JANICE DECOMMISSIONING St Andrews, 16 November 2016
Background
Janice History
• Central North Sea
• 175 miles SE of Aberdeen
• Field discovered in 1990
• First production in Feb 1999
• Over 70 million barrels production over its lifetime
• Asset reached its economic end of field life in 2015
Title of presentation | page 3
Title of presentation | page 4
Decommissioning Strategy
Title of presentation | page 6
Full removal of Janice FPU, risers, flowlines, umbilicals, control jumpers and spool
pieces.
Complete removal of James pipeline
and umbilical.
Oil, Gas and Affleck Pipelines to be
remain in situ with rock dump at ends.
Commencement of approx 400 days P&A campaign :
Janice – 13 Wells
James – 2 Wells
Affleck – 2 Wells (TBC)
Project Phasing & Status page 7
Phase 1
•Pipeline cleaning
•FPU Clean down
•FPU Departure
Phase 2
•Clearance of seabed for arrival of Rig
Phase 3
•Well P&A
Phase 4
•Seabed Clearance in compliance with decommissioning programme
Q2/Q3 2016 Q3/Q4 2016 2018 - 20 Q4 2016 – Q2 2018
Activities to Date
Project Key Dates
17th Aug 2015 Maersk announce intention COP the Janice FPU
Project team initiated
10th March 2016 COP of Janice FPU approved by the OGA
20th May 2016 FPU Shutdown
15th July 2016 Plant Hydrocarbon Free
11th Sept 2016 FPU commenced sailaway to disposal site
24th Oct 2016 Decommissioning programme approved by BEIS
Title of presentation | page 9
Fast track programme
• Early, open and honest engagement with the regulator and stakeholders helped deliver this project.
• An integrated project team made up of Operator and Contractor personnel set up at both Company and Contractor sites.
• All contractors aligned and engaged with the project goals and company way of working.
Title of presentation | page 10
Contracting Strategy
• As an E&P Operator Maersk Oil’s primary focus is not decommissioning
• Maersk Oil relied on its strength as a Project Integrator to optimise the supply chain in support of the delivery of the decommissioning programme and Project Activities .
• Existing frame agreements used as far as possible
• Financial stability of suppliers a focus area
Title of presentation | page 11
Key Success Factor 1 People, People, People
• Engagement with operations crew:
• Your offshore crew are your #1 stakeholder
• Humbleness – Recognise the operations team face uncertainty
• If you think you’ve done enough communication, you’re probably wrong.
Title of presentation | page 12
Title of presentation | page 13
Phase 1 DFPV & Sail Away
Phase 2 Subsea Clearance
Phase 3 Well P&A
Key Success Factor 2 Supply Chain Collaboration
Title of presentation | page 14
Key Success Factor 2 Operator Collaboration
Title of presentation | page 15
MER UK Awards
Success Factor 3 Humbleness & Expecting the unexpected
Title of presentation | page 16
Known Knowns Data within your knowledge repository, but does it tell you the whole story?
Unknown Knowns Offshore operations team and supply chain have a wealth of experience you don’t know. How will you access this information?
Known Unknowns Be 100% honest with yourself, your team and supplier. What skill / knowledge gaps do you have?
Unknown Unknown There will be surprises, but the right team will react to these surprises proactively and diligently.
Title of presentation | page 17
Coming together is a beginning. Keeping together is progress. Working together is success.
Henry Ford
Thank you for listening