johnny o'neil lsr habitat restoration and fuels reduction...
TRANSCRIPT
Johnny O'Neil LSR Habitat Restoration and Fuels Reduction
Project
FEIS
Geology Resource Report
Prepared by:
Angie Bell
Geologist, Klamath National Forest
for:
Happy Camp/Oak Knoll Ranger Districts
5 January 2011
Updated 21 March 2012
Table of Contents
Executive Summary .................................................................................................................... 1
Analysis Indicators and Methodology ....................................................................... 1
Spatial and Temporal Context .................................................................................. 1
Affected Environment ............................................................................................... 1
Environmental Effects .............................................................................................. 1
Alternative 1........................................................................................................................ 1
Alternatives 2, 3 and 4 ........................................................................................................ 2
Compliance with law, policy, regulation, and the KNF Forest Plan ........................... 3
Introduction ................................................................................................................................. 3
Overview of Issues Addressed ................................................................................. 3
Environmental Indicators .................................................................................................... 5
Affected Environment ............................................................................................... 5
Geology ............................................................................................................................... 5
Historical Disturbance ........................................................................................................ 6
Project Design Features for Geology ..................................................................... 10
Environmental Consequences ............................................................................... 11
Methodology ..................................................................................................................... 11
Spatial and Temporal Context (bounding of analysis area) for Effects Analysis ............. 12
Direct, Indirect and Cumulative Effects of Proposed Activities ....................................... 12
Comparison of Alternatives .................................................................................... 14
Alternative 1 – No Action ................................................................................................. 14
Alternative 2 – Proposed Action ....................................................................................... 16
Alternative 3 – Modified Proposed Action ....................................................................... 22
Alternative 4 – No Temporary Roads ............................................................................... 25
References (Literature Cited) ................................................................................. 28
Appendix A- Regulatory Framework ...................................................................... 29
List of Tables
Table 1: Miles of altered channel by 7th field watershed from 1964 flood event in Horse Creek. (USFS
2002) ..................................................................................................................................................... 7
Table 2: Cumulative effects modeling results from the CWE-Geo model of the current landslide potential
based on current and past actions for the 7th field watersheds. ........................................................... 15
Table 3: Proposed actions on unstable lands (active landslides, inner gorge, toe zones and steep dissected
granitic lands) in Alternative 2 ............................................................................................................ 16
Table 4: Proposed activities on ultramafic bedrock for Alternative 2 ........................................................ 17
Johnny O’Neil Geology Report
ii
Table 5: Cumulative effects results from the CWE-Geo model of the current landslide potential based on
past, present, reasonably foreseeable future and Alternative 2 proposed actions for the 7th field
watersheds. .......................................................................................................................................... 21
Table 6: Proposed actions on unstable lands (active landslides, inner gorge, toe zones and steep dissected
granitic lands) in Alternative 3 ............................................................................................................ 22
Table 7: Proposed activities on ultramafic bedrock for Alternative 3 ........................................................ 22
Table 8: Cumulative effects results from the CWE-Geo model of the current landslide potential based on
past, present, reasonably foreseeable future and Alternative 3 proposed actions for the 7th field
watersheds. .......................................................................................................................................... 24
Table 9: Proposed actions on unstable lands (active landslides, inner gorge, toe zones and steep dissected
granitic lands) in Alternative 4 ............................................................................................................ 25
Table 10: Proposed activities on ultramafic bedrock for Alternative 4 ...................................................... 25
Table 11: Cumulative effects results from the CWE-Geo model of the current landslide potential based on
past, present, reasonably foreseeable future and Alternative 4 proposed actions for the 7th field
watersheds. .......................................................................................................................................... 27
List of Figures
Figure 1: Geomorphology of the Horse Creek 6th Field watershed (outlined in black for reference). ......... 8
Figure 2: Bedrock geology of the Horse Creek 6th field watershed (outlined in black for reference) .......... 9
Figure 3: Alternative 2 and the geomorphology of the Horse Creek 6th Field watershed (outlined in black
for reference). ...................................................................................................................................... 18
Figure 4: Alternative 2 and the bedrock geology of the Horse Creek 6th Field watershed (outlined in black
for reference). ...................................................................................................................................... 19
Johnny O’Neil Geology Report
1
Executive Summary
Analysis Indicators and Methodology
Analysis indicators include the effects of alternatives on landslide potential, slope stability, and
hazard from naturally-occurring asbestos (NOA) in ultramafic rock.
Spatial and Temporal Context
The spatial analysis area for the effects to geologic indicators is the project area for landslides
and slope stability. Because some units and portions of units have greater likelihood of effects
than others, the area potentially affected can be site specific. For NOA hazards, the area
potentially affected is only units or portions of units that contain ultramafic rock. The short term
for geologic effects is immediately following implementation of the project for the first 5-10
years. Long-term effects are beyond 10 years and can be indefinite.
Affected Environment
The landscape of the project area is geologically active and prone to landslides. The area is
dominated by both active and dormant landslide activity, steep slopes and inner gorges of
streams, and areas containing ultramafic rock.
The geology of the project area is described generally in Final Environmental Impact Statement
for the Forest Plan (USDA Forest Service 1995b), and more specifically in the Horse Creek
Ecosystem Analysis (USDA Forest Service 2002).
Environmental Effects
Alternative 1
Direct and Indirect Effects
Alternative 1 (the no action alternative) has no short-term impacts to landslide potential;
however, tree mortality due to disease or competition will increase landslide potential over the
long-term.
Cumulative Effects
Adding the effects of this alternative to the effects of reasonable foreseeable future actions within
the project area, as displayed in Appendix C, will not result in cumulatively significant effects.
The Horse Creek Road Rehabilitation project is projected to reduce the potential for landslide-
related sediment by 1,530 cubic yards per decade in the Lower Horse Creek 7th
field watershed.
This leads to a 7% reduction in the cumulative watershed effects risk ratio, using the GEO
model, as noted in the Hydrology resource report, available on the KNF website at
http://www.fs.fed.us/nepa/fs-usda-pop.php/?project=31052. The actual estimated sediment
available for landsliding will be reduced by 3,350 cubic yards by the Horse Creek Road
Rehabilitation project; therefore, the model reduction in landslide potential is an underestimate
Johnny O’Neil Geology Report
2
and risk of landslides is substantially reduced. No other reasonable foreseeable projects are
currently planned or being implemented within segments of the project area that are geologically
active, prone to landslides, or containing ultramafic rock.
Alternatives 2, 3 and 4
Direct and Indirect Effects
Landslide potential will be increased in the short-term due to the reduction of root support and
precipitation interception by trees from thinning. Increased stand health and reduction of fire
severity will decrease landslide potential over the long term. Temporary road and landing
construction will increase landslide potential indefinitely. The increase will be minimized, but
not negated, by hydrologic stabilization after completion of the project. Fuels reduction activities
(mastication, hand-piling, and underburning) will not impact slope stability in this project
because prescribed fire will be low severity due to the implementation of project design features
displayed in Table 2-1 (see also the Fire and Fuel resource report available on the KNF website
at http://www.fs.fed.us/nepa/fs-usda-pop.php/?project=31052. The naturally-occurring asbestos
(NOA) hazards will increase locally during ground-disturbing activities, but subside within a few
hours of cessation of the activity on ultramafic rock.
Alternative 2 will have the largest short-term and long-term increase in landslide potential of the
3 action alternatives, followed by Alternative 3. The main action influencing the landslide risk
will be the construction of temporary roads. The cumulative effect of the alternatives on
landslide potential will be nearly identical. The actions proposed in the alternatives will be small
relative to the impacts of past actions; therefore, the subtle difference between the alternatives is
small in the model output. All the risk ratios of the watersheds are currently under the threshold
of concern for the GEO model (explained in more detail in the Hydrology resource report,
incorporated by reference and available on the KNF website at http://www.fs.fed.us/nepa/fs-
usda-pop.php/?project=31052. However, the Middle Creek (0.98) and Salt Gulch (0.98) 7th
field
watersheds have elevated risk ratios due to private harvest and wildfire respectively. Actions
proposed in the Alternative 2 and Alternative 3 increase the risk ratios of these two watersheds to
1.00 and 0.98 respectively.
Alternative 2 has the largest NOA hazard potential; the NOA hazard potential is almost as great
but slightly less in Alternative 3. Alternative 4 will have the lowest NOA hazard potential
because it will have the least amount of ground-disturbing activities such as stand treatments,
new temporary road construction and landings proposed on ultramafic rock.
Cumulative Effects
Adding the effects of these alternatives to the effects of reasonable foreseeable future actions will
not result in cumulatively significant effects. The Horse Creek Road Rehabilitation project is
projected to reduce the potential for landslide-related sediment by 1,530 cubic yards per decade
in the Lower Horse Creek 7th
field watershed. This leads to a 7% reduction in the cumulative
watershed effects risk ratio, using the GEO model. The actual estimated sediment available for
landsliding will be reduced by 3,350 cubic yards by the Horse Creek Road Rehabilitation
Johnny O’Neil Geology Report
3
project; therefore, the model reduction in landslide potential is an underestimate and risk of
landslides is substantially reduced. No other reasonable foreseeable projects are currently
planned or being implemented within segments of the project area that are geologically active,
prone to landslides, or containing ultramafic rock.
Compliance with law, policy, regulation, and the KNF Forest Plan
All the alternatives proposed in this project will comply with laws, regulation, policy, direction
in the KNF Forest Plan (USDA Forest Service 1995a) related to geology and with the Aquatic
Conservation Strategy objectives that are included in the Forest Plan (Appendix F) as noted on
the KNF Forest Plan checklist for this project, available on the KNF website at
http://www.fs.fed.us/nepa/fs-usda-pop.php/?project=31052.
Introduction
The Johnny O’Neil LSR project area is located about 7 miles northeast of Seiad Valley,
California in the Horse Creek 6th
field watershed. This report focuses on the potential effect of
proposed activities on geologic resources, and hazards, including landslides and debris flows,
and airborne asbestos. It also provides resource protection measures which would greatly reduce
the potential for project-related adverse effects. For information on surface erosion and
hydrologic processes, refer to the soils and hydrology sections of the FEIS respectively. The
project proposes to thin plantations and natural stands and reduce fuels with underburning and
mastication.
Overview of Issues Addressed
Landslide and Debris Flow Hazards
Landslides, or mass wasting, can adversely affect human life and property, watershed condition
and fish habitat. Management activities which can increase landslide rates include: a)
Disturbance associated with the construction of new or the re-opening of existing roads or
landings. b) Removal of excessive vegetation from unstable areas through logging or prescribed
fire; and c) Disturbances to soil in unstable areas associated with mechanized yarding of timber.
For this analysis, unstable areas are considered to be active landslides, toe zones of dormant
landslides, inner gorge features and steep dissected granitic lands (See Figure 1). Landslide
hazards in the project area can be addressed in three categories as described below:
1. Deep, Slow-Moving Landslides (Earthflows and Slumps) - A large proportion of the
project area is underlain by dormant landslides (slumps and earthflows). There are a few
small active earthflows within these landforms. These landforms are common in the west
side of the project area. Disturbance of the layer of loose layer of material covering solid
Johnny O’Neil Geology Report
4
rock (regolith) and the concentration of surface runoff would increase the potential of
reactivating these features (DMG 1999).
2. Shallow Rapid Landslides (Debris Slides) - Several debris slides have occurred in Horse
Creek and its tributaries on steep (≥65%) slopes. Debris slides are common in such areas
of the KNF. Decreasing root support and cohesion would increase the probability of
shallow landsliding on steep ground (≥65%) and areas with previous active landsliding
(DMG 1999).
3. Debris Flows - Debris flows are sediment-laden flows which usually develop in channels,
and move rapidly downstream, mobilizing bed material, and stripping away vegetation.
They can be triggered by landslides in the headwaters during winter storms, or by high-
intensity, short-duration summer storms which do not trigger landslides. Inner gorge
features are commonly associated with debris flows. Disturbances in stream channels and
an increase in small materials due to management would increase debris flow probability
in the management area (DMG 1999).
Naturally Occurring Asbestos Hazards
Airborne asbestos is a human health hazard. Ultramafic rock is the most likely to contain
naturally occurring asbestos in the Klamath Mountains, which includes the Johnny O’Neil LSR.
If present, there is a potential for asbestos fibers to be introduced into the air by the removing
rock from quarries in ultramafic rock. The risk is also present during the construction of new
temporary roads, temporary roads on existing roadbeds, or landings in ultramafic rock. Figure 2
(Bedrock) shows the distribution of ultramafic rock relative to existing and proposed roads,
proposed harvest, proposed mastication units, and prescribed burn areas. The KNF has
completed testing for naturally occurring asbestos testing on unauthorized routes that were added
to the National Forest Transportation System (NFTS) (Record of Decision for Motorized Travel
Management on the KNF, 2010). Forty-one samples were taken from routes in ultramafic rock
scattered throughout the western part of the KNF including the Johnny O’Neil LSR. Over the
entire Forest, no asbestos was detected in 29 of the samples (70%). The remaining samples were
found to contain low levels of chrysotile asbestos (less than 0.25%) including the route in the
Johnny O’Neil LSR.
Geologic Resources
Geologic resources which could be affected by the project include groundwater and unique
geologic areas.
1. Groundwater- Springs are common in the project area, particularly within landslide
deposits on the east side of the project area in the Rainey Saddle Area. Since this project
consists mostly of thinning and underburning, effects on the groundwater resource due to
alteration in precipitation interception and evapotranspiration are expected to be slight
and the changes immeasurable. Effects on groundwater are not addressed further as a
result.
Johnny O’Neil Geology Report
5
2. Caves- Caves are classified as significant if they meet the criteria specified by the Federal
Cave Resource Protection Act of 1988. No known caves occur within the project area,
and as a result, this resource is not addressed further.
3. Unique Geologic Areas- There are no Geologic Special Interest Areas in the project area;
as a result, Geologic Special Interest Areas are not addressed further in this report. There
are travertine springs in the Crawfish Gulch Area within the area of proposed treatment.
The impacts to these features will be avoided through project design features to minimize
disturbance.
Environmental Indicators
• Acres of disturbance on unstable ground: Comparing acres of disturbance from thinning,
underburning, and mastication on unstable ground. To evaluate landslide potential, the
amount of disturbance (area) of each project activity on certain landslide-prone
geomorphic terranes (inner gorges, toe zones of dormant landslides, steep dissected
granitic lands, and active landslides) is tracked. This allows an overall look at how much
activity would be occurring in unstable areas by alternative.
• Mile of new temporary road construction or temporary roads on existing roadbeds in
unstable lands: Comparing miles of temporary road construction and temporary roads on
existing roadbeds on unstable ground. To evaluate landslide potential, the amount of
disturbance (area) of each project activity on certain landslide-prone geomorphic terranes
(inner gorges, and toe zones of dormant landslides, active landslides) is tracked. This
allows an overall look at how much activity would be occurring in unstable areas by
alternative.
• Acres of disturbance on ultramafic rock: To evaluate the airborne asbestos hazard, the
area for each activity on ultramafic rock is tracked.
• Miles of Temporary Road Construction in Ultramafic Rock: To evaluate the airborne
asbestos hazard, the area for each activity on ultramafic rock is tracked.
• Geo Model Risk Ratio: Comparing Risk Ratios from the GEO Model. The KNF has
adopted a management threshold for landslide sediment production of 200% over
background, and this translates to a risk ratio of 1.0. Watersheds with risk ratios of 1.0 or
greater exceed the threshold of concern. This indicator is an index which allows for the
comparison of cumulative watershed effects from landslide processes between
alternatives.
Affected Environment
Geology
The Condrey Mountain Schist suite of rocks makes up the bedrock in the eastern two-thirds of
the project area. The schist underlies large deep-seated dormant landslides deposits. These
features are most likely thousands of years old, related to wetter climates and possibly past
earthquake activity. The dormant landslides have areas of intermittent deep-seated and earthflow
active landslide when portions of the deposit are reactivated during flood events. Typically, large
Johnny O’Neil Geology Report
6
(10- to20-year) early winter storms produce landslides that have delivered coarse sediment to the
streams in the project area. The most recent storms occurred in 1964, 1974, 1997 and 2006.
The bedrock of the western third of the area proposed for treatment (in the LSR) consists of the
metasedimentary rocks of the Rattlesnake Terrain. The landslides in this area are shallow
landslide features that may trigger debris flows in low-order (headwater) streams and dry
depressions with poorly defined channels (swale) with sediment bulked in the channel. There is a
granitic intrusion which is covered with landside deposits in the Crawfish Gulch area. There are
a few small bodies of ultramafic rock near Robinson Creek and Rainey Saddle and a portion of a
larger body in the southwest portion of the proposed area for treatment.
Historical Disturbance
Many of the roads in the Johnny O’Neil LSR project area were built in the late 1950’s to support
the timber harvest and fire suppression activities. Harvest activities were the heaviest in
beginning in the 1970’s to the 1990’s. The county road next to the main stem of Horse Creek
was put in prior to 1955 to access private land. The main Fish Gulch road (Forest Service Road
46N50 within the LSR) was also built before 1955. Within the area designated as the Johnny
O’Neil LSR in 1995, prior to 1955 there was some timber harvest south of Seiad Gap and the
stands near Rainey Saddle. Additional regeneration harvest (clear cutting) occurred in the
Rainey Saddle area and south of Fish Gulch between 1955 and 1964; however, there was no
major road construction. There were clear cutting (40 acres) and road building activities in
Hamburg Gulch between 1955 and 1964. There were approximately 210 acres of timber harvest
activities in Middle Creek and the Rainey Saddle area between 1965 and 1975 along with road
building to support the harvest activities.
Wildfires have been suppressed to keep them small (< 1800 acres) over the past 60 years.
Suppression was possible due to the high road density in the project area. Fire suppression was
primarily to protect the private property in the watershed. The White Cloud fire (1935) burned
1,100 acres in the Lower Horse Creek drainage. The Red Fir fire burned 350 acres of the Middle
Horse Creek drainage in 1971 and the Buckhorn fire burned 1,100 acres in 1977. The Copper
Fire in 1987 burned 1,800 acres in the Salt Gulch and West Fork Horse Creek drainages. The
scars of the 1977 and 1987 wildland fires were still apparent on the 1999 air photos. There were
approximately 6,200 acres of salvage logging and plantations planted in response to the 1977 and
1987 wildfires in Horse Creek (USFS 2002, pg. 4-21).
Large flood events affected the watershed in 1955, 1964, 1970, 1974, 1997 and 2006. All of
these winter storms had a rain-on-snow component that increased their impact on mass wasting
processes. Debris slides triggered debris flows in several stream channels and landslides were
reactivated as a result of the storms. The magnitude and impact of the mass wasting processes
increased as the disturbance in the watershed increased. No debris flow alteration to channels
was seen in the 1955 air photos. The 1964 storm resulted in most of the streams in the Horse
Creek 6th
field watershed showing some length of channel altered by debris flows and flood
waters (see Table 1). There was some channel alteration in the lower portion of Horse Creek and
Johnny O’Neil Geology Report
7
in Middle Creek as a result of the 1970 storm. There was some scour in Upper and Lower Horse
Creek as a result of the 1970 and 1974 storms. The 1997 storm event had minor effects on the
stream channels in the watershed. No systematic inventory of channel alteration was completed
for the 2006 flood event. It is probable that a few of the streams had channel alterations in 2006
but no evidence was observed during field visits.
Table 1: Miles of altered channel by 7th
field watershed from 1964 flood event in Horse
Creek. (USFS 2002)
7th
Field Watershed Miles of Altered Channel from 1964 Flood
Upper Horse Creek 1.28
Lower Horse Creek 5.19
Middle Creek 2.99
Buckhorn Creek 7.66
Landslides were also activated or reactivated during the storm events. Earthflows and deep-
seated landslides are common on the dormant landslide deposits of the eastern 2/3 of the
proposed area of treatment. The landslides in this area are almost all associated with human-
caused disturbances such as construction of roads and regeneration timber harvesting (clear
cutting). Debris slide features are more common than the deep-seated landslides on the eastern
1/3 of the proposed treatment area... These shallow landslides are often associated with
construction of roads or regeneration timber harvests. There are landslides in the LSR in
drainages north of Robinson Gulch (from the 1944 air photos) that are prior to management
activities in that part of the watershed. The debris slides in the LSR in the headwaters of West
Fork Horse Creek from the 1970 flood event are also not associated with any management
activities.
Johnny O’Neil Geology Report
8
Figure 1: Geomorphology of the Horse Creek 6th Field watershed (outlined in black for reference).
Johnny O’Neil Geology Report
9
Figure 2: Bedrock geology of the Horse Creek 6th field watershed (outlined in black for reference)
The star illustrates the naturally occurring asbestos (NOA) testing that has been done in the project area. Traces of NOA
were found in samples from the road on this ultramafic body.
Johnny O’Neil Geology Report
10
Project Design Features for Geology
The following general measures will be applied to address geologic hazards and resources. They
will greatly reduce the potential for adverse direct, indirect, and cumulative watershed effects.
1. Roads and Landings- New temporary roads and landings will be constructed in matrix
lands (outside of Riparian Reserves), and away from locations where sediment could
directly enter streams. Following use, all temporary roads will be decommissioned, fills
removed from draws, and natural runoff patterns re-established (outsloping, dips, etc.).
On existing temporary roads, berms will be removed, and conditions which concentrate
surface runoff would be eliminated. Following use, all temporary roads will be
decommissioned, fills removed from draws, and natural runoff patterns re-established
(outsloping, dips, etc.). Any modification to temporary road alignments during the
implementation phase of the project (not analyzed in the planning phase) will be
reviewed by an earth scientist.
2. Skyline in Riparian Reserves –Cable yarding corridors would not be place in stream
Riparian Reserves parallel to the channel unless field assessment by an earth scientist and
sale planner or administrator determines that this can be accomplished without damage to
residual trees or soil.
3. Mechanical Equipment and Mastication- Tractors and mechanical harvesters will be
excluded from unstable land Riparian Reserves except in situations where field
investigation by an earth scientist determines that no adverse effects would occur. Water
bars would be constructed upon completion of the project to avoid diversion of runoff.
Best Management Practices (BMP) as outlined in the hydrology report would be
followed, as would specific measures recommended in the soils report. Mastication
equipment would follow the same general guidelines as tractors.
4. Prescribed Fire in Riparian Reserves- Prescribed fire will be designed to result in low
severity burns in all Riparian Reserves (including the unstable land component of
Riparian Reserves). During underburning, fire will generally be backed down into
Riparian Reserves, and ignition will usually not occur there. However, there may be
exceptions where ignition inside the Riparian Reserve may actually allow for lower
severity fire in those areas. Specific problem spots, such as high concentrations of fuel
located on unstable areas, will be field reviewed by fuels and earth science personnel
during development of the burn plan and appropriate mitigations developed. The
potential for high severity fire can be mitigated by modifying the ignition pattern, or
handpiling of slash accumulations on unstable areas prior to ignition. Other unstable
areas within burn boundaries will be evaluated during development of burn plans, and
protected as necessary.
5. Protection of Unique Geologic Features: Several carbonate springs have been mapped
in Crawfish Gulch and the surrounding hillslope. Mechanized equipment would be
excluded from the carbonate spring areas. Similarly, cable yarding corridors would be
excluded from these areas unless full suspension can be attained. The bottom 250 feet of
Crawfish Creek in Unit 508 contains carbonate springs, as does the northern most point
of unit 427.
Johnny O’Neil Geology Report
11
6. Asbestos- There is a small body of ultramafic rock north of Rainey Saddle which
underlies FS route 12 and 47N65. There is also a body of ultramafic rock underlying the
southwestern corner of the project area. Purchasers of the timber sale would be informed
of harvest units and roads underlain by ultramafic rock which may contain asbestos. If
haul-routes change during project implementation, any additional roads would be
checked against the bedrock map to determine if they are underlain by ultramafic rock,
and the asbestos standards applied. Standard mitigation measures would be applied,
including watering roads during use or surfacing with material which does not contain
asbestos. Crews constructing fire lines for underburns would similarly be informed of
areas underlain by ultramafic rock. Mitigation measures would be applied, including
constructing lines during wet soil conditions, or watering lines as appropriate. The
temporary road that has been proposed for construction between units 420 and 488 is
partially underlain by ultramafic rock.
Environmental Consequences
Methodology
Each alternative was evaluated according to: a) its potential direct, indirect, and cumulative
effects; b) the environmental Indicators; and c) how well it would meet direction from laws,
regulations, Forest Service policy and the KNF Forest Plan. Direct, indirect, and cumulative
effects were assessed through field and air photo assessments, and GIS analyses using the
bedrock and geomorphology coverages. Aerial photos were used to identify geomorphic
features in units and along roads, to develop a history of landsliding and debris flows in the
project area dating back to 1944, and to prioritize units for field visits. Units on unstable lands,
as identified on the Forest geomorphology coverage, or on air photos, were selected for field
review.
Reasonably Foreseeable Future Actions Considered in Cumulative Effects
Within the Horse Creek 6th
field watershed, two projects on the KNF are considered in projecting
potential cumulative effects of the Johnny O’Neil LSR project. These projects are selected
because their effects may be considered to overlap those of the Johnny O’Neil LSR project in
space and in time, they include activities that are similar to the project (thinning of timber,
temporary roads) and their environmental effects may be additive to those of the project. The two
reasonably foreseeable projects on the KNF are:
Middle Creek Project (planning ongoing) is located within the Middle Creek 7th
field sub-
watershed. The project entails approximately 70 acres of thinning of commercial-sized trees
(>10” in diameter at breast height (dbh)) using ground-based mechanical logging systems.
Horse Heli (planning complete in 2007, implementation ongoing) is located partially in the
Middle Creek and Buckhorn 7th
field watersheds. Two NFTS roads (0.92 miles) will be
decommissioned in the Middle Creek 7th
field watershed, and NFTS roads (1.06 miles) will be
decommissioned in the Buckhorn Creek 7th
field watershed. In addition, the Horse Heli project
decision includes decommissioning of unauthorized roads (1.55 miles) in the Buckhorn Creek 7th
Johnny O’Neil Geology Report
12
field watershed for a total of 3.53 miles of road decommissioning. One harvest unit is located
within Middle Creek 7th
field watershed and 26 units are within the Buckhorn Creek 7th
field
watershed.
Spatial and Temporal Context (bounding of analysis area) for Effects Analysis
Effects are analyzed in the context of short and long term. Short term effects are taken to be 0-5
years, during which site conditions should essentially recover from the proposed thinning and
underburn activities. The long term is taken to be greater than 5 years. The effects of high
severity wildfire would likely last up to 50 years. New temporary roads are considered to be
permanent fixtures, and never fully recover, since cuts and fills remain, even after hydrologic
stabilization. The spatial context is the Horse Creek 6th
field watershed with modeling done at
the 7th
field watershed level.
Direct, Indirect and Cumulative Effects of Proposed Activities
The direct, indirect, and cumulative effects of proposed project activities are described in general
terms below. Alternative specific analysis is outlined in the comparison of alternatives. Indirect
effects are those which occur in association with and as a result of direct effects, but may be
delayed in time, and be distributed over different space.
Direct and Indirect Effects
Direct effects of the thinning with ground-based yarding logging system are 1) soil/regolith
disturbance and compaction, 2) decreased root support and evapotranspiration, 3) rerouting of
surface runoff, 4) potential disturbance to the springs and wet areas if entered with equipment
and 5) introduction of dust into the air. Skyline yarding would have direct effects of disturbing
and displacing the soil and disturbance to residual vegetation in cable yarding corridors caused
by dragging logs. Where logs cannot be adequately suspended, gouging of the ground surface
may reroute surface runoff. The potential direct effects of mastication on the soil would be very
similar to those of ground-based yarding including production of dust, since tracked vehicles
would be used.
The effect of changes to evapotranspiration on landsliding processes is dependent on the timing
of the potential landslide-producing storm. In the Klamath Mountains, most major landslide
producing storms occur in the early winter when evapotranspiration processes have little impact
on the hillslope hydrology (Swanston & Dryness 1973, Reid 2010). Summer storms tend to be
short duration, high intensity storms. The main player in hillslope hydrology during these storms
is precipitation interception. A decrease in interception will increase the amount of water that
enters the shallow groundwater and unsaturated zone of soil (vadose zone) effecting local
groundwater tables (Reid 2010). This is especially true for unstable lands which are sensitive to
groundwater changes, such as dormant landslide deposits (DMG 1999).
In the short term, thinning would generally result in a small to negligible increase in landslide
rates due to the minimal reduction in root support, evapotranspiration and precipitation
interception. In the long term, thinning would be expected to produce healthier stands which
Johnny O’Neil Geology Report
13
would replace and exceed any lost root support or evapotranspiration, and also reduce the risk of
intense wildfire.
Salt Gulch and Lower Horse Creek watersheds are susceptible to shallow debris slides due to the
steepness of the slopes, the number of dry depressions with poorly defined channels (swale), and
inner gorges. The decrease in root support and localized re-routing of surface flow from thinning
and masticating would increase landslide potential in the short-term (Reid 2010). Middle Horse
and Middle Creek watersheds are susceptible to reactivation of deep-seated landslides and
earthflows due to the extent of landslide deposits and springs in the watersheds. The alteration of
ground water due to the decrease in interception and evapotranspiration would most likely
increase the landslide potential in these watersheds. The short-term reduction in canopy cover
would increase landslide potential but the increase in stand health and recovery of canopy would
reduce landslide potential over the long-term.
Construction of new temporary roads and landings would: 1) remove vegetation; 2) disturb
soils/regolith; 3) alter slopes through cuts and fills; 4) reroute surface runoff; and 5) introduce
dust into the air. Building temporary roads on existing roadbeds would remove trees and brush
which in some cases might be up to 40 years old. All of the road and landing activities would
have the potential to introduce dust into the air.
Temporary road and landing construction would increase landslide potential indefinitely in all
the watersheds due to irreversible changes in groundwater and surface hydrology. This impact
would be most pronounced in Lower Horse Creek watershed due to the steep slopes which may
require some roadcuts and/or fills. The landslide potential would be increased over the long-term
as a result of the hillslope modifications if full-bench temporary road construction is required.
These impacts would be minimized, but not negated, by effective hydrologic stabilization. The
hydrologic stabilization of the temporary roads would include the minimization of surface flow
concentration and the removal of any existing road fills. Building temporary roads on existing
roadbeds could increase landslide potential due to the removal of trees and brush, but the
subsequent hydrologic stabilization would have an offsetting effect by removing fills and
contouring to prevent concentration of surface water onto the hillslope. .
Prescribed underburning would result in the killing or setting back of low understory vegetation
and the addition of ash to the soil. There would be a small risk of small isolated areas (a few
acres in size) burning at moderate or high severity. Construction of firelines would have the
potential to introduce dust into the air.
Prescribed fire, including underburning and handpile-burning, would not affect landslide
potential. If any pockets of moderate or high intensity burning occur, leading to large tree
mortality, landslide potential would be increased locally in the long term. Mastication could
concentrate surface flow onto unstable lands and would disturb the understory. The application
of drainage structures on mastication access trails (i.e., waterbars) where needed would reduce
the effects to negligible.
Johnny O’Neil Geology Report
14
Operation in ultramafic areas under dry conditions could introduce asbestos fibers, if present,
into the air and pose a health hazard. Application of project design features and the Air Resource
Board’s Air Toxic Control Measures (where applicable) would mitigate this risk.
Dust generating activities such as thinning, new temporary road construction, building temporary
roads on existing roadbeds, mastication and underburning operations in ultramafic rock would
have a risk of exposure to NOA hazards, if NOA is present. The risk would be local and would
subside within a few hours of cessation of the activity as the dust subsides.
Cumulative Effects
The landslide model (GEO) which is used to evaluate cumulative watershed effects predicts the
volume of landslide sediment (cubic yards) which would likely be delivered to the stream system
under a variety of road, timber harvest, and fire conditions. Landslide production coefficients
were developed in the Salmon River basin, about 40 miles south of the project area. A risk ratio
is used as an indicator of the potential for adverse cumulative watershed effects. The risk ratio is
determined by comparing post-project sediment production to that which would occur under
background conditions (fully forested with no roads, harvest or fire).
The relative change in sediment production (percent over background) is computed as follows:
post-project sediment production, minus background sediment production divided by
background sediment production, times 100. When the percent over background approaches,
200%, it is assumed that the risk for adverse cumulative watershed effects rises rapidly, and this
value is considered a management threshold. This value of 200% was developed by analyzing
model outputs for the entire KNF, and identifying those which appeared to exhibit actual
physical signs of adverse cumulative watershed effects. The risk ratio is computed by dividing
the threshold value of 200% by the computed post-project percent over background. When the
percent over background equals 200%, the risk ratio is 1.0. This analysis follows the procedure
described in 2004 Cumulative Watershed Effects analysis models (see Water (Hydrology)
section of Chapter 3 of the FEIS). The cumulative effects of the project are the added effects
produced by the project to those of the past, present, and reasonably foreseeable future actions as
described earlier.
Comparison of Alternatives
Alternative 1 – No Action
This is the no action alternative. This is the continuation of the current level of management and
use. It includes road maintenance, dispersed recreation (e.g., hunting, camping, fishing, and
hiking), watershed restoration activities and a modeled wildfire.
Direct Effects and Indirect Effects
There would not be new ground disturbance to impact landslide potential due to the effects of
taking no action. There would be no disturbance of ultramafic bedrock under the no action
Johnny O’Neil Geology Report
15
alternative and, therefore, no NOA risk related to this alternative. However, no treatment in the
project area would lead to increased mortality due to competition in the timber stands over time.
Without treatment the species diversity of the timber stands would decrease, making the stand
more likely to be impacted by high intensity and severity wildfire (see Vegetation section of
Chapter 3 of FEIS). The large tree mortality would increase landslide potential by reducing root
cohesion (Swanson & Dryness 1973) and precipitation interception (Reid 2010). Alterations to
evapotranspiration and precipitation interception processes due to tree loss would also increase
landslide potential across the watersheds. High severity wildfire, which is associated with tree
mortality, would increase the landslide potential should an event occur.
Cumulative Effects
Since no actions are taken in this alternative, there are no additive effects and no cumulative
effects. However, the modeled effects of this alternative in the CWE analysis are due to the
effects of past fires, timber harvest or road construction. The effects of past and present activities
on landslide potential are summarized in Table 2. All of the 7th
field watersheds are below the
threshold of concern for the geo model. Salt Gulch has a risk ratio close to 1.0 due to the 1987
fire effects. Middle Creek has a risk ratio close to 1.0 as a result of harvesting on private land and
the high road density in the watershed.
Table 2: Cumulative effects modeling results from the CWE-Geo model of the current landslide
potential based on current and past actions for the 7th
field watersheds.
Current [past & present]
Drainages [7th-field]
Background Harvest
& Fire
Roads Road
treatments Current
1/
Risk ratio
3/
[cumulati
ve] [cumula
tive] [direct/ indirect]
[cumulative]
East Fork Horse Creek 10,421 1,155
10,624
22,200 0.57
West Fork Horse Creek 8,268 850
6,412
15,530 0.44
Middle Horse Creek 7,857 1,949
9,581
19,387 0.73
Salt Gulch 5,486 2,731 8,067 16,285 0.98
Lower Horse Creek 19,329 880
20,224 -452
39,981 0.53
Middle Creek 18,941 4,866 31,268 -375 54,701 0.94
Buckhorn Creek 30,589 7,560
31,803 -377
69,575 0.64
Horse Creek 100,892 19,992 117,98 -1,204 237,660 0.68
Johnny O’Neil Geology Report
16
6th -field 0
Compliance with Forest Plan and Other Relevant Laws, Regulations, Policies and
Plans
Alternative 1would comply with law, regulation, Forest Service policy and direction in the KNF
Forest Plan, including Aquatic Conservation Strategy Objectives.
Summary of Effects
The increased tree mortality due to no action would increase the landslide potential in the
watersheds due to the loss of root cohesion and alteration to evapotranspiration. Salt Gulch and
Middle 7th
field watersheds are close to the threshold of concern due to past wildfire, harvest and
road construction.
Alternative 2 – Proposed Action
Alternative 2 is the proposed action. This alternative proposes treatments to protect and enhance
late-successional habitat and communities on approximately 7,250 acres. Approximately 1530
acres of thinning would occur in plantations and natural stands. Underburning would occur on
6390 acres throughout the project area. Mastication would occur on 740 acres and handpile and
burning on 120 acres. Approximately 2 miles of new temporary road would be constructed for
the project and 5.7 miles of temporary road on existing roadbeds would be used. All temporary
roads would be hydrologically stabilized after project completion. Approximately 42 existing
small (<.75 acre) landings would be used and 4 existing larger landings (1.5 to 2 acres). A
maximum of 150 new landings would be constructed, most of which are small and 3 of which
could be larger (1.5 to 2 acres).
Table 3: Proposed actions on unstable lands (active landslides, inner gorge, toe zones and steep dissected
granitic lands) in Alternative 2
Alt 2
Harvest
units
(acres)
Underburn
(acres)
Mastication
(acres)
Temporary
Roads on
Existing
Roadbeds
(feet)
New
Temporary
Roads (feet)
East Fork Horse
Creek 0 11 0 0 0
Middle Creek 0 0 10 0 0
Lower Horse
Creek 66 580 1 940 115
Middle Horse
Creek 1 188 1 0 0
Salt Gulch 3 40 6 0 0
West Fork
Horse Creek 0 5 2 0 0
Total 70 824 20 940 115
Johnny O’Neil Geology Report
17
Table 4: Proposed activities on ultramafic bedrock for Alternative 2
Alt 2 Units Mastication Underburn
Temporary
Roads on
Existing
Roadbeds
(feet)
New
Temporary
Roads (feet)
Umrx (acres) 5.3 0.2 117 na na
Umrx (feet) na na na 0 350
Johnny O’Neil Geology Report
18
Figure 3: Alternative 2 and the geomorphology of the Horse Creek 6th Field watershed (outlined in black for reference).
Johnny O’Neil Geology Report
19
Figure 4: Alternative 2 and the bedrock geology of the Horse Creek 6th Field watershed (outlined in black for reference).
Johnny O’Neil Geology Report
20
Design Features and Mitigation Measures
Outlined below are the unit specific mitigation measures that are in addition to the general
measures discussed above.
• Unit 508 – Full suspension across Crawfish Gulch to avoid damage to the travertine
springs and associated features in the drainage.
• Unit 427 – No harvest or disturbance to the landslide scarp on the eastern edge of the
unit. There is a definite break in slope from 10% on the bench to 70% on the scarp. The
presence of groundwater (and travertine springs) and the steepness of the scarp make it
sensitive to disturbance.
• Unit 439 – Exclusion of ground-based equipment on the northern 1/3 of the unit to avoid
disturbance on the active landslide in the headwaters of Horse Creek.
• Unit 447 – Equipment exclusion on the earthflow feature and spring complex in the
southern end of unit.
• Unit 455 – Equipment exclusion on the active landslide in the southwestern corner of the
unit.
Direct and Indirect Effects
The increase to landslide potential would be larger in alternative 2 than both alternative 3 and
alternative 4 in the short-term. The difference is a result of the difference in acres that would be
thinned, treated for fuels and the miles of temporary road constructed or re-opened overall and
on unstable lands (See Table 3). The reduction in landslide potential due to stand health and fire
resiliency, over the long-term, would be slightly larger in alternative 2 compared to alternative 3
and alternative 4. Although, due to the difference in temporary road construction, the small
difference in landslide potential due to stand health is lost. The overall long-term landslide
potential would be higher in alternative 2 than in alternative 3 and 4.
The NOA hazard potential is would not be measurably different between alternative 2 and
alternative 3. The ground disturbing activities in ultramafic rock is nearly identical between these
two alternatives (see Table 4 & Table 7). The NOA hazard potential for alternative 2 would be
higher than in alternative 4. There would be no new temporary road construction in ultramafic
rock in alternative 4and the acres of thinning in ultramafic rock is reduced (Table 10).
Cumulative Effects
The cumulative watershed effects model for landslide potential for this alternative is summarized
in Table 5. The risk ratio for landslide potential would be below threshold for all the watersheds.
The risk ratio would be elevated in Salt Gulch and Middle Creek 7th
field watersheds, with ratios
of 0.98 and 1.00 respectively. The elevated risk ratio in Salt Gulch is due to the impacts of the
1987 wildfire that burnt in the watershed. The risk ratio in Middle Creek is 1.00 mainly a result
of private timber harvest and the high road density in the watershed. Temporary road
construction has a large impact on the landslide potential in each watershed. However, the
Johnny O’Neil Geology Report
21
attribution to the risk ratio is small due to the small area disturbed. The main player in the change
in the risk ratio is the thinning activities. These are low to moderate disturbances in the model
and are small relative to the past disturbances in the watersheds.
Table 5: Cumulative effects results from the CWE-Geo model of the current landslide potential
based on past, present, reasonably foreseeable future and Alternative 2 proposed actions for the
7th field watersheds.
Alt. 2 and Future Action
Drainages [7th-field]
Acres Background Units &
Landings Temp Roads
Current + proposed
Risk ratio
[direct/ indirect]
[direct/ indirect
]
[cumulative]
East Fork Horse Creek 4,707 10,421 48 14
22,223 0.57
West Fork Horse Creek 3,348 8,268 0
15,492 0.44
Middle Horse Creek 3,325 7,857 1,208 35
20,586 0.81
Salt Gulch 2,405 5,486 72 10 16,266 0.98
Lower Horse Creek 7,971 19,329 1,727 244
41,998 0.59
Middle Creek 8,047 18,941 473 94 56,686 1.00
Buckhorn Creek 9,153 30,589
71,717 0.67
Horse Creek 6th -field
38,955 100,892 3,527 377 244,967 0.71
Compliance with Forest Plan and Other Relevant Laws, Regulations, Policies and
Plans
This alternative of the Johnny O’Neil project complies with the Aquatic Conservation Strategy
Objectives, as well as direction in the Northwest Forest Plan, and the Klamath National Forest
Land management Plan.
Summary of Effects
The short-term landslide potential for this alternative would be higher than both alternative 3 and
4. The temporary road construction proposed in this alternative causes alternative 2 to have an
elevated long-term landslide potential compared to alternative 4 but similar to alternative 3. The
NOA hazard potential is similar to alternative 3 but higher than alternative 4.
Johnny O’Neil Geology Report
22
Alternative 3 – Modified Proposed Action
Alternative 3 is the proposed action. This alternative proposes treatments to protect and enhance
late-successional habitat and communities on approximately 7,280 acres. Approximately 1360
acres of thinning would occur in plantations and natural stands. Underburning would occur on
6440 acres throughout the project area. Mastication would occur on 745 acres and handpile and
burning on 90 acres. Approximately 1.4 miles of new temporary road would be constructed for
the project and 5.0 miles of temporary road on existing roadbeds would be used. All temporary
roads would be hydrologically stabilized after project completion. Approximately 40 existing
small (<.75 acre) landings would be used and 4 existing larger landings (1.5 to 2 acres). A
maximum of 117 new landings would be constructed, most of which are small and 3 of which
could be larger (1.5 to 2 acres).
Table 6: Proposed actions on unstable lands (active landslides, inner gorge, toe zones and steep dissected
granitic lands) in Alternative 3
Alt 3
Harvest
units
(acres)
Underburn
(acres)
Mastication
(acres)
Temporary
Roads on
Existing
Roadbeds
(feet)
New
Temporary
Roads (feet)
East Fork Horse
Creek
0 11 0 0 0
Middle Creek 0 10 0 0 0
Lower Horse
Creek
37 581 1 400 115
Middle Horse
Creek
1 188 1 0 0
Salt Gulch 3 40 6 0 0
West Fork
Horse Creek
0 5 2 0 0
Total 41 835 9 400 115
Table 7: Proposed activities on ultramafic bedrock for Alternative 3
Alt 3
Harvest
units
(acres)
Underburn
(acres)
Mastication
(acres)
Temporary
Roads on
Existing
Roadbeds
(feet)
New
Temporary
Roads (feet)
Johnny O’Neil Geology Report
23
Umrx (acres) 5.0 0.2 117 na na
Umrx (feet) na na na 0 350
Design Features and Mitigation Measures
Outlined below are the unit specific mitigation measures that are in addition to the general
measures discussed above.
• Unit 508 – Full suspension across Crawfish Gulch to avoid damage to the travertine
springs and associated features in the drainage.
• Unit 427 – No harvest or disturbance to the landslide scarp on the eastern edge of the
unit. There is a definite break in slope from 10% on the bench to 70% on the scarp. The
presence of groundwater (and travertine springs) and the steepness of the scarp make it
sensitive to disturbance.
• Unit 447 – Equipment exclusion on the earthflow feature and spring complex in the
southern end of unit.
• Unit 455 – Equipment exclusion on the active landslide in the southwestern corner of the
unit.
Direct and Indirect Effects
The increase to landslide potential would be smaller in alternative 3 than alternative 2 but larger
than alternative 4 in the short-term. The difference is a result of the difference in acres that would
be thinned, treated for fuels and the miles of temporary road constructed or re-opened overall and
on unstable lands (See Table 3). The reduction in landslide potential due to stand health and fire
resiliency, over the long-term, would be slightly smaller in alternative 3 compared to alternative
2 and higher compared to alternative 4. Although, due to the difference in temporary road
construction, the small difference in landslide potential due to stand health is lost. The overall
long-term landslide potential would be higher in alternative 3 than in alternative 4, but smaller
than alternative 2.
The NOA hazard potential is would not be measurably different between alternative 2 and
alternative 3. The ground disturbing activities in ultramafic rock is nearly identical between these
two alternatives (see Table 4 & Table 7). The NOA hazard potential for alternative 3 is higher
than in alternative 4. There is no new temporary road construction in ultramafic rock in
alternative 4and the acres of thinning in ultramafic rock is reduced (Table 10).
Cumulative Effects
The cumulative watershed effects model for landslide potential for this alternative is summarized
in Table 8. The risk ratio for landslide potential would be below threshold for all the watersheds.
The risk ratio would be elevated in Salt Gulch and Middle, with ratios of 0.98 and 1.00
Johnny O’Neil Geology Report
24
respectively. The elevated risk ratio in Salt Gulch is due to the impacts of the 1987 wildfire that
burnt in the watershed. The risk ratio in Middle is 1.00 mainly a result of private timber harvest
and the high road density in the watershed. Temporary road construction has a large impact on
the landslide potential in each watershed. However, the attribution to the risk ratio is small due to
the small area disturbed. The main player in the change in the risk ratio is the thinning activities.
These are low to moderate disturbances in the model and are small relative to the past
disturbances in the watersheds.
Table 8: Cumulative effects results from the CWE-Geo model of the current landslide potential
based on past, present, reasonably foreseeable future and Alternative 3 proposed actions for the
7th field watersheds.
Alt. 3 and Future Action
Drainages [7th-field]
Acres Background Units &
Landings Temp Roads
Current + proposed
Risk ratio
[direct/ indirect]
[direct/ indirect]
[cumulative]
East Fork Horse Creek 4,707 10,421 48 14
22,223 0.57
West Fork Horse Creek 3,348 8,268 0
15,492 0.44
Middle Horse Creek 3,325 7,857 1,252 35
20,630 0.81
Salt Gulch 2,405 5,486 72 10 16,266 0.98
Lower Horse Creek 7,971 19,329 1,224 141
41,411 0.57
Middle Creek 8,047 18,941 473 94 56,686 1.00
Buckhorn Creek 9,153 30,589 71,717 0.67
Horse Creek 6th -field
38,955 100,892 3,068 294 244,424 0.71
Compliance with Forest Plan and Other Relevant Laws, Regulations, Policies and
Plans
This alternative of the Johnny O’Neil project would comply with the Aquatic Conservation
Strategy Objectives, as well as direction in the Northwest Forest Plan, and the Klamath National
Forest Land management Plan.
Summary of Effects
The short-term landslide potential for this alternative would be higher than alternative 2 but
lower than alternative 4. The temporary road construction proposed in this alternative causes
Johnny O’Neil Geology Report
25
alternative 3 to have an elevated long-term landslide potential compared to alternative 4 but
similar to alternative 2. The NOA hazard potential is similar to alternative 2 but higher than
alternative 4.
Alternative 4 – No Temporary Roads
Alternative 4 is the proposed action. This alternative proposes treatments to protect and enhance
late-successional habitat and communities on approximately 7,280 acres. Approximately 1160
acres of thinning would occur in plantations and natural stands. Underburning would occur on
6440 acres throughout the project area. Mastication would occur on 745 acres and handpile and
burning on 90 acres. Approximately 0.1 miles of new temporary road would be constructed for
the project and 5.0 miles of temporary road on existing roadbeds would be used. All temporary
roads would be hydrologically stabilized after project completion. Approximately 40 existing
small (<.75 acre) landings would be used and 4 existing larger landings (1.5 to 2 acres). A
maximum of 104 new landings would be constructed, most of which are small and 3 of which
could be larger (1.5 to 2 acres).
Table 9: Proposed actions on unstable lands (active landslides, inner gorge, toe zones and steep dissected
granitic lands) in Alternative 4
Alt 4
Harvest
units
(acres)
Underburn
(acres)
Mastication
(acres)
Temporary
Roads on
Existing
Roadbeds
(feet)
New
Temporary
Roads (feet)
East Fork Horse
Creek
0 11 0 0 0
Middle Creek 0 10 0 0 0
Lower Horse
Creek
22 581 1 400 0
Middle Horse
Creek
0 188 1 0 0
Salt Gulch 2 40 6 0 0
West Fork
Horse Creek
0 5 2 0 0
Total 22 835 9 400 0
Table 10: Proposed activities on ultramafic bedrock for Alternative 4
Alt 4
Harvest
units
(acres)
Underburn
(acres)
Mastication
(acres)
Temporary
Roads on
Existing
Roadbeds
New
Temporary
Roads (feet)
Johnny O’Neil Geology Report
26
(feet)
Umrx (acres) 3.4 0.2 117 na Na
Umrx (feet) na na Na 0 0
Design Features and Mitigation Measures
Outlined below are the unit specific mitigation measures that are in addition to the general
measures discussed above.
• Unit 508 – Full suspension across Crawfish Gulch to avoid damage to the travertine
springs and associated features in the drainage.
• Unit 427 – No harvest or disturbance to the landslide scarp on the eastern edge of the
unit. There is a definite break in slope from 10% on the bench to 70% on the scarp. The
presence of groundwater (and travertine springs) and the steepness of the scarp make it
sensitive to disturbance.
• Unit 414 – Equipment exclusion on the small earthflow (active landslide) in the swale in
the center of the unit.
• Unit 447 – Equipment exclusion on the earthflow feature and spring complex in the
southern end of unit.
• Unit 455 – Equipment exclusion on the active landslide in the southwestern corner of the
unit.
Direct and Indirect Effects
The increase to landslide potential would be smaller in alternative 4 than alternative 2 and 3 in
the short-term. The difference is a result of the difference in acres that would be thinned, treated
for fuels and the miles of temporary road constructed or re-opened overall and on unstable lands
(See Table 9). The reduction in landslide potential due to stand health and fire resiliency, over
the long-term, would be slightly smaller in alternative 4 compared to alternative 2 and 3. The
overall long-term landslide potential would be lower in alternative 4 than in alternative 2 or 3.
The NOA hazard potential for alternative 2 and 3 would be higher than in alternative 4. There
would be no new temporary road construction in ultramafic rock in alternative 4and the acres of
thinning in ultramafic rock is reduced (Table 10).
Cumulative Effects
The cumulative watershed effects model for landslide potential for this alternative is summarized
in Table 11. The risk ratio for landslide potential would be below threshold for all the
watersheds. The risk ratio would be elevated in Salt Gulch and Middle Creek sub-watersheds,
with ratios of 0.98 and 0.99 respectively. The elevated risk ratio in Salt Gulch is due to the
impacts of the 1987 wildfire that burnt in the watershed. The risk ratio in -Middle is 0.99 mainly
a result of private timber harvest and the high road density in the watershed. Temporary road
construction has a large impact on the landslide potential in each watershed. However, the
attribution to the risk ratio is small due to the small area disturbed. The main player in the change
Johnny O’Neil Geology Report
27
in the risk ratio is the thinning activities. These are low to moderate disturbances in the model
and are small relative to the past disturbances in the watersheds.
Table 11: Cumulative effects results from the CWE-Geo model of the current landslide potential
based on past, present, reasonably foreseeable future and Alternative 4 proposed actions for the
7th field watersheds.
Alt. 4 and Future Action
Drainages [7th-field]
Acres Background Units &
Landings Temp Roads
Current + proposed
Risk ratio
[direct/ indirect]
[direct/ indirect]
[cumulative]
East Fork Horse Creek 4,707 10,421 29 0
22,190 0.56
West Fork Horse Creek 3,348 8,268 0
15,492 0.44
Middle Horse Creek 3,325 7,857 1,229 12
20,584 0.81
Salt Gulch 2,405 5,486 70 3 16,257 0.98
Lower Horse Creek 7,971 19,329 850 4
40,900 0.56
Middle Creek 8,047 18,941 450 33 56,602 0.99
Buckhorn Creek 9,153 30,589
71,717 0.67
Horse Creek 6th -field
38,955 100,892 2,628 52 243,742 0.71
Compliance with Forest Plan and Other Relevant Laws, Regulations, Policies and
Plans
This alternative of the Johnny O’Neil project would comply with the Aquatic Conservation
Strategy Objectives, as well as direction in the Northwest Forest Plan, and the Klamath National
Forest Land management Plan.
Summary of Effects
The short-term landslide potential for this alternative would be lower than alternative 2 and 3.
The temporary road construction proposed in alternatives 2 and 3 would be elevated long-term
landslide potential compared to alternative 4. The NOA hazard potential is smaller than
alternative 2 or 3.
Johnny O’Neil Geology Report
28
References (Literature Cited)
Resource air photos 1955 (bw) 14P-156:160,14P-175:182, 20P-140-148; 1964 ENU (bw) 18-
133:145, 14-77:79; 1965 DCC (bw) 16FF-145:150; 1975 (c) 2475-265:269, 2475-271:275,
2475-247:252, 2475-224:229; 1999 (c) 599-155:161, 599-49:54, 599-32:39,499-196:199.
(DMG) Division of Mines and Geology. 1999. Factors Affecting Landsliding in Forested
Terrain. Note 50. California Department of Conservation.
Reid, L. 2010. Cumulative Watershed Effect of Fuel Management in the Western United States:
Chapter 6 – Cumulative Effects of Fuel Treatments on Channel Erosion and Mass Wasting.
USDA, US Forest Service. RMRS-GTR-231.
Swanston, D., Dyrness, C. 1973. Stability of Steep Land. Journal of Forestry.
USFS 2002. Horse Creek Ecosystem Analysis. Klamath National Forest, November 2002.
Johnny O’Neil Geology Report
29
Appendix A- Regulatory Framework
The following statutory authorities govern geologic resources and services activities essential to
Forest Service programs:
FSM-2880.11 - Statutory Authority
1. Organic Administrative Act of June 4, 1897, as Amended (30 Stat. 34, as Supplemented
and Amended; 16 U.S.C. 473-478, 482-482(a), 551. (FSM 2501.1.) This act authorizes the
Secretary of Agriculture to issue rules and regulations for the occupancy and use of the
National Forests. This is the basic authority for issuing special use permits for the collection
of vertebrate paleontological resources for scientific and educational purposes on National
Forest System lands.
2. Preservation of American Antiquities Act of June 8, 1906 (34 Stat. 225; 16 U.S.C. 431 et
seq.). (FSM 2361.01.) This act authorizes permits for archeological and paleontological
exploration involving excavation, removal, and storage of objects of antiquity or permits
necessary for investigative work requiring site disturbance or sampling which results in the
collection of such objects.
3. Federal Aid Highway Act (72 Stat. 913; 23 U.S.C. 305). This section of the United States
Code allows federal funding for mitigation of archeological and paleontological resources
recovered pursuant to Federal aid highway projects.
4. Multiple Use -- Sustained Yield Act of June 12, 1960 (MUSY) (74 Stat. 215; 16 U.S.C.
528-531). (FSM 2501.1.) This act requires due consideration for the relative values of all
resources and implies that the administration of nonrenewable resources must be considered.
5. Watershed Protection and Flood Prevention Act of August 4, 1954, as Amended (68
Stat. 666; 16 U.S.C. 1001). (FSM 2501.1.) This act authorizes the Secretary of Agriculture
to share costs with other agencies in recreational development, ground-water recharge, and
water-quality management, as well as the conservation and proper use of land.
6. Federal Water Pollution Control Act of July 9, 1956, as Amended (33 U.S.C. 1151)
(FSM 2501.1); Federal Water Pollution Control Act Amendments of 1972 (86 Stat. 816)
(FSM 2501.1), and Clean Water Act of 1977 (91 Stat. 1566; 33 U.S.C. 1251). (FSM
2501.1, 7440.1.) These acts are intended to enhance the quality and value of the water
resource and to establish a national policy for the prevention, control, and abatement of water
pollution. Ground water information, including that concerning recharge and discharge areas,
and information on geologic conditions that affect ground water quality are needed to carry
out purposes of these acts.
7. Wilderness Act of September 3, 1964 (78 Stat. 890; 16 U.S.C. 1131-1136).
(FSM 2501.1.) This act describes a wilderness as an area which may also contain ecological,
geological, or other features of scientific, educational, scenic, or historical value. These
geological features are generally identified for wilderness classification purposes.
8. National Forest Roads and Trails Systems Act of October 13, 1964 (78 Stat. 1089; 16
U.S.C. 532-538). (FSM 7701.1.) This act provides for the construction and maintenance of
an adequate system of roads and trails to meet the demands for timber, recreation, and other
Johnny O’Neil Geology Report
30
uses. It further provides that protection, development, and management of lands will be under
the principles of multiple use and sustained yield of product and services (16 U.S.C. 532).
Geologic conditions influence the final selection of route locations.
9. Wild and Scenic Rivers Act of October 2, 1968 (82 Stat. 906 as Amended; 16 U.S.C.
1271-1287). This act states that it is the policy of the United States that certain selected rivers
of the Nation which, with their immediate environments, possess outstanding scenic,
recreation, geologic, fish and wildlife, cultural, or other similar values shall be preserved in
free-flowing condition.
10. National Environmental Policy Act of January 1, 1970 (NEPA) (83 Stat. 852 as
Amended; 42 U.S.C. 4321, 4331-4335, 4341-4347). (FSM 1950.2.) This act directs all
agencies of the Federal Government to utilize a systematic interdisciplinary approach which
will ensure the integrated use of the natural and social sciences in planning and in decision
making which may have an impact on man's environment. Geology is one of the applicable
sciences.
11. Mining and Minerals Policy Act of December 31, 1970 (84 Stat. 1876; 30 U.S.C. 21a).
This act provides for the study and development of methods for the disposal, control, and
reclamation of mineral waste products and the reclamation of mined lands. This requires an
evaluation of geology as it relates to ground water protection and geologic stability.
12. Endangered Species Act of 1973 (ESA) (87 Stat. 884, as amended; 16 U.S.C. 1531-1536,
1538-1540). This act provides for the conservation of endangered and threatened species and
their habitats.
13. Archeological and Historical Conservation Act of 1974 (AHCA) (88 Stat. 174; 16 U.S.C.
469). (FSM 2361.01.) This act requires all Federal agencies to notify the Secretary of the
Interior when a construction project threatens to irreparably harm or destroy significant
scientific, prehistoric, historic, or archeological data. The paleontological resource may have
significant scientific and historic value.
14. Disaster Relief Act of 1974 (88 Stat. 143; 42 U.S.C. 5121, 5132). Section 202(b) states that
the President shall direct appropriate Federal agencies to ensure timely and effective disaster
warnings for such hazards as earthquakes, volcanic eruptions, landslides, and mudslides. The
Federal Register, Vol. 42, No. 70 of April 12, 1977, "Warnings and Preparedness for
Geologic Related Hazards," implies coordination with the U.S. Geological Survey in such
warnings.
15. Forest and Rangeland Renewable Resources Planning Act of August 17, 1974 (RPA) (88
Stat. 476; 16 U.S.C. 1600-1614) as Amended by National Forest Management Act of
October 22, 1976 (90 Stat. 2949; 16 U.S.C. 1609). (FSM 1920 and FSM 2550.) This act
requires consideration of the geologic environment through the identification of hazardous
conditions and the prevention of irreversible damages. The Secretary of Agriculture is
required, in the development and maintenance of land management plans, to use a systematic
interdisciplinary approach to achieve integrated consideration of physical, biological,
economic, and other sciences.
16. Resource Conservation and Recovery Act of 1976 (RCRA) (90 Stat. 2795; 42 U.S.C.
6901) as Amended by 92 Stat. 3081. This act, commonly referred to as the Solid Waste
Disposal Act, requires protection of ground water quality and is integrated with the Safe
Drinking Water Act of December 16, 1974, and Amendments of 1977 (42 U.S.C. 300(f)).
(FSM 7420.1.)
Johnny O’Neil Geology Report
31
17. Surface Mining Control and Reclamation Act of August 3, 1977 (SMCRA)
(30 U.S.C. 1201, 1202, 1211, 1221-43, 1251-79, 1281, 1291, 1309, 1311-16, 1321-28). This
act enables agencies to take action to prevent water pollution from current mining activities,
and also promote reclamation of mined areas left without adequate reclamation prior to this
act.
18. Archaeological Resource Protection Act (ARPA) October 31, 1979 (93 Stat. 721; 16
U.S.C. 470 aa). This act protects archeological resources, and prohibits the removal, sale,
receipt, and interstate transport of archeological resources obtained illegally from public
lands. Archeological resources include paleontological resources in context with
archeological resources. Also, this act authorizes the Secretary of Agriculture to issue permits
for archeological research, investigations, studies, and excavations.
19. Comprehensive Environmental Response, Compensation and Liability Act of 1980, as
amended (CERCLA) (94 Stat. 2767; 42 U.S.C. 9601, et seq). This act provides authority to
the Environmental Protection Agency and to other federal agencies, including the United
States Department of Agriculture, to respond to release of hazardous substances, pollutants,
and constituents. It also provides for joint and several liability to potentially responsible
parties (PRPs) for cleanup costs of existing water contamination. See also FSM 2160.
20. Federal Cave Resources Protection Act of 1988 (102 Stat. 4546; 16 U.S.C. 4301 et seq). This act provides that Federal lands be managed to protect and maintain, to the extent
practical, significant caves.
FSM-2880.12 - Executive Orders
The following Executive Orders provide direction for geologic resources and services activities
on National Forest System lands:
1. Executive Order 11593, Protection and Enhancement of Cultural Environment, May
13, 1971 (3 CFR 559, 1971-75 Compilation). This Executive Order directs agencies to
preserve, restore, and maintain the historic and cultural environment of the Nation.
2. Executive Order 12113, Independent Water Project Review, January 5, 1979. This
Executive Order requires an independent water project review by the Water Resources
Council on preauthorization reports and preconstruction plans for Federal and federally
assisted water and related land resource plans. The technical review will evaluate each plan
for compliance with the Council's principles and standards, agency procedures, other Federal
laws, and goals for public involvement.
Other Management Directives
1. Klamath National Forest Land and Resource Management Plan (LRMP): The KNF
LRMP Geology Standards and Guidelines provide a framework for the geologic resources
and hazards evaluation and geologic report content. The geologic hazards include naturally
occurring asbestos and unstable lands. The geologic resources outlined in the Standards and
Guidelines include rock sources, cave resources, and water. The LRMP also includes the
Aquatic Conservation Strategy (ACS) (Appendix A) which emphasizes a watershed-based
Johnny O’Neil Geology Report
32
analysis of the effect of existing and proposed activities in the watershed on water quality
(including sediment delivery).
2. Klamath National Forest Sufficiency Standards for Geology: This suite of guidelines
outlines the goals and standards for evaluating geologic hazards and resources on National
Forest lands (Appendix B). The goals of the assessments are to assure we:
1. Manage for Aquatic Conservation Strategy Objectives.
2. Protect water quality and quantity to meet State and Federal water quality standards,
Forest Service policy and 2880 manual direction.
3. Protect public health, safety, welfare and property from geologic hazards on National
Forest System Lands.
4. Protect geologic resources (minerals, groundwater, geothermal power, rock aggregate,
Geologic Special Interest Areas, and caves) from being adversely affected by land
management activities.