jodl1pu1-(raj.), road rouse circuit 6-wcst pmel nagar, lf...('t) provision of mines act, l 952...
TRANSCRIPT
30
Govcmmeul of Rajasthan Office of Spudtg. Mining Engineer, Depar1ment of Mines and Geology, Jodhpor Circle. Jodhpur.
6-Wcst Pmel Nagar, Circuit Rouse Road Jodl1pu1-(Raj.), Tclepnonc ~o.-029 1 -2510746, Fm< No.- 0291-2.517418
No.SME/JO/CC/Jodhpur/Mhior/M.L./11011993/ lf o~L__-To,
Shri Bankat LaJ Modi SJO Shri Jaidev Modi, RIO Modi Building, Sojat Road, Pali Dist.· Pali (Raj).
[}.1ted:~~
Sub: Approval of Mining Piao \\lirh Pr<>gressive Mine Clousre Plan in respect of Mjning Lease for Mineral Limestone (Burning) near village Barna , Teh.sil Bilara, District JodJ1pur for an area of 6625 Hect. Submitted under Rule 37 (G) & 37 (E) ( vj) of MMCR 1986.
Dear Sir, ln exercise of the powers conferred by the clause (b} of sub-section (2) of settion 5 mines and
mineral (regulation & Development) act, 1957 read with the Government oflndia order No. GSR 743 (E) dated 25-09-2000 arid GSR 3 l (E) dat~d 22-01-2001 and GSR 55(E) dated 17-01-2000, I hereby APPROVE the above said Mining Plan Willi Progressive Mine Clo us re P lan. This approval is subject to the following conditions:-(D The Mining Plan With Progressh·e )1ine Clousre Plan js approved without prejudice to any
other laws applicable to the mine/area from time to time whether made by the Central Government, Stace Government or any other authority.
(ii) lt .i.5 clarified Lbat the approval of your afotesaid Mining Plan With Progressive Mine Clousre Plan does not in any way imply the approval of the Government in terms of any other provisions of the Mines and Minerals (Regulatron and Development)Act, 1957 or the Rules framed thereunder and any other laws.
(iii) It is further clarified that approval of the Mining Piao Wilh Progressive Mine Clousre Plan is subject to the provisions ofForest (Conservation) Act, 1980, Forest (Conservation) RuJes, 19& I ane Enovironment (Protection) Act, l 986 and o tber relevant statutes. orders and guidelines as ma)' be applicable to the lease from frme to time.
(iv) The Mining Plan With Progressive Mine Clousre Pinn is approved without prejudice to any order or dirt"ction from ?.ny Court nf com;Jete:l! ju.~d icl!r.::.
('t) Provision of mines Act, L 952 aitd rules & Regulations ruade there Uilder including subrnjssion of notice of opening appointment of manager and other statutory officials as required by the mines Act, 19>2 shall be compUed witb.
(vi) The lessee should submit financial assurance as requited under mle 23 F (3) of the amended MCDR 1988.
Two copies of lhe approved Mining Plan Wi!h Progressive Mine Clousre Plan are being sect to your RQP as advised in i;onsent letter.
No. Datetl: Copy forwarded for kind info1mation to:
1. The Regiooal Controller of Mines, Ajmer Region, IBM, Makhuqpura fod ial Estate, Ajruer 30S008. 2. The Director of Mines Safety, Directorate Ge11eral of Mines Safo1y, Aj er. 3. Shri Sawai Singh Rajpurnhit (RQP) Clo Pramod Kuwadia Shop no 3-4, ;:isemant Utkarsb Plaza
Near Sanischarji Ka Than Jodbpur, Along with rwo copies of approved Min g Pl:io \\'ith Progressive Mine Clousrc Plan
4. Guard file.
SUPDTG. MINING ENGINEER, Jodhpur Circle, JouJ1pur
MINING PLAN
WITH
PROGRESSIVE MINE CLOSURE PLAN
(Rajasthan Minor Mineral Concession rules, 1986 & second amende
For Working Lease]
OF
LIMESTONE(Burning), M.L. 11011993 VILLAGE- BARNA,
TEHSIL- BILARA, DISTRICT JODHPUR, STATE RAJASTHAJ'I
LEASE AREA 66.25 Hect. (FOREST NIL, NON-FOREST NIL Hect)
PERIOD OF LEASE FROM 21-01-1994 TO 30 YEAR
APPLICANT /LESSEE
Shri Bankat Lal Modi SI o Shri Jaidev Modi
R/o- "Modi Building" Sojat Road,Pali
Dist. Pali (Rajasthan)
PREPARED BY
Sawai Singh Rajpurohit
RQPISME/Jodhpur/2014101
Valid Upto 26.03.2019 (K P. CONSULTANT)
Clo Pramod Kuwadia,
Shop No. 3~4, Basemant, Utkarsh Plaza, Near Sanischarji Ka Than, Jodhpur (Raj)
Tel.- 0291-2630067, 9983311406, 9785011406
E-mail:- [email protected]
INDEX
S.NO. DESCRIPTION
I. GENERAL
2. LOCATION AND ACCESSIBILITY
3. GEOLOGY AND EXPLORATION
4 MINING
5. BLASTING 17
6. MINE DRAINAGE 19
7. STACKING OF MINERAL REJECTS 20
AND DISPOSAL OF W ASTEE
8. USE OF MINERAL 21
9. OTHERS 22
I 0. MINERAL BENEFICIAT!ON 23
11. ENVIRONMENT MANAGEMENT PLAN 24
·1 12 ANY OTHER INFORMATION 31
13. PROGRESSIVE MINE CLOSURE PLAN 32-42
LIST OF PLATES
S. No. PARTICULARS PLATE NO. SCALE I
1. M.L. AREA MAP I l:SOOOO
I 2. I LOCATION MAP 2 I :SOOOO
3. SURFACE PLAN ' 3 1:2000
4. SURFACE GEOLOGICAL PLAN AND 4 1 :2000
·SECTIONS
S. YEAR WISE PART WORKING PLAN 1: !000
' AND SECTIONS
!YEAR I
SA
II YEAR 5B
III YEAR SC
i IV YEAR SD
VYEAR SE
6. ENVIRONMENT PLAN 6 1 :SOOO
7. . CONCEPTUAL PLAN 7 1 :2000 I ' I
8. PROGRESSIVE MINE CLOSURE I 8 l :2000 ' i
PLAN I
i
LIST OF ANNEXURES
S.NO. PARTICULARS ANNEXURENO.
1. PHOTOCOPY OF RQP CERTIFICATE I
2. PHOTOCOPY OF LEASE DEED II
L_ .. ~-~' _PH_o_To_co_P_Y_o_F_D_EMA ___ R~AT!?_N_R_EP_o_R_T_~ __ n_I __ ~
AUTHORISATION LETTER BY THE APPLICANT/ LES
I Bankat Lal Modi lessee hereby authorize Shri Sawai Singh ; ,,., ' '
RQP/SME/JODHPUR/2014/01 to prepare the Mining plan including PMCP Uride!')l.ule (s) 37 (F), '~~ '• ·,>>
of Rajasthan Minor Mineral Concession rules 1486 & second amended Rule 20·l6._ ~ __ respect
of BARNA M.L. No.110/1993 Survey No over an area of 66.25 hect for mineral(s) Lime
(Burning )Mine Village BARNA Tehsil Bilara District Jodhpur State Rajasthan of Shri Bankat
Lal Modi.
I request the Department of Mines & Geology, Supriedenting Mining Engineer,
Jodhpur to make further correspondence regarding modification/withdrawl/re-submission and to
collect the approved copies of the aforesaid Mining Plan with PMCP with the said recognized
person on his following address:
Name of RQP Sawai Singh Rajpurohit
Registration no. RQP/SME/JODHPUR/2014/01
Validity till 26.03.2019
Address ofRQP K. P. CONSULTANT Clo Pramod Kuwadia. Shop No. 3-4, Baseman!,
Utkarsh Plaza, Near Sanischarji Ka Than, Jodhpur (Raj) E-mail:- [email protected].
Place:Jodhpur Shri Bankat Lal Modi Name of Applicant
M-9983311406,97850-11406, E-Mail : [email protected],
K~P.
CERTIFICATE
I/We, Sawai Singh Rajpurohit hereby certify that
I. The Provisions of Rajasthan Minor Mineral Concession rules 1486 & second
amended Rule 2012 have been observed in the Mining Plan including Progressive Mine
Closure Plan for BAR.i'lA M. L. No.110/1993 Survey No av.er ~ area of 66.25 hect for
mineral(s). Lime Stone (Burning )Mine Village BARNA Tehsil Bilara District Jodhpur
State Raja".!\than of Bankat Lal Modi and wherever specific permissj-On is required the
Applicant/lessee will approach the concerned authorities of Department of Mines &
Geology, for Granting the permission."
2. It is also certified that provisions of Mines Act, Rules and Regulations made there under
have been observed in the aforesaid Mining Plan including PMCP and wherever specific
permissions are required the applicant/lessee will approach the Director General ofMiiles
Safety.
3. It is further certified that the aforesaid Mining Plan including PMCP is prepared as per
the copies of the records and documents provided by applicant /lessee and Information
given as per discussions held with applicant/lessee/his representative
4. lt is also certified that the information furnished in the aforesaid Mining Plan including
PMCP are true and correct to t the best of my/cAr Knowledge &Belief and 1ncase of
default the approval would be withdrawn. '{l Place: Jodhpur Dated s~?cs) ofRQP
Sawai Singh Rajpurohit
RQPRegistrationNo.
RQP/SME/JODHPUR/2014101
RQP Validity 26.03.2019
CERTIFICATE
.<::~, ,/A'4 . <;'A,, .. "'
;:;,.,\..' .,;·'""""''"<::·· \ ~ •, ·' ~ ,,< ''<:';~. '/;. // ,;;>··,~ '-
;: v/.' . ,,. }( !;r :
1. It is certified that the provisions of Mines Act, Rules and Regulations mad,,.~~ under have
been observed in the Mining Plan with Progressive Mine Closure Plan {Of: BARNA M.L. ·\ ,,-,
No.110/1993 Survey No over an area of 66.25hect for mineral(s) Lime Sto'ne (Burning . . )Mine Village BARNA Tehsil Bilara District Jodhpur State Rajasthan ofShri Bank-at'Lal~\,~,,.
Modi and wherever specific permissions are required, the applicanVlessee will approa~:\;\'- -
Director General of Mines Safety. Further the standards as prescribed by DGMS in respect
of miner's health will be strictly l1nplementecL
2. The Progressive Mine Clouser Plan for BARNA M.L. No.110/1993 Survey No over an area
of 66.25 hect for mineral(s) Lime Stone (Burning )Mine Village BARNA Tehsil Bilara
District Jodhpur State Rajasthan of Bank:at Lal Modi., complies all the Statutory Rules
,Regulations, order made by the Central Government or State , Statury orgarrizations,Court
etc. and have been taken into consideration. Wherever any specific pennission is required,
the applicant/lessee will approach the concerned authorities.
Place:Jodhpur Shri Bankat Lal Modi Name of Applicant
ID . 'z:y:V~-
Si gnatlltej
DECLARATION
.6/~ifc .· 1/i:>'" •.. (~-;,.,..---~-li A._;,); /.f'
-'f"-f,,.•/ ;/C:Y j -i c:- i
The Mining Plan including Progressive Mine Closure Plan For BARl~A M.L. NW.~0/1993 Survey ';:'.: i
No over an area of 66.25 hect for mineral(s) Lime Stone (Burning) Mine Villake-J!ARNA Tehsil ... Bilara District Jodhpur State Rajasthan of Shri Bank.at Lal Modi has been prepru:ed in full
consultation with me and I understand its contents and agree to implement the same in-3:c~o~d~~~\";Y" -_.,,,,,..' - ,t;
with law and in case of default the approval would be withdrawn. ·-- ->· - -',! '·
Place:Jodhpur Shri Bankat Lal Modi Name of Applicant
~ Signature
UNDERTAKING
I. Bankat Lal Modi on behalf of lessee/applicant for BARNA M.L. No.110/
over an area of 66,25hect for mineral(s) Lime Stone (Burning )Mine Village B
-1-ehsil Bilara District Jodhpur State Rajasthan hereby under take that all the com
so made in the aforesaid Mining Plan w-ith PMCP by the RQP Sawai Singh Rajpurohit to
be deemed to have been made with my Knowledge and consent and as such shall be
acceptable to me and binding on me in all respects.
2. I Bankat Lal Modi on behalf of BARNA M.L. No.110/1993 Survey No over an area of
66.25hect for mineral(s) Lime Stone (Burning )Mine Village BARNA Tehsil Bilara
District Jodhpur State Rajasthan hereby also undertake that all the measures proposed in
this Progressive ?vfine Closure Plan will be implemented within one year/ in a time bound
manner from the date of approval of this PMCP as proposed.
3. l Bank.at Lal Modi further undertake that information and requisite plates as required under
CCOM's Circular No.2/10 regarding provisions of fixing of boundary pillars, Geo
referenced Cadastral Map/rJining lease map etc., shall be submitted within 180 days from
the date of approval of -chis document comprising "Mining Plan with Progressive Mine
Closure Plan For the aforesaid lease Area/mine,
Place:Jodhpur Shri Bankat Lal Modi
Name of Applicant
I.GENERAL
1.1. Name & Address of Applicant
Shri Bankat Lal Modi, S/o Shri Jai Dev Modi
Rio -"Modi Building" Sojat Road Dist Pali
1.2. Status of Applicant
Private Individual
1.3. Mineral Which Applicant Intend to :Mine
Limestone (Burning)
1.4. Period for Which the Mining Lease is Granted I Renewed
Mining lease was granted to Shri Bankat Lal Modi, for 30 years from date of registration
i.e21.0l.1994 to30Years.
The photocopy of lease agreement is enclosed as Annexure No. I
1.5. Name of RQP Preparing the Mining
Sawai Singh Rajpurohit,
Registration No.- RQP/SMEIJODHPUR/2014/01
Address- (K. P. CONSULTANT)
Clo Pramod Kuwadia,
Shop No. 3-4, Baseman~ Utkarsh Plaza,
Near Sanischarji Ka Than, Jodhpur (Raj)
E-mail:- [email protected]
Certificate valid till 26.03.2019.
Certificate is enclosed annexure I.
llillft•r '!ll'lf ~ 1-~ ~ ~' !li', lli'l!i::J'I: .
1.6. Name of Prospecting Agency
No prospecting agency was engaged. Applicant himself opens and develops the pits after
granting the mining lease. There are seventeen working pits in the lease area.
1. 7. Reference No. And Date of Consent Letter From The State Government
This Mining Plan has been prepared, (Under Rule 37 (B) & 37 (E) (vi) of Rajasthan
Minor Mineral Concession rules, 1986 & second amended Rule 2012)
2
2. LOCATION AND ACCESSIBILITY
A) Details of Area (With Location Map) Enclosed as plate no. 2
District & State -Jodhpur, Rajasthan
Tehsil (Taluka) - Bilara,
Village- Barana,
Mining Lease Area -66.25 Hectare
Whether the area is recorded to be in forest (Protected, Reserved etc.)
No, the area does not fall in forest land.
Owner Occupancy -All land is Govt. Waste Land.
Top sheet No: - The lease area falls in Survey of India Topo sheet no. 45 F/12
Infrastructure :-
Existence of public road I railway, if any nearby and approximate distance-
Barana Limestone Deposit is situated on the Bilara- Sojat City road (Major State
Road), 15 km from Bilara. Bilara is approximately 80 km SEE of District HQ Jodhpur
and at about 64 km north of Pali. The limestone deposit is well connected to Jodhpur,
Beawar, Pali, Sojat city and Ajmer. Sojat City is on the NH-14 (Beawar-Pali-Sirohi-
Kandla) which joins NH-65 (Ambala-Hissar-Churu-Pa1i) near Pali and NH-8 (Delhi-
Jaipur-Ajmer-Udaipur-Ahmedabad-Mumbai) at Beawar. The nearest Airport is Jodhpur
and the nearest Sea port is Kandla in Gujarat which is approximately 600 km. The
Beawar-Kandla National Highway passes through Sojat City, which is 45 km from the
Barana-Harsh Limestone Deposit.
Bilara is the nearest rail head, about 15 km from the deposit on the Jodhpur-Pipar
City-Bilara broad gauge section of the North-westen1 Railway .
................................ J
Land use pattern (Forest, Agricultural, Grazing, Barren etc.)
The entire 66.25Hectare land is Govt. Waste land.
B) Attach a general location and vicinity map showing area boundaries and existing
and proposed access routes. It is referred that the area be marked on a survey of
India topographical map or a cadastral map or forest map as the case may be.
Ho\vever if none of these are available, the area should be shown in plan.
Location plan enclosed as Plate No. 2
4
PART-A
3. GEOLOGY AND EXPLORATION
3.1. Physiography
The M.L. area under M.L. is having mostly undulating topography. The highest counter
in the area is 324mRL and the lowest counter is 300.0mRL. There is no public well with
in the M.L. area. There is no water channel bodies in the area. There are two small
seasonal nallas flowing in the area. The general sloop of the area is in all direction. The
rainwater spread out in the area & nearby areas. The villayati and deshi babool trees are
scattered in and around of the area. The grollild water level is moderated depth with
average depth of 60 to ?Omts below the surface and ground water is somewhat hard and
salt tolrent crops can be grown. The common flora consists in and around the area of
Babul (Acaciaratica), Neem (Azadirachta indica) and thorny bushes.
No forest area falls within the lease area
3.2 Regional Geology
The limestone deposit is a part of the nearly N-S oriented limestone belt of Bilara
Group of Marwar Supergroup that extends from Sojat in the south through Bilara to
Gotan in the north from where it takes an ENE trend upto Mundwa_ The general
stratigraphic sequence is given as below:
I Recent to Sub Recent i Alluvium and blown sand duUe-Sandstone and Clay -~
f---·~-----------~~~~~~~"'------------ ' ____ -------------------------Unconformity -----·--::------------ 1
I Marwar Group
~gaur Group Taniklian Sandstone I (Upper --------Unconformity-------1 Arenaceous Nagaur Sandstone \ Rocks)
Super ! Bilara Group I (Calcareous I Rocks)
! Pondlo Formation ~ Dolomite, Dolomitic [ -
1
: limestone, Cherty dolomite, Siliceous oolites. i
Gotan Formation - Limestone with bands of I i chert and dolomite I ! Dhanapa Formatio11 - Stromatolitic limestone, : I dolo1nite, dolomitic limesone, chert and cherty : i dolomite. I
~--- ---- ------- ---"- -- - " " ......... ----- -- - ----- _l__ -- - - -- ----------- '"'"--"·--------·· ------·-·· .. ··----·-~---- ·----~
5
--------------~---------------" -----~ Jodhpur Group I Girbhakar Sandstone
(Lower I Sonia Sandstone ' Arenaceous I Pokaran Boulder Beds
Rocks -------------------:--~:----------------- U nconf ormi ty ------------- ------ -----=--..::=:..---···
Basement Rocks General stratigraphic succession of Jodhpur district.
The limestone deposit under reference forms a part of the Gotan For1nation of the
Bilara Group that comprises predominately of limestone with bands of chert, siliceous
limestone and dolomite. The Pondlu and Dhanapa Formations are mainly dolomitic
limestone and dolomite. Apart from clay, the limestone is free from inclusions.
3.3 Local Geology
In the lease area the lime stone beds, which belong to the Pondlu formation of Bilara
group are horizontal indicating the absence of any tectonic effect.
Following geological setting in the areao
1. Soil
2. Limestone (Burning)
3. Siliceous Limestone (Partly area covered)
4. Dolomitic limestone
5. Limestone (Burning)
The limestone occur as alternate bands with siliceous limestone, dolomitic/high
MgO limestone layer by lay-er which arc clearly visible from the old working pits in the
Mining Lease Area of Barana Limestone Deposit. Clay is seen filled between the
magnesianldolomitic limestone and the limestone horizons. The percolating surface
water, along the cracks and crevasses, has carried the clay, therefore its deposition is
found to the extent of these cracks and crevasses, as developed in the area_
The magnesian limestone can be distinguished from the h-igh grade limestone
(bun1ing) 1n the field, on the basis of its physical characteristics. The
magnesian/dolomitic liinestone is yellowish brown in colour with shades of buff. It is
medium to coarse grained, thi11ly to thickly bedded compact and hard in nature. The high
6
-~' L¢ - ,r---"'~",,-. ___ •. ,,,o.·~, /~ /-~ ~---· ?\,•\ /;,.;· r ____ ._,,,.
'v( ·'·
grade limestone can be distinguished from the above on the basis of its «~r, which is
mostly gray to dark gray and the fine-grained. The siliceous limestone i~:·.(iark gray to
black coloured, coarse to medium grained, inter layered with dolomite limestone.
Description of the above formations is given below: -
Overburden alluvium - LOMts.
Hard dolomitic Limestone- 2.0Mts.
Limestone (Burning) 2.0 Mts
Hard dolomitic Limestone 2.0 Mts
Limestone (Burning) 6.0 Mts
Hard dolomitic Limestone 2.0 Mts
Limestone (Burning) 6.0 Mts
Partly area covered with Siliceous Limestone. It is waste rock to be removed_ Generally it
is of dark grey to black in colour. It often includes layers of dolomite limestone and
reddish in colour at places due to iron leaching often these have intruded into crevices.
There are seventeen working pits in the lease area. The size and litho units of various pits
are given below table -
i Pit No. Dimensions Litho units
Pit - I 94mx63mxl5.0m Soil: 1.0 Hard dolomitic Limestone: 2.0mts Siliceous Limestone -12mts.
Pit· 2 '5lmx34m~6m Soil: LO Hard dolomitic Limestone: 2.0mts Siliceous Limestone - 3mts .
. iPit-3 35mx25mx2.5m Hard dolomitic Limestone: 2.0mts
Limestone (Burning) - 0.Smts.
Pit~ 4 27mxl8mx3.0m Hard dolomitic Limestone: 2.0mts Limestone (Burning)- l .Omts.
I Pit~ 5 50mx48mx7.5m : Alluvium - LOMts
i Hard dolomitic Limestone: 2.0mts I Limestone (Bummg) -4.5mts.
Pit - 6 53mx26mx7 .Om Alluvium - 1.0Mts Hard dolomitic Limestone: 2. Omts Limestone (Buming)-4.0mts.
Pit - 7 ! 30mx22mx2.5m Alluvium - 1.0Mts I Hard dolomitic Limestone: l.Smts
Pit - 8 27mxl8mx2.0m Alluvium - l.OMts Hard dolomitic Limestone: 1.0mts
Pit - 9 20mxllmx2.0m Alluvium - 1.0Mts
I Hard dolomitic Limestone: 1.0mts
Pit-IO 30mx25mx4.0m Alluvium - l.OMts Hard dolomitic Limestone: 2.0mts Limestone (Burning) -1.0mts.
Pit-11 I 56mxl lmx2.0m I Alluvium - l.OMts · Hard dolomitic Limestone: l .Omts
• : Pit - 12 65mx28mx6.0m i Alluvium - 1.0Mts
Hard dolomitic Limestone: 2. Om ts Limestone (Buming)-3.0mts.
Pit - 13 62mx27mx6.0m Alluvium - l.OMts Hard dolomitic Limestone: 2.0mts
: Limestone (Burning)-3.0mts.
Pit - 14 80mx83mx5.0m Alluvium - l.OMts Hard dolomitic Limestone: 2.0mts Limestone (Burning) -2.0mts.
Pit-15 I 85mxl6mx4.0m Alluvium- 1.0Mts Hard dolomitic Limestone: 2.0mts Limestone (Burning) -1.0mts.
Pit - 16 36mx22mxlm Soil: 1.0 Siliceous Limestone - lmts.
I 'Pit-17 !02mxl3mxlm Soil: 1.0
Chemical Analysis report of the Limestone (Burning):
Calcium Oxide (CaO)
Magnesium Oxide (MgO)
Alumina (AL203)
Silica (Si02)
52.23%
01.56%
00.33%
03.03%
Chemical Analysis report of the dolomitic Limestone:
Calcium Oxide (CaO)
Magnesium Oxide (MgO)
Alumina (AL203)
Silica (Si02)
3.4. Exploration Work Done to Date
26.16%
9.58%
2.20%
05.33%
;
f
No formal prospecting works was done by any agencies in this M.L. area, applicant
himself open and develop the pits after granting the mining lease. There are seventeen
working pits in the lease area. Pit size and depth have been shown in above table.
3.5. Exploration Proposed to Be Carried Out in the First S Years
In order to confirm the present limestone in the promising area, certain amount of bore
hole necessary to delineate depth, grade and attitude of the limestone. It is proposed to
carry out following prospecting works in the next five years are given as below: -
Year Pronosed Bore Hole Location Depth II PBH-1 190N I 600W 50mts
III. PBH-2 200N I 200W 50mts IV. PBH-3 600N I 00 50mts v. PBH-4 600N / 600W 50mts
3.6. Reserves
On the basis of present working pits (limestone is exposed) area have been
considered under proved category reserves.
The depth for the limestone is considered 8.0mts on basis of present pits in & nearby
area.
The reserves are considered in proved category in depth as on basis of working mines in
the area to proved the mineral availability in the area in two beds.
9
3.6.1. Reser\•es Estimation
Proved Reserves
Based on previous expenence of similar type deposits exposed limestone has been .
considered under proved category of reserves. Area calculated is multiplied· by thickness
of the limestone bed to get the volume.
B. Probable Reserves
The area covered upto a further dip depth as well as along the strike direction fQ.( a further .. ~~~·
distance of SOmts from the block earmarked for the proved category of the reserves, has ~---- ~ --- ~ --- --
been used to compute the probable category of reserves.
C. Possible Reserves
Similarly area further 50mts extension has been considered under the possible .. reserves
category ofreserv~ ····
Reserves of limestone (Burning)
I Average I Category Area Thickness
Volume Tonnage ·---·-·----
Sqm. (m) Cum MT
I ! 2 3 4 5
Proved 362348 8 2898784 7246960
Mind out 48200 2 -96400 -241000 Reserves
Net Proved 2802384 I 7005960 I I
Probable 73718 8 589744 1474360
Possible 55465 8 443720 I !09300
Total 3835848 9589620 Bulk density is taken 2.5 tonne/cum
Reserve Dolomitic Limestone (as a waste)
Category Area Average Thickness Volume Tonnage
Sqm. (m) Cum MT Dolomitic 662500 6 3975000 9937500* Limestone Mind Out 73718 2 -147436 - 368590
Net Reserve 3827564 9568910
IO
• it is as a waste
UNFC code for reserve transcription limestone (Burning)
Classification ! Code I Q_uantity in M.T. __ I -- --
Total Mineral resources (A +B) I i 9589620 •. :;~·,;r·:·· Mineral Reserve :- ' a.
L Proved Mineral Reserves 111 7005960
2. Probable Mineral Reserves 121 & 122 1474360
b. Remaining Resources :-i
L Feasibility Mineral Resources 1211
2. Prefeasibility Mineral Resources 1221 &222 '
3. Measured Mineral Resources ' 331 I 4. Indicated Mineral Resources '332 1109300
5. Inferred Mineral Resources 333 1,
6. Reconnaissance Mineral Resources 334
The limestone produced in thts mine ts suitable for burning grade.
3.6.2 Mineable Reserves
Mineable reserve= Total reserve of proved & probable - (Reserve blocked in proposed
benches +Reserve blocked in barrier)
Total reserve"' 8480320 MT
Reserve blocked in banieF 6800X 8X 2.5~ l 36000MT
Reserve blocked in benches= 12500X 8 X 2.5 = 250000MT
Total reserve blocked= 386000MT
Then mineable reserve= 8480320 (proved+ Probable)- 386000 = 8094320MT
Total mineable reserves= 8094320MT
11
4.MINING
This mining plan is prepared for the mineral Limestone of mining M.L. area of
66.25 Hects. is based on consideration of following aspects_
• Information of the deposit based on the geological and surveying field work.
• Mining method.
• Different mining operations.(Drilling, Blasting, Mucking and Transportation)
• Future production targets.
4.1. Proposed Mining Method
The limestone is overlain by Alluvium with kankar, so to extract limestone it becomes
necessary to remove the overburden as well as soil. Since the deposit occurs at a depth of
3mts and the thickness of the deposit is sufficient to be economically mineable. Opencast
semi mechanize method is the suitable method for mining. The mining will be done by
making systematic benches. Road and ramps will be made at gentle gradient during
mining as per requirement. The height of the benches will be kept 3.0mts maximum in
overburden & 3.0mts in mineral and width of the benches will not be less than height.
The removal of the O.B. carried out as first bench is advanced to expose the limestone.
The limestone area in has a top covering of soil 3.0mts thickness. The O.B./l.B. is
re1noved and transported with the arrangement of trucks/dumpers and heaped separately.
The main development work will be the systematic benching. This benching will also
give the desired production of the limestone. The proposed production of limestone will
be 2,70,000 tons per year.
Proposed Year wise production
Year Limestone Limestone Sub grade I Waste/O.B./.I. R.0.M. marketable 10% (MT) B. (cum) (MT) 90% (MT) '
' '
[ vear 119525 107572.5 11952.5 83457
II vear 119045 107140.S ' 11904.5 74203 I
' III vear '
338737.5 304863.75 ' 33873.75 90330
' !Vyw 320107.S 288096.75 : 32010.75 640215 ' I I
. Vvear 418262.5 376436.25 41826.25 48595
Total '
B15677.5 1184109.75 131567.75 936800
12
4.1.l. Drilling '" The drilling will be done with the help of compressor and jackharrlfuer. In .this
mine the diameter of hole will be 32-34 mm and depth of hole will be kept from 0_8~i:~S·--3.3rn in a single hole.
4.1.2. Blasting
The hole will be blasted by using ANFO and SG 80 o/o. The detail of blast design
is given in chapter no. 5.
4.1.3. Loading and Transportation
Mechanical loading equipment as a small capacity excavator is deployed in
removal and loading of the limestone.
Transport from mine head to destination will be done by the trucks & dumper on hire
basis.
4.2. Composite Plan And Yearwise Section
Proposed working plan and sections are attached as Yearwise Working Plan and
Sections, Plate No. 5.
4.3. Plan Showing Pit Layouts, Dump, Sub Grade, Mineral Stack etc.
The proposed five-year working is shown in Plate No. 5. The Waste and soil will
be stacked separately inside the ML area where there is no planning in the present M.L.
period. There is sub-grade mineral will be generated will be stacked separately inside the
ML area.
4.4. Proposed Rate of Production and Expected Life of Mine -
The proposed rate of production for the first five years is 270000MT per annum.
Expected life of mine on the basis of proved & probable category of reserves from the
present targeted rate of production: 8094320MT/270000 = 29.97say 30years.
4.5. Conceptual Plan for The Entire Life of the Mine -
(1). Exploration: ~In order to confirm the present limestone in the promising area,
certain amount of bore hole necessary to delineate depth, grade and attitude of the
limestone. It is proposed to carry out following prospecting \ilorks :in the next five years
are given as below: -
Year Pronosed Bore Hole Location Den th II I PBH-1 190N / 600W 50mts III. PBH-2 200N /200W 50mts IV. PBH-3 GOON I 00 50mts v PBH-4 GOON /600W 50mts
(2). Reclamation: - At end of the life of mine total 34.45hectares excavated area, in which
about 12.35hactare area will be backfilled from excavated.
(3). Plantation: - Total 5.65hectares will be covered along the boundary barrier and road
for plantation by the end life of mine.
4.6. Open Cast Mines
4.6.1 Salient Features of Mode of Working
The mining will be entirely semi mechanization will be the drilling of the holes
through compressed air operated jackhammer. The proposals of mining for the next
five-year working are given on the benches up to 297.00MRL in mineral limestone.
The mineral production wili be started from the first year.
4.6.2 Description of layout of mine workings, the layout of faces and sites of
disposal of Waste (Refer Plate No. 5.)
The mining will be confined to a limited area during ext five years. The developme11t
and production plans and their sections have been prepared on l: I 000 scale. The
position of mine benches has been shown on Year Wise Development and Production
Plans, Plate No. SA & SE respectively for the first five years of mining operation.
The working for next five years is proposed in five pits namely pits no. 5 to l 0 in the
ratio of70:30 to maintain the RoM quality.
Soil, encountered during the mining operations during the exploitation of low grade
limestone only, will be re1noved by scraping/dozing, before exploitation of limestone,
with the help of excavator & dumper combination and stacked separately.
14
Year Bench
I vear
I
II
III
II vear
I
II
III
III vear
N
v
IV -vear
VI
Vvear
I
II
III
N
v VI
In the next five ·years of mining plan, each year about 2,70,000 MT-. _limestones will
be excavated. The bench wise calculations are given in table below:-
Productiou proposed & generation of Waste/soil/O.B. & Limestone il!'jC,~::'', ,.,,.,..- •'' _,,
next five years
Bench RL in Work. mts (average Area
RL.) (sqmt)
From To 310 309 27819
309 307 27819
307 305 23905
From To 310 309 25203
309 307 24500
307 305 23809
From To 305 303 45165
303 JOO 45165
From To 300 297 42681
From To 310 309 16351
309 307 16122
307 305 15929
305 303 15504
303 300 15035
300 297 14610
4.7. Underground Mining
Not applicable
Average Volume height (cum) (mts)
I 27819
2 55638
2 47810
Total
1 25203
2 49000
2 47618
Total
2 90330
3 135495
Total
3 128043
Total
1 16351
2 32244
2 31858
3 46512
3 45105
3 43830
Total
Grand Total
15
Limestone Limestone Subgrade O.B., RO.M, marketable 10°/o Waste (MT) 90% (MT) (MT) (cum)
27819
55638
119525 107572,5 11952.5
119525 107572.5 11952,5 83457
25203
49000
119045 107140,5 119045
119045 107140.5 11904.5 74203
90330
338737,5 304863,75 33873,75
338737.5 304863.75 33873.75 90330
320107,5 288096,75 32010,75 640215
320107.5 288096.75 32010.75 640215
16351
32244
79645 ! 71680,S 7964.5 I
116280 104652 11628
112762,5 I 0148625 11275,25
109575 98617.5 10957.5
418262.5 376436.25 41826.25 48595
509280 1184109.75 131567.75 203580
4.8. Extent of Mechanisation -
4.8.1. Drilling Machines
During Mining operations shall be carried out by following mining machineries
S.No. Name of the Machine Capacity Nos.
].
2.
13 4.
5.
6
' I Hydraulic Excavator/Loader
i Wagon drill
Jack Hammer
Tippers
Dozer
Water Sprinkler
* On hire basis
4.8.2. Loading Equipment
•
1.0 Cum. 2
lOOmm (4") dia 2
37 mm dia 2
9 tonne 5
- 2
5000 ltr. 1
Mechanical loading equipment as a small capacity excavator is deployed in
removal and loading of the limestone.
4.8.3. Haulage and Transportation equipment
a) Haulage within mining lease hold - From working faces mineral and Waste
shall be transported by tractor trolleys at pithead.
b) Transport from mine head to destination - Transport from mme head to
destination will be done by the trucks & dumper on hire basis.
16
5.BLASTING
The limestone and waste rock being medium hard category requires drilling and blas_ting
for excavation.
5.1. Broad Blasting Parameters
Depth ofHole-0.8 m to 3.3 m
Diameter of Hole - 32 mm to 34 mm
Blasting Pattern - The blasting pattern entirely depends on the situation of the joints
present in the rocks. The drilling is done as per t..1.e requirement of the block size to be
excavated.
Type of explosive and detonator used
a) Special gelatine 80 % as primer.
b) Ammonium nitrate with fuel oil (ANFO)
c) No.6 or No, 8 ordinary detonators with safety fuse.
Amount of charge per hole- Sp. GI. =125 gm. ANFO =375 gm.
Numbers of holes required per month - On average 20 holes of 1.5 m depth are
drilled per day.
Number of holes needed I month: 500 holes
Average requirement of explosive - Number of holes blasted per month 500
a) Sp. Gelatine 80 % ~125 gm X 500 ~ 62.50 Kg.
b) ANFO ~ 375 gm X 500 ~ 187.5 Kg.
Total explosive required per month - 250.00 Kg
Explosive needed per year (12 month):
a) Sp. Gelatine 80 % ~62.50 X l2 ~ 750 Kg.
b) ANFO ~ 187.5 X 12 ~ 3250 Kg.
17
5.2. Storage of explosive
The blasting shall be done daily. The explosive shall be handled by the blasting
party himself and the blasting will be done by the blasting contractor same as per the
present practice. Hence no storage of explosive is required at the site.
Precautions
The mining is done on the flat portion and though there is no human settlement in
that area, special precautions will have to be taken for the fly rock problem.. All the
adequate precautions as per provisions MMRl 961 will be taken.
i8
6. MINE DRAINAGE
A) The lease area is undulating topography. There is small seasonal nalla flowin
the area. As per study and available data from the nearby water bodies the likely depth of
water table (Pre monsoon) is about 70mts below ground level and 60 mts after monsoon.
B) The mineral availability and depth of working is at higher level i.e up to 20 mts from
ground level There is no chance of ground water in the pit.
C) It is the only rainwater, which may flow inside the pit from the surface. The flow of
water inside the pit may check by oonstructing a drain trench all around the working pit.
However the amount of water, which gets accumulated in the pit, may pump out as and
when required. The average rainfall in the area is 400mm.
19
7. STACKING OF MINERAL REJECTS AND DISPOSAL OF WASTE
7.1. Nature and quantity of topsoil, overburden and Wastee likely to be generated
during the first five years: -
Soil with kankar: - The soil with kankar spread most of the area having thickness of
l .Omts and is friable, moist in nature.
Dolomatic limestone: - Below the grit and kankar a Dolomatic limestone having
thickness of2.0mts and is friable, moist in nature.
Sub grade: - About l 0% of mineral is sub grade_
7.2. Selection of Dumping Site
The O.B)waste, and sub grade are generated during the five period of the mining plan are
given as below: -
!
Year Subgrade 10o/o ! WasteJO.B.11.B. (MT) (cum)
I year I 11952.5 ; 83457
II year ! 11904.5 ! 74203 III year . 33873.75 ' 90330 IV year i 32010.75 640215
Vvear ! 41826.25 48595
Total 131567.75 936800 Waste generated m the next five years, which will be separately stacked inside the area
near boundary pillar B', Waste will be stacked over an area about 2_15hect with 6m
height as shown in the Proposed Part -working plan, plate no. 5A to SE.
7.3. Maximum Height and Spread of Dump
The height and spread of Waste dumps that is likely to be stacked shall be
2.1 Shect with 6m height.
7.4. Stacking of Subgrade Mineral
Sub grade will be stacked separately and will not be mixed with O.B./waste and will be
backfilled. Retaining wall wiU be provided around the sub grade to prevent wash off &
spreads of the sub grade. Sub grade stack in next five years will be stacked inside the
lease area.
7 .5. Selection of Site and Spread for Stacking of Subgrade Mineral
Sub grade stack in next five years will be stacked inside the lease area near boundary line.
20
8. USE OF MINERAL \ ·~ ~/··
The 1imestone produced in this mine is suitable for burning and hard doIO:nlitiC ·Limes~ »,, ·, - "' ~ '
is as waste but partly used for construction of houses.
21
'
9. SITE SERVICES AND EMPLOYMENT POTENTIAL
9.1. Site Services
As per Mines Rules & Regulations following statutory site services shall be made
available: -
1. Office cum store: An office cum store has been provided at the mine area.
2. Water supply: Water for drinking purposes and for plantation will be arranged from
public water supply and for other purpose \\rill be arranged from surface water sources
from nearby areas by means of mobile tankers.
3. Electric supply: No electric po\\rer is required at mine site.
4. First Aid Facility: A first aid box with all necessary material is maintained at all the
times in the office at mine site.
9.2. Employment Potential
A) Management and Supervisory Staff
For safe and systematic mining sufficient technical and supervisory staffs will be
provided at mine site, which are detailed below:
S.No. Category Qualifications Type Requirement ---------
1. Mine Manager First class Cert. Holder . One 2 Mining Engineer B.E. Mining . One
3. Mine Foreman &
Certificate Holder One each Survevor
.
4. Mine Mate Certificate Holder Skilled 1 5. Chowkidar Ex-serviceman Semi-skilled 1
B) Labours
Small capacity excavator will be used for removal overburden & mineral, which will
reduce dependency of manual labour.
Excavator operator - 2N os.
Skilled - 4 Drillers,
Unskilled - 4 labors wili be requiring for miscellaneous jobs .
Total 301abour will be required.
22
10. MINERAL BENEFICIA TION
sizing will be carried out at site.
23
PART-B
11. ENVIRONMENTAL MANAGEMENT PLAi'<
11.1. Base Line Information -
a) Existing land Use Patte.-n -
This M.L. area is in the form of a undulating topography. The land use pattern in
Prescribed Performa is given below table.
Present Land Use Pattern of Area
! Forest Govt. Grazing i Was tee Others ! Total Land Acquired I
I Land Waste Land Land : Outside Lease 1
Land Area (if any) : i
ln llectares Pits & Quanies - 4.82 - - - I 4.82 -Dumps Of Ore - l.22 - - ! - I 1.22 -Waste & Over burden Infrastructure - 2.01 - - -
' 2.01 -
'Office &Workshon ' Township - - - - - -Others - - - - i - -Total Occupied Area - 66.25 - - I 66.25 i -Area back filled, If Not So Far 'nv Area afforested by About l50tress present in the area. mine owner
b) Water Regime-
There is no river or nalla flowing with in the M.L. area. There is no pond with in
the M.L. area. There is a one well outside the M.L. area for water requirements. The rain
water is the other source of the water within the area_ The average rainfall in the area is
750 - 850 mm annuaily. The water table lies at a depth of 60-70 m ffom ground level.
24
\ _,,_,
c) Flora and Fauna-
i) Flora - In general the growth of vegetation is poor in the area. Only- wild~;-~'"'-,
vegetation (given with local name), which includes Kair, Khejdi, Jal, Vilayati Baboo( -/
Neem and shrubs with thorny bushes, are found around M.L. area. The average tree
density of such trees is counted to be less than 2-3 trees per hect. In this region (in
general) the crops of coarse grains such as Bazra, Munge, Moth and Chana arc grown.
ii) Fauna - No camivoros animals are seen around 5 Kms.radius because there is no
wild life or games sanctuary is observed. Sometimes Rabbit, Wolf, Snakes are seen in the
area. The villagers also keep pet animals like Cow, Goat, Sheep, etc.
d) Quality Of Air, Water And Ambient Noise Level -
The quality· of air is natural, clean and free from any pollution as there is no
industry or any pollution source of air is present in vicinity of the area.
The quality of water which being used for drinking purpose at mine and at around
area is good.
The ambient noise level is within specified limit, as there is no permanent source of
noise generation present in and around M.L. area. Thus it is quite and calm.
e) Climate Condition -
Desertic climate with large variation of temperature and scanty rainfall are the
main characteristics of the climate of area. The area experiences temperature variation of
40° to 48° in summer and 5° to I 0° in winter season. Strong wind blows during the
summer seasons.
f) Human Settlement -
There is no human settlement within the M.L. area. No villages are close to
mining area. The rehabilitation and resettlement issues are not involved in the project.
25
g) Public building, places and monuments -
There is no national monument, place of worship, place of tourist interest,
sanctuary, national park and any public building has exist in and around the M.L. area
which could be affected by the mining activities being under taken in this area.
11.2. Environmental Impact Assessment.
Generally the mining activity leaves its impact directly or indirectly on the
adjacent environment. The mining activity as described within this mining plan of such
scale and nature that nD significant environments unbalance is or can be seen. As a result,
no adverse impact on environment and surrounding is likely to arise and the post~mining
scenario will not be.much affected.
However, assessment of various issues pertaining to environment in the identified
field, have been studied and given below.
a) Land environment
i) Landscape - The impact of proposed mining on the landscape of area would be the
degradation of land by cutting of surface, stacking of mineral, transportation of mineral
resulting 1n change 1n present topography. table.
Land Use Pattern of Area after fifth year
Forest Govt. Grazing Wastee Others i Total Land Acquired Land Waste I.and Land Outside Lease
Land Area (if any)
Jn Hl!(:tares
i Pits & Quarries ' 9.55 ' '
' 9.55 '
Dumps Of Ore - 3.37 - - ' I 3.37 '
Waste & Over burden ' Infrastructure ' 2.25 - ' '
I 2.25 '
(Office &~~ks~---· --···- ·-·-~- ' Township ' ' - ' - ' ' '
Others ' ' ' I '
' '
Total Occupied Area - 66.25 ' ' 66.25 ! '
Area back filled, If Nil •nv Area afforested by 1.25hect.
'
'
i
I ' _mine owner
''-"""- ' ' ·······-··- --·-"'"""····---··-·-··--------~-·--·--·-·--- -~·-·-'
26
( f£, l /<'"'- jf
ii) Aesthetic environment - The aesthetic environment cf th€:'~ will not ~~~y ' . .
adverse effect. Since the M.L. area is confined to remote area, whieli'.
populated, and there is no tourist spot, forest, water reservoir, wild life s
etc.within and around the M.L. area, so no adverse impact is envisaged on the aesthetic
environment.
iii) Soil And Land Use Pattern-The ML area is a soil with kankar covered, So this soil
with kankar will be used in plantation in purpose.
iv) Agriculture -AJI Land is Govt. Waste land so no agriculture land work is going in
the M.L. area
v) Forest- There is no forest land falling within the M.L. area.
vi)Vegetation-The area where mining operation and allied activities has been proposed,
it is devoid of vegetation and as such, that will not affect the flora within the mining area
and its surroundings.
vii) Public Building, Places and Monuments - There is no public building, cultural or
historical monument or place of worship exist in the M.L. area. Hence there w·ill be no
impact on them.
b) Water Environment -
i) Surface Water - The m1n1ng activities, including Waste dumping have been so
planned to prevent any of the disturbance to natural flow of water and also the drainage
system of the area will not be affected.
ii) Ground Water - The water table in the area is sufficiently below the ground level
(about 60-70 mts.). Therefore quantity as well as quality wise, the ground water in the
area is not likely to be affected at all by future mining activities.
iii) Quality Of Water-There will be no impact of mining on quality of water.
27
c) Air Environment-
i) Noise - There will be occasional sound of the compressors & Jackhammers and
operation of small capacity excavator and plying trucks/dumpers. To avoid this proper
maintenance of the m/c will be done and the earplugs shall be provided to the drillers.
ii) Air- Drilling will generate the dust in the air. This will affect the air environment.
Other than this, there will be some impact on quality of air at the time of machine
working & plying of trucks/dumpers may generate some dust, which will be under safe
limits. The applicant shall be use dry dust extractor if dust generation is more. Water
sprinkling may be also done.
iii) Climate Conditions -The mining activity will be such a small scale that there will be
no impact on climate conditions of the area.
d) Socio~ economic Environment-
i) Social and demographic Profile - Socially the region is backward. The mining
activities directly or indirectly will help in improvement of social behavior and living
status of the socially backward society of the area by giving better employment
opportunities. So ultimately, mining activity will cause uplifment of the social as well as
demographic profile.
ii) Occupational Health and safety- There will be no impact on health and safety of the
villagers.
iii) Human Settlement - There is no human settlement with in M.L. area. The human
settlement in the nearby areas is not likely to be effected rather it will encourage it on
account of possibility of getting employment at the mine.
iv)Recreational facility - There will be no impact on recreational facilities, as they are
not provided at the mine.
28
11.3 Environment Management Plan -
and to do so have following plan outlines. The effort will be made to mi .;:r
environment degradation due to mining operations in the area. below are the proposed
mitigation measures that will be taken to manage the environment in the area.
a) Temporary Storage and Utilization of Topsoil
The ML area is a soil with kankar covered, so this soil with kankar will be used
simultaneously in plantation in purpose.
b) Proposal For reclamation of Land Affected by mining activities during and at the
end of M.L. period
In the First five years, there is no proposal for reclamation of the land affected by mining
because no sufficient space for backfilling in the next five years.
At end of the life of mine total 34.45hectares excavated area, in which about 12.35hactare
area will be backfilled from excavated.
Total 5.65hectares will be covered along the boundary barrier and road for plantation by
the end life of mine
c) Programme of afforestation
Although the area is devoid of any forestland a phased plantation scheme has been
proposed in order to improve eco~system. It is proposed to plant 2000 trees every year in
the area near boundary line and along the road. The plants/trees are Khejdi, Jal, Babool
and Neem. So during the proposed five-year period about 10,000 trees will be planted in
an area of l .25hect area. The site of plantation has been marked in Environment Plan,
Plate No. 6. Proper after care by manuring, watering and pesticides etc. will be taken by
proper staff. The plantation programme, which shall be implemented during five years, is
as under:
Phased Programme for the plantation
Year No.Of Type of Plant Location Plant (for first 5 yrs.)
I 2000 Neem, Babool As Shown In
II 2000 Neem, Jal, Babool Plate No. 5 & 6.
lII 2000 Neem, Jal, Khejdi
IV 2000 Jal, Khejdi, Bahool
v 2000 Neem, Babool
d) Stabilization and Vegetation of Dump
Talcing all the safety measures will stabilize Waste dumps. Retaining wall will be made at
the bottom of the dump when it will be required.
e) Treatment and Disposal of Mine Water
There will be no make of water during any of the mining operation; therefore there
will be no need of treatment and disposal of mine water.
O Measures for minimizing adverse affect on Water Regime
The water table in the area lies at the depth of approximately 60-70 m. below surface.
So water table will not be encountered during inining operation. -Therefore, there will be
no adverse affect of mining on water regime_
g) Protective Measures For ground Vibrations I Air blast Caused by blasting The
scale of blasting at the mine is very small and that is not generate any significant ground
vibration and air blast. Therefore, there is be no protective measures are required for
ground vibration and air blast.
h) Measures for dust Control
The dust is generated during drilling. Therefore proper care is taker. by using dr)' dust
extractors to prevent the dust being air borne.
30
i) Measures for protecting historical monuments and for rehabilitatio ~mf'.'.~· settlements likely to be disturbed due to mining activity '"'~~~;:;·,.
't>:;:.c;,,
There is no public building, cultural or historical monument or place of worship
human settlements exist in and around the M.L. area. Therefore, there will be none
protective measures for it.
j) Soci°'"Economic Benefits arising out of mining
At present the major occupation of the villagers are farming and cattle rearing. The
mine in the area will provide regular employment to the villagers of the area.
12. ANY OTHER RELEVANT INFORMATION
NIL
ll!li'm''ll .
'1!111' ~ 'l:-·f\$$1M ~
~' a!l~
,, /\ ~~! '
' -1/ ~
SIGNA-&RE OF RQP SAW AI SINGHRAJPUROHIT (RQPISMEIJODHPCR/2014101)
PROGRESSIVE MINE CLOSURE PLAN
1.0 INTRODUCTION
(a) Name of applicant & complete address: -
Shri Bankat Lal Modi, S/o Shri Jai Dev Modi
Rio - "Modi Building" Sojat Road Dist Pali
(b) M.L. area: - ML area-<56.25 hect (Govt. Waste land)
(c) Location: -
Village- Barana,
Tehsil (Taluka} Bilara,
District & State-Jodhpur, Rajasthan
(d) Type of area: - Non-forestland, total 66.25hect.
Present land use pattern is as follows :
I. Area excavated =
2. Storage for Topsoil =
3. 0.BJDump ~
4. Mineral storage =
5. Infrastructure (Workshop/Adm. building)=
6. Roads/Cart track=
7. Railways =
8. Green belt =
9. Tailing pond =
10. Effiuent treatment plant=
11. Mineral separation plant=
12. Township area=
13. Others (fo specify}~
4.82hect
Nil
I .22hect
Nil
0.10hect
I .95hect
Nil
Nil
Nil
Nil
Nil
Nil
Nil
The opencast mining method is proposed for exploitation of mineral and waste. Except
sorting the mineral by manual means no mineral beneficiation is proposed at site.
32 .
1.1 Reason for Closure
The mine closes either due to depletion of mine-able reserves or due to uneconomic
mining or due to more economic substitute for mining product.
This progressive mine closure plan is submitted as a statuary requirement for the M.L.
area. Hence the aforesaid reasons for closure are not applicable at this stage for the
M.L. area.
Statutory Obligations
Various rules applicable under MCDR & MCR for reclamation & rehabilitation of the
worked out area, safe & systematic mining under 1961 before abandonment of the
worked out area and applicable rules for pollution control & environment will be
taken into consideration. The void created due to mining activities shall be properly
fenced and used as water reservoir.
1.1.1 CLOUSER PLAN PREPRA TION
NAME OF THE LESSEE
Shri Bankat Lal Modi,
NAME, ADDRES AND REGISTRATION NUMBER OF THE
RECOGNIZED PERSONS PREPARING THE CLOUSRE MINING PLAN
Sawai Singh Rajpurohit,
Registration No.- RQPISMEIJODHPUR/2014101
Address - (K. P. CONSULTANT)
Clo Pramod Kuwadia,
Shop No. 3-4, Basemant, Utkarsh Plaza,
Near Sanischarji Ka Than, Jodhpur (Raj)
E-mail:- [email protected] __ ....-,~
Certificate valid till 26.03.2019
NAME OF EXECUTING AGENCY
Shri Bankat Lal Modi,
33
i:;i1\il ~s::~ ,;c'•,
.........•....•............................•........•...............................•....
2 MINE DESCRIPITION
2.1. Physiography .. · · .. · ·~ The M.L. area under M.L. is having mostly undulating topography. -The highest"~~~,,<:;:'-"'"
-«1:v"a•
in the area is 324mRL and the lowest counter is 300.0mRL. 'fhere is no public well -With
in the M.L. area. There is no water channel bodies in the area. There are two small
seasonal nallas flowing in the area. The general sloop of the area is in all direction. The
rainwater spread out in the area & nearby areas. The villayati and deshi babool trees are
scattered in and around of the area. The ground water level is moderated depth with
average depth of 60 to 70mts below the surface and ground water is somewhat hard and
salt tolrent crops can be grown. The common flora consists in and around the area of
Babul (Acaciaratica), Neem (Azadirachta indica) and thorny bushes.
No forest area falls within the lease area
2.2. Local Geology
In the lease area the lime stone beds, which belong to the Pondlu formation of Bilara
group are horizontal indicating the absence of any tectonic effect
Following geological setting in the area:
I. Soil
2. Limestone (Burning)
3. Siliceous Limestone (Partly area covered)
4. Dolomitic limestone
5. Limestone (Burning)
The limestone occur as alternate bands with siliceous limestone, dolomitic/high
MgO limestone layer by layer which are clearly visible from the old working pits in the
Mining Lease Area of Barana Limestone Deposit. Clay is seen filled between the
magnesianldolomitic limestone and the limestone horizons. The percolating surface
water, along the cracks and crevasses, has carried the clay, therefore its deposition is
found to the extent of these cracks and crevasses, as developed in the area.
The magnesian limestone can be distinguished from the high grade limestone
(burning) m the field, on the basis of its physical characteristics. The
......................... 34
magnesian/dolomitic limestone is yellowish brown in colour with shades of buff. lt is
medium to coarse grained, thinly to thickly bedded compact and hard in nature. The high
grade limestone can be distinguished from the above on the basis of its colour, which is
mostly gray to dark gray and the fine-grained. The siliceous limestone is dark gray to
black coloured, coarse to medium grained, inter layered with dolomite limestone.
Description of the above formations is given below: -
Overburden alluvium - LOMts.
Hard dolomitic Limestone- 2.0Mts.
Limestone (Burning) 2.0 Mts
Hard dolomitic Limestone 2.0 Mts
Limestone (Burning) 6.0 Mts
Hard dolomitic Limestone 2.0 Mts
Limestone (Burning) 6.0 Mts
Partly area covered with Siliceous Limestone. It is waste rock to be removed. Generally it
is of dark grey to black in colour, It often includes layers of dolomite limestone and
reddish in colour at places due to iron leaching often these have intruded into crevices.
2.3 RESERVES
Reserves of limestone (Burning)
Category Area Average
Volume Tonnage i Thickness
I Sqm. (m) Cum MT 1 ' 2 3 4 5 !
' Proved I 8 2898784 7246960 362348
Mind out I
Reserves 48200 2 -96400 -241000
Net Proved 2802384 7005960
Probable I 73718 8 589744 1474360
' I Possible I 8 443720 1109300 ' 55465 !
Total I 3835848 9589620 ' _J Bulk density ls taken 2.5 tonne/cum
35
Reserve Dolomitic Limestone (as a waste)
Category Area Average Thickness
S m. m Dolomitic
662500 6 Limestone
3975000
Mind Out 73718 2 - 147436 - 368590 Net Reserve 3827564 9568910
• It is as a waste
Mineable Reserves
.Mineable reserve= Total reserve of proved & probable - (Reserve blocked in proposed
benches +Reserve blocked in barrier)
I otal reserve= 8480320 MT
Reserve blocked in barrieF 6800X 8X 2.5~ l 36000MT
Reserve blocked in benches= 12500X 8 X 2.5 = 250000MT
Total reserve blocked= 386000MT
Then mineable reserve~ 8480320 (proved+ Probable)- 386000 ~ 8094320MT
Total mineable reserves= 8094320MT
2.4 MINING METHOD
The limestone is overlain by Alluvium with kankar, so to extract limestone it becomes
necessary to remove the overburden as well as soil. Since the deposit occurs at a depth of
3mts and the thickness of the deposit is sufficient to be economically mineable. Opencast
semi 1nechanize method is the suitable method for mining. The mining will be done by
making systematic benches. Road and ramps will be made at gentle gradient during
mining as per requirement. ·The height of the benches will be kept 3.0mts maximum in
overburden & 3.0mts in mineral and width of the benches will not be less than height.
The removal of the O.B. carried out as first bench is advanced to expose the limestone.
The limestone area in has a top covering of soil 3.0mts thickness. The O.B./I.B. is
removed and transported with the arrange1nent of trucks/dumpers and heaped separately.
The main development work will be the systematic benching. This benching will also
give the desired production of the li1nestone. The proposed production of limestone will
be 2,70,000 tones per year .
......................................... 3.6 ....
3.0 REVIEW OF IMPLEMENTATION OF MINING PLAN/SCHEME OF
MINING INCLUDING FNE YEARS PROGRESSIVE CLOSURE PLAN UPTO
THE FINAL CLOSURE OF MINE
This progressive mine closure plan is first plan for this area, hence this chapter is not
applicable at present.
4.0 PROGRESSIVE CLOUSRE PLAN
4.1 MINED OUT LAND
Land use pattern at the end of (Five year) progressive closure plan :
1. Area to be excavated=
2. Storage for Topsoil=
3. O.B./Dump ~
4. Mineral storage =
5. Infrastructure (Workshop/Adm. building)=
6. RoadsJCart track =
7. Railways=
8. Green belt=
9. Tailing pond ~
10. Effluent treatment plant=
11. Mineral separation plant=
12. Township area=
13. Others (To specify)=
4.2 WATER QUALITY MANAGEMENT
9.55hectares.
Nil
3.37 Hect.
0.20 hect.
0.1 OHect.
1.95 Hect.
Nil
l.25Hect
Nil
Nil
Nil
Nil
Nil
The mining activities, including Waste dumping have been so planned to prevent any of
the disturbance to natural flow of water and also the drainage system of the area will not
be affected.
The water table in the area is sufficiently below the ground level (about 60-70 1nts.). The
proposed deepest working is far above the general ground water table. Therefore quantity
as well as quality wise, the ground water in the area is not likely to be affected at all by
future mining activities.
37
No toxic mineral is present, which pollute the quality of ground water.
No tailing pond is proposed, which pollute the quality of ground water.
The proposed deepest working is above the ground water table thus quality of water w·
not decrease by proposed mining.
The rain water will accumulate in the working, which will be dewatered by centrifugal
pump of 20 H.P. The dewatering is proposed through a sump made in the bottom of the
pit to check the silt, which may spread in nearby area.
4.3 AIR QUALITY SURVEY
The Quality of air is free from any pollution at this time, as there is no major source of
polluting the air with in the area or nearby the area. During the summer air becomes a
little dusty. There is no source of air-deterioration in this region and therefore ambient air
quality in the area as well as in the region of 5.0km radius is natural and pure.
4.4 WASTE MANAGEMENT
Soil with kankar: - The soil with kankar spread most of the area having thickness of
l .Omts and is friable, moist in nature.
Dolomatic limestone: - Below the grit and kankar a Dolomatic limestone having
thickness of2.0mts and is friable, moist in nature.
Sub grade: - About 10% of mineral is sub grade.
The O.B./waste, and sub grade are generated during the five period of the mining plan are
given as below: ·
Year ; Subgrade 10°/o !
Waste/O.B.11.B. ' (MT) (cum)
'
I year 11952.5 i 83457
II year 119045 74203 i
III year 33873.75 90330
IV year 32010]5 640215
V vear i 41826.25 i 48595
Total ! 131567.75 936800 ' Waste generated m the next five years, which will be separately stacked inside the area
near boundary pillar B', Waste will be stacked over an area about 2.15hect with 6m
height as shown in the Progressi\.re Mine Closure Plan plate No. 8.
Stacking of Subgrade Mineral
38
Sub grade will be stacked separately and will not be mixed with O.B./waste and will be
backfilled. Retaining wall will be provided around the sub grade to prevent wash off &
spreads of the sub grade. Sub grade stack in next five years will be stacked inside the
lease area.
4.5 Top Soil Management
The ML area is a soil with kankar covered, so this soil with kankar will be used
simultaneously in plantation in purpose.
4.6 Tailing Dam Management
No Tailing dam is proposed hence this paragraph is not applicable.
4.7 Infrastructure
Existence of public road I railway, if any nearby and approximate distance -
Barana Limestone Deposit is situated on the Bilara- Sojat City road (Major State
Road), 15 km from Bilara. Bilara is approximately 80 km SEE of District HQ Jodhpur
and at about 64 km north of Pali. The limestone deposit is well connected to Jodhpur,
Beawar, Pali, Sojat city and Ajmer. Sojat City is on the NH-14 (Beawar-Pali-Sirohi
Kandla) which joins NH-65 (Ambala-Hissar-Churu-Pali) near Pali and NH-8 (Delhi~
Jaipur-Ajmer-Udaipur-Ahmedabad-Mumbai) at Beawar. The nearest Airport is Jodhpur
and the nearest Sea port is Kand.la in Gujarat which is approximately 600 km. The
Beawar-Kandla National Highway passes through Sojat City, which is 45 km from the
Barana~Harsh Limestone Deposit.
Bilara is the nearest rail head, about 15 km from the deposit on the Jodbpur-Pipar
City-Bilara broad gauge section of the North-western Railway
4.8 Disposal of Mining Machineries
No machinery is proposed to disposed off during the period of this progressive mine
ciosure plan. The machineries, which will be deployed at mines during the period of
proposed five years, will also not dispose off during five years.
39
4.9 Safety and Security
For safety purpose the following proposals are proposed: -
Barbed wire fencing is proposed around the proposed excavation to check the inadvertent
entry of human and livestock in the mining area (excavation).
A watchman is employed for ward and watch duty. In the period of discontinuance the
watchman is proposed to continue for ward and watch duty. The watchman will not allow
any general public person and livestock near the deep cuttings of the proposed workings.
The safe workings are proposed in the supervision of technical and qualified supervisory
staff. Safety measures will be provided as per Mines Act.
4.10 Disaster Management and Assessment
It is a working tnine. The proposed working will be opencast m1n1ng method.
Underground mining is not proposed. No tailing dam is proposed. Thus high risk
accidents like land slide, subsidence, flood, inundation, fire, seismic activities etc. not
come across.
In case of ac-cident a well-equipped first aid station will be provided at mine site for
giving first aid to injured persons. The area is near the state highway and vehicles on this
highway with good frequency. The lessee vehicle also remains at site most of the time
during working. The applicant is capable to meet any type of risk_
4.11 Care and maintenance during temporary discontinuance:
In case of temporary discontinuance or if mine closes temporarily, than the mining
working will be in the watch ofa watchman. Before re-open of the mine the maintenance
will be provided to all the machineries deployed at mine. Before entering the labourers
into mine workings/faces the w·orkings and faces are proposed to inspect by Mines
Manager for safety purpose as per Mines Act.
.............................. 4.0. .................................................... .
5 ECONOMIC REPERCUSSIONS OF CLOSURE OF MINE AND
MANPOWER RETRENCHMENTS
5.1 Number of Local Residents Employed
As per proposed mining plan total 15 workers (unskilled) and 4 supervisory staff
(technically qualified) are proposed to be employed. The labourers will be employed
from nearby village. Some local habitants of the area will get indirect job from the mining
activities and by transportation etc.
Compensation
The compensation to the employees with sustenance of himself and their family members
will be provided as per Labour law and Mines Act.
5.3 Satellite occupations connected with mining activity:
The mining activities have been instrumental in raising the economic status of
nearby area and people have already started setting in other professional like agriculture
and jobs not related to mining.
5.4 Continued engagement of employment in the rehabilitated, status of mining lease
area and any other remnant activities:
Not applicable in this progressive mine closure plan
5.5 Envisaged repercussions on the expectation of the society around due to closure
of mine:
This paragraph belongs to final closure of the mine and not related with this
Progressive Mine Closure Plan .
.............................. 4 .•. 1 •........ •····································
6.0 TIME SCHEDULING FOR ABANDONMEN
No part of the mine is proposed abandonment during the period of this p
closure plan. These details will be provided in fmal closure plan whenever applica
7.0 ABk'!DONMENT COST
Abandonment is not proposed in the period of this plan; hence abandonment cost is not
related with this plan. But Rs. 50000.00/year will be expenditure made for plantation &
Waste management.
8.0 FINANCIAL ASSURANCE
As per rule 37 J (3) of MMCR (A Second Amendment) 2012, the applicant will submit
the financial assurance in terms of bank guarantee or in any other as asked by authorized
officer of the Department of Mines & Geology before M.L. agreement.
9.0 CERTIFICATE
Certificate id enclosed with report.
10. PLAN & SECTIONS
Plan & sections area prepared & enclosed with this plan.
Shri Bank.at Lal Modi Name of Applicant
Ii! .
~ ~ '1:-f"f;;T"' 1'l" ''1°!T I
ll I "' SIGN~FRQP
SA WAI SINGH RAJPUROHIT (RQP/SME/JODHPUR/2014/01)