iso-ne net loads with increasing behind-the-meter pv€¦ · iso-ne net loads with . increasing...

20
ISO-NE PUBLIC JUNE 10, 2016 | WESTBOROUGH, MA Jon Black MANAGER, LOAD FORECASTING ISO-NE Net Loads with Increasing Behind-the-Meter PV

Upload: others

Post on 08-Jun-2020

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ISO-NE Net Loads with Increasing Behind-the-Meter PV€¦ · ISO-NE Net Loads with . Increasing Behind-the-Meter PV . ISO-NE PUBLIC 2 Outline • Introduction • Net Load Simulation

ISO-NE PUBLIC

J U N E 1 0 , 2 0 1 6 | W E S T B O R O U G H , M A

Jon Black M A N A G E R , L O A D F O R E C A S T I N G

ISO-NE Net Loads with Increasing Behind-the-Meter PV

Page 2: ISO-NE Net Loads with Increasing Behind-the-Meter PV€¦ · ISO-NE Net Loads with . Increasing Behind-the-Meter PV . ISO-NE PUBLIC 2 Outline • Introduction • Net Load Simulation

ISO-NE PUBLIC 2

Outline

• Introduction

• Net Load Simulation - Methodology

• Net Load Simulation – Results

• Conclusions

Page 3: ISO-NE Net Loads with Increasing Behind-the-Meter PV€¦ · ISO-NE Net Loads with . Increasing Behind-the-Meter PV . ISO-NE PUBLIC 2 Outline • Introduction • Net Load Simulation

ISO-NE PUBLIC ISO-NE PUBLIC

INTRODUCTION

3

Page 4: ISO-NE Net Loads with Increasing Behind-the-Meter PV€¦ · ISO-NE Net Loads with . Increasing Behind-the-Meter PV . ISO-NE PUBLIC 2 Outline • Introduction • Net Load Simulation

ISO-NE PUBLIC 4

Introduction

• Large-scale growth of distributed, behind-the-meter (BTM) photovoltaic (PV) resources is occurring in New England and is forecast to continue

• Distributed PV is generally not metered in real-time and therefore is not visible to or dispatchable by ISO operations

• ISO is seeking to understand the effects of large-scale PV on the region’s future load characteristics

• This presentation describes the results of a net load (i.e., load net of PV) simulation with up to 8,000 MW of PV installed

• This simulation is in part meant to illustrate the effects of larger-than-expected PV penetrations to help identify key changes in net load characteristics as PV increases

Page 5: ISO-NE Net Loads with Increasing Behind-the-Meter PV€¦ · ISO-NE Net Loads with . Increasing Behind-the-Meter PV . ISO-NE PUBLIC 2 Outline • Introduction • Net Load Simulation

ISO-NE PUBLIC

PV Growth: Reported Historical vs. Forecast

5

0

500

1000

1500

2000

2500

3000

3500

PV N

amep

late

, MW

(ac)

2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025

Hx Growth

2014 Fx

2015 Fx

2016 Fx

Page 6: ISO-NE Net Loads with Increasing Behind-the-Meter PV€¦ · ISO-NE Net Loads with . Increasing Behind-the-Meter PV . ISO-NE PUBLIC 2 Outline • Introduction • Net Load Simulation

ISO-NE PUBLIC ISO-NE PUBLIC

NET LOAD SIMULATION – METHOD

6

Page 7: ISO-NE Net Loads with Increasing Behind-the-Meter PV€¦ · ISO-NE Net Loads with . Increasing Behind-the-Meter PV . ISO-NE PUBLIC 2 Outline • Introduction • Net Load Simulation

ISO-NE PUBLIC

• Future net load scenarios are based on coincident, historical hourly load and PV production data for the period 1/1/2012 – 8/31/15

• PV production data accessed via Yaskawa-Solectria Solar’s SolrenView* – >1k PV sites totaling > 125 MWac

• Normalized PV profiles were developed for each New England state, blended into a regional profile which was then “upscaled” to each PV scenario

7

Net Load Simulation Method

*Accessed via http://www.solrenview.com/

Yaskawa-Solectria Sites

Page 8: ISO-NE Net Loads with Increasing Behind-the-Meter PV€¦ · ISO-NE Net Loads with . Increasing Behind-the-Meter PV . ISO-NE PUBLIC 2 Outline • Introduction • Net Load Simulation

ISO-NE PUBLIC

Net Load Simulation Method continued

• Existing PV system design and technology trends are not anticipated to change significantly over the next decade. – It is assumed that upscaling of these profiles yields a reasonable estimate

of future profiles associated with larger PV fleets that is adequate for simulation purposes

• Hourly load profiles were first reconstituted for active demand response as well as BTM PV in existence during the historical period used

• Hourly net load profiles were then calculated by subtracting calculated production from increasing amounts of PV developed in 200 MW (AC nameplate) increments up to 8,000 MW

• Slides 11-13 show resulting characteristic seasonal daily profiles for 1GW increments of PV

8

Page 9: ISO-NE Net Loads with Increasing Behind-the-Meter PV€¦ · ISO-NE Net Loads with . Increasing Behind-the-Meter PV . ISO-NE PUBLIC 2 Outline • Introduction • Net Load Simulation

ISO-NE PUBLIC

Hourly Reconstituted Loads and Normalized PV 1/1/2012 – 8/31/2015

9

Page 10: ISO-NE Net Loads with Increasing Behind-the-Meter PV€¦ · ISO-NE Net Loads with . Increasing Behind-the-Meter PV . ISO-NE PUBLIC 2 Outline • Introduction • Net Load Simulation

ISO-NE PUBLIC ISO-NE PUBLIC

NET LOAD SIMULATION – RESULTS

10

Page 11: ISO-NE Net Loads with Increasing Behind-the-Meter PV€¦ · ISO-NE Net Loads with . Increasing Behind-the-Meter PV . ISO-NE PUBLIC 2 Outline • Introduction • Net Load Simulation

ISO-NE PUBLIC

• PV does not reduce winter peak

• Load reductions from PV can be significant during midday hours on sunny winter days

• High PV penetrations will increase the need for ramping capability throughout sunlight hours

Winter Season Net Load Profile

Tuesday, January 7, 2014

11

Page 12: ISO-NE Net Loads with Increasing Behind-the-Meter PV€¦ · ISO-NE Net Loads with . Increasing Behind-the-Meter PV . ISO-NE PUBLIC 2 Outline • Introduction • Net Load Simulation

ISO-NE PUBLIC

• Profile sometimes referred to as the “Duck Curve”

• Lowest loads often occur on weekend days during spring/autumn and low demand for heating/cooling

• Increased PV will displace significant amounts of synchronous generation

• Potential minimum generation emergency events during midday hours (minimum load hours are shown in green)

Shoulder Season Net Load Profile

Sunday, April 20, 2014

12

Page 13: ISO-NE Net Loads with Increasing Behind-the-Meter PV€¦ · ISO-NE Net Loads with . Increasing Behind-the-Meter PV . ISO-NE PUBLIC 2 Outline • Introduction • Net Load Simulation

ISO-NE PUBLIC

• As PV penetrations become higher:

1. The timing of peak net loads (blue dots) becomes later in afternoon/evening

2. Each successively larger PV scenario contributes less to serving summer peak net loads (which now occur later in the day), due to the setting of the sun

• The 2016 PV forecast incorporated results of analysis showing expected diminishing reductions of future summer peak loads due to PV (refer to slides 71-90 here: http://www.iso-ne.com/static-assets/documents/2016/05/2016_pvforecast.pdf )

Summer Season Net Load Profile

Friday, July 19, 2013

13

Page 14: ISO-NE Net Loads with Increasing Behind-the-Meter PV€¦ · ISO-NE Net Loads with . Increasing Behind-the-Meter PV . ISO-NE PUBLIC 2 Outline • Introduction • Net Load Simulation

ISO-NE PUBLIC

Magnitude and Timing of Summer Peak Net Loads Daily Peak Net Loads – Jun-Sep, 2012-2015

14

No PV 1 GW PV 2 GW PV

4 GW PV 6 GW PV 8 GW PV

Page 15: ISO-NE Net Loads with Increasing Behind-the-Meter PV€¦ · ISO-NE Net Loads with . Increasing Behind-the-Meter PV . ISO-NE PUBLIC 2 Outline • Introduction • Net Load Simulation

ISO-NE PUBLIC 15

PV Contribution to Serving Load

• Based on the PV production data described on slide 7 PV in aggregate is estimated to have an annual capacity factor of ~14.1%

• An estimated profile associated with the 2025 PV total nameplate forecast (3,272 MWac) was developed and compared to hourly and daily loads (shown on next slides)

Page 16: ISO-NE Net Loads with Increasing Behind-the-Meter PV€¦ · ISO-NE Net Loads with . Increasing Behind-the-Meter PV . ISO-NE PUBLIC 2 Outline • Introduction • Net Load Simulation

ISO-NE PUBLIC

Contribution of PV to Hourly Loads Assumes 2025 Total PV Forecast (3,272 MWac Nameplate)

16

Page 17: ISO-NE Net Loads with Increasing Behind-the-Meter PV€¦ · ISO-NE Net Loads with . Increasing Behind-the-Meter PV . ISO-NE PUBLIC 2 Outline • Introduction • Net Load Simulation

ISO-NE PUBLIC

Summer Season Net Load Profile Zoomed Out – July 19, 2013

17

>90% of Load Energy Remains with 8 GW of PV

Each GW of PV Lowers Daily Energy on 7/19/13 by ~1%

Page 18: ISO-NE Net Loads with Increasing Behind-the-Meter PV€¦ · ISO-NE Net Loads with . Increasing Behind-the-Meter PV . ISO-NE PUBLIC 2 Outline • Introduction • Net Load Simulation

ISO-NE PUBLIC

Contribution of PV to Daily Load Energy Assumes 2025 Total PV Forecast (3,272 MWac Nameplate)

18

Average = 3.3%

Page 19: ISO-NE Net Loads with Increasing Behind-the-Meter PV€¦ · ISO-NE Net Loads with . Increasing Behind-the-Meter PV . ISO-NE PUBLIC 2 Outline • Introduction • Net Load Simulation

ISO-NE PUBLIC

Conclusions

• Large-scale PV that is installed “behind-the-meter” will significantly impact the regional load profile

• The amount of PV forecast for 2025 could serve more than 20% of hourly loads during light loads and ~3.3% of annual energy

• Results of net load simulation shows the following key changes: – Increased potential for minimum generation emergency events during

light load conditions – Shifting of the timing of summer peak loads to later in the day outside

of summer reliability hours – Overall increase in load ramping during all seasons

19

Page 20: ISO-NE Net Loads with Increasing Behind-the-Meter PV€¦ · ISO-NE Net Loads with . Increasing Behind-the-Meter PV . ISO-NE PUBLIC 2 Outline • Introduction • Net Load Simulation

ISO-NE PUBLIC 20