JAXA Space Science Program and International Collaboration
The 21st “Science in Japan” Forum US-Japan Collaboration in Space Sciences
-Past, Present and Future- 10 June 2016
Cosmos Club, Washington, DC
Saku Tsuneta Institute of Space and Astronautical Science
Japan Aerospace Exploration Agency
http://www.iki.rssi.ru/eng/iki50.htm
![Page 2: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/2.jpg)
HAYABUSA 2003-2010 Asteroid Explorer
AKARI(ASTRO-F)2006-2011 Infrared Astronomy
KAGUYA(SELENE)2007-2009 Lunar Exploration
SUZAKU(ASTRO-E2)2005- X-Ray Astronomy
M-V Rocket
AKATSUKI 2010- Venus Meteorogy
Hisaki 2013 Planetary atmosphere
HINODE(SOLAR-B)2006- Solar Observation
IKAROS 2010 Solar Sail
JAXA recent science missions
HAYABUSA2 2014-2020 Asteroid Explorer
2
Hitomi(ASTRO-H) 2016- X-Ray Astronomy
![Page 3: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/3.jpg)
Fiscal Year 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Operating / C
oncluded
Under D
evelopment S
ounding
B
eing considered
R
ocket
ASTRO-EII(SUZAKU)’05
GEOTAIL’92
SOLAR-B(HINODE)’06
MUSES-C(HAYABUSA)’03
HAYABUSA1/2 SUZAKU
Daytime Dynamo ’11,’13 ▼ ▼ CLASP ’15 ▼
MMS ’14 ▼
Space Science Cooperation with NASA and ESA
ASTRO-F(AKARI)’05
PLANET-C(AKATSUKI) ’10
BepiColombo ’16 SPICA ’27-28
JUICE ’22 ▼
SPICA
Bepi Colombo
cooperation with NASA cooperation with ESA
HAYABUSA2 ’14 ▼
▼
▼
▼
▼
ASTRO-H’15
ATHENA ’28 ▼ Cooling Chain Core Technology Program
HINODE HITOMI
![Page 4: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/4.jpg)
ASTRO-H X-ray Observatory
The ASTRO-H Hitomi was the result of close collaboration between NASA, JAXA and other countries from its initial concept throughout its construction.
![Page 5: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/5.jpg)
Hitomi Launched in 17 Feb. 2016
![Page 6: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/6.jpg)
Hitomi SXS In-flight calibration 4.6eV FWHM at 6keV 50mK achieved by the cryogenic system
Cryogenic soft X-ray spectrometer was in perfect shape until the moment when communication to the spacecraft was lost (Mar 26)
![Page 7: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/7.jpg)
Hitomi SXS In-flight calibration 4.6eV FWHM at 6keV 50mK achieved by the cryogenic system
The Quiet Intracluster Medium in the Core of the Perseus Cluster submitted to Nature
Cryogenic soft X-ray spectrometer was in perfect shape until the moment when communication to the spacecraft was lost (Mar 26)
![Page 8: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/8.jpg)
Hitomi mishap
• JAXA declared the shutdown of Hitomi on April 28, before achieving regular operations for science. This deeply disappointed the astrophysics community in the world, particularly people who have been involved in the development of the instruments aboard Hitomi over the years.
• We were able to obtain SXS data of the Perseus cluster in the initial operation phase, which is a stunning demonstration for the in-orbit performance of the X-ray micro-calorimeter developed by NASA/GSFC.
• ISAS, ISAS ASTRO-H project, primary contractor (NEC) and Japanese X-ray astronomy community are deeply aware of responsibility for the disaster. 8
![Page 9: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/9.jpg)
Anomaly investigation and recovery of the mission
• The anomaly is due to two different design-problems and one improper operation procedure all related to the Hitomi’s attitude control/safe-hold system.
• Technical culprit was identified and deeper cause of the problems including sociological factors were analyzed in the JAXA report to GOJ. All findings are open to public.
• My priorities have been (1) to fix the problems in our system that led to the mishap, (2) to recover the Hitomi science with SXS with NASA, and (3) to maintain the strong partnership with NASA and other agencies. 9
![Page 10: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/10.jpg)
とうえい
Mysterious bow in super-rotating Venus atmosphere
Akatsuki Long-wave infrared (LIR) camera
![Page 11: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/11.jpg)
Akatsuki IR2 camera
![Page 12: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/12.jpg)
Hayabusa 2 • Sample return from a
primordial asteroid Ryugu (formerly 1999JU3).
• Small lander MASCOT provided by DLR/CNES for surface spectroscopy with microscope.
• Small Carry-on Impactor to expose fresh subsurface materials
![Page 13: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/13.jpg)
Hayabusa2 current status
13
■ Original plan ● Revised plan ● Result (● and ● are overlapping with difference of 300m)
Allowed window to reach Ryugu
color contour every 10km, gray line altitude from Earth
l1300 hours of ion-engine operation lPrecision (300m) navigation with DDOR
technique lConsistent with JPL shadow navigation lExcellent calibration data using Earth and
Moon taken during flyby
![Page 14: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/14.jpg)
OH/H2O
H2O/CO2 absorption feature
H2O
CO2
14
Hayabusa2 Earth swingby ONC TIR
NIRS3 Earth
Plant distribution Color image TIR thermal image ONC-T multi color
Australia(higher T)
NIRS3 Moon
OH/H2O absorption feature?
![Page 15: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/15.jpg)
Hayabusa 2 mission
1/5
falcon
hayabusa
Hayabusa2-OSIRIS-REx collaboration in operation
15
![Page 16: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/16.jpg)
Hayabusa 2 mission
1/5
falcon
hayabusa
Hayabusa2-OSIRIS-REx collaboration in operation
ISAS/JAXA HAYABUSA2 mission • Launched: 2014, arrival:2018, departure: 2019,
return: 2020 • Earth swing-by completed in Dec 2015 on its way for
arrival at Ryugu in 2018 NASA OSIRIS-Rex mission • Launch: 2016, arrival:2018, departure: 2021, return: 2023 • Target: BENNU Sample & return is regarded as a high-risk mission and the collaboration including sample-exchange serves as
a means for insurance for both science teams.
16
![Page 17: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/17.jpg)
2010 2020 2030
Hisaki(2013)
SPICA (2027-28)
BepiColombo (ESA, 2016)
SLIM(2020) #4 (2022) #5(2024)
ERG (2016)
Astro-H (2016)
JUICE (ESA, 2022)
ATHENA(ESA, 2028) WFIRST(NASA, 2025)
Phobos/Deimos (2022) LiteBIRD, Solar-Sail, Solar-C (2025)
Proposals being reviewed
NASA NewFrontiers2016
Strategic Large Missions (300M$ class) for JAXA-led flagship science mission with HIIA vehicle (3 in ten years)
Competitively-chosen medium-sized focused missions (<150M$ class) with Epsilon rocket (every 2 year)
Missions of opportunity for foreign agency-led mission
Space Policy Commission under cabinet office intends to guarantee predetermined steady
annual budget for space science and exploration to maintain its scientific activities
![Page 18: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/18.jpg)
Large-size #3 Under selection
LiteBIRD, Solar-Sail, (Solar-C)
Strategic L-class missions with HIIA/H3
#4 ESA-Led SPICA
#2 Martian Moons eXplorer (MMX)
#1 ASTRO-H (Hitomi)
Strategic Large Missions (300M$ class) for JAXA-led flagship science mission with HIIA/H3 vehicle (3 in ten years) FY2015
FY2022
FY2025
FY2027
![Page 19: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/19.jpg)
Large-size #3 Under selection
LiteBIRD, Solar-Sail, (Solar-C)
Strategic L-class missions with HIIA/H3
#4 ESA-Led SPICA
#2 Martian Moons eXplorer (MMX)
#1 ASTRO-H (Hitomi)
Strategic Large Missions (300M$ class) for JAXA-led flagship science mission with HIIA/H3 vehicle (3 in ten years) FY2015
FY2022
FY2025
FY2027 In spite of Hitomi mishap, MMX and SPICA are our top-priority missions. These missions should reach implementation phase as early as possible.
![Page 20: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/20.jpg)
MMX JAXA’s exploration of the two moons of Mars with sample return from Phobos
![Page 21: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/21.jpg)
MMX JAXA’s exploration of the two moons of Mars with sample return from Phobos
JAXA’s mission to the Martian moons (MMX) will make close-up remote
sensing and insitu observations of both moons, and return samples from Phobos.
![Page 22: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/22.jpg)
MMX Mars at the outer-edge of the rocky planet region of the solar system
Rocky planets
Mars The location of the snow line
Gas giants, icy planets
![Page 23: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/23.jpg)
The big question to be addressed with MMX
• Delivery of water, volatiles, organic compounds etc. from outside the snow line to entitle the rocky planet region to be habitable
• Small bodies as delivery capsules • Dynamics of small bodies around the snow line in the early solar
system • Mars at the gateway position to witness the process
Comet (ice) Primodal asteroid (Hydrous mineral)
![Page 24: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/24.jpg)
- Two leading hypotheses, unsettled controversy. - Revealing the origin would lead to better understanding of
the behavior of small bodies around the snow line in the early solar system.
MMX Enigmatic origin of the Martian moons
Phobos samples are mixture of Mars materials and impactor materials: Mars sample return realized! We do learn about dynamics of the impactor.
Phobos sample analysis characterizes a capsule that was on its way to deliver water and organic compounds to the inner-solar system.
Mars sample return: When debris from the Mars surface found, we will be able to read-out the history of the Martian surface environment.
![Page 25: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/25.jpg)
SPICA – Space Infrared Telescope for Cosmology and Astrophysics
• SPICA is optimized for mid- and far-IR astronomy. • SPICA unveils the “dusty era” in the Universe (evolution of
galaxies), and finds a route to habitable planets (formation of planetary systems).
• SPICA is launched at ambient temperature, and cooled down in space. The cryo-cooler system is a key heritage of JAXA ASTRO-H.
• To be proposed to the ESA M5 slot as an ESA-led mission.
l Baseline specifications lTelescope : 2.5 m aperture cooled <8 K lCore wavelength : 17–230 mm lOrbit : S-E L2 Halo Orbit l Launcher : JAXA H3 Vehicle l Launch Year : 2027–2028
![Page 26: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/26.jpg)
AKARI FIS-FTS
JWST/MIRI
Lim
iting
Lin
e Fl
ux (5
s-1h
r) /
Wm
-2
10-16
10-18
10-17
10-19
100 1000 20 200 350
Wavelength / mm
2010's
SPICA Sensitivity Dramatic improvement
´100 Improvement
AKARI IRC
SPICA 2020's
ALMA
10-20
10
10-15
SPICA/SAFARI R=25000
R=300
SOFIA
HERSCHEL
Spitzer
R=3000
![Page 27: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/27.jpg)
? Foreign agency-led
Large missions
#3 Athena (ESA)
#2 Jupiter Icy moons JUICE (ESA)
#1 Bepi-Colombo (ESA)
FY2018
FY2022
FY2028
Missions of opportunity for foreign agency-led mission
![Page 28: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/28.jpg)
CNES Athena
![Page 29: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/29.jpg)
ISAS Astrophysics and fundamental physics 2020s Lead cryogenic astrophysics missions
29
Hot and Energetic Universe
Reds
hift
(z)
Wavelength (m) 10-12-10-8 m 10-5-10-4 m 10-3-10-2 m
z=0.5
z=3
z>>10
Galaxy Evolution Formation of Solar Systems
SPICA(ESA-led)
ATHENA(ESA-led)
Cosmic Microwave Background and Inflation
(X-ray) (IR) (Milli-wave)
LiteBIRD (JAXA-led) under assessment
![Page 30: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/30.jpg)
Medium-size #4 Under selection
Competitive M-class missions with Epsilon
#3 Moon landing (SLIM)
#2 van Allen belt (ERG)
#1 Hisaki (UV planet)
Competitively-chosen medium-sized focused missions (<150M$ class) with Epsilon rocket (every 2 year) FY2013
FY2016
FY2019
FY2021
![Page 31: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/31.jpg)
Current Status • Assembly, integration,
verification activities are going on at ISAS.
• To be launched via upgraded Epsilon#2 in 2016
ERG Flight model
31
![Page 32: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/32.jpg)
ISAS Engineering: Small lunar-lander (SLIM) for pinpoint landing technology
demonstration
![Page 33: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/33.jpg)
SLIM (Smart Lander for Investigating Moon)
SLIM is a mission to demonstrate the technology for pin-point soft landing on lunar or planetary surface. • Image-based navigation utilizing Lunar terrain • Autonomous obstacle detection • Robust pin-point guidance • Landing shock absorber • High-performance propulsion • One science payload • Precursor of full-scale lunar or planetary missions
Total Weight:520kg
![Page 34: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/34.jpg)
BepiColombo MMO(ESA-led)
Martian Moons eXplorer(MMX) (JAXA-led)
Asteroid Sample Return Hayabusa, Hayabusa2 (JAXA-led)
JUICE (ESA -led)
34
SLIM Moon landing (JAXA-led)
ISAS Planetary science 2020s Lead sample & return
Solar-power sail to Jupiter Trojan asteroids (JAXA-led) under assessment
SPICA(ESA-led)
![Page 35: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/35.jpg)
New JAXA Deep Space Station (available 2018, 54m, X&Ka bands)
• The location is in favor of cooperation with oversea deep space stations. – Provide new attractive baseline of triangular shape for DDOR with
either NASA or ESA stations. – Provide a complementary station for Australia.
● NASA ● ESA ● JAXA
● Goldstone
● New Norcia
Usuda ●
●Canberra
Madrid ● ● Cebreros
● Maralgüe
Hayabusa2 Earth flyby attained GNC accuracy of 300m via Differential One-way Ranging (Delta-DOR)
![Page 36: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/36.jpg)
Technology driven Leads and creates space
science programs
Science driven Stimulates and encourages
new technology development
Uniqueness of ISAS: Close ties between space science and space technology
Space Science Divisions Space Astronomy Astrophysics
Solar System Science Interdisciplinary Space Science
Space Technology Divisions Space Flight Systems
Spacecraft Engineering
36
![Page 37: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/37.jpg)
Recent accomplishments HAYABUSA & IKAROS
Led by JAXA Lunar & Planetary Exploration Program Group 37
![Page 38: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/38.jpg)
[Tech. Demo. #1] Solar sail deployment
[Tech. Demo. #3] Photon propulsion
[Tech. Demo. #4] Solar sail guidance, navigation and control
Launch (21/May/2010)
Venus Flyby (8/Dec/2010)
[Tech. Demo. #2] Power generation by sail-mounted thin film solar cells
Extended operation phase (Jan/2010 - now)
~9/June/2010
~10/June/2010
IKAROS Technology Demonstration of Interplanetary Solar Power Sail
Thin film solar cell
Solar sail Diagonal 20m
Led by JAXA Lunar & Planetary Exploration Program Group 38
![Page 39: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/39.jpg)
2003 HAYABUSA-1 2014 HAYABUSA-2 2022 Phobos/ Deimos SR
Various missions related to sample return and/or atmospheric-entry are being discussed and proposed.
Phobos/Deimos SR Trojan SR with Solarsail Mars EDL mission
Deployable Aeroshell w/U. Tokyo
HTV-R capsule(JAXA)
Systems for 12km/s (Mpeak=40) reentry speed
Thermal durability and response in high aerodynamics heating environment are evaluated with various materials in ISAS arc wind tunnel.
39
![Page 40: "JAXA Space Science Program and International Collaboration"](https://reader031.vdocuments.site/reader031/viewer/2022011722/587ea92d1a28ab2a4a8b7497/html5/thumbnails/40.jpg)
Summary
• JAXA and space science community deeply appreciate substantial support from NASA and US scientists during the Hitomi crisis
• My priorities have been (1) to fix the problems in our system that led to the mishap, (2) to recover the Hitomi science with SXS with NASA, and (3) to maintain the strong partnership with NASA and other agencies.
• JAXA moves forward in spite of Hitomi disaster. This mishap shall make us and our system stronger, and make us more reliable partner in space science in the long run.