jan 16, 2004tom gaisser 1.3 cost & schedule review the icetop component of icecube...

16
Jan 16, 2004 Tom Gaisser 1.3 Cost & schedule review The IceTop component of IceCube Area--solid-angle ~ 1/3 km 2 sr (including angular dependence of EAS trigger)

Upload: jane-rogers

Post on 13-Dec-2015

217 views

Category:

Documents


3 download

TRANSCRIPT

Jan 16, 2004 Tom Gaisser1.3 Cost & schedule review

The IceTop component of IceCube

Area--solid-angle ~ 1/3 km2sr (including angular dependence of EAS trigger)

Jan 16, 2004 Tom Gaisser1.3 Cost & schedule review

Outline

• Scientific goals

• Pictures of test-tanks & Doms, 03/04

• Cost & schedule review– WBS structure & definitions– Schedule– Budget

Jan 16, 2004 Tom Gaisser1.3 Cost & schedule review

IceTop:the surface component of IceCube

• A 3-dimensional air shower array for– Veto (i.e. tagging downward events)– Calibration– Primary composition from PeV to EeV– Calibration, composition analyses similar to SPASE-AMANDA

but• 5000 x larger acceptance• wider energy range, better resolution

• IceTop at high altitude (700 g/cm2) – 125 m spacing between IceTop stations – Ethreshold ~ 300 TeV for > 4 stations in coincidence– Useful rate to EeV

Jan 16, 2004 Tom Gaisser1.3 Cost & schedule review

Small showers (2-10 TeV) associated with the dominant background in the deep detector are detected as 2-tank coincidences at a station.Detection efficiency ~ 5% provides large sample to study this background.

Showers triggering 4 stations give ~300 TeV threshold for EAS array

Large showers with E ~ 100-1000 PeV will clarify transition from galactic to extra-galactic cosmic rays.

Jan 16, 2004 Tom Gaisser1.3 Cost & schedule review

IceTop station schematic

Two DOMs: 10” PMTOne high-gain; one low-gain in each tank

To DAQ

IceCubeDrill Hole

~10-20 m

HG HG LGLG

Two Ice Tanks 3.1 m2 x 1 m deep (a la Haverah, Auger)• Coincidence between tanks = potential air shower• Signal in single tank = potential muon• Significant area for horizontal muons• Low Gain/High Gain operation to achieve dynamic range

Tank simulation with GEANT-4

Jan 16, 2004 Tom Gaisser1.3 Cost & schedule review

Fill tanks

• Tank10– Successful fill Nov 22

• 20 minutes to fill• < 10 RPSC man hours

for transport and filling

• Tank09– Filled Nov 26

Jan 16, 2004 Tom Gaisser1.3 Cost & schedule review

Cable runs looking toward MAPO away from SPASETank10 is on the right, Tank09 on the left. Power cable is on the left. There are 5 cables on the right:2 freeze-control cables, two twisted quads for DOMS, and Stoyan’s cable to read temperatures during the winter. The latter is somewhat thicker than the other four.

Jan 16, 2004 Tom Gaisser1.3 Cost & schedule review

4 IceCube DOMs runningFrom: SMTP%"[email protected]" 15-JAN-2004 15:56:19.45To: [email protected]: First Four IceCube DOMs DeployedI'm pleased to report that the first four IceCube digital optical modules have been successfully deployed at the pole. They are currently frozen into two IceTop surface tanks, located near the SPASE building. The DOMs are operating normally, and we are looking forward to dark-adapting the tanks and taking real data.John Kelley, UW-Madison

Jan 16, 2004 Tom Gaisser1.3 Cost & schedule review

WBS structure• 1.3.2 IceTop

– 1.3.2.1 Tanks– 1.3.2.2 Cables– 1.3.2.3 DOMs– 1.3.2.4 IceTop specific engineering

• 1.3.2.4.1 system design• 1.3.2.4.2 detector simulations• 1.3.2.4.3 Data acquisition

– Integration of SPASE– IceTop management

IceTop is the surface component of IceCube. By detecting cosmic-ray showers in coincidence with the deep detector it provides certain unique calibration and veto functions for neutrino astronomy in addition to permitting IceCube to function as a three-dimensional air shower array for study of cosmic-ray astrophysics up to PeV energies.

Jan 16, 2004 Tom Gaisser1.3 Cost & schedule review

Tanks, DOMs, Cables• 1.3.2.1 Tanks

• 1.3.2.2 Cables

• 1.3.2.3 DOMs

Design and build tanks; design and test freezing procedures to provide working ice-Cherenkov detectors for the surface array component of IceCube. Exclusion: Provision of water to fill the tanks is excluded because it will be an integral part of deployment (see 1.2.3.3.4 under 1.2.3.3 Field Season Operations). There is also a need for coordination with drilling (1.2.2) in connection with water supply.Tank deployment is under 1.2.

Specification of cabling to power and monitor freezing, testing and operation of tanks. Exclusion: Cabling for tank DOMs should be included in the main surface cables (1.3.1.2). We assume the surface cable will include conductors suitable for monitoring the tanks and for providing power during deployment. (1.3.1.2)Connections from the DOMs to the surface cables must beProvided, as well as cables connecting the DOMs to each other.(1.3.1.2)

Integration of optical modules into tanks. Exclusion: Construction of DOMs is excluded because the DOMs for IceTop will be part of DOM production runs (1.3.1.1). Design of modifications that may be needed for IceTop will be carried out in collaboration with 1.3.3 and 1.3.4 as part of IceTop specific engineering (1.3.2.4).

Develop FAT & verification test for IceTop DOMs

deployment and

Jan 16, 2004 Tom Gaisser1.3 Cost & schedule review

1.3.2.4 IceTop Specific Engineering

• 1.3.2.4.1 System design Engineering resources

• 1.3.2.4.2 Detector simulations

• 1.3.2.4.3 Data acquisition add .4.4 and .4.5

Design, Maintenance, calibration and operation of the surface component of IceCube to the extent that these require special procedures. IceTop is an integral component of the IceCube detector. To a large extent, both its hardware and software components are similar, if not identical, to those of the deep detector. This element includes integration of air shower detector calibration, DAQ, trigger, reconstruction and simulation intothe corresponding IceCube processes.

Develop engineering resources necessary for the design, verification, calibration and operation of IceTop components. Thisincludes an IceTop instrumentation and development facility and a tank test station on campus at U of Delaware, a tank test station at UW River Falls, mobile test tanks and a tank test station at the SPASE.

Develop simulations needed for IceTop design, verification, calibration and operation. Develop air shower simulations ofcommon interest for IceTop and for simulation of backgrounds in the deep detector (in coordination with WBS 1.4.3).

Design, specify and produce IceTop-specific DAQ firmware and software components, including triggering and feature extraction algorithms in the on-board FPGA and software for data handling, triggering and reconstruction. Specify requirements For IceTop mainboards, including any variations from mainboards to be used in ice. Coordinate with related activities in WBS elements 1.3.4, 1.4 and 1.5.

e.g. simulation of tank response, simulations for triggering are in this WBS; simulations for backgroundIn IceCube are under 1.4.3.1

Jan 16, 2004 Tom Gaisser1.3 Cost & schedule review

SPASE

• 1.3.2.5 Integration of SPASE

• 1.3.2.6 IceTop management

Maintenance and operation of the existing SPASE air shower detector to the extent it remains useful as a calibration device for IceCube. Lower threshold subsample of coincidences; tank calibration

Local project monitoring and reporting to project office.

Jan 16, 2004 Tom Gaisser1.3 Cost & schedule review

Schedule

PY3 PY4 PY5 PY6 PY7 PY8 PY9Strings deployed 4 12 16 18 18 12Tanks deployed 8 24 32 36 36 24

manufctd 8 24 32 96 (accel)

Freeze units (*) 8 (+2?) 16 (+2?) 12 0 manufctd (accel)

•Assumes each freeze unit reused up to 5 times. Probably should add some extras

Jan 16, 2004 Tom Gaisser1.3 Cost & schedule review

Hardware costs

• Capital– Tanks: 160 @ $6037 =

$965,920– Frz units: 36 @ $6002 = 216,072– O’flow units 36 @ $ 561 = 20,196– Sunshade 36 @ $1922 = 69,129– Misc Tank Equip 38,550– Test station Equip (inc. $45K at UWRF) 75,000– 4 test station tanks + ancillary equip 60,000– Computer cluster 180,000

• Total capital $1,564,867(+$60K)

Jan 16, 2004 Tom Gaisser1.3 Cost & schedule review

Materials & supplies (inc shipping)+ travel (both unburdened)

• 1.3.2.1 Tanks $ 18,850 – (not enough for shipping)

• 1.3.2.4.1 (Test stations) 31,000 • 1.3.2.4.3

– DAQ computers 27,000 reduce to $15K, move to.4.1

– Misc hardware 100,750 move to .4.1

• 1.3.2.5 -000-• 1.3.2.6 48,000 (replacement work

stns)• Total M & S $225,600• Travel $549,000

Jan 16, 2004 Tom Gaisser1.3 Cost & schedule review

Labor breakdown

• By institution person months (total project)– UD: 572, UW: 87, LBNL: 8, UWRF: 7

• Individuals involved part-time

Scientists: 13 1 0 1

Engrs, techs: 5 1 2• Labor cost by Project year (burdened)

PY3 4 5 6 7 8 9 10

1.23 1.23 1.14 1.00 0.81 0.70 0.32 0.16

Total: $6.64 M