John Arthur
PIXEL Project status [email protected]
April 7, 2005
Status of the Proposed PIXEL ProjectJohn ArthurSSRL/SLAC
Photon Instrumentation
for
X-ray Experimentsat
LCLS
John Arthur
PIXEL Project status [email protected]
April 7, 2005
Boundary conditions that define the PIXEL projectLCLS construction scheduleDOE funding profileLCLS science thrusts endorsed by SAC
Organization of the PIXEL projectOrg chartPhased approach
John Arthur
PIXEL Project status [email protected]
April 7, 2005
LCLS Construction Schedule
NEH beneficial occupancy June 2007
FEH beneficial occupancy September 2007
First electrons through undulator May 2008
Begin LCLS operations phase April 2009
John Arthur
PIXEL Project status [email protected]
April 7, 2005
PIXEL possible funding profile
Asking for a total of $50-60M extending over FY06-FY12. About $18-22M would arrive in FY06-08. The funding profile is still being worked out with BES; nothing is certain yet.
John Arthur
PIXEL Project status [email protected]
April 7, 2005
The LCLS Science Thrust Areas
Coherent scattering at the nanoscale (XPCS)
Atomic, Molecular, and Optical Science
Pump/probe diffraction dynamics
Pump/probe high-energy-density (HED) science
Nano-particle and single-molecule (non-periodic) imaging
John Arthur
PIXEL Project status [email protected]
April 7, 2005
BES approach to the Thrust Areas
AMO science will be included in LCLS construction project
HED science deemed to be outside the mission of BES
John Arthur
PIXEL Project status [email protected]
April 7, 2005
Proposed PIXEL Scope
Build instruments that address the 3 remaining Thrust Areas
within BES mission
Include one additional instrument, for soft-x-ray coherent
imaging of magnetic domains (also endorsed by SAC)
John Arthur
PIXEL Project status [email protected]
April 7, 2005
DOE BES project requirements
PIXEL will be a major item of equipment (MIE) procurement project
Not a line-item in the DOE budget
Can include construction funding and R&D funding
Must build distinct instruments, separate from what LCLS builds
Assume all new rules for BES project management apply
John Arthur
PIXEL Project status [email protected]
April 7, 2005
PIXEL organization
Keith HodgsonSSRL Director
Jerry HastingsSSRL Asst. Dir for LCLS Science
John ArthurPIXEL Project Director
TBDPIXEL Project Chief Engineer
BudgetES&HPMCS
DatabasePurchasing
Administration
Engineering&
Development
4-5 Engineers2-3 Designers
Inst #1Instrument Scientist
Inst #2Instrument Scientist
Inst #3Instrument Scientist
Inst #4Instrument Scientist
LCLS Science Teams
John Arthur
PIXEL Project status [email protected]
April 7, 2005
Why a phased approach is needed
Each instrument costs $12M-$15M
Funding profile provides ~$22M maximum by end of FY08
So at most two instruments can be funded through FY08
John Arthur
PIXEL Project status [email protected]
April 7, 2005
What will $12M-$15M buy?
Controls (including laser timing)+ComputersSlitsFlight pathValves/windows/pumpsKB focusing system (1 µm and sub-µm options)X-ray pulse split+delay with tableCrystal monochromator with tableDiffractometer with tableOptical table for laserLaser PPSLaser system (10 mJ Ti:sapphire plus OPA)Laser diagnosticsX-ray diagnostics2d detector
Typical PIXEL“instrument”
+
PEOPLE
John Arthur
PIXEL Project status [email protected]
April 7, 2005
The phased approach
Build two instruments in Phase 1, plus a prototype 2d detector
Have Phase 1 instruments able to use first light (summer 2008)
Start to roll Phase 1 science resources onto LCLS ops in 2009
End Phase 1 in 2009-2010 time frame
Begin Phase 2 in 2009, hire additional scientists
Phase 2 includes two instruments plus additional detectors
Finish Phase 2 in 2012
John Arthur
PIXEL Project status [email protected]
April 7, 2005
Proposed Project Milestones
CD0 (Statement of mission need, beginning of project) mid 2005
CD1 (Completion of conceptual design) mid 2006
CD2a (Baseline costs of Phase 1) late 2006
CD3a (Begin construction of Phase 1 mid 2007
CD4a (Finish Phase 1) 2009-2010
CD2b (Baseline Phase 2) 2008-2010
CD3b (Construction Phase 2) 2009-2010
CD4b (Finish Phase 2) 2012
John Arthur
PIXEL Project status [email protected]
April 7, 2005
Phased Scheme Presented to LCLS
Science Team Leaders
Not yet approved by SAC, for
discussion only
John Arthur
PIXEL Project status [email protected]
April 7, 2005
Far Experimental Hall
Near Experimental Hall
Soft X-ray StationAMO Physics (funded by LCLS)
Hard X-ray Diffraction StationPump-probe dynamics (funded by PIXEL)XPCS (funded by PIXEL)
Hard X-ray Imaging StationCoherent imaging (funded by PIXEL)Extreme states of matter (funding?)
2008-9
Green applications do not have full capability, but can do preliminary experiments
John Arthur
PIXEL Project status [email protected]
April 7, 2005
Far Experimental Hall
Near Experimental Hall
Soft X-ray StationAMO PhysicsMagnetic imaging
Hard X-ray Diffraction StationPump-probe dynamics
Hard X-ray Imaging StationCoherent imaging
by 2012
Hard X-ray StationExtreme states of matter(assumes funding found)
Hard X-ray Diffraction StationXPCS
John Arthur
PIXEL Project status [email protected]
April 7, 2005
SummaryThe funding profile constraints on the PIXEL project,
along with the LCLS schedule, indicate that a phased
approach is needed
Two instruments in Phase1, two in Phase2, along with a
detector development program
Funding for this project is lean, especially in the first
years
Strong support from the Science Teams will be needed