Page 1: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

JOINT COMMITTEE MEETING

Department of Housing and Community Development

Revitalization Programs

April 6, 2006

Redevelopment Activities in Commercial Revitalization Districts and Areas

Page 2: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

1

Revitalization = ProsperityThe Department of Housing and Community Development (DHCD) Revitalization Programs:

• Provide connectivity between community, developers and regulatory agencies to channel private development investment into areas that achieve the highest and best economic returns

• Provide financial development incentives to encourage private sector investment into Fairfax County’s older commercial areas and surrounding neighborhoods ensuring continued economic vitality

• Recognize market conditions to develop and expand financial tools, complimented by public investment, to realize community and revitalization goals

Page 3: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

2

Commercial Revitalization Districts and Areas

Fairfax County Department of Housing and Community Development (DHCD), Revitalization Programs, monitor and provide project services for seven (7) designated Commercial Revitalization Districts and Areas

Page 4: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

3

Annandale Commercial Revitalization District

Page 5: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

4

Park Hotel Project

4

Page 6: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

5

Park Hotel Project

• Moon Sik Park, owner/developer

• $20 million full service hotel project

• 2 acre site fronting Little River Turnpike, east of intersection with Backlick Road

Architectural Rendering Project components:Seven (7) story100 room, full service hotel 24,500 SF retail, including:

ShopsRestaurantBanquet Facilities

370 parking spaces

Current Conditions

Page 7: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

6

K-Mart Property Project

6

Page 8: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

7

K-Mart Property Project

• Michael Kim, owner/developer• $80 million mixed use project• 15 acre site at intersection of Little River Turnpike and John Marr

Drive• Seven (7) story building• Mixed use office, retail, and residential components

Current Conditions

Architectural Rendering

Architectural Rendering

Page 9: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

8

Bailey’s Crossroads-Seven Corners Commercial Revitalization District

Arlington County

City of Alexandria

City of Falls Church

Page 10: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

9

Arlington County

City of Alexandria

City of Falls ChurchSoutheast Quadrant Redevelopment Project

9

Page 11: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

10

Southeast Quadrant Redevelopment Project

• Future development

• 4.5 acre site bounded by Moncure Avenue and Columbia Pike

• Mixed use redevelopment with office, retail, and residential components

• Potential East County Center

Mixed Use Concept

Bailey’s Crossroads Charette Study Area

Page 12: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

11

Lake Anne Commercial Revitalization Area

Page 13: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

12

Crescent Apartment Acquisition

12

Page 14: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

13

Crescent Apartments Acquisition

• $49.5 million FCRHA purchase of 180 unit Crescent Apartment Complex located adjacent to the Lake Anne Revitalization Area

• 16.5 acre site bounded by North Shore Village Drive and Village Road

• Preservation of affordable housing units

Page 15: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

14

Lake Anne Commercial Revitalization Area Expansion

On-going Revitalization Activity:

• Special study Lake Anne redevelopment

• Lake Anne Architectural Guidelines for redevelopment

Lake Anne – View from the North

Page 16: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

15

Wiehle Village Center and Metrorail Station

15

Page 17: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

16

Wiehle Village Center and Metrorail Station

• $500 million PPEA multi-modal transit oriented, mixed use redevelopment project

• Leverage Fairfax County owned 9 acre site bounded by the Dulles Toll Road, Wiehle Avenue, and Sunset Hills Road for design and construction of required project elements

• Project components:High density retail, office and residential 2,300 parking, and 46 kiss and ride spaces12 revenue, and 3 layover bus baysBike racks and lockers

Leveraging Public Investment to Ensure Economic Vitality

Fairfax County Owned 9 Acre Site

Page 18: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

17

McLean Commercial Revitalization District

Page 19: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

18

The Palladium at McLean

18

Page 20: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

19

The Palladium at McLean

• Waterford McLean LLC

• $70 million high-end mixeduse project

• Bounded by Chain Bridge Road and Old Dominion Drive

Project components:

6,000 SF office

10,000 SF retail with restaurant

69 residential units

113 space, surface and structured parking

Performing Arts Park

Page 21: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

20

Merrifield Commercial Revitalization Area

Page 22: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

21

Vantage at Merrifield Town Center Uniwest–Phase 1

21

Page 23: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

22

Vantage at Merrifield Town Center Uniwest – Phase 1

• $125 million mixed use redevelopment project

• Part of 80 acre Merrifield Town Center site

• Minutes from the Dunn Loring Metro at Crossroads of Route 29, Route 50 and the Beltway

Project components:Two (2) Seven (7) Story mixed use buildings80,000 SF retail25,000 SF office270 residential unitsStructured Parking;4 stories per building

Under ConstructionArchitectural Rendering

Page 24: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

Merrifield Town Center Clark Realty–Phase 2

23

Page 25: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

24

Merrifield Town CenterClark Realty – Phase 2

Project components:

878,000 SF residential (926 units)

507,000 SF retail

20,000 SF office

120,000 SF theater

1.67 acres parkland

5,700 space underground parking

• $750 million mixed use redevelopment project

• 1.525 million SF total project

• 27 acre site continues “Main Street” Town Center theme

Architectural Rendering

Current Condition

Page 26: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

25

Courtyard Dunn Loring Fairfax

25

Page 27: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

26

Courtyard Dunn Loring Fairfax

• Marriot

• $28 million redevelopment project

• Located at Dunn Loring Metro Stop at intersection of Prosperity Avenueand Gallows Road

Project components:

Ten (10) story, select service hotel

206 rooms

1,650 SF total meeting space; Two (2)conference rooms and executive board room

Restaurant

Open for Business

Page 28: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

27

Wilton House

27

Page 29: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

28

Wilton House

Project components:

Fifteen (15) story high-rise residential condominium project

259 luxury studio, one and two bedroom units

Public areas include a party room, health club, billiard room and business center

Roof-top pool

• Wilton House Apartments LLC, a joint venture of LCOR, Lehman Brothers, andBlackRock Realty

• $44 million redevelopment project reporting $96 million in sales; Sold out

• Located directly across from the Dunn Loring Metro

Page 30: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

29

Halstead at the Metro

29

Page 31: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

30

Halstead at the Metro • DSF/Long Metro LLC

• $48 million, 452,958 SF, mixed useredevelopment project

• Six (6) acre site, immediately across from Dunn Loring Metro

Project components:

Two (2) buildings housing:436 2 bedroom/2 bath luxury condominiums

4,914 SF retail

8,000 SF clubhouse, leasing office and conference center

1,000 SF business center

Structured parking; 727 spaces

Surface parking - retailUnder Construction

Page 32: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

31

Dunn Loring Metro Project

31

Page 33: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

32

Dunn Loring Metro Project• Trammell Crow Residential

Development

• $300 million redevelopment of Dunn Loring/Merrifield Metro 15 acre parking lot

Project components:

Merrifield Avenue, North of Prosperity:Three separate residential buildings720 residential units Ground level retail

Merille Drive, Street level of the parking garage:Retail stores line extended Merilee Drive 500 parking spaces stacked over stores85,000 SF free-standing retail building

Encouraging high quality architectural and urban design that combines functionality with

sophistication

Town Center Concept

Page 34: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

33

Richmond Highway Commercial Revitalization District

Fort Belvoir

Page 35: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

34

Alexandria

Fort Belvoir

Huntington Station

34

Page 36: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

35

Huntington Station

• Back to index

• Huntington Metro, LLC; a Stout andTeague Company; and, Clark RealtyCapital Joint Venture

• $375 million mixed use redevelopmentof Huntington Metro surface parking lot

• 31.5 acre site near intersection of Richmond Highway and I-495

Project components:10-Story Story Office-Retail Building -Stout & Teague/Clark

250,000 SF office30,000 SF retail

Residential units – 650 Total48 Townhomes - Pulte421 Low-rise, 4-Story - Centex181 High-rise,14-Story - Stout & Teague/Clark

1,450 parking - WMATA

Pulte Townhomes – Under Construction

Page 37: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

36

Alexandria

Fort Belvoir

Alexandria

Fort Belvoir

Mid-Town Alexandria Station

36

Page 38: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

37

Mid-Town Alexandria Station

• KSI• $150 million redevelopment

condominium project• Across from Huntington Metro Station

Architectural Rendering

Under Construction

Project components:368 residential units1 Guest Suite5,000 SF fitness center, cyber café,party room with outdoor seating8,000 SF pool deck with barbeque

Page 39: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

38

Alexandria

Fort Belvoir

Kings Crossing

38

Page 40: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

39

Kings Crossing

• JPI Development Partners, Inc/Archon Group

• $500 million mixed-use redevelopment

• 42 acre site fronting Richmond Highway

Project components:160,000 SF retail 100,000 SF office 750 residential

Page 41: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

40

Alexandria

Fort Belvoir

The Heights of Groveton

40

Page 42: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

41

The Heights of Groveton

• MDP Groveton, LLC • $100 million mixed use redevelopment • 4.6 acre, former Groveton School site, at Richmond Highway and Memorial

Street, 1.5 miles from Huntington Metro Station Project components:

70,000 SF Mixed Use Building: 290,000 SF Residential: 50,000 SF office 282 Condominium20,000 SF retail 15 Townhouse

Current Conditions

Architectural Rendering

Page 43: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

42

Alexandria

Fort Belvoir

Mt. Vernon Gateway

42

Page 44: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

43

Mt. Vernon Gateway

• Landmark Property Development, LLC• $225 million mixed use redevelopment use redevelopment• 15 acre site bounded by Buckman Road, Janna Lee Avenue and

Richmond Highway

Project components:70,000 SF office10,000 SF retail 428 residential units

Architectural Rendering

Architectural Rendering of Condominiums

Current Conditions

Page 45: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

44

Springfield Commercial Revitalization District

Page 46: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

45

Springfield Community Business Center (CBC) Park and Ride Facility

45

Page 47: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

46

Springfield Community Business Center (CBC)

Park and Ride Facility• $20 million PPEA multi-modal transit oriented redevelopment project

• Potential development site located at Southwest Corner of Old Keene Mill Road and Amhurst Avenue

• Leverage $6 million dollars of public funds to activate construction of a 1,000 space structured parking facility within a mixed use project

Project components:

Mixed use redevelopment with office, retail and residential

Promote new business development by nesting a multi-modal transportation facility within a retail, office and residential mixed use development

Accommodate “Slug Lines” and facilitate commuters unimpeded access to HOV lanes

Page 48: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

47

Springfield Community Business Center (CBC)

Park and Ride Facility

Mixed Use Parking Garage Facility Concept

Encouraging high quality architectural and urban design that combines functionality with sophistication

Page 49: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

48

Mid-Town Springfield

48

Page 50: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

49

Mid-Town Springfield

• KSI

• $500 million mixed-useredevelopment

• 9 acre site bounded by Commerce Street, Brandon Avenue, and I-95

Project components: Three (3) 28, 20, and18-storytowers800 residential units10-story 100,000 SF full servicehotel 100,000 SF retail 40,000 SF office 7,000 SF community space2,200 parking garage

Site Location Current Conditions

Page 51: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

50

Mid-Town Springfield

Architectural Rendering – View from Augusta Drive and I-95

Page 52: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

51

Mid-Town Springfield

Architectural Rendering – Entrance from Bland Street

Page 53: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

52

Springfield Residence Inn

52

Page 54: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

53

Springfield Residence Inn

• Marriot

• $22 million Marriot Extended Stay Hotel redevelopment project

• 1.2 acre site at intersection of Backlick and Old Keene Mill Road

Project components:

Six (6) story, 110,000 SF building163 suitesThree (3) levels structured parking

Architectural Rendering

Current Conditions

Page 55: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

54

Waterford at Springfield

54

Page 56: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

55

Waterford at Springfield

• Springfield Hospitality, LLC

• $9 million rehabilitation of former Mattress Land/Carpetland site

• Intersection of Commerce Street and Franconia Road

Project components:

44,000 SF conference-wedding reception facility

1,400 person capacity

100 space structured parking; 330 space surface parking

Under Construction – Main Entrance

Side View – Structured Parking

Opening Spring 2006

Page 57: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

56

Springfield Mall Redevelopment

56

Page 58: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

57

Springfield Mall Redevelopment

Mixed Use Town Center Concept – Walkable, Livable Communities

• Franconia Two, LP (aka Vornado)

• $1 billion redevelopment of 49 acre Springfield Mall site

• Potential inclusion of four (4) neighboring parcels, totaling 31 acres, would increase development site to 81 acres

• Bounded by Spring Mall Road, Loisdale Road, Franconia Road, andFrontier Drive, site provides easy access to I-95; and, close proximity to Franconia-Springfield Metro Station

• Mixed use with office, retail and residential components

Current Conditions

Page 59: JOINT COMMITTEE MEETING 4.5.06.ppt REVISIONDrive • Seven (7) story building • Mixed use office, retail, and residential components Current Conditions Architectural Rendering Architectural

58

Commercial Redevelopment Activities

Featured Projects23

Total Investment

$4,915,500,000