER: Yeah, I’m just, okay ---
10456. THE CHAIRPERSON: Well, we thank you for your patience as
we’re trying to work through this.
10457. I’m just wondering if it would be a good idea if you tried dialing back
in if that might be of help on the technical side. Just give us one minute, Dr.
Wier.
--- (A short pause/Courte pause)
10458. MR. JAMES MIHELL: Madam Chair, the other thing that might be
helpful is if she could reference the page number that she’s referencing, we can all
go to that page number and read what she’s referring to and, that way, if there’s a
communication breakdown, we can still get the gist of what she’s getting at.
10459. DR. WIER: It’s one page.
10460. THE CHAIRPERSON: I was going to say the written evidence is
one page.
10461. So okay, Dr. Wier, your voice is coming in clearly again. Let’s give it
another try. I know that, like I say, our sound technician is working diligently in
the back of the room.
10462. So I’m sorry to have to ask you to do this again but we’ve got your
written evidence on the screen. Would you please repeat your question and take
your time because it helps us be able to understand you when you speak more
slowly?
10463. DR. WIER: Thank you.
10464. Are the others aware of the uncertainty regarding the safety of the
transportation of dilbit reflected in the amendment in the Act, last December?
10465. MR. JAMES MIHELL: Yes, we -- we are looking at the evidence
now and we have read this particular paragraph making reference to a proposed
study that the Secretary of Transportation is expected to undertake.
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
10466. DR. WIER: So what -- why has dilbit then not -- the nature of this
fuel not included in the risk assessment then?
--- (A short pause/Courte pause)
10467. MR. JAMES MIHELL: I’m sorry for the delay. I’m just looking for
a document here; so bear with me.
--- (A short pause/Courte pause)
10468. MR. JAMES MIHELL: So I understand your question to be: Are
we aware of the study that is referenced in this document and the need to address
dilbit corrosivity?
10469. There have been a number of records back and forth -- a number of
documents back and forth on the record pertaining to dilbit corrosivity and, you
know, I guess perhaps the most comprehensive discussion on that was provided in
Haisla IR number 2, B45-8, Adobe page 28.
10470. And while that’s being called up, I can also just give you our
experience with regard to dilbit corrosivity.
10471. So what we did is we basically found a pipeline that is operating with
the same type of products as is proposed for the Northern Gateway pipeline, in the
same hydraulic regime, the same sort of flow rates, same turbulent flow and had
extensive operating experience with that pipeline.
10472. And we referred to that as our “analog pipeline” and it’s 36-inch Line
4. And there’s extensive amount of inline inspection data on that pipeline that we
reviewed and we characterize that review as representing 10,000 kilometre years'
worth of ILI information. And by that term, 10,000 kilometre years, what I mean
is that basically there’s a -- if there was 1,000 kilometres' worth of ILI data, it
would have been 10 years at the time that the ILI data was taken.
10473. So lots of -- ample time for corrosion to initiate and manifest itself and
show itself on in-line inspection logs and so we would expect to see evidence of --
sorry, evidence of internal corrosion had that pipeline been susceptible to active
internal corrosion. And in fact, we didn’t see evidence of internal corrosion.
10474. And when I first went through the in-line inspection data on this
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
analog data set, I was a little bit flummoxed because, ultimately, I was tasked with
defining a finite failure likelihood for the Northern Gateway pipeline. And I
remember saying to one of the corrosion engineers at Enbridge, "You know,
you’re not making this easy for me to come up with a finite number".
10475. And in order to come up with a finite number, I need to be able to see
any evidence, some sort of evidence that there has been active internal corrosion
going on on this analog pipeline. And in fact, I’m seeing nothing. And he
pointed out to me that, well, perhaps I should just call it as I see it.
10476. So nevertheless, we didn’t stop there. We did some modeling to try to
ascertain, you know, why that would be the case. And the modeling suggested
that the -- what little water might be entrained in the product stream and it’s
characterized in terms of a commodity called BS&W, Basic Sediment and Water,
which is no more than 0.5 percent would be fully entrained in a fine dispersion
and that the surfaces of the pipeline would be oil wet -- what they call oil wet.
10477. And basically, oil wet pipelines don’t corrode. If you put oil on
pipelines or any steel and keep the water away from the surface of the pipe, it
won’t corrode.
10478. So we also, in addition to that, looked around for other people's
experience and we found some reference to other people’s experience. And I’m
going to cite from the SQRA document B75-2, Adobe page 120.
10479. And specifically -- I’ll wait for that to come up on our end. And
presumably, Dr. Wier, you’ll have B75-2 open at your end. But if you could to
Adobe page 120, we could all be on the same page.
10480. And there’s a section there called 2.2.1.1. It has a starting paragraph
followed by a second paragraph and a couple of bullets embedded within that
second paragraph, and I can perhaps just read from that.
10481. DR. WIER: I don’t think -- 125?
10482. MR. JAMES MIHELL: I’m sorry; it’s Adobe page 120.
10483. DR. WIER: Twenty (20), oh.
10484. MR. JAMES MIHELL: Let us know when you’re there.
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
--- (A short pause/Courte pause)
10485. DR. WIER: Yeah, I am on that.
10486. MR. JAMES MIHELL: Okay. And so what we’re just saying there
at the end of the first paragraph is that:
“Therefore, because no water accumulation is expected, no
[…] internal corrosion is expected on this pipeline.”
10487. It goes on to say that:
“This conclusion is consistent with an API publication [called]
'Pipeline Transportation of Diluted Bitumen from the
Canadian Oil Sands' which states among its findings: That
although oil sands diluted bitumen has been transported
through Canadian and U.S pipelines for more than a decade,
there have been no instances of crude oil releases caused by
internal corrosion from pipelines carrying Canadian diluted
bitumen.”
10488. And the second point there says that:
“Corrosivity of diluted bitumen is largely similar to crude oil,
which is considered to be low.”
10489. The paragraph below that says that:
"The above findings were also corroborated in a presentation
given by Cheryl Trench to the 6th
Annual Pipeline Safety
Conference in November, 2011. The issue of crude oil sourced
from Canadian oil sands was included in that presentation,
and the results of an investigation into the internal corrosion
history of pipelines carrying that product were provided. The
study investigated PHMSA accident data for pipelines that
have interconnections to Canadian crude sources. It also
investigated data from U.S Energy Information Administration
Form 814; shipment-by-shipment crude imports to determine
which refineries were sourcing Canadian oilsands crude.
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
Finally, it investigated pipeline industry information to
determine all interconnections, including storage hubs to
determine which part of the pipeline infrastructure could have
transported Canadian oilsands crude. The results of this
analysis established that there has not been one failure in any
of this infrastructure that is attributed to internal corrosion
resulting from the transportation of Canadian oilsands crude.”
10490. DR. WIER: If I may say, one wonders why the U.S are spending
money doing a review and even amending their Act. So I want you to keep in
mind that it’s not known, that you are implying and you are quoting resources that
the reality is there is an uncertainty factor. And I want to keep that in mind.
10491. Okay. You mentioned this NPS 36, line 4 and you say it’s an analog,
but there’s no -- I couldn’t find any information. What is this NPS 36, line 4?
Which terrain, which length? How old is it? Since when were the ILI data
obtained? What is the presentation of the line inspected? So could you -- or
should I go one by one?
10492. MR. JAMES MIHELL: I see where you’re headed with that. And
again, there was an information request to that effect and it was answered as
response to JRP No. 11. The document number on that was B101-2, and I’ll wait
for it to be called up. And we need to go to Adobe page 33.
10493. While we’re doing that, I would just like to respond to your assertion
that not everything is known, that there is some uncertainty. And I have to say
that I don’t disagree with you on that. You know, this is not something that we
should pretend is a foregone conclusion.
10494. All we’re saying is that when we look to our analog ILI information
and the experience of others, it doesn’t appear that dilbit pipelines are unusually
exposed to internal corrosion. However, that doesn’t mean that we can be
satisfied to the extent that we can say we don’t need to do anything about
worrying about internal corrosion. We do.
10495. We need to treat it as a very real concern and, to that extent, I think -- I
have to be careful. I always -- I always am tempted to wander outside of the
scope of this panel, which is really design.
10496. But there’s another panel on operations, and I think they would be
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
very happy to go into a lot of discussion about the things that they will be doing
on this pipeline in terms of inspection and maintenance to ensure that internal
corrosion doesn’t manifest itself on this pipeline to the point where it presents a
threat at any time in the future.
10497. I think I need to stop there with respect to operations issues because
it’s outside the scope of this panel. But I just wanted to point out that I agree with
you, Dr. Wier, that there is uncertainty, always. There’s -- we can be assured that
we have to be vigilant against this threat all the time, so ---
10498. DR. WIER: Thank you.
10499. MR. JAMES MIHELL: At this point, do you have -- let’s see ---
10500. DR. WIER: I think -- what number -- what was the page number you
were referring to on B101?
10501. MR. JAMES MIHELL: Sure. It was Adobe page 33, and there’s a
Table 2 there.
10502. DR. WIER: Yeah.
10503. MR. JAMES MIHELL: And I won’t read out from that table
because there’s a lot of information, but I’ll give you time to peruse that table and
maybe ask any specific questions you might have.
10504. DR. WIER: Well, those were not the questions I had. It was more
like what is the length of this pipeline and how old is it, stuff like that. Ninety-
nine ('99), so -- okay.
10505. And the inspection, what length were -- of the pipeline was inspected?
10506. MR. JAMES MIHELL: Is there -- I don’t have this table open on
my computer, but is there a row in here that talks about length? If not, I'll have to
confer with some of my colleagues to get you that answer. So I apologize for the
delay.
10507. DR. WIER: No, I don’t find the length. And I wonder if stating the
percentage of it that was inspected because 10,000 kilometre years doesn’t really
speak to me.
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
--- (A short pause/Courte pause)
10508. DR. WIER: Did I lose the connection?
10509. THE CHAIRPERSON: No, you're right here. I think that the
witness panel was just conferring, so we'll just let them seek to get the -- I think
the question is the length of the pipeline.
10510. DR. WIER: The question is the length of the pipeline and the lengths
of the inspected -- the inspected lengths of it. Was it 10 percent of it was
inspected, or how much?
10511. MR. JAMES MIHELL: I think we've got a preliminary answer to
that, and I apologize for the delay.
10512. The number I'll give you right now is going to be subject to check. It's
on the order of about 1,000 kilometres. Oh, and the amount -- all of that 1,000
kilometres was inspected.
10513. DR. WIER: Oh, okay, 100 percent. So it's been inspected for 10
years.
10514. MR. JAMES MIHELL: Well, it's been inspected twice, actually.
And -- so it's the most recent data set that is the most instructive, I think, because
-- again, this is going to be subject to check because I'm going on my memory
here, but I believe it was inspected one time in 19 -- sorry, 2007. And I think that
the second time it was inspected was in 2010.
10515. I'm just looking over my shoulder just to see if anybody is waving at
me that I might have those numbers as wrong. But as I say, that’s all subject to
check.
10516. And we really like to focus on the 2010 data because, of course, the
pipeline is older in 2010 and it, therefore, has been given more time to corrode.
So that’s really where we focused, is the 2010 data.
10517. DR. WIER: As a side question -- I’m a little bit surprised. So it was
built in 1999 and it took eight years for the first inspection?
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
10518. MR. JAMES MIHELL: Yes, that’s what it sounds like.
10519. DR. WIER: Is that -- is that common practice?
10520. MR. JAMES MIHELL: Well, back in the early part of the last
decade -- so the -- like the 2000s, I think that was probably typical of practice
then. Since that time, I think inspection intervals have decreased; the periods
between inspections have decreased.
10521. Again, I have to be careful here because I'm getting into the realm of
operations, but I'm just going to try to be responsive to your question based on my
general observations. I think the inspection periods have decreased typically
corresponding with the availability and reliability and the performance
characteristics of these new in-line inspection tools, which have now become very
adept at identifying very small features. And as such, they're very effective at
finding corrosion features. And so it's become quite common practice now to
inspect at a little bit more regular intervals.
10522. And I think that you can probably ask the operations team about
inspection intervals if you like, but I'm not qualified to address that.
10523. DR. WIER: Thank you.
10524. You write -- or the -- in the report, I read that the pipeline will operate
in fully turbulent mode and with the BSW that you mention. What -- the question
is, what is the percentage of the time the pipeline will not operate in fully
turbulent mode?
10525. And we heard about in previous hearings -- in the previous hearing
when there will be -- there will be time when this will not happen. Any idea?
10526. MR. RAY DOERING: The pipeline is expected to operate in
turbulent flow virtually always. There could be short periods of time where the
pipeline would be shut down for maintenance and inspection requirements, but
while it's operating it's expected to be operating in fully turbulent flow.
10527. I -- and Dr. Wier, we did just check. We have made a commitment for
Northern Gateway -- and it has been described in the previous IR responses; we'll
see if we can find that -- that the in-line inspection -- the suite of in-line inspection
tools will be run for Northern Gateway within the first two years of going into
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
operations.
10528. So that gets to Mr. Mihell's comments that the frequency of in-line
inspections such as the one we would do for internal corrosion not only have been
increased, but the base line is established very early on in the project life.
10529. DR. WIER: Thank you.
10530. My next question refers to B97, page 9.
10531. THE CHAIRPERSON: And just ---
10532. DR. WIER: It's a simple -- simple thing. Is it on the screen?
10533. THE CHAIRPERSON: It is. I was just going to ask -- it's Sheila
again, Dr. Wier. I was just going to ask the witness panel if you would please
identify yourself just when you're beginning your answer to your question so that
Dr. Wier knows who she's talking with.
10534. Thank you.
10535. DR. WIER: Thank you.
10536. Okay, so -- can I ask my question?
10537. THE CHAIRPERSON: Yes, Dr. Wier, please go ahead.
10538. DR. WIER: Are any of -- okay, the response b to the -- the question
was:
“How many of those failures occurred in mountainous terrains
similar to the ones in [...] BC?”
10539. And the answer was “They haven’t been” ---
“[...] there have been no oil pipeline failures in BC in
mountainous terrain.”
10540. And I wasn’t clear what he'd meant. Are any of those pipeline in
mountainous terrains?
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
10541. THE CHAIRPERSON: Again, Dr. Wier, it's Sheila Leggett here and
I think the panel's just thinking. So when you hear the silences, that’s all that’s
going on.
--- (A short pause/Courte pause)
10542. MR. RAY DOERING: Well, one of the -- certainly one of the
pipelines that would have been used here to compile this data -- sorry, this is Ray
Doering speaking, by the way, Dr. Wier.
10543. DR. WIER: Thank you.
10544. MR. RAY DOERING: One of the pipelines that would have been
considered for the B.C. data would have been the Trans Mountain Pipeline, which
certainly does cross mountainous terrain within British Columbia. And I think
what this -- and other pipelines involved in this would have been other National
Energy Board regulated pipelines in B.C. and I’m not sure if that’s Spectra
Pipelines or Pembina Pipelines in this case. We'd have to go look at the source.
10545. But in the case of Trans Mountain Pipeline, yes, it does cross
mountainous terrain, but I think the indication is that there were no failures within
that mountainous terrain ---
10546. DR. WIER: M'hm.
10547. MR. RAY DOERING: --- on Trans Mountain Pipeline.
10548. DR. WIER: Yeah, that’s the -- that was the question. Thank you.
10549. My next question refers to B97, page 10-11 ---
10550. THE CHAIRPERSON: We have page 10 on the screen now, Dr.
Wier.
10551. DR. WIER: Thank you.
10552. So to the question -- I ask the question:
“How old is the oldest 'modern' pipeline with shows the 80%
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
reduction of corrosion risks?”
10553. The answer is:
“The 80% used in the QRA is a qualitative assessment based
on expert opinion and is not based on historical data.”
10554. So I'm curious, you know, what is the qualitative data that
substantiates the 80 percent reduction of corrosion risk expert opinion if it's not
historical?
10555. THE CHAIRPERSON: And Dr. Wier, it's Sheila Leggett again.
Just to continue the blow-by-blow, they're just -- the Panel just looks like they’re
seeking additional information.
10556. DR. WIER: Thank you.
10557. MR. JAMES MIHELL: So I’m sorry, I had a brief conference back
there to figure out this question.
10558. My name is Jim Mihell by the way, Dr. Wier.
10559. DR. WIER: Hi.
10560. MR. JAMES MIHELL: And I wonder if we could scroll up a little
bit so I could re-read this question, a little -- I’d like to see some of the -- and
perhaps the preamble to E, if I could see it?
10561. DR. WIER: I don’t have it on the ---
10562. MR. JAMES MIHELL: I’m okay. I can see it here, thanks.
10563. So this -- yeah, this question, Dr. Wier, refers to a preliminary very
high-level risk assessment that was performed and was subsequently replaced by
the SQRA that you referenced earlier that is the most current and representative
risk assessment. It’s the one that we are using at this point, that risk assessment
that is shown is B75-2.
10564. So I think the previous risk assessment being that it’s been supplanted
by this later risk assessment I think we’d prefer to really focus on the most current
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
and representative risk assessment if we could.
10565. DR. WIER: Okay.
10566. Can we go back to the 80-percent reduction?
10567. Is the 80 percent reduction of corrosion risk the opinion of experts
working for Enbridge or is it a rate that’s generally agreed in the field?
--- (A short pause/Courte pause)
10568. MR. JAMES MIHELL: So I am led to believe that this -- I
apologize, this report -- this earlier report isn’t my work and so it’s difficult for
me to speak to it.
10569. But it was the expert opinion of Dr. Bercha, I believe, and he had some
means of evaluating that 80 percent.
10570. Again, that earlier risk assessment has since been replaced and I guess
we are now using what we feel is a better representation, a better basis for the
Design-Based Risk Assessment and that’s the risk assessment that’s in B75-2.
10571. DR. WIER: Okay. Thank you.
10572. Now, my next questions, I’m going to pull quite a few references, B97,
page 12.
--- (A short pause/Courte pause)
10573. THE CHAIRPERSON: That’s on the screen now, Dr.Wier.
10574. DR. WIER: It mentions that, regarding the NTSB Accident Report, it
mentions that:
“While operational factors contributed to the failure to detect
this incident promptly, the probable cause in the NTSB view
was due to physical failure mechanisms and not an operational
one.”
10575. And I’ll stop there.
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
10576. Now, I would like to pull evidence D4-5, no, D4.5.5 ---
10577. THE CHAIRPERSON: Excuse me ---
10578. DR. WIER: --- which is the interview of Mr. Zupan -- I don’t know
how to pronounce it -- regarding the Marshall accident, the Kalamazoo spill, on
page 17, and -- if you let me know when it’s on the screen?
10579. THE CHAIRPERSON: It’s on the screen now, Dr. Wier.
10580. DR. WIER: Okay, so Mr. Zupan mentioned that it’s clear that we --
that in hindsight the person should have had additional training. It’s clear to us
what we could have done more to train and support those people. Now, on page
19, on the same document of Mr. Zupan.
--- (A short pause/Courte pause)
10581. THE CHAIRPERSON: We have page 19 on the screen.
10582. DR. WIER: On line 25 -- on line 24:
“...our loss rate was higher than that, and so we were [on line
25 we were] continually in a...”
10583. Replacement and retraining mode.
10584. On page 42 ---
10585. THE CHAIRPERSON: That’s now on the screen too, Dr. Wier.
10586. DR. WIER: Mr. Zupan mentioned there’s a long journey, on line 11:
“…we've looked at is this is still a journey…”
10587. On line 16:
“We will not be able to get there in a short period of time
because of the whole training piece.”
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
10588. Now, so this is it for Mr. Zupan.
10589. For the conclusion of the NTSB investigation on B92-3, page 133 to
135.
10590. THE CHAIRPERSON: We have page 133 on the screen now.
10591. DR. WIER: Okay, so line:
“Conclusion 7: Enbridge Integrity Management Program was
inadequate.
11: The inefficacy performance of control centre.
Conclusion 12: Enbridge failed to train control centre staff in
team performance.
Number 13: Enbridge failed to ensure that all Control Staff
Centres had adequate knowledge.
Number 14: Enbridge management did not prohibit control
centre staff from using unapproved procedures”
10592. That’s very important.
“Number 17: Enbridge control centre staff had developed a
culture that accepted not adhering to procedures”
10593. Very important.
“18: Enbridge review of its public awareness program was
ineffective in identifying and correcting deficiencies”
10594. And:
“Conclusion 27: Enbridge’s failure to exercise effective
oversight of pipeline integrity and control centre operation,
implement an effective public awareness program and
implement an adequate post-accident response were
organizational failures that resulted in the accident and
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
increased its severity.”
10595. Okay, that’s pretty well-known and next reference would be Volume
86, October 10th ---
10596. MR. LANGEN: Madam Chair ---
10597. DR. WIER: Line 5921 ---
10598. THE CHAIRPERSON: Dr. Wier, counsel for Northern Gateway,
Mr. Langen, has something that he’d like to say at this point.
10599. DR. WIER: Okay.
10600. MR. LANGEN: Sorry to interrupt you, Dr. Wier.
10601. I appreciate Dr. Wier’s jumping us through a number of exhibits or
documents that are on the record that relate to the NTSB investigation of Line 6B,
it appears, and I was patiently waiting for a question and I appreciate that she may
want to go to other documents, but I think it would be helpful to know what her
question might be because I may suggest that this line of questioning go to
another panel.
10602. So if she could indulge us, with your indulgence, Madam Chair, we
might save some time here if she can just give us an idea where she might be
going given that she keeps referring to multiple documents.
10603. DR. WIER: If I may? Thank you.
10604. I’m exactly there. The -- what’s happening is the Semi-Quantitative
Risk Assessment revised concludes on, may I quote it, B75-2, page 24, that the
probability -- maybe I’ll wait for it to be on the screen?
10605. THE CHAIRPERSON: Dr. Wier, what page was it?
10606. DR. WIER: Page 24.
10607. THE CHAIRPERSON: Thank you. It’s on the screen now.
10608. DR. WIER: It says:
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
“Therefore, the probability of incurring full-bore failures
related to incorrect operations is considered negligible.”
10609. It’s not even looked at in assessment.
10610. DR. WIER: So my question is, is it correct to call lack of oversight,
lack of implementation, lack of training and support, lack of adhering to
procedures, operational failures? That’s my question.
10611. MR. JAMES MIHELL: Okay. It's Jim Mihell again, Dr. Wier.
There's a couple of things I'd like to point out.
10612. One was that the findings of the NTSB were that the initial release in
the Marshall incident was actually cracking underneath a polyethylene tape
coating system which gave rise to a corrosion -- or an environmental cracking
mechanism which, by the way, we don’t anticipate with high performance coating
systems these days any longer. But that being the case, I do acknowledge that
there were operational failures in recognizing the leak and reacting promptly to
the leak.
10613. I -- again, because I'm on the design panel here, can't go into the
outcomes of the Marshall incident and describe what sorts of changes have been
undertaken with respect to ensuring that a Marshall incident type of occurrence
with respect to identifying and isolating a leak on time doesn’t ever happen again.
That’s the purview of the Operations Panel and I will defer to them to talk to that.
I’m sure they’ll have lots of opportunity to speak to that.
10614. Secondly, with respect to the SQRA, perhaps I can take you to page
138 of the SQRA. And the SQRA document is B75-2.
10615. THE CHAIRPERSON: Dr. Wier, can you let us know when you're
there, please?
10616. DR. WIER: Yeah, I will. Okay. And which page?
10617. MR. JAMES MIHELL: Page 138.
10618. DR. WIER: Thank you. I am on it.
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
10619. MR. JAMES MIHELL: Okay. And so near the bottom we get into
incorrect operations and it talks about the approach that was used to derive failure
estimate -- failure frequency estimates on operations failures.
10620. And just over the page -- we're just starting into the start of incorrect
operations there, but just over the page it concludes that:
“This equates to a failure frequency of 5.607x10-5
failures/km.yr.”
10621. It is a finite failure frequency that was anticipated bearing in mind,
once again, that, technically speaking, the root cause of the actual release at
Marshall was environmentally assisted cracking and not technically an operations
related failure, acknowledging at the same time that operations failures
subsequent to the release led to an unacceptably long time to detect and respond
to that leak. That’s a separate matter.
10622. So we are, for the purposes of the SQRA, not discounting the
possibility of operations failures occurring. We looked at the PHMSA database
associated with other past operations failures to guide us in terms of the
magnitude of releases that are typical of operations failures and concluded that
these tend -- these types of failures tend not to be characterized as full bore
ruptures, but as releases of smaller magnitudes.
10623. And so for the purposes of, I guess, pairing up rupture frequency with
rupture consequences, the rupture risk associated with incorrect operations was
considered to be zero. However, there is not considered to be a zero risk
associated with incorrect operations. It's considered in the SQRA and was
evaluated as part of the SQRA and will be there to instruct the risk-based design.
10624. DR. WIER: Well, what's missing in your evaluation is the failure of
the -- it's not the crack. It's the failure of the integrity management system and the
whole corporate structure around it. So it -- it appears -- anyway, this is not the
place to argue, but I want for the record to mention that there is more than a crack
to a crack. It's what led to the crack and what's been ignored and all the warnings
and so on. I'm not going to be late on this.
10625. Okay, so next question is leak detection sensibility. And I was very
puzzled with last week statement, Volume 86, October 10, line 5783.
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
--- (A short pause/Courte pause)
10626. THE CHAIRPERSON: Dr. Wier, that’s now on the screen.
10627. DR. WIER: Thank you. So -- I can't pronounce -- Mr. Barry Callele
says that:
“The CPM has a minimum threshold detection [...] of 1.5 to 3
percent of nominal flow under steady state operating
conditions.”
10628. And on line 5786, I believe it's the same person who said:
“...at this point in time that’s the best estimate of future
performance given a 1 percent to 2 percent range of sensitivity
on the metres.”
10629. So I did not understand those two numbers. So it is correct to
understand that, with a sensitivity range of 1 to 2 percent for 1.5 to 3 percent
nominal flow, there will be cases that no leak can be detected?
10630. MR. BARRY CALLELE: Dr. Wier, it's Barry Callele, and it's okay
to say “Callele” as well. It's understood in my family both ways.
10631. What we were describing here, Dr. Wier, was a future predicted state
for Northern Gateway Pipeline given a meter frequency described previously as
having ultrasonic meters at every pump station and custody transfer meters at the
inlet and the outlet of the pipeline.
10632. So it's not a theoretical future performance, although that’s kind of the
wording. I wish we wouldn’t have used the word “theoretical” at the time. But
anyways, what it is, is it's a calculation of future predicted performance of a
computational pipeline model.
10633. Now, that last statement I redacted it or had errata on it. I think I
mentioned in it that it's the best estimate of future performance given a 1 percent
sensitivity of the meter. The variability occurs due to different volume balance
segment lengths in the pipeline.
10634. DR. WIER: So it's 1.5 to 3 percent plus or minus 1 percent?
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
10635. MR. BARRY CALLELE: No, it's 1.5 to 3 percent depending upon
which segment you're in in the pipeline.
10636. DR. WIER: So what's this latest 1 percent?
10637. MR. BARRY CALLELE: That’s just indicating -- sorry. That’s just
indicating, Dr. Wier, what we assume to be the accuracy of the meters that we use
to measure the flow rate on the pipeline.
10638. DR. WIER: Oh. yeah, okay. Okay, thank you. Thank you very
much.
10639. MR. BARRY CALLELE: You're welcome.
10640. DR. WIER: Next question regards quality assurance in Volume 87 on
line 7631.
--- (A short pause/Courte pause)
10641. THE CHAIRPERSON: Dr. Wier, that -- that’s up on the screen
now.
10642. DR. WIER: Okay. So line -- Mr. Leadem asks:
“[If the] quality assurance and inspection apply to the work
done by contractors as well?”
10643. And Mr. Fiddler on line 7633, “Absolutely” was the response.
10644. And this is, to me, in quite contrast with what took place in Wisconsin.
And if you want to look at D217-21, page 6, which is my written evidence.
10645. THE CHAIRPERSON: It's on the screen now.
10646. DR. WIER: Okay. So I mention that:
“Enbridge's more than 500 construction permits violations in
Wisconsin in 2007-2008 were settled by the Wisconsin
Department of Justice for a meagre $1.1 million.”
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
10647. That was significant, more than the pipeline ropes that Mr. Fiddler
mentioned in Volume 87, line 7683 and it wasn’t that debris was being left
uncovered. It was debris such as the pipe rope that I mentioned that wasn’t
necessarily being picked up on the same day.
10648. So Mr. Fiddler seemed to really downplay the seriousness of those
violations.
10649. In D217-9-4, page 1 …
--- (A short pause/Courte pause)
10650. THE CHAIRPERSON: That’s on the screen now, Dr. Wier.
10651. DR. WIER: The Wisconsin Wetland Associated describes the very,
very significant and repeated violations during construction:
“… 60 violations from July 30 to September the 9th …”
10652. That’s more than one a day related -- well, just about one a day:
“…related to erosion control, wetland restoration, land
clearing, trenching, dewater and lack of compliance with Best
Management Practices;
Over 19,000 gallons of oil were spilled in Clark County, WI on
January 2nd
, 2007 when a pipeline ruptured contaminating
farmers’ fields;
Over 150,000 gallons of crude oil spilled into a farm’s field
and seeped into the groundwater table in Rusk Country;
In May, 2008, the Wisconsin Department of Natural Resources
referred the case of Enbridge … repeated failure to comply
with its wetland and waterway to the Department of Justice.”
10653. So my question is: Given this awful record, what is the plan to
monitor and act on repeated violations during construction and operation?
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
10654. MR. LANGEN: Madam Chair, it’s Mr. ---
10655. DR. WIER: How are you going to assure us that you’re going to do
better than four years ago?
10656. THE CHAIRPERSON: Mr. Langen?
10657. MR. LANGEN: Dr. Wier, it’s Mr. Langen speaking, counsel for
Northern Gateway.
10658. The last question that she just provided I think was a fair question.
The prior question had a nested assertion in it and an argumentative one and I
would ask her to frame her question, the one that she just asked in the course of
my interrupting her. If she wants to reframe that question, I’m happy with it.
10659. The earlier one, we’re seeing a pattern of assertions and I understand
that Dr. Wier may feel strongly about this but I’d like the questions to be fair
questions to the witnesses without assertions in the more argumentative portions
to them.
10660. If I can ask for that I’d appreciate it. Thank you, Madam Chair.
10661. DR. WIER: So, if I may, as I understand from the material I quoted,
the quality assurance and inspection will apply absolutely to contractors, fine.
10662. The records show that, very recently, this hasn’t been the case. So,
how can we trust that, once again, very minor fines will not deter contractors to
repeat what they’ve done recently?
10663. MR. TOM FIDDLER: Ms. Wier, it’s Tom Fiddler here and I want to
back up, if I could briefly and you may not have caught up to all of the transcripts
subsequently because this line of questioning has come up again.
10664. And I made clear that, in the initial line of questioning, that there’s an
extent of limitation to my knowledge and Mr. Underhill on the Operations Panel
will speak to that. I believe. Mr. Leadem made note of that. And so I wasn’t
discounting or suggesting there weren’t other environmental violations, I just
don’t understand or have the details.
10665. Further to that, though, of the 500 permit violations, I did make note
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
and have some notes in front of me that advise that 115 were alleged to be non-
compliances in the end and, ultimately, all the wetlands were cleaned up to the
satisfaction to the Wisconsin DNR.
10666. That’s not to discount that there were some procedural and work
practice issues. And I -- in follow on questioning elaborated on our Construction
Management Environmental Protection Management Plan and Program inclusive
of a detailed orientation of not only the workforce, of the contractors but also
enhanced expectations and training and qualification of our inspection staff
including focused environmental inspectors.
10667. And, in that regard, we are committed to an objective -- not unlike our
leak goal -- of zero regulatory non-compliances and permit condition non-
compliances.
10668. DR. WIER: So how binding is the commitment that you just made on
the record?
10669. Because I understand that this was also a commitment that was also
made for the Lakehead.
10670. MR. TOM FIDDLER: And all I can do, personally, is reassure you
by our follow-up activities. We built two projects shortly after that, immediately
after that, in Wisconsin and Minnesota without a non-compliance of any
significance for certain and I can’t go beyond that.
10671. And we’ve built thousands of kilometres in Western Canada since
then, continually improving and working with our contractor community on
compliance and environmental risk mitigation.
10672. DR. WIER: Thank you.
10673. This leads very nicely to the next question--
10674. THE CHAIRPERSON: Dr. Wier, it’s Sheila Leggett here.
10675. DR. WIER: It’s my last question.
10676. THE CHAIRPERSON: I just wanted to check with you. We were
supposed to finish sitting at 12:30 and it’s now 10 to 1, what’s your estimate of
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
the remaining time that you need for the rest of your questions?
10677. DR. WIER: Probably 5 to 10 minutes, if possible?
10678. THE CHAIRPERSON: Let’s continue in that vain but we --
unfortunately, because of scheduling constraints, we will need to stop sitting at
1:00 o’clock and so, if we’re not finished by then, we’ll just pick up again with
you on Monday morning when we sit again.
10679. DR. WIER: Thank you.
10680. If Louise could pull aid to cross-examination which is a website which
is the letter that the National Energy Board posted yesterday or October the 11th
regarding Trans-Canada compliance with technical -- no -- what is it --
TransCanada non-compliance with technical standards.
10681. And it’s very sad. It’s -- this letter posted two days ago shows that a
large pipeline company, again, is not following procedures and regulations and it
has a strong echo with the Marshall accident with the enumeration of non-
compliance practices.
10682. And it’s very, very distressing to see that the regulator had not flagged
those non-compliances and that it takes a whistle-blower, at great costs I’m sure
to that person, to uncover them.
10683. So here we just heard Mr. Fiddler -- okay, so I don’t want to be
argumentative so here are the questions: How can Northern Gateway commit to
the use of a certified independent party for welding inspections and non-
destructive examination to forward results to NEB to inspections that meet the
requirements of the onshore pipeline regulations?
10684. Which was not done by the other company?
10685. So how can Northern Gateway commit?
10686. MR. TOM FIDDLER: Ms. Wier, it’s Tom Fiddler again.
10687. What I can describe to you is our process and, not to suggest anything
of a negative nature to our friends at TransCanada, but our practice is that we
independently hire and qualify all of our pipeline inspectors.
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
10688. That includes written tests that includes prerequisite -- not only
training but work experience and demonstration and verification of that work
experience. We do accommodate -- and I want to clarify this -- we do
accommodate opportunities for -- I’ll call them “apprentice inspectors” if you will
-- in the process but, certainly, under the oversight of individuals who have
significant experience.
10689. We’re very proud of -- and we’ve just evolved to a computer-based
training program with a complete Inspection Performance Management Program,
if you will, around pipeline inspectors so that if you envision and are familiar with
quality management practices, it’s a quality management circle around inspector
performance qualification as a prerequisite, so they’re pre-qualified. They’re
examined and tested relative to the Enbridge specifications and expectations, and
that’s both written as well as audits, and then we archive that information relative
to that individual inspector. And we also do a post-project assessment of their
performance.
10690. And there's other dimensions to an inspector's performance, as you
may understand, in any workplace and team environment. So we’ve got a very
robust -- and I know for a fact, having participated with API committees and the
CSA committee, that our Inspection Performance Management Program around
pipeline inspectors is world class.
10691. DR. WIER: So if failure to have done, which from the leak had --
okay. If failure to have done so is discovered and it -- what is Northern Gateway
prepared to offer as a clear and robust indication that it has outgrown its corporate
culture of deviance?
10692. MR. TOM FIDDLER: No, you’re crossing up an operational culture
with a construction culture. And not to again suggest one’s lesser than the other
---
10693. DR. WIER: Okay, so that will close my questioning.
10694. MR. TOM FIDDLER: What I could say, Ms. Wier, just to give you
some reassurance, within Enbridge as a whole, and it is a fairly recent evolution,
we do have a whistleblower system and hotline, if you will, that allows for
anonymous and independent accusations and investigations inclusive of internal
legal team and in an anonymous and very rigorous way.
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
10695. So we’ve got mechanisms that we make the workforce, including the
contractor community and our stakeholders of, in terms of advising of concern
with ethical conduct or performance of work conduct or the like, so ---
10696. DR. WIER: So are any member of the public who witnesses a
crossing of a creek or whatever outside the regulations able to phone that
whistleblower line?
10697. MR. TOM FIDDLER: Yes, they are.
10698. DR. WIER: Do you have to be employed by Enbridge?
10699. MR. TOM FIDDLER: No, you don’t.
10700. DR. WIER: And how long has this been in place?
10701. MR. TOM FIDDLER: I’d have to verify that. It is certainly
something that’s evolved in the last three or four years. It doesn’t go back that far
in terms of being one of the management systems and mechanisms in the
organization.
10702. DR. WIER: After the Lakehead problems -- well, thank you very
much. This closes just on time for a beautiful day.
10703. THE CHAIRPERSON: Thank you very much, Dr. Wier, for your
questions of this panel.
10704. So just as we’re wrapping up for the day, we’ll start on Monday
morning and call Alberta Lands Ltd., then Enoch, Ermineskin and Samson Cree
Nations, followed by Northwest Institute of Bioregional Research and then
counsel for the Secretariat as well as the Panel. That will be the order that we will
proceed in for this panel.
10705. So with that, we’ll call for any other preliminary matters that parties
want to raise at this point.
10706. MS. SHANNON: Sorry, I don’t want to delay, but we just have two
quick preliminary matters.
Enbridge Northern Gateway Panel 2
Examination by Dr. Wier
Transcript Hearing Order OH-4-2011
10707. The first is Northern Gateway is ready to file a response to
Undertaking No. 32.
10708. THE CHAIRPERSON: Ms. Niro, could we have an exhibit number
for that, please?
10709. THE REGULATORY OFFICER: That will be B-140.
--- EXHIBIT NO./PIÈCE No. B-140:
Enbridge Northern Gateway’s Response to Undertaking U-32
10710. MS. SHANNON: Thank you, Ms. Niro.
10711. Also, we were asked this morning to confirm the order of panels that
will be seated in Prince Rupert. And the order that is currently listed in our
responsibility document is correct, but I’ll just confirm that that will be the
Marine Environmental Socioeconomic Assessment Panel followed by the Marine
Preparedness and Emergency Response Panel, then the Kitimat River Valley
Panel, the Aboriginal Engagement and Public Consultation Panel and, finally, the
Shipping and Navigation Panel.
10712. THE CHAIRPERSON: Thank you, Ms. Shannon.
10713. And with that, we’ll close and thank everybody for your participation
and involvement this week and we will sit again on Monday morning at 9 o’clock.
Thank you.
--- Upon adjourning at 12:58 p.m./L’audience est ajournée à 12h58