iugaza pm 20171 ch1.pptsite.iugaza.edu.ps/aabuzarifa/files/iugaza-pm_20171_ch11.pdf · 2017. 9....

23
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 Project Management EIND 5306 2017_1

Upload: others

Post on 11-Sep-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: IUGAZA PM 20171 CH1.pptsite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH11.pdf · 2017. 9. 23. · Dr. Anwar Abu-Zarifa . Islamic University of Gaza . D epartment of Mechanical

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018

Project ManagementEIND 53062017_1

Page 2: IUGAZA PM 20171 CH1.pptsite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH11.pdf · 2017. 9. 23. · Dr. Anwar Abu-Zarifa . Islamic University of Gaza . D epartment of Mechanical

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018

OutlineInstructor: Associate Professor Anwar Abu-Zarifa (PhD)Office: New Administration Building, Department of Mechanical & Industrial EngineeringLecture: Sun, Tue 09:30 – 11:00 K517 (Male, 101)

Sun, Tue 12:30 – 14:00 I602 (Female, 201)Office Hrs.: (Sa, Mo, We)Email: [email protected]: Wysocki, Robert K., Effective Project Management, 5nd Edition, Wiley Publishing, 2009Grading:Midterm 30% Project 25%Final exam 45%

Page 3: IUGAZA PM 20171 CH1.pptsite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH11.pdf · 2017. 9. 23. · Dr. Anwar Abu-Zarifa . Islamic University of Gaza . D epartment of Mechanical

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 3

Introduction to project management, Definition and characteristics ofa project, Management Functions, Project management andsuccess-making factors, Project manager and his/her role.

Project Planning, Project planning and its functions, Why projectplanning, The stages of the project planning process, Projectbudgeting, Project organizing, structuring, and scheduling.

Project Monitoring, Evaluating, and Control, Project control, thecontrol cycle, Earned Value Technique.

Project Close-Out, System testing and start –up, Inspection, records. Microsoft Project Application. Human aspects, Motivation, time management, Communications.

Topics

Page 4: IUGAZA PM 20171 CH1.pptsite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH11.pdf · 2017. 9. 23. · Dr. Anwar Abu-Zarifa . Islamic University of Gaza . D epartment of Mechanical

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 4

Chapter 1 What Is a Project?

Page 5: IUGAZA PM 20171 CH1.pptsite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH11.pdf · 2017. 9. 23. · Dr. Anwar Abu-Zarifa . Islamic University of Gaza . D epartment of Mechanical

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 5

A project is a sequence of unique, complex, and connected activitieshaving one goal or purpose and that must be completed by a specific time, within budget, and according to specifications.

What is a Project?

- Effective Project Management , Wysocki

Page 6: IUGAZA PM 20171 CH1.pptsite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH11.pdf · 2017. 9. 23. · Dr. Anwar Abu-Zarifa . Islamic University of Gaza . D epartment of Mechanical

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 6

A project is a temporary endeavor undertaken to create a unique product, service, or result

-- Project Management Body of Knowledge (PMBOK), 2004

A project is a combination of human and nonhuman sources pulled together in a temporary organization to achieve a specified purpose.

-- Cleland and Kerzner, 1985

Page 7: IUGAZA PM 20171 CH1.pptsite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH11.pdf · 2017. 9. 23. · Dr. Anwar Abu-Zarifa . Islamic University of Gaza . D epartment of Mechanical

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 7

Projects Vary in Size and Scope• NASA shuttle launch• Building a boat• Building a hospital• Organizing the Olympic games• Developing a new software program• Getting a university degree

Page 8: IUGAZA PM 20171 CH1.pptsite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH11.pdf · 2017. 9. 23. · Dr. Anwar Abu-Zarifa . Islamic University of Gaza . D epartment of Mechanical

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 8

What is Project Management?

Project management is a set of principles and tools for

•Defining•Planning•Executing•Controlling•Completing a PROJECT

Page 9: IUGAZA PM 20171 CH1.pptsite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH11.pdf · 2017. 9. 23. · Dr. Anwar Abu-Zarifa . Islamic University of Gaza . D epartment of Mechanical

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 9

Why is Project Management Important?

• Organize your approach• Generate a credible schedule• Track progress and control your project• Identify where to focus your efforts • Identify problems early – before they are

crises• Saves you TIME….MONEY

Page 10: IUGAZA PM 20171 CH1.pptsite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH11.pdf · 2017. 9. 23. · Dr. Anwar Abu-Zarifa . Islamic University of Gaza . D epartment of Mechanical

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 10

• 66% of all IT projects fail, come in over budget or run past the original deadline

• Every year, $55 billion is wasted on failed IT projects in the U.S.

Fail15%

Over time or over budget

51%

Succeed34%

Source: Chaos Chronicles 2015, The Standish Group

continue

Only one in three software projects will turn out to be successful. According to Standish Group’s 2015 Chaos report, 66% of technology projects (based on the analysis of 50,000 projects worldwide) end in partial or total failure. More surprisingly, these statistics have been the same for the last five years, the report shows. Furthermore, 17% of large IT projects go so badly that they can threaten the very existence of a company.

Page 11: IUGAZA PM 20171 CH1.pptsite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH11.pdf · 2017. 9. 23. · Dr. Anwar Abu-Zarifa . Islamic University of Gaza . D epartment of Mechanical

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 11

Circa 530 kilometers cables are necessary for A380.The cables were (by the first design) only few centimeters short.This Deferens caused by Airbus a loss of 4,8 Billions Euro. Cause: incompatibility of Software(In Germany and Spain Catia V4, in France Catia V5)

CAD- Incompatibility causes by Airbus a loss of Billions

Managementfailure:

Project-Coordinationwas poor

Page 12: IUGAZA PM 20171 CH1.pptsite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH11.pdf · 2017. 9. 23. · Dr. Anwar Abu-Zarifa . Islamic University of Gaza . D epartment of Mechanical

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 12

Engineer activities

PM

Sale

HR, Manag.

Training, educationother

Design,Manufacturing,Evaluation

Research

Page 13: IUGAZA PM 20171 CH1.pptsite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH11.pdf · 2017. 9. 23. · Dr. Anwar Abu-Zarifa . Islamic University of Gaza . D epartment of Mechanical

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 13

• Projects are oriented towards a goal.• There is something unique about every

project.• Projects have a finite duration.• Projects require coordination of

interrelated activities.

Project Management Criteria

Page 14: IUGAZA PM 20171 CH1.pptsite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH11.pdf · 2017. 9. 23. · Dr. Anwar Abu-Zarifa . Islamic University of Gaza . D epartment of Mechanical

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 14

Project Characteristics• Defined goal• Primary sponsor or customer• Set of activities

– Unique, complex, sequenced• Start & finish

– Temporary, time frame for completion• Limited resources

– Dollars, people• Uncertainty, risk

Page 15: IUGAZA PM 20171 CH1.pptsite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH11.pdf · 2017. 9. 23. · Dr. Anwar Abu-Zarifa . Islamic University of Gaza . D epartment of Mechanical

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 15

Defining a Project• Sequence of Activities• Complex Activities• Connected Activities• One Goal• Specified Time• Within Budget• According to Specification

Page 16: IUGAZA PM 20171 CH1.pptsite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH11.pdf · 2017. 9. 23. · Dr. Anwar Abu-Zarifa . Islamic University of Gaza . D epartment of Mechanical

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 16

• Project management is a set of principles and tools for– Defining– Planning– Executing– Controlling . . . and – Completing a PROJECT

What is Project Management?

Page 17: IUGAZA PM 20171 CH1.pptsite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH11.pdf · 2017. 9. 23. · Dr. Anwar Abu-Zarifa . Islamic University of Gaza . D epartment of Mechanical

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 17

What is Project Management?

• PM is the application of knowledge, skills, tools and techniques to project activities in order to meet project requirements. (PMI)

• PM– is an art.– is a science.– has a set of tools and methods.

Page 18: IUGAZA PM 20171 CH1.pptsite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH11.pdf · 2017. 9. 23. · Dr. Anwar Abu-Zarifa . Islamic University of Gaza . D epartment of Mechanical

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 18

Three Disciplines

Page 19: IUGAZA PM 20171 CH1.pptsite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH11.pdf · 2017. 9. 23. · Dr. Anwar Abu-Zarifa . Islamic University of Gaza . D epartment of Mechanical

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 19

What Is a Program?

• A collection of projects• NASA

Page 20: IUGAZA PM 20171 CH1.pptsite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH11.pdf · 2017. 9. 23. · Dr. Anwar Abu-Zarifa . Islamic University of Gaza . D epartment of Mechanical

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 20

Scope Triangle

ScopeQuality

Cost Time

Resources

The Scope Triangle: Time, Cost, Resources

Page 21: IUGAZA PM 20171 CH1.pptsite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH11.pdf · 2017. 9. 23. · Dr. Anwar Abu-Zarifa . Islamic University of Gaza . D epartment of Mechanical

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 21

Project Creep (Wysocki)• Scope creep

– any change not in original plan– IT particularly prone to creep– major challenge for PMs

• Hope creep– will catch up next week..(The team members

“hope” they can catch up by the next report period or project team meeting to be back on schedule)

• Effort creep– 95-99% complete but never 100%– Feature creep

• team member adds features

Page 22: IUGAZA PM 20171 CH1.pptsite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH11.pdf · 2017. 9. 23. · Dr. Anwar Abu-Zarifa . Islamic University of Gaza . D epartment of Mechanical

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 22

Classification by Project CharacteristicsRiskBusiness ValueLengthComplexityTechnologyNumber of DepartmentsCost

Page 23: IUGAZA PM 20171 CH1.pptsite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH11.pdf · 2017. 9. 23. · Dr. Anwar Abu-Zarifa . Islamic University of Gaza . D epartment of Mechanical

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 23

Classification by Project Type

SoftwareHardwareRecruiting & hiring