james webb space telescope mission status

49
1 James Webb Space Telescope Mission Status Bill Ochs JWST Project Manager NASA Goddard Space Flight Center 29 July 2011 1 Presentation to: IEEE Neuclear Space and Radiation Effects Conference Goddard Contractors Association Dec. 5, 2012

Upload: others

Post on 12-Sep-2021

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: James Webb Space Telescope Mission Status

1

James Webb Space Telescope

Mission Status

Bill Ochs

JWST Project Manager

NASA Goddard Space Flight Center

29 July 2011 1 Presentation to: IEEE Neuclear Space and Radiation Effects Conference

Goddard Contractors Association Dec. 5, 2012

Page 2: James Webb Space Telescope Mission Status

2

MISSION OVERVIEW AND

STATUS

Page 3: James Webb Space Telescope Mission Status

3

JWST System Hierarchy

James Webb Space Telescope System

Launch Segment Observatory Segment Ground Segment

Optical Telescope Element (OTE)

Spacecraft Element (SE)

Launch Vehicle

Payload Adapter

Launch Site Services

Science and Operations Center (SOC)

Common Systems

Institutional Systems

Spacecraft Bus

Sunshield

Ariane Launcher

Deep Space Network Space Telescope Science

Institute

Provided by NASA

Provided by NGAS

Provided by STScI

Provided by ESA

Integrated Science Instrument Module

(ISIM)

FGS NIRSpec

Provided by CSA

JWST Observatory

MIRI NIRCam

Page 4: James Webb Space Telescope Mission Status

4 4 Presentation to: IEEE Neuclear Space and Radiation Effects Conference

Telescope

Optical Telescope Element (OTE)

Integrated Science Instrument Module (ISIM)

Spacecraft

Sun Shield

Ground System

Page 5: James Webb Space Telescope Mission Status

5

Telescope Architecture Overview

Secondary Mirror Support

Structure (SMSS)

Primary Mirror Segment

Assemblies (PMSA)

Primary Mirror Backplane Assembly (PMBA)

Aft Optics

Subsystem (A0S)

Secondary Mirror

Assembly (SMA)

• PM Backplane Support Structure (PMBSS)

• PM Backplane Mechanism

Deployment Tower

Assembly (DTA)

Thermal Management

Subsystem (TMS)

• Deployable “Batwings”

• Fixed Diagonal Shield

• Deployable Stray-Light “Bib”

OTE Electronics

• Cold Junction Box

• Cold Multiplexer Units

Page 6: James Webb Space Telescope Mission Status

6

All Mirrors Are Complete!

Three flight primary mirror

segments and the secondary

mirror have been delivered to

GSFC

Aft Optics Assembly (AOS)

integration and testing complete

Flight Cryo Electronics • All 21 CMUs have been assembled

& completed cryo testing

• CJB has been assembled and has

completed its acceptance testing

• EM ADU has been delivered and

flight ADU is in board-level testing

Page 7: James Webb Space Telescope Mission Status

7

Assembly consists of ~3,200 bonded composite piece parts

Buildup of Telescope Flight Structure

Flight Deployable Tower Integration Underway

Flight Backplane Center Section

assembly is complete !

BSF Assembly Initiated

99% of composite billets and 87% of

composite parts and 91% of all invar fittings

are complete

Wing production continues

100% of composite parts are complete

Page 8: James Webb Space Telescope Mission Status

8

Telescope Assembly Ground Support Equipment

AOAS Hardware has been installed at GSFC

Ambient Optical Alignment Stand Complete

Page 9: James Webb Space Telescope Mission Status

9

Demonstrations of placement of mirror mass model on BESTA completed

Placement of engineering/flight spare mirror on BESTA scheduled for Jan.

Primary Mirror Segment Assembly (PSMA) Installation

Fixture (PAIF) delivered and installed on AOAS

Page 10: James Webb Space Telescope Mission Status

10 10 Presentation to: IEEE Neuclear Space and Radiation Effects Conference

Sunshield consists of three main

JWST Full Scale Model

Optical Telescope Element (OTE)

Integrated Science Instrument Module (ISIM)

Spacecraft

Sun Shield

JWST Full Scale Model

Ground System

Page 11: James Webb Space Telescope Mission Status

11

Log scale: 2.0” x 2.0” Linear scale: 2.0” x 2.0”

Sunshield Facts - Measures 73 x 40 feet (about the size of a

tennis court) and has 5 layers

- Contains 400 temperature sensors

- Sun side reaches 358 K (185o F)

- Dark side stays at 40 K (-388o F)

JWST’s 5 Layer Sunshield

Page 12: James Webb Space Telescope Mission Status

12

Sunshield Template Membrane Work On-Going Templates Verify Design/Manufacturing Prior to Flight Build

Preliminary Template Layer 3 Scan

Template Layer 3 - Completed & Delivered

Template Layer 4 – Completed & Delivered

Template Layer 5 – Completed & Delivered

Template Layer 2

Manufacturing in process

Template Layer 1

Manufacturing in process

Layer 3

Layer 5

Membrane Removed From Container

Membrane Installed Onto Rim

And Deployed

Page 13: James Webb Space Telescope Mission Status

13 13 Presentation to: IEEE Neuclear Space and Radiation Effects Conference

Integrated Science Instrument Module

JWST Full Scale Model

Optical Telescope Element (OTE)

Integrated Science Instrument Module (ISIM)

Spacecraft

Sun Shield

JWST Full Scale Model JWST Full Scale Model

Flight ISIM

Structure

Ground System

Page 14: James Webb Space Telescope Mission Status

14

ISIM is the Science Instrument Payload of JWST

Approximately 1.4 metric tons, ~20% of

JWST by mass

The ISIM system consists of:

Four science instruments

Nine instrument support systems:

• Optical metering structure system

• Electrical Harness System

• Harness Radiator System

• ISIM electronics compartment (IEC)

• Cryogenic Thermal Control System

• Command and Data Handling System

(ICDH)

• ISIM Remote Services Unit (IRSU)

• Flight Software System

• Operations Scripts System

Page 15: James Webb Space Telescope Mission Status

15

INSTRUMENTS

Page 16: James Webb Space Telescope Mission Status

NIRCam will provide the deepest near-infrared images

ever and will identify primeval galaxy targets for NIRSpec

Developed by the University of Arizona with Lockheed Martin ATC

Operating wavelength: 0.6 – 5.0 microns

Supports OTE Wavefront Sensing

Current Status

Cryo-Vac 1 testing has completed.

• All objectives of test met

• Stray light found in SW channel and light leak in LW channel.

• Optical performance looks very good

Cryo-Vac 2 is underway

• Temporary stray light fixes are in place for Cryo 2. Flight fixes to be installed following the test

Delivery dates to GSFC for completion of environmental testing

Mid-Feb. to Early April depending on approach taken to test stray light and light leak fixes

Will not be included in ISIM Cryo Vac #1 16

Module A

Module B

NIRCam Entering Chamber for

Cryo Testing

Page 17: James Webb Space Telescope Mission Status

NIRSpec Will Acquire Spectra Of Up To 100 Galaxies In A

Single Exposure

Developed by the European Space Technology Center (ESTEC) with

Astrium GmbH and Goddard Space Flight Center Operating wavelength: 0.6 – 5.0 microns

Aperture control:

• Programmable micro-shutters, 250,000 pixels

• Fixed long slits & transit spectroscopy aperture

• Image slicer (IFU) 3x3 arc sec

Current Status Flight spare optical bench being utilized because of cracks in original flight bench

• Completed instrument reintegration and end to end optical path verification

• Held close-out meeting for the bench crack issue

Late discovery of fatigue issue with kinematic mounts (OBKs) • Will require replacement following the SI level cryotest in February

Successful PER conducted

MSA issue and detector debond

Delivery to I&T scheduled for July 2013 ISIM Cryo Vac Test 1 will use NIRSpec Engineering Test Unit

17

Page 18: James Webb Space Telescope Mission Status

MIRI will detect key discriminators that distinguish

the earliest state of galaxy evolution from more

evolved objects

Developed by a European Consortium and JPL Operating wavelength: 5 - 29 microns

Coronagraphic imager and Spectroscopy

Current Progress Delivered to GSFC at end of May

Post-ship functional testing and metrology successfully completed

ISIM flight electrical system testing (EICIT, IVT) complete. • FSW change required for ambient functional completion (2 days) in January

18

MIRI in Clean Room

at GSFC

Page 19: James Webb Space Telescope Mission Status

Developed by Canadian Space Agency with ComDev Operating wavelength: 0.8 – 4.8 microns

Current Progress Delivered to GSFC at end of July

Post-ship functional testing and metrology successfully completed

FGS/ISIM Electrical Check-Out has initiated

FGS provides imagery for telescope pointing control & imaging

spectroscopy to reveal primeval galaxies and extra-solar planets

19

Page 20: James Webb Space Telescope Mission Status

20

• ISIM Command & Data Handling Units (ICDHs) 1 & 2

• Delivered to ISIM I&T

• ISIM Remote Servicing Unit (IRSU)

• Delivered to ISIM I&T

• ISIM Electronics Compartment (IEC)

• Delivered to I&T August 14

• OTE Simulator (OSIM)

• Cryo certification testing complete and out of SES Chamber

• Test results review conducted October 15-16

• OSIM delivered to ISIM I&T in Aug.

• Cryo recertification process scheduled to start in Jan.

ISIM Status

Flight ICDH

Flight IRSU

Flight IEC

Page 21: James Webb Space Telescope Mission Status

21 21 Presentation to: IEEE Neuclear Space and Radiation Effects Conference

Spacecraft

JWST Full Scale Model

Optical Telescope Element (OTE)

Integrated Science Instrument Module (ISIM)

Spacecraft

Sun Shield

JWST Full Scale Model JWST Full Scale Model

Ground System

Page 22: James Webb Space Telescope Mission Status

22

Component level designs reviews continue leading to S/C CDR in Dec. 2013

including:

Solar Array PDR

Reaction Wheel Assembly PDR

Deployment Unit Converter PDR

Propellant Management Device Concept Review

Command and Telemetry Processor CDR

Battery PDR

S/C Mockup Completed

Flight Solid State Recorder Delivered

Flight Solar Cells Delivered

Several Component level tests in progress including

CCU EQM in EMI/EMC testing

Flight TAU Vibration Testing

L2 Thermal Control Coating for LVIR Radiation Testing

EM Transponder functionality risk reduction testing

Spacecraft Status

Page 23: James Webb Space Telescope Mission Status

23

SSR Flight Unit Delivered To I&T

Ka-band Modulator

Engineering Model

Upgraded MRE-1 Thrusters with

shunts Instrumented MRE-1

Thruster

High Gain Antenna and

Medium Gain Antenna

Type-2A SCSim & IES

Command Control Unit

EQM

S-Band

Transponder EM

LVIR Forging

Ka-Band Filter

Star Tracker

Spacecraft Progress

Various Flight and Engineering Model Components Are In Fabrication

Page 24: James Webb Space Telescope Mission Status

24

Ground System

24 Presentation to: IEEE Neuclear Space and Radiation Effects Conference

Spacecraft

Optical Telescope Element (OTE)

Integrated Science Instrument Module (ISIM)

Spacecraft

Sun Shield

Page 25: James Webb Space Telescope Mission Status

25

Ground Segment and Operations Status

Majority of current effort is geared towards preparations for and support of

ISIM I&T

STScI contributing test engineers, operations products (onboard scripts,

project reference databases) and data analysis

NGAS contributing operations products (procedures, telemetry format tables),

review of limitations and constraint implementation and simulator support

Releasing updates of Common Command and Telemetry System (CCTS),

Flexible Image Transport System Writer (FITSWriter), science pipeline,

NIRSpec noise reduction software as needed

Adding additional data storage capabilities at multiple testing locations to

enable long-term archive of test data

• Also supporting upgrade, relocation of various SITS, SIDU systems

Certification Lab being heavily utilized for operations product certification, test

rehearsal

Page 26: James Webb Space Telescope Mission Status

26

Ground Segment and Operations Status

Science and Operations Center (S&OC)

General

• Released updated version of Science Operations Design Reference Mission

(SODRM)

Operations Scripts Subsystem (OSS)

• Certified and delivered onboard scripts for MIRI ambient testing

• Developing and testing onboard scripts for ISIM Cyro #1 testing

Project Reference Database Subsystem (PRDS)

• Delivered multiple databases for ISIM I&T, spacecraft simulator (SCSim)

Proposal Planning Subsystem (PPS)

• Release 1.5 of Exposure Time Calculator (ETC) prototype available to potential

users on STScI website

Wavefront Sensing and Control (WFS&C) Software Subsystem (WSS)

• Conducting testing of WSS Build 1.1

Data Management Subsystem (DMS)

• Conducting System Design Review #2 December 6,7

Page 27: James Webb Space Telescope Mission Status

27

Ground Segment and Operations Status

Institutional Systems

Deep Space Network (DSN)

• Utilizing Solar Dynamics Observatory (SDO), Goldstone 34m antenna to collect

performance data that will be indicative of Ka-band receiver implementation loss,

antenna pointing loss for JWST

• Performed successful testing of NGAS S-band transponder engineering model at

GSFC RF lab

• Updating documentation for TDRS, ESTRACK launch and ascent support

Flight Dynamics (FD)

• Supporting multiple analyses for determining orbit box size, launch windows, mass savings

Communications Service Office (CSO) [the former NISN]

• Supporting planning for JSC network configuration

Page 28: James Webb Space Telescope Mission Status

28

OTE + ISIM = OTIS

TESTING

Page 29: James Webb Space Telescope Mission Status

29

OTE/OTIS I&T Flow

Modal Surveys

Prep / Ship to

GSFC OTE

I&T

Integrate

Structure

Deployment Tests

Prep/Ship To NGAS

Observatory

I&T

Integrate Flight

Optics

Ship to JSC/CryoVac Prep

•Walkout OTE for optical I&T

•Release SMSS at field joint

Begin TMS install

• Install mass simulators

•Stowed Modal Survey

•Deployed Modal Survey

• Install Wings, SMSS,

DTA, harness

•Perform deployment & repeatability tests

Pre-Env.

Test

• COCI

• Alignment Metrology

• Electrical Functional

Integrate

Flight ISIM

(Begin Obs. I&T)

• Integrate Flight ISIM

• Integrate Flight IEC

• Integrate Radiators•Complete TMS install

Observatory (OTIS)

Cryo Optical Test

•Verifies OTE-ISIM

Alignment

•Cross check optical and thermal performance

Post Env.

Test

Acoustic &

Sine-Vibe Tests

•Electrical Functional

•1st Motion Checks

•COCI

•Obs. Level: CST, EMC,

•Acoustic, Shock Vibe,

Deployment

• PMBSS, Wings, DTA,

Harnesses

•SMSS manufactured at NGAS

•Electrical Functional

•SMSS Walkout

•Wing & DTA Deployment• Configure OTE for cryovac test

Receive OTE

Structures at NGAS

PMSA 1-18

AOS & SMA

Green=Test

Peach= Integration

Blue=Shipment

Page 30: James Webb Space Telescope Mission Status

30

Prior to final Observatory Integration the OTE + ISIM (OTIS) will be tested in

a large chamber at JSC

Modifications to Chamber A are completed creating the world’s largest

Cryo-Vacuum Chamber

Functional Testing Complete

• Overall functional operations finished on 8/20

• All primary objectives were met

OTE + ISIM = OTIS

GHe Door Shroud Installation

Page 31: James Webb Space Telescope Mission Status

31

OTIS Test GSE Architecture and Subsystems Status

Center of Curvature Optical Assembly

(COCOA)

• Multiwavelength interferometer, null,

calibration equipment, coarse/fine PM

phasing tools, Displacement Measuring

Interferometer

Testing at MSFC-XRCF

Completed Cryo Vac Test - excellent

optical and thermal results

Contamination Cert. – complete @ 15X

better than requirement

Being stored at XRCF

3 Autocollimating Flat Mirrors (ACFs)

• Piston and Tilt actuation

1st unit complete. 2 & 3 polished

Cryo Position Metrology (CPM)

• 4 photogrammetry (PG) windmills

in warm canisters

Canister delivered. Cryo test in

progress.

• Absolute Distance Measurement

(ADM) on HOSS

• Targets and codes

Cryo tested target

Tube holders at XRCF.

• Scale Bars

Post PDA

Hanging Configuration

• Down Rods

• Upper Suspension Frame (USF)

• Telescope Tension Rods

• Hardpoint Offloader Support Structure

(HOSS)

Passed dCDA June 12, ’12

Contract in place. Manufacturing has started

Chamber Isolator

Contract in place for Isolators 2-6

Manufacturing has started.

LN2 and Helium Cryogenic Shrouds

and “barn door”

Space Vehicle Thermal

Simulator (SVTS) w/ cryo-cooler and

electronics

Concept

AOS Source Plate and cable w/

fishing pole support Concept

Deep Space Edge Radiation

Sink (DSERS)

Concept Verified

MSFC-XRCF

31 JWST.ISIM. SEPT. MPR

Page 32: James Webb Space Telescope Mission Status

32

TRANSPORTATION

Page 33: James Webb Space Telescope Mission Status

33

Space Telescope Transporter for Air, Road & Sea (STTARS)

STTARS Is Completed

Page 34: James Webb Space Telescope Mission Status

34

SCHEDULE STATUS

Page 35: James Webb Space Telescope Mission Status

35

JWST Master Schedule 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019

FY10 FY11 FY12 FY13 FY14 FY15 FY16 FY17 FY18 FY19

2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3

JWST Overview

Schedule

Major Mission Milestones

Integration & Test

OTE

Primary Mirrors

Flight Structure (PMBSS)

Sunshield

Spacecraft

ISIM I&T

NIRSpec

MIRI

NIRCam

FGS

Cryo Cooler System

Ground Segment

Launch Segment

4

CDR

3

TRR

4

MOR

9

SIR

12

KDP-D

8

PSR

9

FRR/KDP-IV

10

LRD

4

ORR

4

SC Panel Integ

7

CCA,PropInteg

8

SS Integ

10

SC Test

7 9

SC/OTE I&T

5 9 10

Launch Site

2

JSC CH AGSE Install

4

PF Install/ Test

11 4

OTIS I&T

7

10

PF SMSS/StrutInteg

8 11

PF Optics Integ

2

8

Start EDU3rd Cryo Test

4

Del PFPMSA

9

1st Batch

2

Last Batch

9

PMSA Gear MotorRe-Qualification

12

Gear Motor Rework on Last PMSA

Flt OpticsInteg

4 10

3

BSF Assy Start Wing Assy StartFlight

PMBSS

7

OTE StructureAssy/Test

4

TemplateMembrane Fab

1 5

Flt Membrane MRR Flt Membrane Fab

11

2

Astro Tube Fab

9 11

GSE Design/Fab

3

12

Structure Mfg & Test

12 8

Integ Skeleton& Membrane

2

12

CDR

7

SC Panel

11

SC Structure

7

Start I&T

3

PER

8

9

10

Del Flt ISIM to OTIS

1

ETU Del

4

Flt Del

8

3

STM Del

5

Flt Del

5

ETU Del

11

Flt Del

6

5

ETU Del

7

Flt Del

4

Fit CheckCHA

7

Non-Flt CHA

6

Flt CHA

10

ETUCCES/CELS

2

Flt CTA

11

Flt CCA/CCE(Spares)

1

Flt CCA/CCE

4

CCTS B2.3

9

CCTSB3.0

1

CCTSB3.1

5

CCTSB3.2

2

CCTSB3.3

9

CCTSB4

10

Begin End-to-EndGrnd/Flt Seg Testing

10 4

Comissioning

12

LV Lift Perf. Verified

2

Safety Submittal #2

8 3

Flight Adapter for Elec/Mech Fitcheck

1

Ariane Adapter 2

Safety Submittal #3

5 6

RAMF

7

DCI Release 2 (Final)

4

PCLA6

11 1

Flight Adapter Fit Check & Shogun

3

PCLA7

10 7

FCLA2

1 3

FCLA3

6 9

LV Readiness Review (RAV)

4

3

2

6

8

16

8

14 Months of Funded Critical Path Slack 4 Months at Observatory I&T 3 Months at OTIS level 7 Months of Slack at OTE level

3

2

7

3

Baseline 5/24/12 Rev K

1

9

7

Impact from GPM slip*

2

* Project is actively seeking ways to recover lost schedule margin

Page 36: James Webb Space Telescope Mission Status

36

JWST Master Schedule

CY 2011 CY 2012 CY 2013 CY 2014 CY 2015 CY 2016 CY 2017 J

CY 2018 F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J

Spacecraft I&T

ISIM Envir Test/Detector C/O

ISIM & Instrument Fab/Assy/Test

Optics Integ

Mirror Fab

Sunshield Mfg, Fab, & Test I&T Sunshield Design/Dwgs

LRD

SC Subsystem Development

ISIM Integ

Launch

Site SC

Structure

To I&T

SC

Panels

To I&T

4

8

3

16

8

2

6

7

3

SC Fab/Assy/Test

PMSA Gear Motor Rework

CY 2019

OTIS I&T

Obs I&T

OTE

OTE Fab Assy & Test

2

Impact from GPM slip* Need SES For OSIM

SES Avail

* Project is actively seeking ways to recover lost schedule margin

Page 37: James Webb Space Telescope Mission Status

37

JWST FY12 Milestones Note: Milestones assume the budget approved in APMC Decision Memo of 9/23/11, profile in quarterly

template of 9/23/2011, and timely availability of FY12 funding. As of 9/30/12

Month Milestone Responsible Comments

Oct „11 Initiate Delivery of Ambient Alignment Optical Stand (AOAS) to GSFC ITT Completed 10/4

Nov ‟11 ISIM Electronics Simulator Engineering Model Test Bed Complete

Software Development & Verification Simulator Delivery to Software Development Lab

ISIM

NGAS

Completed 11/15

Completed 10/27

Dec ‟11 JSC Helium (GHe) floor shroud installed

ESA NIRSpec preliminary root cause and corrective action assessment

JSC

ESA

Completed 10/26

Completed 12/15

Jan ‟12 Spacecraft-Optical Telescope Element (OTE) Vibration Isolation IDR 3/4 (CDR)

Center of Curvature Optical Assembly (COCOA) Assembly complete

S/C equipment panel Mechanical Ground Support Equipment (MGSE) Preliminary Req Review

Complete Aft Optic System Integration & alignment

Update Program Plan and Program Commitment Agreement to reflect replan

NGAS

ITT/GSFC

NGAS

NGAS/Ball

HQ

Completed 12/15

Completed 1/13

Completed 12/1

Completed 12/22

Completed 1/28

Feb ‟12 Complete assembly & verification testing (MSFC testing) of Primary Mirror Segment Assemblies (PMSAs )

JSC GHe wall shrouds installed

NGAS/Ball

JSC

Completed 12/19

Completed 12/29

Mar ‟12 Complete System Engineering Team thermal margin assessment

Optical Ground Support Equipment (OGSE) -1 Test Concept assessment complete

GSFC

GSFC

Completed 3/19

Completed 3/1

Apr ‟12 ICDH Flt #2 delivered to ISIM I&T

Flight MIRI delivery

Sunshield Support Structure IDR 3/4 (CDR)

Deployable Tower Assembly (DTA) Composite flight components fabrication complete

ISIM

ESA

NGAS

NGAS/ATK

Part failure in T/V. Corrected & completed 5/16

Completed 5/29

Completed 3/21

Completed 2/28

May „12 Complete COCOA assessment at ITT

Complete Sunshield template layer 5 shape verification

Conduct review of initial implementation of replan

ITT/GSFC

NGAS/Nexolve

HQ/SRB

Completed 3/9

Completed 4/23

Completed 5/30

Jun ‟12 JSC Chamber mods complete

Communications support structure IDR 3/4 (CDR) complete

Hardpoint Offloader Support System (HOSS) & Upper Suspension Frame Design Audit Complete

Sunshield deployment MGSE SRR (was originally PDR – typo)

JSC

NGAS

ITT/GSFC

NGAS

Completed 6/30

Completed 6/13

Completed 6/21

Completed 6/28

Jul ‟12 Program Office agreement on FY13 spending plan

Flight FGS delivered

ISIM Flt S/W Integrated Construction 12.6(“Build” 12.6) to ISIM I&T

Solar array Preliminary Design Audit

Cryo Cooler Cold Head Assembly delivered to ISIM I&T

Complete flight Secondary Mirror Support Structure End Fitting Fabrication

HQ/GSFC

CSA

ISIM

NGAS

NGAS/JPL

NGAS/ATK

Completed 7/10 - Approved by SMD AA

Completed 7/30

Completed 5/11

Completed 6/14

Flight CHA to be delivered in June 2013. Work

around In place.

Completed 7/13

Aug ‟12 Order remaining Chamber A isolators from Minus K ITT/GSFC Completed 8/9

Sept „12 Flight NIRCam Delivered

OTE Simulator delivered to ISIM I&T

Start Photogrammatry (PG) canister cryo test

Complete Primary Mirror Backplane Support Structure center section

Flight NIRSpec delivered

UoA/LMATC

ISIM

ITT/GSFC

NGAS/ATK

ESA

NLT delivery 8/1013 Work around in place

Completed 8/17

Completed 8/9

Completed 3/28

NLT delivery 8/2013. Work around in place.

Page 38: James Webb Space Telescope Mission Status

38

JWST FY13 Milestones Note: Milestones assume the budget approved in APMC Decision Memo of 9/23/11, profile in quarterly

template of 9/23/2011, timely availability of FY13 funding, and having access to the SES by January 2, 2013.

Month Milestone Organization Comment

October „12 Funding Direction per plan

Battery PDA

Command & Telemetry Processor (CTP) IDR4

Optical Ground Support Equipment #2 Audit

HQ

NGAS

NGAS

OTIS

Completed 9/15

Completed 9/6

Completed 8/30

Completed 10/17

November ‟12 Bib & Batwing PDA-2

Spacecraft J2 Equipment Panel IDR3/4

Complete integrated MIRI/ISIM electrical checkout

NGAS

NGAS

ISIM

Completed 10/18

Completed 10/4

Completed 11/19, 2 days of testing required in Jan. due to FSW bug

(divide by zero)

December ‟12 CTP Engineering Model #1 Delivered to Engineering Model Test Bed

Beam Image Analyzer re-integrated onto OSIM

Complete integrated FGS/ISIM electrical checkout

NGAS

ISIM

ISIM

January ‟13 Aft Optical System Complete

Space Telescope Transporter for Air, Road & Sea (STTARS) delivery

Data Management Subsystem System Design Review #2

Deliver MIRI Shield to ISIM I&T

NGAS

OTIS

STSci

ISIM

February ‟13 Secondary Mirror Support Structure Floor Assembly Jig complete

Wing Assembly complete

Spacecraft Primary Structure Manufacturing Readiness Review (MRR)

OSIM Cryo Certification Test #2 Start

NGAS

NGAS

NGAS

ISIM

March ‟13 Funding Direction for remainder of the year (assuming a continuing resolution)

Deliver last Cryo Multiplex Unit

Fine Sun Sensor CDA

Space Vehicle Thermal Simulator SRR

Complete FGS & MIRI integration onto ISIM

HQ

NGAS

NGAS

OTIS

ISIM

April ‟13 Sunshield Template Membrane Layer 2 fabrication complete

Communications Subsystem CDA

Wave Front Sensing & Control Software Build 1.1

NGAS

NGAS

STSci

May „‟13 Backplane Support Fixture (BSF) Assembly Complete NGAS

June ‟13 Spacecraft Thermal Control System CDA

Spacecraft Harness CDA

JSC Downrods & Telescope Rod complete

ISIM Cryo-vacuum test #1 (Risk Reduction) start

NGAS

NGAS

OTIS

ISIM

July ‟13 Cryo-cooler flight Cold Head Assembly delivered to GSFC

Spacecraft FSW Build 2.1 Test Readiness Review

Program Office agreement on FY14 spending plan

JPL

NGAS

HQ

August ‟13 NIRCam Delivered to ISIM I&T

BSF/Center Section Integration complete

UoA/LMATC

NGAS

September „13 Flight NIRSpec delivered

Sunshield Membrane Cover Assembly MRR

Mass margin return-to-green complete

ISIM Cryo-Vacuum test #1 complete

Chamber A Upper Support Frame ready for paint

ESA

NGAS

NGAS

ISIM

OTIS

Page 39: James Webb Space Telescope Mission Status

39

CONCERNS

Page 40: James Webb Space Telescope Mission Status

40

Thermal margins have experienced degradation since the Mission CDR due to a

variety of sources (Liens) across the observatory elements:

Design maturation

Analysis latency (i.e. analysis catching up to design)

Model errors

Issue is closed

Cryogenic thermal margins have been brought back to acceptable levels

without any impact to mass

Thermal architecture modifications including Aft Deployed ISIM Radiator to

increase the radiative cooling capability of the observatory have been

completed

Concerns – Thermal Margin Issue

–V1 Aft Deployable ISIM Radiator (ADIR)

40K Radiators

RTG ADIR

Solution Shows

Robust

Performance

Side radiator

moved to

ADIR

Deployment

Rotation

Page 41: James Webb Space Telescope Mission Status

41

Issue Closed Flight detector testing shows a degradation in pixel operability

• Impacts NIRCam, NIRSpec, and FGS

Detector FRB complete • Found that detector degradation is caused by a design flaw which degraded its

performance

• Determined manufacturing and/or post-manufacture handling process changes are

appropriate

• Defined tests needed to screen-out degradation prone parts and insure the

continued integrity of flight part

Manufacturing of Flight Detectors underway • 1st set off three shortwave SCAs detectors completed testing at Teledyne and are

at Arizona

• Next 3 shortwave SCAs have completed test and are expected to deliver to

Arizona December 10. • Preliminary results on these parts look good

• Another 3 parts will have begun testing at Teledyne

On Track for Detector Swap Out in 2014

3rd ISIM Cryo Test Added

Concerns – Detector Degradation

Page 42: James Webb Space Telescope Mission Status

42

Concerns - Mass Margin Issue

Unexpected mass increases for Pendings (Mass Liens) and Potentials

(Mass Threats). Among them:

Spacecraft Bus increases primarily for harness (~ 112kg)

Mass impacts due to the recent Coupled Loads Analysis (~ 10kg)

Although the Project is carrying 208.3 kg of mass reserve, these increases

will decrease this to unacceptable levels if uncorrected.

Coordinated efforts to improve the mass margin have been actively

pursued by the Observatory and Systems Teams since March of 2012.

The pursuit of these opportunities is being coordinated and monitored as part

of the Architecture Working Group (AWG).

These savings opportunities are to be implemented in time to have system

level analysis completed in time for the Spacecraft Bus CDR currently

scheduled for December 2013.

Page 43: James Webb Space Telescope Mission Status

43

Instrument Schedules MIRI and FGS delivered

NIRCam and NIRSpec will arrive too late for 1st ISIM Cryo Test (CV-1)

• NIRCam – Instrument Module level cryo-vacuum test #1 completed and cryo 2 has begun, but

execution of cryo 1 was much longer than expected

– Must resolve stray light and light leak issues

– NIRCam will not be delivered in time for CV1

• NIRSpec – Instrument integration is complete but deliver date has slipped to June 2013

– Existing Optical Bench Kinematic (OBK) Mounts did not undergo sufficient thermal

tempering and etching of the alpha layer. As a result, fracture toughness is marginal and

may not meet requirements of ISIM pad motion load case and the ISIM vibration test

» New OBKs are being manufactured

NIRCam and NIRSpec will be installed in ISIM for CV2

GPM SES Testing Impact on ISIM I&T ISIM was scheduled to start Jan. 1, but slips in GPM Thermal Vac have impacted ISIM

start date in SES chamber

ISIM schedule reserves are impacted by GPM exit from the SES

• GPM must be done with the chamber by end of Jan. to constrain reserve impact to only 1

month

• Physical removal of GPM from the chamber does not equal facility readiness for ISIM. Chamber has to

be clean, dry and empty for the next “customer”. Likely add 1-2 weeks from actual GPM removal

Concerns - Instrument Delivery Schedule and ISIM I&T

Page 44: James Webb Space Telescope Mission Status

44

Why does JWST have a cryocooler?

Telescope and instruments are passively-cooled behind sunshield. HgCdTe near-IR detectors in the

three near-IR instruments operate at ~37K, and telescope operates at 50+K and below to limit

background

The single mid-IR instrument (MIRI), which uses Si:As detectors requires further cooling to 6.7K

JWST cryocooler is a combination of a pulse tube (PT) and a Joule-Thomson (JT) cooler. PT part

has three stages, precooling from room temps to as low as ~14K, enabling JT to engage and

operate down to 6.2K

Cooler compressors and control electronics reside in spacecraft bus, but MIRI heat exchange

occurs several meters away inside ISIM

Cryocooler challenges particular to JWST – cryocooler performance margin, heat loads, vibration

isolation/attenuation, distributed integration

PT precooler must overcome heat loads to enable JT to operate

• Must have margin to cover uncertainties in heat loads and unknown-unknowns to ensure MIRI detectors will

reach operating temperature

Cooling lines between compressors and MIRI must accommodate deployment and be secure for

launch loads while being as decoupled thermally from rest of observatory as possible

Compressor vibration must be limited to enable diffraction-limited optical performance at 2 microns.

• Requires vibration isolation between compressors and bus, as well as vibration attenuation of shorting path via

cryocooler lines

Cooler hardware is delivered in pieces to different and separate integration and test activities (ISIM,

OTE, S/C and OTIS)

Concerns – MIRI Flight Cooler

Page 45: James Webb Space Telescope Mission Status

45

Various issues have caused schedule delays (biggest risk), but progress is being seen

Flight valve production

• Cryo bypass valves for JT bypass during cooldown and for de-icing exterior of

cooler lines are still in development – Difficulty meeting leak spec, especially given power/thermal dissipation limitations

– Pursuing parallel valve developments

Electronics schedule

• Technical issues nearly resolved, but only 1 month schedule margin to need date in

2015 – Examining ways to accelerate and add slack

Pulse Tube (PT) pre-cooler performance

• Modified flight design prototyping effort continues – Design adjustments being made to 2nd and 3rd PT stages to assure required performance

» Flight prototype demonstration scheduled for early CY2013

Concerns – MIRI Flight Cooler

Page 46: James Webb Space Telescope Mission Status

46

NIRSpec Micro-Shutters

During testing of the JWST Micro-shutter subsystem at IABG facility in Ottobrunn,

Germany , anomalous behavior was witnessed in flight Micro-shutter Subsystem (MSS)

• Micro-shutter Array Quadrants 1, 2 and 4 show a significant to severe increase in failed closed

shutters

Current theory is that during vibration or acoustic testing shutter shifts in plane and is

pushed into the light shield where it is wedged closed

Following root cause determination, assess both instrument and MSA design

modifications to mitigate the problem

• Acoustic testing currently underway has replicated the failure on an MSA test unit. Several

more tests of this unit, both stand-alone as well as installed on the ETU NIRSpec, will be

conducted in the next two months

Production of a complete flight spare MSA is in process, with scheduled completion by

mid-2014

• Potential for replacement during the already planned detector swap-out activities

Detector De-BondFailure

A Flight FPA experienced a failure at the bond joint between the base of an SCA and

its mounting structure

• Spare FPA used for replacement in Flight NIRSpec

Failure FPA was shipped back to GSFC for failure analysis

• Evidence is mounting that the epoxy bond workmanship (contact area, adhesive batch

strength, etc) was the failure cause

Concerns – NIRSpec Micro-Shutters & Detector De-Bond Failure

Page 47: James Webb Space Telescope Mission Status

47

CLOSING REMARKS

Page 48: James Webb Space Telescope Mission Status

48

Excellent progress has been made over the last year!

Challenges still lie ahead

Schedule • Need to get rest of instruments in-house

• Continuous risk mitigation in progress – “Always have work-arounds”

Technical • Mass Recovery, Cryo cooler, detector swap, micro-shutters, etc.

Integration – Starting “Put all the pieces together”

Testing • ISIM, OTIS, Observatory, etc.

Project continues execute to baseline!

Closing Remarks

Page 49: James Webb Space Telescope Mission Status

49

QUESTIONS