Report - May 2011 …Transforming Jamaica’s infrastructure JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP)

Upload: phungdang

Post on 06-Mar-2018

238 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Report - May 2011

…Transforming Jamaica’s infrastructure

JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP)

Page 2: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

EXECUTIVE SUMMARY The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under

which the island’s road infrastructure will be rehabilitated and restored over the next five years.

The Jamaica Development Infrastructure Programme (JDIP) is the outcome of a Preferential

Buyer’s Credit (PBC) facility from the Government of China through the China Export-Import

Bank and the programme of works is being executed by the Contractor, China Harbour

Engineering Company (CHEC) Limited. The first year works are being implemented by the

National Works Agency (NWA) on behalf of the Ministry of Transport and Works (MTW).

The programme will address the identified problems of the road and drainage network of the

entire island which has reached a critical stage of deterioration. This deterioration is largely due

to a barrage of intense named weather systems such as Hurricanes Ivan (2004), Dean (2005),

Gustav (2008) and Nicole (2010).

The more than 10,000-km of parochial/community/farm roads which are in severely deteriorated

condition is also being addressed by this programme. It is well known that this deterioration is

due in part to the lack of rationalized periodic maintenance over a long period of time, improper

roadway elevations as well as the need for good, sustainable drainage systems.

In addition the constant risk of damage to the properly maintained infrastructure by natural

events such as flooding caused by sustained heavy rains over periods lasting between two and

seven days at a time is always a cause for concern while human factors such as the overloading

of trucks and other vehicles continue to severely damage our road infrastructure with impunity.

The hilly terrain, delays and other challenges in land acquisition and the inadequacy in

construction standards often due to economic constraints, also render the parochial roads and/or

arterial national highways vulnerable and susceptible to the following problems:

Page 3: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

The hidden defects caused by inconsistency and difference in road design standard;

The unfavourable horizontal and vertical linear index, poor traffic condition and low traffic

capacity;

Too many grade intersections or crossings which retard the speed of safe traffic movements;

Too densely-distributed traffic conflict points at grade intersections causing vehicles to

spend a too much time in allowing the other road users required safe access (“giving way”

frequently);

The locations of many of the highways along the coast are low in elevation so traffic is

liable to be interrupted by hurricanes and floods. (This applies mainly to our Class A main

roads);

Most roadway and pavement of the highways along the foot of mountain lack

appropriate/adequate gutters or other drainage system and become spillways in the rainy

season, usually causing roadway to be transversely washed away leading to serious damage

to the highway, and the pavement is often severely scoured or even completely destroyed.

The defect or damage of road network caused by the factors outlined has had observed negative

impacts on economic growth, the commercial livelihood of the populace, personal life and

property, transport, traffic and tourism. The fact is that most roads now need to be widened,

reconstructed or substantially rehabilitated to meet the needs of the island adequately.

Although the problems are well known and are documented, due to the lack of sufficient

financial support from the Capital A Budget of the Government of Jamaica, the reconstruction

and periodic maintenance of the existing road network fall behind and the road condition become

progressively worse.

To address this critical problem which hampers economic progress and to end the ever-

increasing damage to the roads, the Jamaican Government has established a package of programs

by levying a given portion of fuel surcharge for Reconstruction, rehabilitation, maintenance and

development of road network.

Page 4: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

The roads slated for maintenance and rehabilitation under the JDIP are included in the main and

parochial network and are all essential for the movement of goods and services throughout the

island. As was previously stated, the further deterioration of these roads and infrastructure will

continue to have even more adverse effects the economy of the communities along the affected

corridors if the problems are not addressed urgently.

The NWA and CHEC have agreed on the Master list of projects from which works will be

designed, priced and awarded upon the approval of the MTW over the next five years based on

the priority assigned. The selection of Projects will take into account the priorities of the

National Transport Policy, the Road Sector Maintenance Master Plan and consultation with

stakeholders including the elected representatives. Local subcontractors have been nominated for

most of the rehabilitation works, while CHEC will focus on the design and implementation of the

larger projects. The NWA will also work closely with the Parish Councils during

implementation.

The year 1 and 2 works have now started in earnest and the public is excited as the signs are

erected to herald the upcoming works.

The identified works for Year 1 and 2 can be classified in the following main categories:

A. Rehabilitation of parochial and housing scheme roads

B. Rehabilitation of main roads

C. Construction of retaining walls

D. Purchase and construction of bridges

E. River training works

F. Traffic Management

G. Institutional Strengthening

Page 5: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Rehabilitation of Parochial and Housing Scheme Roads

As was noted before, The National Works Agency collaborated with the Department of Local

Government to identify a number of projects to be considered for implementation within the

USD-400-million loan framework to facilitate the improvement and general rehabilitation of the

existing municipal road system, including a number of housing scheme roads which require

urgent attention. Works have already begun in the residential community of Havendale, St.

Andrew and Karlston Glades in Clarendon and Fairview Community Roads in St. Catherine.

Housing Scheme Roads

Over the years numerous Housing Developments have suffered from the problem of poor road

condition usually caused by inadequate drainage.

Under the JDIP, Housing Scheme Roads were prioritised based on size (population), strategic

location, traffic volume and urgency of condition. Fairview Housing Scheme in St. Catherine for

example, faces flooding during heavy rains and several residents had to abandon their homes.

Rehabilitation of Main Roads

According to the requirements of the National Works Agency as well as site visits made by

CHEC, the projects within the USD-400-million loan framework consists of the improvement of

arterial national highways as well as the general rehabilitation of existing municipal road system,

especially the urban roads which are mostly distributed in downtown area of Kingston, the

capital of Jamaica and the arterial roads to be reconstructed are dispersed in all areas of the

entire island, as listed below:

This programme will also address roads with critical routine and periodic maintenance needs.

Page 6: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Construction of Bridges

The construction of the bridges to facilitate the movement of people and goods between

communities as well as to address the safety concerns of the public has thankfully started. These

represent a few of the most critical bridges that are in need of urgent repairs and also the areas

where bridges need to be constructed over fords on major thoroughfare.

Work has now been initiated on the following bridges:

Eden Bridge, St. Mary

The existing bridge is a very narrow double span, concrete deck on steel

girders bridge. Located in the parish of St. Mary it crosses the Oracabessa

River. The bridge’s sole intermediate pier support is settling, as its foundation

has been undermined by scour. The bridge is located at a bend in the river and

protective river bank protection is necessary to contain the river within its

banks and to prevent damage to the new bridge. The proposed bridge has

been designed, with bridge components currently in NWA Storage.

Bull Bay Compact 200 Bridges

Two communities in the Bull Bay area are currently cut off from Main road

access. Citizens are forced to traverse the river in high run off periods. The

existing bridges are to be retrofitted and river training installed to contain the

river.

11 Miles Box Culverts, St Thomas

The 11 Miles Fords represents a safety issue during high rainfall events.

Motorists are at risk and St. Thomas is at risk of being cut off from Kingston

at these locations. Two box culverts are proposed to address this issue.

Page 7: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Port Maria Pedestrian Bridge, St Mary

A compact 200 modular pedestrian bridge is proposed to replaced the

collapsed structure and restore access for residents of Port Maria between the

main business area (east) and west bank.

The impacted communities welcome these works as they anticipate the expected benefits.

River Training Works

This component aims to carry out works to prevent excessive scouring and damage to properties.

It will also help protect our infrastructure assets.

The works include;

- Provision of Gabion Baskets

- Rock Revetment

- Sea Defence

- Bunding

- Desilting of channels

- Realignment of channels

Gabion baskets are currently being established at Llandewey in St. Thomas to sure up the areas

which are prone to breakaways.

Traffic Management

This aims to ease Traffic Congestion and resulting delays in several urban centres across the

island. Work will involve:

- Widening of intersections

Page 8: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

- Provision of new Traffic Signals

- Rehabilitation of new Traffic Signals

The Cross Roads Traffic Improvement project is one of the first beneficiaries of this programme.

The Year 1 and 2 JDIP Programme

The JDIP programme is now fully in progress and Figure 1 demonstrates the relative distribution

of the projects which have now been approved for each parish.

Figure 1

Commitment by Parish for the Jamaica Development Infrastructure Programme

Page 9: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

We should again remind the public that some of these projects proposed in the list provided may

be reorganized as the impact of the TS Nicole damage has affected the prioritization of the

interventions which were previously proposed. This will definitely not reduce the amount of

work to be done in each parish under the programme but specific roads may be dropped as others

are included or the scope of activities may be increased or reduced based on the current

state/condition of the road section.

Currently there are some sixteen (16) subcontractors undertaking about fifty-eight (58) projects

to address issues on over two hundred (200) road sections island wide. These activities are not

just improving the roads and the road conditions but are also providing valuable jobs and are

serving as catalysts to economic development in the areas where they are done.

Two (2) major projects, Christiana Development Road in Manchester and the Rio Grande Bridge

in Portland are being done under the direct supervision of the Contractor (CHEC). These projects

are expected to provide not just first class access to the communities they serve, but also to

stimulate economic development in the surrounding areas.

Conclusion

As the implementation of this programme which is a major undertaking by the Government of

Jamaica progresses, we anticipate that the benefits which will enhance the quality of life of the

citizens of Jamaica. We welcome the ability of this programme to stimulate economic growth

and development and we await the positive effects which will be brought by it.

This five year programme has been established by selecting areas and roads where the most

urgently needed interventions are to be implemented, but we are mindful that the country’s

current weather patterns has the potential to derail our most carefully planned activities. It

therefore means that the selection criteria used for the inclusion of roads and other components

will be applied on a continuous basis in order to address the most critical and pressing

infrastructure need in the most timely manner possible

Page 10: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Major Projects

Rio Grande Bridge

This bridge will guarantee access to and from Port Antonio for residents, businesses and visitors.

PROJECT OBJECTIVE

SCOPE OF WORKS

The pavement will have a design life of 20yrs

Road Works

The 450m approach road will match the just concluded North Coast Highway.

Bridge

Construction of a 210m length, 4-span, 2-lane bridge across the Rio Grande River. The bridge is

designed to accommodate the 50 year return flood.

Project Cost: US$28.8M

Main Contractor: China Harbour Engineering Company Ltd.

Progress to date: 27%

Duration: 20 months (Oct .2010-Jul. 2012)

Page 11: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Christiana Development Road

The intended purpose of the project is to reduce congestion in the town of

PROJECT OBJECTIVE

Christiana while improving travel times along the Manchester to Trelawny main road. An expected benefit from this project is also an increase in commercial activity.

SCOPE OF WORKS

The proposed development road will be approximately 1 km long and runs west of

Christiana town centre. It includes the construction of a typical 2 lane urban carriageway with

hard shoulders, drainage infrastructure, traffic signals, etc.

Main Contractor: China Harbour Engineering Company Ltd.

Duration: 12 months (March 2011-March 2012)

Progress to date

: 34%

Queens Borough and Cassia Park Bridges

The project is intended to improve the safety and efficiency of traffic transit in the Queens-

borough and Cassia Park community and environs.

Project Objective

SCOPE OF WORKS

The proposed works comprise of plate girder superstructures with a 2 lane roadway, sidewalks

railings and approaches, spanning approximately 38 & 30 meters respectively between

abutments. The works to be carried out will also include repairs to the existing waterway

Contract Sum: J$126,995,005.65 (Queensborough)

Contract Sum: J$151,267,432.06 (Cassia Park)

Main Contractor: China Harbour Engineering Company Ltd.

Sub-Contractor: Y.P. Seaton & Associates Limited

Duration: 12 months (March 2011-March 2012)

Page 12: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Progress to date: Queens Borough -10%,

Cassia Park - pre-construction activities in progress

Fern Gully Restoration and Rehabilitation Project-Stages 11&111

The project is intended to improve the safety and efficiency of traffic transit through the Fern

Gully and reduce the impact of flooding in the Ocho Rios community and environs.

Project Objective

The reconstruction of approximately 1.6km of the existing roadway through Fern Gully using

Rigid Pavement construction with ancillary roadside drainage. The pavement structure consists

of a Jointed Plain Concrete Pavement slab, with tied concrete shoulders; supported by a 150mm

cement stabilized aggregate base and a 150 mm granular sub-base on sub-grade.

Project Scope - Stage II

The construction of approximately 1km of reinforced concrete storm water ‘U’-drain including

the supporting infrastructure of box culverts, pedestrian sidewalk, and protective handrails along

the length of the proposed drain adjacent to the existing carriageway upon approach to Ocho

Rios. This drain will replace the existing open channel earthen drain.

Project Scope - Stage III

Contract Sum: J$535,442,285.00(Stage 11 & 111)

Main Contractor: China Harbour Engineering Company Ltd.s

Sub-Contractor: Y.P. Seaton & Associates Limited

Duration: 12 months (March 2011- March 2012)

Progress to date: Stage 11 – 10%,

Stage 111-pre-construction activities in progress

Page 13: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

GOJ/NWA: Jamaica Development Infrastructure Programme

CONTRACTOR: China Harbour Engineering Company Limited

SUBCONTRACTOR: Asphaltic Concrete Enterprise Limited

PROJECT TITLE: Lloyds – Lowe Mountain, Springfield

REPORTING DATE: May 2011

CONSTRUCTION PROGRESS SUMMARY: 90 %

Lloyds – Lowe Mountain (20% Complete)

BEFORE DURING

DURING

Page 14: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Construction of gabion retaining wall

Page 15: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Lloyd’s – Lowe Mountain (20% Complete)

DURING

RR wall under construction. RR wall and Parapet.

Page 16: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

GOJ/NWA: Jamaica Development Infrastructure Programme

CONTRACTOR: China Harbour Engineering Company Limited

SUBCONTRACTOR: Alcar Construction & Haulage Company Limited

PROJECT TITLE: Bath – Barrett’s Gap, Middleton, Stewart Mountain Road & Eleven Miles Bull Bay Box Culverts, St. Thomas (RW-034)

REPORTING DATE: May 2011

CONSTRUCTION PROGRESS SUMMARY: 23 %

Bath – Barrett’s Gap (10 % Complete)

DURING

RR wall foundation 1st tier being measured

Morant Crossing – Whitehall (15 % Complete)

Page 17: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

DURING

RR wall under construction Excavation for culvert

Friendship – Wilmington

DURING

Rehabilitation of the roadway

Page 18: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

GOJ/NWA: Jamaica Development Infrastructure Programme

CONTRACTOR: China Harbour Engineering Company Limited

SUBCONTRACTOR: Y.P Seaton & Associates

PROJECT TITLE: Hope Bay – Cooper’s Hill

REPORTING DATE: May 2011

CONSTRUCTION PROGRESS SUMMARY: 5 %

DURING

Excavation of side drains and basework underway

Page 19: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

GOJ/NWA: Jamaica Development Infrastructure Programme

CONTRACTOR: China Harbour Engineering Company Limited

SUBCONTRACTOR: Y.P Seaton & Associates

PROJECT TITLE: Mount Pleasant, Smithfield Road, Silver Hill and Norman Lane, Portland

REPORTING DATE: May 2011

CONSTRUCTION PROGRESS SUMMARY: 47 %

Bangor Ridge – Mahoe (Silver Hill) (12 % Complete)

DURING

Excavation for side drains and the channel being compacted to receive concrete for side drains

Page 20: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Mt Pleasant (32% Complete)

DURING

Roadway after priming and sanding

Friendship Road (41% Complete)

DURING

Construction of drainage structures (V and U Drains)

Page 21: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

GOJ/NWA: Jamaica Development Infrastructure Programme

CONTRACTOR: China Harbour Engineering Company Limited

SUBCONTRACTOR: Pavement and Structures Limited

PROJECT TITLE: IWP-003

REPORTING DATE: May 2011

CONSTRUCTION PROGRESS SUMMARY: 100 %

James Road

BEFORE AFTER

Tower Street

DURING AFTER

Patching of the roadway

Page 22: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

East Queen’s Street DURING AFTER

Second Avenue

DURING AFTER

Deanery Road

DURING AFTER Patching of potholes

Page 23: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

GOJ/NWA: Jamaica Development Infrastructure Programme

CONTRACTOR: China Harbour Engineering Company Limited

SUBCONTRACTOR: S & G Road Surfacing Materials Limited

PROJECT TITLE: Pedro Cross – Lititz, Santa Cruz Bypass, Institution Drive, Black River – Pedro Cross, Delightful, Lacovia – Mountainside, Luana – Tombstone, Middle Quarters – Jacksgate, Santa Cruz – Malvern, School Street, Scotts Cove – Luana and Tombstone – Gutters IWP-002

REPORTING DATE: May 2011

CONSTRUCTION PROGRESS SUMMARY: 100 %

School Street PC Road

BEFORE AFTER

Page 24: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Scott’s Cove - Luana

Patching of the roadway

GOJ/NWA: Jamaica Development Infrastructure Programme

CONTRACTOR: China Harbour Engineering Company Limited

SUBCONTRACTOR: Build Rite Construction

PROJECT TITLE: Chudleigh Housing Scheme (RW-021)

REPORTING DATE: May 2011

CONSTRUCTION PROGRESS SUMMARY: 47 %

Bronte (55% Complete)

DURING

Page 25: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Construction of Random Rubble Retaining Wall

Royal Flat – Land Settlement (60% Complete)

DURING

Construction of V-Drains and Road Rehabilitative works

Webb Road (60 % Complete)

Page 26: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

BEFORE AFTER

Construction of Random Rubble Retaining Wall

Lower Christiana (30% Complete)

DURING

Construction of Random Rubble Retaining Wall

Page 27: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

GOJ/NWA: Jamaica Development Infrastructure Programme

CONTRACTOR: China Harbour Engineering Company Limited

SUBCONTRACTOR: Asphaltic Concrete Enterprise

PROJECT TITLE: Paddington Drive, Bay Farm Road, Chevy Chase, Barbican Road, Meadowland Drive & Maynard Road, St, Andrew (RW-027)

REPORTING DATE: May 2011

CONSTRUCTION PROGRESS SUMMARY: 40 %

BEFORE DURING

DURING

Rehabilitation of the roadway

Page 28: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

GOJ/NWA: Jamaica Development Infrastructure Programme

CONTRACTOR: China Harbour Engineering Company Limited

SUBCONTRACTOR: Roger’s Land Development Company Limited

PROJECT TITLE: Goulbourne Road, Jacks Hill Road, Persimmon Avenue Gully, St. Andrew & Black River Hospital Sea Wall, St. Elizabeth (CW-005)

REPORTING DATE: May 2011

CONSTRUCTION PROGRESS SUMMARY: 62 %

Goulbourne Road (97% Complete)

BEFORE

Page 29: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

DURING

Construction of a random rubble retaining wall

Black River Hospital Seawall (70% Complete)

Page 30: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

BEFORE DURING

DURING

Construction of retaining wall and landscaping

Page 31: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

GOJ/NWA: Jamaica Development Infrastructure Programme

CONTRACTOR: China Harbour Engineering Company Limited

SUBCONTRACTOR: Roger’s Land Development Company Limited

PROJECT TITLE: Mocho – Springfield, St. Elizabeth (RW-008)

REPORTING DATE: May 2011

CONSTRUCTION PROGRESS SUMMARY: 97 %

DURING

Manhole Double Surface Dressing

Headwall Catchment Basin

GOJ/NWA: Jamaica Development Infrastructure Programme

CONTRACTOR: China Harbour Engineering Company Limited

SUBCONTRACTOR: Roger’s Land Development Company Limited

Page 32: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

PROJECT TITLE: Punches-Cataboo; Craige-Bailey Ground; Carish Brook-Dry Harbour; Arlington-Ghetto; Banbury Hall-Cherry Gardens; Belvedere-Queensbury;Newell-Bethany; Craine Road-Parotee; Smoothland-Mount Plymouth; Seaview-Queensbury, St. Elizabeth (RW-025)

REPORTING DATE: May 2011

Punches – Cattaboo (50% Complete) DURING

Earth Side Drain Kerb and Channel

Craige – Bailey’s Ground (83% Complete)

900 x 600 mm U Drain

Barbary Hall – Cherry Gardens (49 % Complete)

Page 33: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Base Course

Bellevue – Queensbury (78 % Complete) DURING

Prime Coat (MC0) Headwall

Leeds - Smoothland / Mount Plymouth (86 % Complete)

DURING

Page 34: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Asphaltic Overlay

Seaview - Queensbury (42 % Complete) DURING

Sidewalk, Kerb & Channel Patching

Carisbrook – Dry Harbour (40 % Complete)

Page 35: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

DURING

Base Course Prime Coat (MC0)

Arlington - Ghetto (53 % Complete) DURING

Base Course Prime Coat (MC0)

Crane Road - Parottee (22 % Complete)

DURING

Page 36: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Base Course Prime Coat

Newell – Bethany / Hounslow (44 % Complete) DURING

Base Course Prime Coat (MC0)

Page 37: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

GOJ/NWA: Jamaica Development Infrastructure Programme

CONTRACTOR: China Harbour Engineering Company Limited

SUB-CONTRACTOR: Valley Slurry Caribbean Limited

PROJECT TITLE: Havendale and Hughenden Communities, Kingston & St. Andrew; Caines Shop – Skull Point, Dump – Highgate Hall, Manchester

REPORTING DATE: May 2011

CONSTRUCTION PROGRESS SUMMARY: 86 %

Havendale (86 % Complete)

DURING

Page 38: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Laying of Kerb blocks

Page 39: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Devon - Skull Point (64 % Complete)

DURING AFTER

Page 40: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

DURING

Construction of “U” Drain (above), Micro Surfacing Works in progress (below)

Page 41: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Dump – Highgate Hall (100 % Complete)

BEFORE AFTER

BEFORE DURING

Construction of rock rubble retaining wall (above), Construction of spill way (below)

Page 42: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Oliver Road (62 % Complete)

BEFORE DURING

AFTER

Page 43: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Micro Surfacing of road surface

Page 44: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Upper Waterloo Road (60 % Complete)

BEFORE AFTER

DURING AFTER

Micro Surfacing of road surface

Page 45: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Roehampton Drive & Close (75 % Complete)

BEFORE DURING

DURING AFTER

Micro Surfacing of road surface

Page 46: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

StatuS

RepoRt on

pRojectS

Page 47: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Jamaica Development Infrastructure Programme Progress Report May 2011

Contractor: China Harbour Engineering Company Region: KMR Parish: KINGSTON

No.

CONTRACT PACKAGE

LOCATION/ DESCRIPTION

SUB-CONTRAC

TOR TYPE OF

WORK COMM. DATE

EXP. COMP DATE

QUANTITY/LENGTH (M3/KM)

PROJECT COST (J $)

EXPENDITURE TO DATE (J $)

OVERALL%

COMP REMARKS

1 RW-005 First Street

Y.P Seaton &

Associates

Road Rehabilitatio

n

15-Nov-10

15-Nov-11 1.022 KM 94,892,219.40

21,247,800.00 60

Excavation: 100 % Subbase:100% Construction of Concrete Manholes: 45 % 450mm NWC sewage main is broken which has severely delayed the progress of work but corrective works are in progress and is expected to be completed by June 3, 2011

2 RW-005 Second Street

Y.P Seaton &

Associates

Road Rehabilitatio

n

15-Nov-10 1.092 KM 94,798,129.80 21,255,240.00 70

Excavation: 100 % Subbase: 100% Construction of Concrete Manholes: 75 % Macadam Base works will commence in June

3

RW-005 Link Road

(between 6th and 7th

Avenues)

Y.P Seaton &

Associates

Road Rehabilitatio

n

15-Nov-10 0.140 KM 12,986,136.24 3,444,218.40 40

Excavation:100 % Subbase: 100% Macadam Base works will commence in June

Page 48: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

4 RW-005 Sixth Avenue

Y.P Seaton &

Associates

Road Rehabilitatio

n

15-Nov-10 0.235 KM 21,799,037.04 5,782,166.40 70

Excavation: 100 % Subbase: 100% Macadam Base works will commence in June

5 RW-005

Storm Water Drainage

Y.P Seaton &

Associates

Road Rehabilitatio

n

15-Nov-10 878 M 47,485,434.48 29,082,540.00 80

Storm water drainage solutions have been reached. A double row of 900mm concrete drain which runs easterly from Marcus Garvey Drain through all the roads including First Street, Third Street and Newport Boulevard is being improved to collect the surface water in this region A proper garbage disposal system and "No Vending" Zones need to implemented immediately in order to prevent the storage of garbage in the manholes as is the current practice by vendors

6 RW-005 Eighth Avenue

Y.P Seaton &

Associates

Road Rehabilitatio

n

15-Nov-10 .235 km 7,878,755.28 1,582,920.00 50

Excavation: 100 % Subbase: 100% Macadam Base works will commence in June

7 RW-005 Ninth Avenue

Y.P Seaton &

Associates

Road Rehabilitatio

n 0 Excavation: 0 %

Pipe Laying: 0%

Preliminaries 32,121,123.73 17,602,959.47

Page 49: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Total 279,839,712.24 82,394,884.80

No.

CONTRACT PACKAGE

LOCATION/ DESCRIPTION

SUB-CONTRAC

TOR TYPE OF

WORK COMM. DATE

EXP. COMP DATE

QUANTITY/LENGTH (M3/KM)

PROJECT COST (J $)

EXPENDITURE TO DATE (J $)

OVERALL%

COMP REMARKS

Havendale Community

Valley Slurry Seal Caribbean Co. Ltd.

Micro Surfacing

164,902,300.86

151,675,781.3

4 86%

Preparatory Works 80%; Pavement 100% Patching 100%

Coolshade Drive

1,136.70 11,599,481 9,765,573 84%

Kerb laying and repairs to be completed.

Havendale Drive

1,600.00 17,981,983 16,423,388 91%

Kerb laying and repairs to be completed.

Morningside Drive

1,142.73 11,381,563 10,126,546 89%

Kerb laying and repairs to be completed.

Parks Avenue 956.80 9,342,635 8,444,072

90% Kerb laying and repairs to be completed.

Vermont Avenue

1,586.16 18,478,315 17,273,134 93%

Kerb laying and repairs to be completed.

Fairfax Drive 1,126.70 12,469,187 11,463,739

92% Kerb laying and repairs to be completed.

Highland Drive 1,181.58 12,578,031 11,571,139

92% Kerb laying and repairs to be completed.

Mannings Hill Road - Havendale Drive

2,223.13 23,232,042 22,443,786

97% Kerb laying and repairs to be completed.

Hughenden Avenue

1,154.04 13,909,816 13,372,415 96%

Kerb laying and repairs to be completed.

Page 50: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Border Avenue 2,643.36 28,132,926 27,279,642

97% Kerb laying and repairs to be completed.

Lydia Drive 231.38 3,273,039 2,898,208

89% Kerb laying and repairs to be completed.

Riverside Drive 2,523,282 614,141

24% Patching 100%

Roehampton Drive & Roehampton Close

Valley Slurry Seal Caribbean Co. Ltd.

Micro Surfacing

1,687.00

32,750,607.00

15,177,640.80 75%

Preparatory Works 65% Pavement 100% Kerb and sidewalk outstanding

Oliver Road

Valley Slurry Seal Caribbean Co. Ltd.

Micro Surfacing

1,215.00

33,556,958.96

23,203,478.96 62%

Preparatory Works 65% Pavement 100% Kerbs and sidewalk outstanding

Upper Waterloo Road

Valley Slurry Seal Caribbean Co. Ltd.

Micro Surfacing

720.00

26,538,350.75

12,151,676.59 60%

Preparatory Works 100% Pavement 100%; Kerbs and side walk outstanding

Total

422,650,518.43

202,208,577.6

9

No.

CONTRACT PACKAGE

LOCATION/ DESCRIPTION

SUB-CONTRAC

TOR TYPE OF

WORK COMM. DATE

EXP. COMP DATE

QUANTITY/LENGTH (M3/KM)

PROJECT COST (J $)

EXPENDITURE TO DATE (J $)

OVERALL%

COMP REMARKS

1 RW-017 Orange St.

Asphaltic Concrete Enterprise Limited

Road Rehab 10-Dec-10

11-Nov-10 2.134km 136,181,324.66 90,105,312.03 95%

Prelim. 90% Drainage 90% Pavements 100%

2 RW-017 West parade

Asphaltic Concrete Enterprise Limited

Road Rehab 10-Dec-10

11-Nov-10 0.175km 45,480,149.69 22,112,965.43 75%

Prelim.70% Concrete works 28% Drainage 70% Road Works 84%

Page 51: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

3 RW-017 East Parade

Asphaltic Concrete Enterprise Limited

Road Rehab 10-Dec-10

11-Nov-10 0.205km 33,106,588.77 19,608,659.77 80%

Prelim .70% Concrete works 10% Drainage 17% Road Works 93%

4 RW-017 North Parade

Asphaltic Concrete Enterprise Limited

Road Rehab 10-Dec-10

11-Nov-10 0.205km 70,346,716.66 44,380,335.65 82%

Prelim. 80% Concrete Works 87% Drainage 60% Road Works 92%.

5 RW-017 South Parade

Asphaltic Concrete Enterprise Limited

Road Rehab 10-Dec-10

11-Nov-10 0.219km 58,322,640.10 22,311,306.11 68%

Prelim. 50% Concrete Works 5% Drainage 0% Road Works 65%

1 RW-031

Port Royal Street

General Paving

Company Limited

Road Rehab 11-Jan-11

10-Dec-11 0.975km 107,731,470.71 48,068,899.64 70%

Prelim. 70% Drainage 20% Pavements 85% Concrete Works 94% Approval granted to extend road section.

2 RW-031

Water Lane & Pechon Street

General Paving

Company Limited

Road Rehab 11-Jan-11

10-Dec-11 73,030,658.12 23,382,798.70 60%

Prelim. 75% Drainage 10% Pavements 70%

3 RW-031

Upper King Street

General Paving

Company Limited

Road Rehab 11-Jan-11

10-Dec-11 51,483,281.14 0%

RW-031 Ocean

Boulevard

General Paving

Company Limited

Road Rehab 11-Jan-11

10-Dec-11 55,687,147.55 0%

RW-031 Church Street

General Paving

Company Limited

Road Rehab 11-Jan-11

10-Dec-11 51,660,173.30 0%

Page 52: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

4 RW-031

West Queen Street

General Paving

Company Limited

Road Rehab 11-Jan-11

10-Dec-11 0.36km 31,167,735.78 14,200,860.44 70%

Prelim. 85% Drainage 17% Pavements 95%

5 RW-031 Haywood Street

General Paving

Company Limited

Road Rehab 11-Jan-11

10-Dec-11 0.215km 28,285,080.40 12,381,941.18 73%

Prelim. 85% Earthworks 100% Drainage 13% Pavements 95%

6 RW-031 Harbour Street

General Paving

Company Limited

Road Rehab 11-Jan-11

10-Dec-11 0.395km 45,082,669.16 3,539,047.19 46%

Prelim. 70% Drainage 15% Pavements 55% Approval given to extend road section

Total 787,565,636.04

300,092,126.14

GRAND-T0TAL

1,490,055,866.71

584,695,588.63

Region: KMR

Parish: ST. ANDREW

No.

CONTRACT PACKAGE

LOCATION/ DESCRIPTION

SUB-CONTRAC

TOR TYPE OF

WORK COMM. DATE

EXP. COMP DATE

QUANTITY/LENGTH (M3/KM)

PROJECT COST (J $)

EXPENDITURE TO DATE

(J $)

OVERALL%

COMP REMARKS

1 CW-005 Goubourne Rd

Rogers Land

Development Ltd.

Random Rubble Wall

6-Oct-10

June 2011 518 M3 47,064,763.68 28,462,655 97%

Prelim 95% Site Clearance 100% Drainage 70% Earthworks 98% Road Works 97% Retaining Structures 97%

Page 53: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

2 RW-029 Goubourne Rd

Rogers Land

Development Ltd.

Road Rehab. 18-Jan-11

Dec 2011 1.25 KM 92,680,989 33,886,372 77%

Prelim 70% Site Clearance 100% Drainage 10% Earthworks 100% Pavment 54% Retaining Structures 85%

3

RW-030 Mannings

Hill/Whitehall (PC Roads)

Chins Constructi

on Company Limited

Road Rehab. 11-Jan-11

Dec 2011 1.25 KM 50,727,806 29,163,780 98%

Prelim. 95% Site Clearance 100% Drainage 98% Earthworks 100% Pavement 98%

4 RW027 Bay Farm Road

Asphaltic Concrete Enterprise

Road Rehab. 18-Jan-11

Dec 2011 2.02 KM 180,837,584 5%

Prelim. 10% Drainage 0% Earthworks 5% Pavement 5%

1 CW-002 Mount Horeb

Rogers Land

Development Ltd

Random Rubble Wall

25/10/2010

25/3/2011 160 m3 36,552,815.70 9,060,023.70 25

Preliminary: 55 Earth works: - ongoing 60% Structure :Gabion wall- ongoing 40% Structure :Construction of RRwall - 0% Pavement :0%

2

CW-002 Papine -

Hardware Gap (Damage at up Yonder) MP15

-16

Rogers Land

Development Ltd

Random Rubble Wall

25/10/2010

25/3/2011 642 m3 30,717,090.00 25,268,949.53 90

Preliminary: 90% Earth Work: 100% Structure: RR wall -100% Parapet wall - 100% Out fall protection: - 20% Pavement: 0%

Page 54: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

3

CW-002 Redlight -

Hardware Gap MP 18,19-20

Rogers Land

Development Ltd

Random Rubble Wall

25/10/2010

25/3/2011 618 m3 19,689,830.27 18,610,793.89 94

Preliminary: 90% Earth Work: 100% Structure: RR wall - 100% Parapet all - 100% Pavement: 0% Outfall Protection 0%

1 CW-005 Jacks Hill Road

Rogers Land

Development Ltd

Random Rubble Wall

25/10/2010

25/5/2011 250m3 76,037,659.13 38,634,503.13 58

Preliminary:58% Earth Work:55% Structure: RRWall: 65% Drainage :- RipRap -30% Outfall Protection: 0% Note - Land aquisition process has started by Property Management

2 CW-005

Persimmon Avenue Gully

Rogers Land

Development Ltd

Random Rubble Wall

25/10/2010

25/5/2011 392m3 63,551,863.44 12,364,246.00 25

Preliminary: 35 % Earth Work: 60% Structures: Gabion wall 40% Outfall Protection : 0%

1 CW-007 Halls Delight

Rogers Land

Development Ltd

Random Rubble Wall

25/10/2010

25/5/2011

65,346,383.17 45,541,127.17 62

Preliminary: 60% Earth Work : 75% Structure: Gabion wall - 70% Outfall Protection: Reno Mattress 100% Drainage 0% Pavement: 0%

2

CW-007 Redlight -

Hardware Gap MP 14-15

Rogers Land

Development Ltd

Random Rubble Wall

25/10/2011

25/5/2012 367m3 37,533,479.50 35,605,985.65 95

Preliminary: 95% EarthWork: 100% Structure RR wall : 100% Pavement: Reinstatement of

Page 55: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Road way 0%

3

CW-007 Redlight -

Hardware Gap MP 16-17

Rogers Land

Development Ltd

Random Rubble Wall

25/10/2010

25/5/2011 677m3 60,357,654.92 55,459,374.92 95

Preliminary: 95% EarthWork: 100% Structures: RR wall - 100% Parapet Wall - 100% Outfall Protection 0%

4 CW-007 Cavaliers

Rogers Land

Development Ltd

Random Rubble Wall

25/10/2010

Actual start

date 5-Mar-11

25/5/2011 0 70,787,313.96 38,257,769.94 54

Preliminary: 30% Earth Work: 60% Structures:RRWall:30% Pavement:0%

5

CW-007 Redlight - Hardware

(damage at up Younder)

Rogers Land

Development Ltd

Random Rubble Wall

25/10/2010

25/5/2011 0 18,351,080.65 9,342,732.00 50

Preliminary:60% Earth works; 100% Structures;Gabion wall : 90% Drainage:V-Drain :0%

6 CW-007 Papine -

Redlight MP# 8

Rogers Land

Development Ltd

Random Rubble Wall

25/10/2010

25/5/2011 188 m3 56,939,698.52 33,845,152.52 59

Preliminary:58% EarthWork: 65% Structure:Gabion wall - 45% Mass concrete - underpin existing RRW 100% Outfall Protection: 0%

Page 56: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

1 RW-029 Shooters Hill

Rogers Land

Development Ltd

Road Rehabilitatio

n

7-Feb-11

14/1/2012 1 Km 56,897,797.56 56,160,297.56 100

Preliminary: 100% Site Clearance:100% Earth Works:100% Drainage :100% Pavement 100% Side Walk:100% Kerb only :100%

2 RW-029 Lunar Drive

Rogers Land

Development Ltd

Road Rehabilitatio

n

21/2/2011

14/1/2012 .5 Km 34,231,755.62 13,819,239.34 40

Preliminary:70% Site Clearance:100% Earth Works:100% Drainage :70% Pavement 70% Side Walk:0%

1 RW-27

Paddington Drive

Asphalt Concrete Enterprise

Road Rehabilitatio

n

1-Mar-11 .4km 36,437,763.68 16,254,239.71 50

Preliminary:95% Earth Works:100% Drainage :90% Pavement 100% Side Walk:100%

2 RW-27 Chevy Chase

Asphalt Concrete Enterprise

Road Rehabilitatio

n

24-Feb-11

24-Mar-11 .585km 21,461,921.73 16,915,169.69 80

Preliminary:95% Earth Works:100% Drainage :100% Pavement 100% Kerb only :90%

3 RW-27 Barbican Road

Asphalt Concrete Enterprise

Road Rehabilitatio

n

2-Mar-11 3.6km 118,123,587.43 22,524,794.38 20

Preliminary:40% Earth Works:0% Drainage :60% Pavement 0% Side Walk:50%

4 RW-27

Meadowland Drive

Asphalt Concrete Enterprise

Road Rehabilitatio

n

24-Feb-11

24-Mar-11 0.6km 29,725,248.94 23,006,282.49 80

Preliminary:98% Earth Works:100% Drainage :95% Pavement 100%

Page 57: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

5 RW-27 Maynard Road

Asphalt Concrete Enterprise

Road Rehabilitatio

n

22-Feb-11

24-Mar-11 .52km 20,596,149.77 15,030,097.83 80

Preliminary:98% Earth Works:100% Drainage :90% Pavement 100%

1 RW031 Temple Meade

General Paving Co.

Ltd.

Road Rehabilitatio

n

22-Mar-11 1.1km 35,740,523.86 25,340,169.95 80

Preliminary:80% Earth Works:100% Drainage 0% Pavement 100%

2 RW-031

Farringdon Cresent

General Paving Co.

Ltd.

Road Rehabilitatio

n

28-Mar-11 1.2km 10,920,672.11 5,495,437.17 50

Preliminary:30% Earth Works:60% Drainage :60% Pavement 0% Side Walk:0%

1 RW 043

Shortwood Road

Surrey Paving & Aggregates Co. Ltd.

Road Rehabilitatio

n 3.3km 202,263,712.47 0 0

Preliminary:0% Earth Works:0% Drainage 0% Pavement 00%

2 RW-043 Belgrade

Heights Road

Surrey Paving & Aggregates Co. Ltd.

Road Rehabilitatio

n 1.2km 53,309,393.94 0 0

Preliminary:0% Earth Works:0% Drainage :0% Pavement 0% Side Walk:0%

3 RW 028

Hope Road JC St. Andrew

Surrey Paving & Aggregates Co. Ltd.

Drainage Structure 64,747,066.14 0 0

Preliminary:0% Earth Works:0% Drainage :0% Pavement 0%

Total

1,591,631,605.8

3 608,049,193

Page 58: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Region: KMR

Parish: ST. CATHERINE

No.

CONTRACT PACKAGE

LOCATION/ DESCRIPTION

SUB-CONTRAC

TOR

TYPE OF WORK

COMM. DATE

EXP. COMP DATE

QUANTITY/ LENGTH (M3/KM)

PROJECT COST (J $)

EXPENDITURE TO DATE

(J $)

OVERALL%

COMP REMARKS

1 RW-015 Sinclair Drive

Construction

Solution Road Rehab 17-Jan-

11 July 2011 0.857 km 44,050,372.19 38,900,966.75 85

Prelim 90% Site Clearance100%; Drainage 100%; Earthworks 100%; Pavements 50%; Retaining Structures 100%.

2 RW015 Lucky Valley Pen

Construction

Solution Road Rehab 17-Jan-

11 July 2011 4 km 95,374,210.85 71,340,749.17 85

Prelim 90%; Site Clearance100%; Drainage75%; Earthworks100%; Pavements60%; Retaining Structures100%. The progress of the drainage is rather slow but the contractor has given me verbal discussion that the drains will be completed in a week time then the asphalting will commence thereafter.

Page 59: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

3 RW015 McVickers Road

Construction

Solution Road Rehab 17-Jan-

11 Nov-11 1.4 km 47,462,072.09 41,253,065.09 90

Prelim90%; Site Clearance100%; Drainage95%; Earthworks100%; Pavements50%; Retaining Structures100%.

4 RW015 Commadore

Construction

Solution Road Rehab 17-1-

2011 Jul-11 1.5km 16,923,006.70 15,080,747.70 100

Prelim 100%; Site Clearance.100%; Drainage100%; Earthworks100%; Pavements100%; Retaining Structures N/A.

5

CW001 Garden Hill Rennal Browns Town

Brighton Engineers Road Rehab 29-Jan-

11 Nov-11 1599m3 89,258,544.63 89,258,544.63 100

Prelim 100%; Site Clearance 100%; Drainage 100%; Earthworks 100%; Pavements 100%; Retaining Structures100%. The retaining wall construction was a success, as it completed within schedule.

6

CW006 Highfield Drive, Ensom City

Alcar Construction

Box Culvert 24-Jan-11 Jul-11 .015km 10,900,713.95 7,150,908.30 100

Prelim100 %; Site Clearance100 %; Earthworks 100%; Pavements100%; Retaining Structures 100%.

7

RW013 Featherbed Lane (Upper - Lower Homestead) Highfield Drive, Ensom City

Alcar Construction

Road Rehab 24-Jan-11 Nov-11 4km 63,987,331.65 9,044,187.21 62

Prelim 60%; Site Clearance100 %; Drainage50%; Earthworks80 %; Pavements 60%;

Page 60: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

8 RW013 Tulloch - Zion Hill Bridge

Alcar Construction

Road Rehab 24-Jan-11 Dec-11 13km 258,481,471.17 161,321,231.4

6 70

Prelim70 %; Site Clearance 100%; Drainage35%; Earthworks 70 %; Pavements 70%; Retaining Structures 90%.

9 RW013 Ewarton - Worthy Park

Alcar Construction

Road Rehab 24-Jan-11 Dec-11 10.22 574,426,756.41 156,658,271.2

3 50

Prelim 50%; Site Clearance 100%; Drainage50%; Earthworks 60 %; Pavements 0%; Retaining Structures 70%.

10

RW019 Riversdale - Pear Tree Grove

Rogers Land Development

Road Rehab 10-Feb-11 Dec-11 12.3km 198,448,919.58 27,701,905.58 30

Prelim 30 %; Site Clearance 80 %; Drainage20%; Earthworks 60%; Pavements35%; Retaining Structures30%.

11

RW019Old Troja Road

Rogers Land Development

Road Rehab Dec-11 3.5 48,027,606.98 0.00 0

Prelim 0 %; Site Clearance 0 %; Drainage0%; Earthworks 0%; Pavements 0%; Retaining Structures 0%.

12

IWP004 Patching ( ACE)- St. Catherine

Asphaltic Concrete Enterprise

Patching 1-Dec-11 Apr-11 6,370m2 16,816,800.00 18,934,080.00 100 Patching 100%

complete.

13

IWP001B Patching ( Surrey)- St. Catherine

Surrey Paving & Aggregate

Patching 1-Dec-11 Apr-11 11,130m2 11,391,600.00 20,367,600.00 100 Patching 100%

complete.

Page 61: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

14 McCooks Pen

Construction Solution

Road Rehab 9-Feb-11 Aug-11 1.45km 43,264,632.62 38,252,757.62 95

Prelim 100%; Site Clearance100%; Drainage95%; Earthworks100%; Pavements100%; Retaining Structures95%.

15

Nightengale Groove

Construction Solution

Road Rehab 6-Feb-11 Jun-11 37,037,220.63 37,037,220.63 100

Prelim100%; Site Clearance100%; River Training 100%; Earthworks100%; Berm 100%. The scope of work has ben completed.

16

RW026- Dark Hole to Brick Hut

Brighton Engineers Road Rehab 25/03/2

011 Mar-12 5.6km 162,815,632.16 0.00 28

Prelim .28%; Site Clearance100%; Drainage 0%; Earthworks 100%; Pavements 65%; Retaining Structures 0%.

17

RW026- Byles to Dover

Brighton Engineers Road Rehab 25/03/2

011 Mar-12 3.6km 60,361,801.85 0.00 22

Prelim 20%; Site Clearance100%; Drainage 0%; Earthworks100%; Pavements60%; Retaining Structures0%.

18

RW018 - Settlement

Construction

Solution Road Rehab 9-Feb-

11 Aug-11 0.75km 43,383,605.20 37,037,220.63 85

Prelim80%; Site Clearance100%; Drainage85%; Earthworks100%; Pavements60%; Retaining Structures95%.

19

RW - 009 Fairview

Community Roads

YP Seaton &

Associates Road Rehab 2-May-

11 2-May-

12 180,000,000.00 12

Prelim12%; Site Clearance 30%; Drainage 0%; Earthworks 12%; Pavements12%; Retaining Structures

Page 62: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

0%.

Total 2,002,412,298.66

769,339,456.00

Region:North East

Parish: ST. THOMAS

No.

CONTRACT PACKAGE

LOCATION/ DESCRIPTION

SUB-CONTRAC

TOR TYPE OF

WORK COMM. DATE

EXP. COMP DATE

QUANTITY/ LENGTH (M3/KM)

PROJECT COST (J $)

EXPENDITURE TO DATE

(J $)

OVERALL%

COMP REMARKS

1 RW-042 Albion -

Llandewey

Alcar Construction Co. Ltd

Road rehabilitation

23-Nov-10

5/25/2012 9 km 448,537,036.03 338,820,586.3

6 75

Preliminary: 60% Site Clearance. 100% Drainage. 65% Earthworks.85% Retaining Structure. 75% Pavement Layers.60%

2

RW-042 Unity- Toms

River(Bellmont/King Weston

St.Thomas

Alcar Construction Co. Ltd

Road rehabilitation

26-Apr-11 204,903,085.20 8,140,209.08 5

Preliminary: 0% Site Clearance. 15% Drainage.0% Earthworks:0% Retaining Structure. 0% Pavement Layers.0%

Page 63: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

3 RW-34

Bath-Barretts Gap

Alcar Construction Co. Ltd

Road rehabilitation

25-Feb-11

1/25/2012 5.7 Km 92,995,312.34 8,565,248.03 10

Preliminary: 30% Site Clearance. 100% Drainage. 0% Earthworks.35% Retaining Structure. 15% Pavement Layers.0%

4

RW-34 Morant

Crossing-White Hall

Alcar Construction Co. Ltd

Road rehabilitation

28-Feb-11

1/25/2012 8.7Km 165,942,867.89 24,907,381.22 15

Preliminary: 20% Site Clearance.40% Drainage.0% Earthworks:0% Retaining Structure. 35% Pavement Layers.0%

5

RW-34 Friendship

Wilmington (Stewart

Mountain Road)

Alcar Construction Co. Ltd

Road rehabilitation

1-Mar-11

1/25/2012 5.7km 46,934,039.16 5,004,678.33 10

Preliminary: 20% Site Clearance. 30% Drainage.0% Earthworks: 0% Retaining Structure. 0% Pavement Layers.0%

6 RW-33

Lloyds - Lowe mountain

Asphalt Concrete Enterprise

Road rehabilitation

21-Feb-11

3/25/2012 4.3km 146,076,047.05 28,844,174.99 20

Preliminary: 40% Site Clearance. -100% Earth Works - 65% Pavement - 50% Structure: RRWall - 35% Structure :Gabion Wall -0% Drainage:0%

7 RW-33 Springfield

Asphalt Concrete Enterprise

Road rehabilitation

21-Feb-11

3/25/2012 .5km 16,688,277.57 11,517,523.46 70

Preliminary: 90% Site Clearance. -100% Earth Works - 100% Pavement - 100 % Drainage:50%

Total 1,122,076,665.

24 425,799,801.

47

Page 64: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Region: North East

Parish: PORTLAND

No.

CONTRACT PACKAGE

LOCATION/ DESCRIPTION

SUB-CONTRAC

TOR TYPE OF

WORK COMM. DATE

EXP. COMP DATE

QUANTITY/LENGTH (M3/KM)

PROJECT COST (J $)

EXPENDITURE TO DATE

(J $)

OVERALL%

COMP REMARKS

1 RW020 Hope Bay - Coopers

Hill

YP Seaton & Associates Co. Ltd.

Road Rehab 1/17/2011

12/29/2011 20.9

394,267,427.17 0 5%

Site Clearance: 84% Earth works: 52%. Drainage: 2.1% (U & V-drain Excavation in progress and channel demolition is 50% ), Pavement 2.5% - Base work no prog. due to recent rains and marl supplier.

Page 65: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

2

RW022 Bangor Ridge - Mahoe (Silver

Hill)

YP Seaton & Associates Co. Ltd.

Road Rehab 1/17/2011

12/29/2011 3.3

80,573,143.91 4,535,292 12%

Site Clearance 85%, Earthworks 47%, Basework 11%, Drainage 23%. Further work delays occured on May 6, and 10 . There still has not been an official reason for the delays from the sub-contractor on this project but reports to the NWA officer on site of civil onrest on the site remain and contributed to the low production.

RW022

Mt. Pleasant (PC)

YP Seaton & Associates Co. Ltd.

Road Rehab 1/17/2011

12/29/2011 0.626

24,562,514.41 12,053,390 32%

Site Clearance 100% Drainage 100% Pavement 50%. Asphaltic concrete overlay to commence 25/5/11. The construction of a "U" drain has been halted due to a dispute with the owners of the land through which it is supposed to pass. The matter is being handled by the Legal Department.

RW022

Smithfield Road

YP Seaton & Associates Co. Ltd.

Road Rehab 1/17/2011

12/29/2011

13,653,694.08 0 0%

Page 66: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

3 Friendship Road

YP Seaton & Associates Co. Ltd.

Road Rehab 1/17/2011

12/29/2011 1.085 0 41%

Site Clearance 100% Formation 100% Drainage 46% Pavement 55%

RW024 Portland

Emergency Work

General Paving Company Limited

Rock Hall

General Paving Company Limited

Road Rehab 1/17/2011

12/29/2011 2.4

24,403,577.28 0 46%

Site Clearance 100%, Drainage 12%, Base work 94%

Cuffy's Head -

West End (Phase I)

General Paving Company Limited

Road Rehab 1/17/2011

12/29/2011 0.65

7,570,260.46 2,371,182 39%

Site Clearance 100%Basework 100%Prime 100%Drainage 100%

Cuffy's Head -

West End (Phase II)

General Paving Company Limited

Road Rehab 1/17/2011

12/29/2011 0.425

12,511,669.93 2,829,764 42% Site Clearance 100% Basework 100% Prime 100% Drainage 100%

Vinery

General Paving Company Limited

DSD 1/17/2011

12/29/2011 0.4

1,987,829.51 100%

Complete

Swift River -Shirley Castle

General Paving Company Limited

Patching 1/17/2011

12/29/2011

2,342,387.50

2,342,388.00 100%

Complete

Page 67: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

Buff Bay - Whitehall

General Paving Company Limited

Temporary Restoration

1/17/2011

12/29/2011

3,391,008.12 3,082,735 79% Earthworks 100% Site clearance 100% Drainage n/a Pavement 100%

Tranquility - Bangor Ridge

General Paving Company Limited

Road Rehab 1/17/2011

12/29/2011

9,400,386.03 2,649,115.98 11% Site clearance 55% Drainage 22.3% (2 no. 900mm culverts replaced).

Fairfield Primary School

General Paving Company Limited

Overlay 4/18/2011

9,271,977.28 - 20%

Site Clearance 100%, Drainage 100%,Earth works 26% Pavement 23%

School House Corner - Swift

River

General Paving Company Limited

Replace Collapsed Culvert

1/17/2011

12/29/2011

3,225,180.04

3,225,180.00 100%

Complete

Chepstowe to Peters Hill

General Paving Company Limited

Temporary Restoration

1/17/2011

12/29/2011

7,094,943.36 3,829,451 100%

Earthworks 100%, site clearance 100%, drainage n/a, pavement 100%

Church Hill

Corner - Muir Park

General Paving Company Limited

Temporary Restoration

1/17/2011

12/29/2011

1,803,418.95 1,534,472 100%

Complete

4 RW023

Buff Bay Valley

Surrey Paving & Aggregate Co. Ltd.

RRW 1/17/2011

12/29/2011

80,972,351.72 8%

Section by-pass base course 80%, Excavation for 1st breakaway RRW fr. Section in prog. 5%, Cascade Gabion retaining wall Extension 15% & adjoining RRW 80%. 2nd RRW in Cascade 100% Bushing at detour

Page 68: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

road 100%.

Total 677,031,769.75

38,452,969.16

Region: North East

Parish: ST. MARY, PORTLAND

No.

CONTRACT PACKAGE

LOCATION/ DESCRIPTION

SUB-CONTRAC

TOR

TYPE OF WORK

COMM. DATE

EXP. COMP DATE

QUANTITY/LENGTH (M3/KM)

PROJECT COST (J $)

EXPENDITURE TO DATE

(J $)

OVERALL%

COMP REMARKS

1 RW 012

St. Mary, St. Ann.

Dwight's Constructi

on Company Limited

Road Rehab 16/12/2010

December 2011

1,433,568,326.91

598,035,053.77 50

Prelim .50%; Site Clearance 95%; Drainage 60%; Earthworks 85%; Pavements 60%; Retaining Structures 30%. The progress of work regained pace and is progressing smoothly

RW 012 St. Mary, St. Ann .Derry

Hazzart

Dwight's Constructi

on Company Limited

Road Rehab 21-Jan-11

December 2011 15.6km 311,722,427 172,301,153.3

9 75

Preliminaries 50%,Site Clearance 100%,Drainage60%,Earth works 100%,Pavement 50%Retaining Walls0%

Page 69: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

RW 012 St. Mary, St.

Ann. Blackstonage- Halifax Bridge

Dwight's Constructi

on Company Limited

Road Rehab 21-Jan-11

December 2011 22.58km 184,932,689 113,286,522.4

7 70

Preliminaries 50%,Site Clearance 100%,Drainage60%,Earth works 100%,Pavement 80%Retaining Walls5%

RW 012 St. Mary, St. Top Valley

Bush

Dwight's Constructi

on Company Limited

Road Rehab 21-Jan-11

December 2011 2.8 52,245,144.17 7,442,166.94 45

Preliminaries 30%,Site Clearance 100%,Drainage30%,Earth works 100%,Pavement 70%Retaining Walls0%

RW 012 St. Mary, St. Ann. Halifax

Bridge- Lucky Hill

Dwight's Constructi

on Company Limited

Road Rehab 21-Jan-11

December 2011 5.4km. 132,832,949 49,958,485.30 40

Preliminaries 30%,Site Clearance 100%,Drainage40%,Earth works 100%,Pavement 55%Retaining Walls0%

RW 012 St. Mary, St.

Ann. Barracks River

Dwight's Constructi

on Company Limited

Road Rehab 21-Jan-11

December 2011 6.8km. 270,148,464.87 59,830,335.22 30

Preliminaries 30%,Site Clearance 30%,Drainage40%,Earth works 50%,Pavement %Retaining Walls 30%

RW 012 St. Mary,

Wellington

Dwight's Constructi

on Company Limited

Road Rehab 21-Jan-11 Dec-11 5.3km. 130,583,933.94 69,738,338.13 85

Preliminaries 50%,Site Clearance 100%,Drainage60%,Earth works 100%,Pavement 80% %Retaining Walls%

RW 012 St. Mary, Lindon

Housing Scheme

Dwight's Constructi

on Company Limited

Road Rehab 21-Jan-11 Dec-11 3km 27,448,483.07 0.00 0

Preliminaries 30%,Site Clearance %,Drainage%,Earth works %,Pavement % %Retaining Walls% Verbal communication was

Page 70: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

had by the Sub-Contractor from NWC rep.

RW 012

St. Mary, Gully Road

Dwight's Constructi

on Company Limited

Road Rehab 21-Jan-11 Dec-11 6km 42,586,029 33,374,834.90 50

Preliminaries 30%,Site Clearance 100%,Drainage40%,Earth works 100%,Pavement 70% %Retaining Wall0% works proceeding Satisfactorily

RW 012 St. Mary, St.

Ann.Free Hill -Geddes Town

Dwight's Constructi

on Company Limited

Road Rehab 21-Jan-11

December 2011 12.4km 234,227,772.55 73,251,290.85 40

Preliminaries 30%,Site Clearance 100%,Drainage40%,Earth works 100%,Pavement 35%Retaining Walls0%,

RW 012 St. Mary,

Mount Alto

Dwight's Constructi

on Company Limited

R.R Wall Construction and Gabion

17/2/2011

December 2012

18,679,104 6,889,597.36 80

Gabion wall section 100%,RR Wall Construction Commenced 60%

RWO12 Back Steet Hunstown

Dwight's Constructi

on Company Limited

Road Rehab 21-Jan-11

December 2011 2km 28,161,331.80 11,962,329.21 85

Preliminaries 30%,Site Clearance 100%,Drainage40%,Earth works 100%,Pavement 80%Retaining Walls0%,

2

CW-004 Alligator

Church, Rio Grande Valley

NF Barnes RR

WallConstruction

10-Oct-10

December 2011

178,184,702.70 159,973,742.70 90

Prelim .65%;Walls.100%. Drainage 45% The progress of work has improved despite consistent heavy rains, Pvement works to be completed

Page 71: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

3 CW-003

Border Cuffy Gully

YP Seaton & Associates

RR WallConstruction

8-Oct-10

December 2011

52,544,975.49 50,621,022.44 100

Prelim .100%;Walls.100%. Drainage 100% Pavement 100% Roadway now reopened to vehicular traffic

Total

1,664,298,005.10

808,629,818.91

Region: North East

Parish: ST. ANN

No.

CONTRACT PACKAGE

LOCATION/ DESCRIPTION

SUB-CONTRAC

TOR

TYPE OF WORK

COMM. DATE

EXP. COMP DATE

QUANTITY/LENGTH (M3/KM)

PROJECT COST (J $)

EXPENDITURE TO DATE

(J $)

OVERALL%

COMP REMARKS

1 CW-008 Lime Hall

General Paving

Company Limited

Random Rubble Wall

12-Dec-10

May 2011 272.6 17,487,851.73 11,258,779.03 80

Prelim .60%; Earthworks 100%; ; Retaining Structures 80%. The work schedule need to be revised. Site instruction given to resume work.

2 CW- 008

Milford Box Culvert

General Paving

Company Limited

Box Culvert Revetment Drainage

82,244,512.54 0

Prelim .6%; Site Clearance 20%.. This work is now on hold because of a dispute between contractor and sub.

3 RW-014 White River-Newstead

Bridge

General Paving

Company Limited

Road Rehabilition

7-Mar-11

87,714,477.31 5,669,839.41 10

Prelim .10%; .Formation35%, %, Clean Earth Drain 100% Work resumed but moving at a slow pace.

Page 72: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

4 RW-014 Thicketts

General Paving

Company Limited

Road Rehabilition

17-Mar-11

17,436,999.79 6,080,010.59 90

Prelim .2%; Site Clearance,.Formation,Clean ing of Outlets, Clean Earth Drain,Base Course Marl, Priming all completed,excavation for kerb and channel, laying of kerb and channel now 99% completed.. Progress of work is satisfactorly.

5 RW-014

Knapdale - Sturge Town

General Paving

Company Limited

Road Rehabilition

28-Mar-11

86,456,977.82 0.00 7

Bushing of embankment and cutting of overhanging trees 95%, cleaning of side drain 90%, and outlets now in progress.

1 RW-014

Culloden - Knibb Street

General Paving Road Rehab. 6-Nov-

10 June 2011 16.25 KM 100,677,389 35,905,595 68%

Prelim.60% Site Clearance 100% Drainage 75% Earthworks 100% Pavement 50%

1 RW-014

Fullerton Park - That

General Paving Road Rehab. 6-Nov-

10 June 2011 4.6 Km 56,381,564 5%

Prelim. 5% Site Clearance 100% Drainage 0% Earthworks 0% Road Works 0% Retaining Structures 0%

Total 448,399,772.49 58,914,224

Region: Western

Parish: TRELAWNY

Page 73: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

No.

CONTRACT PACKAGE

LOCATION/ DESCRIPTION

SUB-CONTRAC

TOR TYPE OF

WORK COMM. DATE

EXP. COMP DATE

QUANTITY/LENGTH (M3/KM)

PROJECT COST (J $)

EXPENDITURE TO DATE

(J $)

OVERALL%

COMP REMARKS

1

RW-035 Martha Brae-

Peru

A.C.E. Road

Rehabilitation

18-Jan-11

Dec 2011 7.8 Km 69,794,239 16,718,263 35%

Prelim.30% Site Clearance 100% Drainage 22% Earthworks 80% Pavment 45%

2

RW-035 Martha Brae-

Kinloss

A.C.E. Road

Rehabilitation

18-Jan-11

Dec 2011 4.3 Km 88,676,005 4,678,437.87 20%

Prelim.30% Site Clearance 100% Drainage 15% Earthworks 70% Pavement 5% Retaining Structures 5%

3 RW-035

Clarks Town - Hyde

Asphaltic Concrete Enterprise

Ltd

Road Rehabilitatio

n

Jan 2011

Jan 2012 1.75 km 32,034,065 16,149,571 60%

Preliminary Works: 60% complete. Site Clearance: (Bushing) - 100% complete. Earthworks: (Prepare Formation) - 100% complete. Drainage: 39% complete. Pavement: 43% complete.

1 RW036

New Hope - Lodge

Rogers Land

Development Ltd

Road Rehabilitation Jan 2011 Jan 2012 1.03 km 24,567,722.87 2,360,993.00 15

1. Preliminary Works: 10% complete 2. Site Clearance: (Bushing) - 100% complete 3. Earthworks: (Prepare Formation) - 100% complete 4. Pavement: 6% complete

Page 74: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

2 RW036

Wait-a-Bit - Joe Hut

Rogers Land

Development Ltd

Road Rehabilitation Jan 2011 Jan 2012 1.65 km 43,563,360.65 11,069,689.83 20

1. Preliminary Works: 16% complete 2. Site Clearance: (Bushing) - 100% complete 3. Earthworks: (Prepare Formation) -100% complete 4. Drainage: 2% 5. Pavement: 40%

3 RW036

Warsop - Thompson Town

Rogers Land

Development Ltd

Road Rehabilitation Jan 2011 Jan 2012 6.42 km 113,762,104.09 0 2

1. Preliminary Works: 5% complete 2. Construction of wall: 3% (Technical Services needed to design Gabion Wall)

Total 372,397,496.38 50,976,954.8

8

Region: Western

Parish: ST. JAMES

No.

CONTRACT PACKAGE

LOCATION/ DESCRIPTION

SUB-CONTRAC

TOR TYPE OF

WORK COMM. DATE

EXP. COMP DATE

QUANT./ LENGTH (M3/KM)

PROJECT COST (J $)

EXPENDITURE TO DATE

(J $)

OVERALL%

COMP REMARKS

1 RW-003 John's Hall

Y P Seaton &

Associates Company Limited

Road Rehabiliation

at John's Hall Bridge

18/11/2010

17/11/2011

446,164,140.60 130,501,162.80 30

Site Clearance 50% Earthworks 50% Box Culvert #1 90% Box Culvert #2 10% Metal Bridge 0%; Temporary Bridge 100% Roadway 30% Detour Roadway 100%.

Page 75: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

2 RW-002 Queen's Drive

Surrey Paving & Aggregate Company Limited

Asphaltic Concrete Overlay

15/09/2010

14/09/2011

174,593,614.55 97,297,117.61 70

Regulation 93% Kerb & Channel 20% Milling 62% Asphalt 74% Sidewalk 101% Kerb 197% Reinstatement of Trench 161% Repair Kerb & Channel 94% Retaining Wall 0%. The progress of work is satisfactory.

1 RW- 037

Dumfries - Canaan

YP Seaton &

Associates Company Limited

Road Rehab Feb.2011 Feb. 2012 5.5 Km. 137,177,255.96 41,066,243.26 35%

1)Cut Overhanging-100%, 2)Bushing-100% 3)Clean Side Drain-100% 4)Prepare Formation-100%, 5)Clean Culverts-100% 6)Repair Public Utility-Water Pipe-(o-going) & Electrical lines -(completed), 7) Sub-base-25%, 8. Construct Earth Drains-40% 9) Subbase 50%, 10) Base Course 25% 11) U-Drain, 12) Culvert 100% (Note: Progress is satisfatory)

Page 76: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

2 Springmount - Sunderland

YP Seaton &

Associates Company Limited

Road Rehab Feb.2011 Feb. 2012 3.2 Km 88,806,878.75 10,718,688.53 25%

1) Bushing-100%, 2)Remove Landslips-100%, 3)Cut Overhanging-100%, 4) Repair Public Utilities-water pipes-(on-going) 5) Dust & Traffic Control-(on-going), 6)RR-Wall-80% 7) Culverts & Catch Basins-75% (Note: Progress is satsfactory)

3 Grnville - Retirement

YP Seaton &

Associates Company Limited

Road Rehab Feb.2011 Feb. 2012 7.3 Km 215,801,644.59 33,239,858.72 20%

1)Bushing, 2)Cut Overhanging, 3)Clean Side Drains, 4) Const. Earth Drains 40% 5)Prepare Formation 100%, 6) Remove Landslips 100% 7) Culvert & Catch Basins 100% 8) Sub-base 100% 9) Dust & Traffic Control, on-going 10) U-Drain-25% 11)Base Course 25% . (Note: Work is behind the schedule)

4 Norwood - Ironshore

YP Seaton &

Associates Company Limited

Road Rehab Feb.2011 Feb. 2012 4.4 Km. 256,861,465.37 50,941,861.21 15%

1) Bushing-50% 2)Fill -25% 3)Site Clearance-95% 4)Prepare Formation-100% 5)Cut Overhanging-100% 6) Dust & Traffic Control-(on-going) 7) Subbase 20% (Note: work is progrssing slowly)

Page 77: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

5 Rosemount - Crescent

YP Seaton &

Associates Company Limited

Road Rehab Feb.2011 Feb. 2012 0.97 Km 41,731,159.18 1,930,745.34 10%

1) Bushing-100% 2) Prepare Formation 100% 3) Base Course 5%4)Kerb & Channel 5%5)Dust & Traffic Control on-going (Note: Progress is slow)

6 Hatfield (PC)

YP Seaton &

Associates Company Limited

Road Rehab Feb.2011 Feb. 2012 0.35 Km 10,002,143.60 1,000,027.02 10%

1) Prepare formation-100% 2) Conc. V-Drain 100% 3) Base Course 25% 4) Dust and Traffic Control on-going (Note: Progress is slow)

7 Kings Street - Green Pond

YP Seaton &

Associates Company Limited

Road Rehab Feb.2011 Feb. 2012 5.4 Km 206,314,793.08 14,120,573.65 10%

1) Clean Drains-100% 2) Prepare Formation-95% 3) Dust & Traffic Control-(on-going) 4) Cut to Spoil -100% (Note: Progress of work on the project is behind and does not comply with the official schedule. The project is affected by NWC issues, but there are several other activities that can be worked on at this time. Mr. Walter Bygrave informed me that Tank-Weld Construction will commence corrective work on the collapsed road section on May 24. NWC is still sourcing 100mm dia water pipes to replace the rotten 50mm dia line and no commitment was

Page 78: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

given on it

8 Palmyra - Cornwall

YP Seaton &

Associates Company Limited

Road Rehab Feb.2011 Feb. 2012 1.36 Km 67,806,515.19 30,780,521.57 50%

1) Bushing -50% 2) Prepare Formation-100% 3) 900mm dia Culverts-100% 4) Repair Public Utility-water pipes (on-going) 5) Rock Excn-100% 6) Borrow to Fill-100% 6) Dust & Traffic Control (on-going) 7) Base Course 60% 8) Conc. U-Drain 75% 9) Entrances 50% 10)Kerb Wall 15% (Note: Progress is satisfactory)

TOTAL

1,645,259,610.87 411,596,799.71

Region: Central

Parish: ST. ELIZABETH

Page 79: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

No.

CONTRACT PACKAGE

LOCATION/ DESCRIPTION

SUB-CONTRAC

TOR TYPE OF

WORK COMM. DATE

EXP. COMP DATE

QUANTITY/LENGTH (M3/KM)

PROJECT COST (J $)

EXPENDITURE TO DATE

(J $)

OVERALL%

COMP REMARKS

1 RW-025 Punches - Cattaboo

Rogers Land

Development

Limited

Road Rehab 2-Feb-11

1-Feb-12

41,817,726.18 20,783,945.99 50

Prelim.50%; Site Clearance 100%; Drainage 62%; Earthworks 100%; Pavements 47%; Retaining Structures Nil%. The progress of work slowly.

2 RW-025 Craige - Bailey Ground

Rogers Land

Development

Limited

Road Rehab 26-Jan-11

1-Feb-12

28,958,289.05 19,742,865.83 83

Prelim.70%; Site Clearance 100%; Drainage 68%; Earthworks 98%; Pavements 74%; Retaining Structures Nil%. The progress of work is progressing smoothly.

3 RW-025 Barbary Hall - Cherry Gardens

Rogers Land

Development

Limited

Road Rehab 17-Jan-11

1-Feb-12

22,064,084.37 11,816,934.37 53

Prelim.50%; Site Clearance 100%; Drainage 100%; Earthworks 100%; Pavements 54%; Retaining Structures Nil%. The progress of work is progressing smoothly.

4 RW-025 Bellevue - Queensbury

Rogers Land

Development

Limited

Road Rehab 24-Jan-11

1-Feb-12

48,216,861.30 27,986,549.07 78

Prelim.70%; Site Clearance 100%; Drainage 97%; Earthworks 100%; Pavements 33%; Retaining Structures 67%. The progress of work is progressing smoothly.

Page 80: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

5

RW-025 Leeds - Smoothland - Mount Plymouth

Rogers Land

Development

Limited

Road Rehab 7-Feb-11

1-Feb-12

46,809,279.08 40,221,378.61 86

Prelim. 60%; Site Clearance 100%; Drainage 100%; Earthworks 100%; Pavements 87%; Retaining Structures Nil%. The progress of work is progressing smoothly.

6 RW-025Seaview - Queensbury

Rogers Land

Development

Limited

Road Rehab 24-Jan-11

1-Feb-12

34,531,178.95 13,338,850.93 42

Prelim.45%; Site Clearance 100%; Drainage 100%; Earthworks 100%; Pavements 35%; Retaining Structures Nil%. The progress of work is progressing smoothly.

7 RW-025 Carisbrook - Dry Harbour

Rogers Land

Development

Limited

Road Rehab 10-Feb-11

1-Feb-12

39,427,018.17 14,821,753.00 40

Prelim. 50%; Site Clearance Nil%; Drainage 50%; Earthworks 100%; Pavements 50%; Retaining Structures 100%. The progress of work is progressing smoothly.

8 RW-025 Arlington - Ghetto

Rogers Land

Development

Limited

Road Rehab 10-Feb-11

1-Feb-12

20,768,405.00 10,564,460.88 53

Prelim.36%; Site Clearance 100%; Drainage 16%; Earthworks 100%; Pavements 57%; Retaining Structures Nil%. The progress of work slightly slowed a few days ago.

Page 81: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

9 RW-025 Crane Road - Parrotte

Rogers Land

Development

Limited

Road Rehab 10-Feb-11

1-Feb-12

58,349,942.95 12,180,405.88 22

Prelim. 55%; Site Clearance 100%; Drainage Nil%; Earthworks 100%; Pavements 20%; Retaining Structures Nil%. The progress of work is progressing slowly.

10

RW - 008 Mocho - Springfield

Rogers Land

Development

Limited

Road Rehab 2-Nov-10

1-Nov-11

163,540,034.34 148,359,127.07 97

Prelim. 95%; Site Clearance 100%; Drainage 99%; Earthworks 100%; Pavements 100%; Retaining Structures 100%. The progress of work is progressing steadilly.

11

CW-005 Black River Hospital Seawall

Rogers Land

Development

Limited

Road Rehab 12-Nov-10

11-Nov-11

26,728,976.50 17,289,176.50 70

Prelim.70%; Site Clearance 70%; Drainage 70%; Earthworks 70%; Pavements Nil%; Retaining Structures 70%. The progress of work is progressing smoothly.

12

RW-025 Newell - Bethany / Hounslow

Rogers Land

Development

Limited

Road Rehab 25-Feb-11

1-Feb-12

34,797,943.20 15,458,509.87 44

Prelim. 50%; Site Clearance 100%; Drainage 2%; Earthworks 100%; Pavements 47%; Retaining Structures Nil%. The progress of work is progressing smoothly.

Page 82: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

13

IW - P002 Black River - Pedro Cross Chocolate Hole Delightful Institution Drive Lacovia - Mountainside Luana - Tombstone Market Street Middle Quarters - Jacksgate Pedro Cross - Lititz Santa Cruz - Malvern Santa Cruz Bypass School Street Scotts Cove - Luana Tombstone - Gutters

S & G Road

Surfacing Materials

Ltd.

Patching 9-Nov-10

9-May-11

27,192,000.00 27,192,000.00 100

Black River - Pedro Cross (850 m2)100%; Delightful (600 m2) 100%; Institution Drive (200 m2) 100%; Lacovia - Mountainside (500 m2) 100%; Pedro Cross - Lititz (1750 m2) 100%; Santa Cruz - Malvern (700 m2) 100%; Santa Cruz Bypass (550 m2) 100%; Middle Quarters - Jacksgate (1200m2)100%; Luana - Tombstone (600m2) 100%; Tombstone - Gutters (400m2) 100%. School Street P.C. Road (100m2) 100%; Scotts Cove - Luana (2085 m2) 100%. The work is complete.

Total 593,201,739.09 379,755,958.

00

Region:Central

Parish: MANCHESTER

No.

CONTRACT PACKAGE

LOCATION/ DESCRIPTION

SUB-CONTRAC

TOR TYPE OF

WORK COMM. DATE

EXP. COMP DATE

QUANTITY/LENGTH (M3/KM)

PROJECT COST (J $)

EXPENDITURE TO DATE (J $)

OVERALL%

COMP REMARKS

Page 83: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

1 001-RW-001 Micro Surface

Package 1

Valley Slurry Seal Caribbean Co. Ltd.

4-Oct-10

4-Sep-11

Devon - Skull Point Micro

Surfacing

127,254,504 91,659,943 64%

Preparatory Works 45%;Pavement 83%; RRW,"U" Drain and bushing outstanding

Dump - Highgate Hall

Micro Surfacing

8,487,336 6,789,576 100%

Preparatory Works 100%;Pavement 0% Dump - Highgate Hall is removed based on a reevaluation of the pavement structure.

1 Rocky Park RW 021

Build Rite Construction CO.Ltd.

Road Rehab 7-Mar-11 .8 Km 30,905,843.89 15,821,394.38 65%

PRELIMINARIES: 25% SITE CLEARANCE: 100% DRAINAGE: 45% EARTHWORKS: 90% PAVEMENT: 40% ROCK EXCAVATION: 90%

2 Retreat Road RW 021

Build Rite Construction CO.Ltd.

Road Rehab 7-Mar-11 .59 Km 10,808,651.21 4,224,209.62 45.0%

PRELIMINARIES: 25% SITE CLEARANCE: 100% DRAINAGE: % EARTHWORKS: 70% PAVEMENT: 10 %

Page 84: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

3

Chudleigh Housing Scheme RW 021

Build Rite Construction CO.Ltd.

Road Rehab 7-Mar-11 2.106 Km 68,065,287.32 44,996,018.83 46.7%

PRELIMINARIES: 57.5% SITE CLEARANCE: 100% DRAINAGE: 25% EARTHWORKS: 68% PAVEMENT: 20% RR WALL (Civil Work) 10%

5 Lower Christiana RW 021

Build Rite Construction CO.Ltd.

Road Rehab 7-Mar-11 1.20 Km 50,274,198.96 7,927,230.05 36%

PRELIMINARIES: 35% SITE CLEARANCE: 100% DRAINAGE: 99% EARTHWORKS: 2% PAVEMENT: % RR WALL (Civil Work) 70%

6 Bruntie RW 021

Build Rite Construction CO.Ltd.

Road Rehab 7-Mar-11 5.950 Km 138,213,246.93 76,221,789.07 71%

PRELIMINARIES: 50% SITE CLEARANCE: 100% DRAINAGE: 48% EARTHWORKS: 90% PAVEMENT: 50% CIVIL WORK: 90%

Page 85: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

7 Top Hill Grove Place RW 021

Build Rite Construction CO.Ltd.

Road Rehab 3.700Km 42,213,031.23 14,768,059.58 63%

PRELIMINARIES: 50% SITE CLEARANCE: 100% DRAINAGE: EARTHWORKS: 90% PAVEMENT: RR WALL 75%

8 Landsettlement Loop RW 021

Build Rite Construction CO.Ltd.

Road Rehab 7-Mar-11 2.5Km 24,611,421.31 16,617,509.72 62.0%

PRELIMINARIES: 50% SITE CLEARANCE: 100% DRAINAGE: 50% EARTHWORKS: 59% PAVEMENT: 50%

9 Wildman Street RW 021

Build Rite Construction CO.Ltd.

Road Rehab .412Km 21,581,820.55 7,093,496.63 62%

PRELIMINARIES: 40% SITE CLEARANCE: 100% DRAINAGE: 5% EARTHWORKS: 90% PAVEMENT: 75%

10

Webb Road RW 021

Build Rite Construction CO.Ltd.

Road Rehab 6.4Km 26,142,187.67 10,329,605.56 69%

PRELIMINARIES: 50% SITE CLEARANCE: 100% DRAINAGE: 30% EARTHWORKS: 90% PAVEMENT:

Page 86: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

75%

Total 548,557,529.52 296,448,832.04

Region: Central

Parish: CLARENDON

No.

CONTRACT PACKAGE

LOCATION/ DESCRIPTION

SUB-CONTRAC

TOR TYPE OF

WORK COMM. DATE

EXP. COMP DATE

QUANTITY/LENGTH (M3/KM)

PROJECT COST (J $)

EXPENDITURE TO DATE (J $)

OVERALL%

COMP REMARKS

1 RW-006 Karlston Glades

Y.P. Seaton &

Associates Ltd.

Infrastructure Works

24-01-2011

Jan 2012 355,143,828.06 76,668,506.83 20%

Prelim: 55% Site Clearance: 100% Drainage: 5% Sewage: 18% Roadworks: 5% Pavements: 0% Retaining Structures: 0%. The progress of work has been back on track. The sewage and road works are ongoing and the construction of the culver bridge has begun.

Page 87: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

1 Whiteshop - Dykes Hill RW 010

Build Rite Constructi

on CO.Ltd.

Road Rehab 10-Jan-11 Mar-11 1.000km 37,077,719.07 32,206,354.45 99%

PRELIMINARIES: 100% SITE CLEARANCE: 100% DRAINAGE: 100% EARTHWORKS: 100% PAVEMENT: 99%

2 Gravel Hill - Ritches RW 010

Build Rite Construction CO.Ltd.

Road Rehab 750m 22,916,680.30 13,458,993.80 86%

PRELIMINARIES: 80% SITE CLEARANCE: 100% DRAINAGE: 90% EARTHWORKS: 100% PAVEMENT: 60%

3 Smithville - Effort RW 010

Build Rite Construction CO.Ltd.

Road Rehab 11-Jan-11 Jul-11 4.250km 75,001,324.13 55,315,333.11 78%

PRELIMINARIES: 75% SITE CLEARANCE: 100% DRAINAGE: 75% EARTHWORKS: 100% PAVEMENT: 60% RR WALL 60%

Page 88: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

4 Chatteau - Rock River RW 010

Build Rite Construction CO.Ltd.

Road Rehab 12-Jan-11 11-Nov 6.200km 195,120,181.08 95,166,325.65 51.0%

SITE CLEARANCE: 100% DRAINAGE: 80% EARTHWORKS: 80% PAVEMENT: 40% RR WALL : 80% Rock Excavation: 30%

5 Rock River - Mitchell Hill

Build Rite Construction CO.Ltd.

Road Rehab 11-Jan-11 11-Mar 5.418km 35,218,513.09 12,654,678.45 32%

PRELIMINARIES: 30% SITE CLEARANCE: 90% DRAINAGE: EARTHWORKS: PAVEMENT: RR WALL: 75%

6

Rock River - Lower Chapelton RW 010

Build Rite Construction CO.Ltd.

Road Rehab 10-Jan-11 11-Oct 8.500km 137,647,483.86 54,622,596.51 43%

PRELIMINARIES: 70% SITE CLEARANCE: 100% DRAINAGE: 70% EARTHWORKS: 90% PAVEMENT: 40%

7 Low Ground RW 010

Build Rite Construction CO.Ltd.

Road Rehab 15-Jan-11 11-Mar 925m 6,332,288.78 1,383,563.24 34%

PRELIMINARIES: 50% SITE CLEARANCE: 100% DRAINAGE: EARTHWORKS:

Page 89: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

20% PAVEMENT:

8 Boredaux Hill RW 010

Build Rite Construction CO.Ltd.

Road Rehab 31-Jan-11 11-Mar 736m 8,083,667.61 4,551,910.28 69%

PRELIMINARIES: 38% SITE CLEARANCE: 100% DRAINAGE: 80% EARTHWORKS: 50% PAVEMENT: 80%

9 Pleasant Hill RW 010

Build Rite Construction CO.Ltd.

Road Rehab 31-Jan-11 11-Mar 580m 9,060,087.95 5,648,994.20 86%

PRELIMINARIES: 50% SITE CLEARANCE: 100% DRAINAGE: 90% EARTHWORKS: 25% PAVEMENT: 90%

10

Dry Hill RW 010

Build Rite Construction CO.Ltd.

Road Rehab 31-Jan-11 11-Mar 1.208km 16,145,604.33 11,599,556.37 65%

PRELIMINARIES: 50% SITE CLEARANCE: 100% DRAINAGE: 40% EARTHWORKS: 90% PAVEMENT: 45%

Page 90: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

11

New Ground RW 010

Build Rite Construction CO.Ltd.

Road Rehab 8-Jan-11 11-Apr 365m 24,475,660.20 19,069,071.53 100%

PRELIMINARIES: 100% SITE CLEARANCE: 100% DRAINAGE: 100% EARTHWORKS: 100% PAVEMENT: 100% RETAINING WALL: 100%

12

Pumpkin - Reckford RW 010

Build Rite Construction CO.Ltd.

Road Rehab 3-Jan-11 11-Nov 7.542km 139,177,277.66 94,891,064.20 62.0%

PRELIMINARIES: 60% SITE CLEARANCE: 100% DRAINAGE: EARTHWORKS: 100% PAVEMENT: 25% RETAINING WALL: 89%

13

Sangsters Heights RW 010

Build Rite Construction CO.Ltd.

Road Rehab 8-Jan-11 11-Jun 3.814km 73,601,883.89 69,814,505.89 87%

PRELIMINARIES: 60% SITE CLEARANCE: 100% DRAINAGE: 90% EARTHWORKS: 100% PAVEMENT: 80% RETAINING WALL: 95%

Page 91: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

14

Aenon Town - McKoy RW 015

Construction Solutions

Road Rehab 12-Jan-11 5.037km 110,868,741.76 52,734,031.32 63%

PRELIMINARIES: 60% SITE CLEARANCE: 100% DRAINAGE: 40 EARTHWORKS: 80% PAVEMENT: 10% ROCK EXCAVATION: 90%

15

Brandon Hill - Cock Shop - Top Hill RW 015

Construction Solutions

Road Rehab 17-Jan-11 2.320km 62,734,207.99 52,666,797.21 96.0%

PRELIMINARIES: 90% SITE CLEARANCE: 100% DRAINAGE: 95% EARTHWORKS: 100% PAVEMENT: 90% RR WALL: 100%

16

Salt River - Lancet RW 010

Build Rite Construction CO.Ltd.

Road Rehab 30-Dec-10 11-Oct 17.800km 335,082,040.56 297,704,771.6

8 74.0%

PRELIMINARIES: 70% SITE CLEARANCE: 100% DRAINAGE: 60% EARTHWORKS: 90% PAVEMENT: 50%

Page 92: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

17

Portland Cottage RW 010

Build Rite Construction CO.Ltd.

Road Rehab 16-Feb-11 11-Apr 9.000km 38,721,567.48 37,188,007.48 99.0%

PRELIMINARIES: 85% SITE CLEARANCE: 100% DRAINAGE: EARTHWORKS: 100% PAVEMENT: 95%

18

Banks RW 010

Build Rite Construction CO.Ltd.

Road Rehab 24-Jan-11 11-May 1.314 Km 58,097,261.69 41,032,170.15 69%

PRELIMINARIES: 60% SITE CLEARANCE: 100% DRAINAGE: 25% EARTHWORKS: 100% PAVEMENT: 60% (Dispute over rates; work stopped)

19

Sunset Crescent RW 010

Build Rite Construction CO.Ltd.

Road Rehab 4-Jan-11 11-Mar 1.200km 40,230,138.03 39,601,528.71 99.0%

PRELIMINARIES: 90% SITE CLEARANCE: 100% DRAINAGE: 90% EARTHWORKS: 100% PAVEMENT: 100%

20

Juno Crescent RW 010

Build Rite Construction CO.Ltd.

Road Rehab 6-Jan-11 11-May 2.200Km 84,877,944.95 72,812,098.11 90.0%

PRELIMINARIES: 75% SITE CLEARANCE: 100% DRAINAGE: 80% EARTHWORKS:

Page 93: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

100% PAVEMENT: 70% VO approved for construction of Drain

21

Glenmuir Housing Scheme RW 010

Build Rite Construction CO.Ltd.

Road Rehab 30-Dec-10 11-Feb 1.775 Km 56,702,000.34 36,114,607.50 80.0%

PRELIMINARIES: 75% SITE CLEARANCE: 100% DRAINAGE: 80% EARTHWORKS: 100% PAVEMENT: 75% On Hold Water Comission

22

North Street RW 010

Build Rite Construction CO.Ltd.

Road Rehab 7-Jan-11 11-Apr 500m 20,626,267.64 18,932,545.54 99%

PRELIMINARIES: 90% SITE CLEARANCE: 100% DRAINAGE: 100% EARTHWORKS: 100% PAVEMENT: 100% RETAINING WALL 100%

23

Guinep Tree - Jacob Hut (May Pen Roads) RW 010

Build Rite Construction CO.Ltd.

Road Rehab 21-Dec-10 11-May 3.287 Km 173,816,055.80 152,248,292.8

0 87%

PRELIMINARIES: 90% SITE CLEARANCE: 100% DRAINAGE: 95% EARTHWORKS:

Page 94: JAMAICA DEVELOPMENT INFRASTRUCTURE PROGRAMME (JDIP) · PDF fileEXECUTIVE SUMMARY. The Jamaica Development Infrastructure Programme (JDIP) is the umbrella programme under which the

95% PAVEMENT: 80%

24

Church Valley RW 010

Build Rite Construction CO.Ltd.

Road Rehab 15-Jan-11 11-Apr 550m 16,969,884.55 13,086,257.09 84%

PRELIMINARIES: 70% SITE CLEARANCE: 100% DRAINAGE: 75% EARTHWORKS: 100% PAVEMENT: 75%

25

Top Bucknor Road RW 010

Build Rite Construction CO.Ltd.

Road Rehab 12-Jan-11 11-May 1.170 Km 45,136,695.30 21,849,889.88 52%

PRELIMINARIES: 74% SITE CLEARANCE: 100% DRAINAGE: 70% EARTHWORKS: 100% PAVEMENT: 70%

26

Cedars - Stewarton RW 010

Build Rite Construction CO.Ltd.

Road Rehab 8-Jan-11 11-Apr 3.383km 53,983,375.67 41,354,223.98 88%

PRELIMINARIES: 80% SITE CLEARANCE: 100% DRAINAGE: 80% EARTHWORKS: 100% PAVEMENT: 80%

Total 2,232,848,381.

77 1,424,376,67

5.96