jimmy r. snow commissioning the wide area augmentation system

32
Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

Upload: gregory-carroll

Post on 05-Jan-2016

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

Jimmy R. Snow

COMMISSIONING THE WIDE AREA AUGMENTATION

SYSTEM

Page 2: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

2

OVERVIEW

WAAS System/Procedures WAAS Commissioning Considerations Ohio University Study MITRE Computer Modeling MITRE/Flight Inspection Validation WAAS Receiver WAAS Limitations Future Challenges

Page 3: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

3

GNSS RNAV PROCEDURES

LPV Takes Advantage of WAAS Capability

Equivalent to Localizer Lateral With Vertical Between ILS and LNAV/VNAV, HAT 250 ft & Up

LNAV/VNAV Vertically Guided Approach With Decreasing Vertical Obstruction Clearance, HAT 350 ftand Up

LNAV Non-Precision Approach With 250 ft ROC, Smaller Protected Area Than VOR, No

Vertical Guidance

CIRCLING Approach Procedure to a runway and then

Maneuver to Land on Another Runway

Page 4: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM
Page 5: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM
Page 6: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

6

Status Of FAAGPS Procedures (9/22/03)

Year 97 98 99 00 01 02 03

GPS Proc Published 573 516 531 504 447 618 510

TOTAL

LPV 7

LNAV/VNAV Published 613

LNAV Published 3,237

Military/Specials 237

GPS Proc Published 4,094

Page 7: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

7

WAAS COMMISSIONINGCONSIDERATIONS

WAAS Commissioning Date Established Approximately Two Years in Advance

Scheduled on Procedures Publication Date, July 10, 2003 Estimated Over 600 LNAV/VNAV Approaches Published for FMS

Baro VNAV Operations Over 3,000 LNAV Approaches Published for TSO C-129 Receivers Very Limited WAAS Flight Inspection Capability (Prototype MMR

Receiver in Lear 60) Technical Center WAAS Coverage Chart and Outage Records Used

to Restrict Certain LNAV/VNAV Approaches Numerous Discussions With Certification and Flight Standards

Page 8: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

8

WAAS COMMISSIONING OPTIONS

No Flight Inspection or Evaluation of Procedures Evaluate Each Procedure on Next Periodic (One and

Half Years or Longer to Evaluate All) Surge Effort After WAAS IOC (up to 1,000 Flight

Hours) Non-Traditional Evaluation of Existing Procedures

Page 9: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

9

OHIO UNIVERSITY SUPPORT

Initiated Discussions With Ohio University, Avionics Engineering Center May 2001

Established Procedure Parameters With FAA Working Group Held Discussions With Ohio University to Evaluate WAAS

Requirements Established a Technical Task Directive With Ohio University

July 2001 to Evaluate WAAS Commissioning Requirements Study Delivery Not Later Than Nine Months After Task Signed

Page 10: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

10

FLIGHT INSPECTION COMPARISON

GPS/Baro VNAVo Obstacle Evaluationo Standard Instrument Approach Procedure (Section 214)o Procedure Design (Database, Waypoints, Accuracy)o Electromagnetic Spectrum (RFI)

WAAS LNAV/VNAVo Obstacle Evaluationo Standard Instrument Approach Procedureo Procedure Designo Electromagnetic Spectrum o Geosynchronous Satellite Signal

Page 11: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

11

OHIO UNIVERSITY CONCLUSIONS

Result• Inspection of GPS/Baro VNAV Procedures Should

Accomplish All Anticipated WAAS LNAV/VNAV Requirements

• EXCEPT Ensuring Adequate GEOSAT Signal Coverage

GEOSAT• Provides Integrity Information, and Differential Corrections• Without, WAAS Receiver Reverts to LNAV Only Capability• Thus, LNAV/VNAV Procedures Can Not Be Conducted

Page 12: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

12

OHIO UNIVERSITY STUDY ASSUMPTIONS

Assumptions• The inherent WAAS monitoring is capable of detecting system faults within the

required time-to-alarm• The WAAS receiver reverts to a GPS-only capability in the absence of a

GEOSAT signal• The FAA has authorized WAAS for supporting LNAV/VNAV approach

procedures• The SIAP procedure has been previously commissioned for GPS/Baro VNAV• The availability of GPS/Baro VNAV and WAAS LNAV/VNAV is at least 95

percent• The descent altitude is the same for the WAAS LNAV/VNAV and GPS/Baro

VNAV procedures• There is a high-correlation between predicted (monitoring) and actual WAAS

system performance

Page 13: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

13

STUDY CONCLUSIONS

~ 600 GPS/Baro VNAV Procedures Expected to be Commissioned Before WAAS IOC

Inspection of GPS/Baro VNAV Procedures Should Accomplish All Anticipated WAAS LNAV/VNAV Requirements EXCEPT Ensuring Adequate GEOSAT Signal Coverage

Computer-based GEOSAT Coverage Screening Models May be Used to Streamline Flight Inspection Process (To determine if GEOSAT is shadowed on final approach segment)

Page 14: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

14

STUDY RECOMMENDATIONS (1)

The Comparison of GPS/Baro VNAV and WAAS LNAV/VNAV Flight Inspection Requirements Should Be Repeated Once Formal Criteria Are Available in FAA Order 8200

The Feasibility and Benefit of Developing a Screening Model for Assessing GEOSAT Signal Coverage Should Be Assessed Further

Low Confidence Cases, the WAAS LNAV/VNAV Procedure Should Be Flight Inspected Before Being Authorized for Use, Low Priority

Page 15: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

15

STUDY RECOMMENDATIONS (2)

Marginal Confidence Cases, the WAAS LNAV/VNAV Procedure Should Be Flight Inspected Before Being Authorized for Use, High Priority

High Confidence Cases, WAAS LNAV/VNAV Operations Authorized and Inspection Performed During Next Periodic Inspection of GPS/Baro VNAV Procedure

For WAAS Procedures Authorized Prior to Formal Flight Inspection, Authorization Should Be Withdrawn if a “Problem Report” Is Received

Page 16: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

16

SECOND PHASECOMPUTER MODELING

FAA Contacted MITRE, Center for Advanced Aviation System Development For Assistance (CAASD)

MITRE Advised They Could Modify an Existing Software Program to Do What Ohio University Recommended

Meetings Were Scheduled to Discuss:• Establishing an Agreement Between FAA and MITRE• Delivery Schedules• Evaluation Requirements• Data Requirements

Page 17: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

17

FAA-MITRE AGREEMENT

AVN Would Provide MITRE the Following:• Airport Identifier• Airport Reference Point (latitude/Longitude)• Airport Elevation• Airport Priority for Screening• If Available Airport Name and Location

MITRE Will Evaluate Each Airport Using the Following Criteria:• Evaluate a point 250 ft Above the ARP From 090 to 270 Degrees

o At Least One WAAS GEO is More Than 10 Degrees Above the Horizono No Terrain Within 40 nm of the ARP More Than 5-deg Elevation Angle Viewed

From 250 ft Above the ARP• MITRE Would Use Worst-case WAAS GEO Positions• MITRE Would Validate the Computer Model and Peer Review Results

Page 18: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

18

Elevation Angles in USA and Canada(POR and AOR-W)

Page 19: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

19

TERRAIN MASKING:Forty Nautical Miles

10 nm 30 nm

MountRanier

(14,400 ft)

4.5°ARP (Sea Level) FAF (Sea Level)

Geo

10° (minimum)

Page 20: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

20

An Airport Passing the Screening Test Will Not Have Geo Masking Due to Terrain and Should Not Require Re-flight Check For Terrain

–A detailed look at the airport is not required

Failure of the Screening Does Not Necessarily Imply That GEO Masking Will Occur During an Approach to that Airport

–Failure implies that a closer look at the airport is warranted

Availability of LNAV/VNAV Approaches Was Not Addressed

TERRAIN MASKING:Results

Page 21: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

21

AVN Airport Database Entries Were Compared With

Jeppesen and Other Databases

GEO Angles Were Computed by Several Methods With No

Significant Differences Between Methods

Terrain Masking Code Was Checked Independently

Terrain Results Were Spot Checked With Sectional Charts

AVN Will Spot Check Some Airports During a Later

Validation Check

VALIDATION EFFORTS

Page 22: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

22

AIRPORT GROUP ONESummary

223 Total Airports With RNAV (LNAV/VNAV) Approaches Developed by AVN

215 Airports Passed Screening• GEO > 10 Degrees Elevation and• Terrain to South < 5 Degrees Elevation

8 Airports Failed Screening• 3 Failed for Terrain• 5 Failed for GEO Elevation

o 3 in Northern Alaska

Page 23: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

23

AIRPORT GROUP TWOSummary

155 Total Airports With RNAV (LNAV/VNAV) Approaches Planned by AVN

142 Airports Passed Screening• GEO > 10 Degrees Elevation and• Terrain to South < 5 Degrees Elevation

13 Airports Failed Screening• 12 Failed for Terrain• 1 Failed for GEO Elevation

Page 24: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

24

AVN VALIDATION

MITRE Evaluated 378 Airports/AVN Flight Inspected 65 Airports To Validate MITRE results• 11 of the 21 Identified by MITRE Did Not Have

GEO Coverage• 2 Additional Airports of the 65 Would Not

Support VNAV For Geo Coverage AVN Accepted the Results As Satisfactory

Page 25: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM
Page 26: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

26

WAAS MMR RECEIVER

Have Six Collins MMR Receivers With WAAS and LAAS Two Lear 60s Have WAAS Capability Due to No TSO Receiver and No STC, Aircraft in Experimental

Status Currently in a MOPS “Beta” Configuration With the FMS We Must Change the MMR Into “Delta”

Configuration, Estimate 2 Years LPV and LAAS Have FAS Datablock That the AFIS Reads Aircraft Flying LNAV/VNAV While AFIS Evaluates LPV New Contract Let to Complete VFR STC (estimate completion

January 05)

Page 27: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

27

LPV FLIGHT INSPECTION RESULTS

Site HPL

Meters

VPL

Meters

XTK

Error

Feet

ATK

Error

Feet

SNR Below Path SNR

Worst

SNR

KFDR 23 16.7 22.4 -3 -8 41 42 39KCHK 16L 14.2 23.2 -4 -3 42 42 40KTYO 17 14.5 19.9 3 -7 41 42 40KGAI 14 16.5 21.1 6 0 41 41 41KOKC 17R 12 21.5 -3 7 40 41 40KOKC 35R 10.5 19 1 -6 40 40 40KOSH 36 12.6 18.6 4 -17 40 41 38

Page 28: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

28

WAAS Approach

ILS Glideslope

ILS vs WAAS LPVFlight Inspection Comparison

Page 29: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

29

Page 30: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

30

WAAS LIMITATIONS

Inverse W on RNAV Approach Charts/Limitations• Indicates WAAS Outages May Occur Daily (32 airports)• WAAS NOTAMS Are Not Provided For the Procedure• Use LNAV Minima For Flight Planning (Destination or

Alternate) • If Receiver Indicates LNAV/VNAV or LPV Available

Guidance May Be Used• If WAAS Is Lost Revert to LNAV Minima If Receiver

Allows or LNAV Data Is Available WAAS VNAV NA on RNAV Charts That Did Not Pass

MITRE Modeling and Flight Inspection

Page 31: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

31

INMARSAT 3AOR/W

54W

INMARSAT 3POR178E

INMARSAT III COVERAGE

Page 32: Jimmy R. Snow COMMISSIONING THE WIDE AREA AUGMENTATION SYSTEM

Jimmy Snow NAVIGATION CONSULTANT

405-249-4329

[email protected]