isg130/01 metering dispensation d/371 - elexon · pdf fileisg130/01 metering dispensation...

12
ISG130/01 v1.0 Page 1 of 2 © ELEXON 2011 ISG130/01 Metering Dispensation D/371 Meeting Name Imbalance Settlement Group (ISG) Meeting Date Ex-committee response requested by 5pm 15 November 2011 Purpose of paper For Decision Summary CE Electric have applied for a Metering Dispensation for a 12MW power plant where the metering CTs and VTs are to be located at a distance from the Boundary Point. This paper seeks ISG’s approval for the Metering Dispensation on the grounds of negligible materiality. 1. BSC Requirements 1.1 Section L 3.2 of the Balancing and Settlement Code (BSC) requires Registrant’s of Meter Equipment to ensure that the Metering Equipment it uses for Settlement purposes is, and remains compliant with the requirements of the relevant Codes of Practice (CoP). Section L 3.4 of the BSC has provision for Registrants to submit an application for a Metering Dispensation where it is not possible, if for practical or financial reasons, to comply with the requirements of a relevant CoP. 2. Background 2.1 Girlington power plant is a new 12MW station that is to be owned and operated by Green Frog Power Limited as Short Term Operating Reserve. 2.2 During the process of application for connection to CE-Electric’s network it was established that costs in the order of £1.5m would be required to accommodate Settlement current and voltage measurement transformers (CTs and VTs). The bulk of these costs are associated with the provision of a new a 33kV substation to accommodate additional HV switchgear containing CTs and VTs. 2.3 On 31 October 2011 we received an application for a Metering Dispensation in accordance with BSCP32 ‘Metering Dispensations’ (Attachment A) from the requirements of Code of Practice 2. 2.4 The applicant proposes to locate the metering CTs and VTs in the customers 33kV switch gear (at a cost of approximately £2,000) which is located 70 metres from the Defined Metering Point. The applicant has assessed the electrical losses between the Boundary Point and the Actual Metering Point and concludes that they are negligible and can be disregarded as they amount to a very small percentage of the allowable accuracy of CoP2. 2.5 The applicant also assesses the materiality and risk to Settlement of approx 60-70kWh per year. This is based on the electrical loss at full export capacity for an estimated run time of approximately 125 hours per year.

Upload: vantu

Post on 01-Feb-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ISG130/01 Metering Dispensation D/371 - ELEXON · PDF fileISG130/01 Metering Dispensation D/371 ... 2.2 During the process of application for connection to CE-Electric’s network

ISG130/01 v1.0

Page 1 of 2 © ELEXON 2011

ISG130/01

Metering Dispensation D/371

Meeting Name Imbalance Settlement Group (ISG)

Meeting Date Ex-committee – response requested by 5pm 15 November 2011

Purpose of paper For Decision

Summary

CE Electric have applied for a Metering Dispensation for a 12MW power plant where the

metering CTs and VTs are to be located at a distance from the Boundary Point. This paper

seeks ISG’s approval for the Metering Dispensation on the grounds of negligible materiality.

1. BSC Requirements

1.1 Section L 3.2 of the Balancing and Settlement Code (BSC) requires Registrant’s of Meter Equipment to

ensure that the Metering Equipment it uses for Settlement purposes is, and remains compliant with the

requirements of the relevant Codes of Practice (CoP). Section L 3.4 of the BSC has provision for Registrants

to submit an application for a Metering Dispensation where it is not possible, if for practical or financial

reasons, to comply with the requirements of a relevant CoP.

2. Background

2.1 Girlington power plant is a new 12MW station that is to be owned and operated by Green Frog Power

Limited as Short Term Operating Reserve.

2.2 During the process of application for connection to CE-Electric’s network it was established that costs in the

order of £1.5m would be required to accommodate Settlement current and voltage measurement

transformers (CTs and VTs). The bulk of these costs are associated with the provision of a new a 33kV

substation to accommodate additional HV switchgear containing CTs and VTs.

2.3 On 31 October 2011 we received an application for a Metering Dispensation in accordance with BSCP32

‘Metering Dispensations’ (Attachment A) from the requirements of Code of Practice 2.

2.4 The applicant proposes to locate the metering CTs and VTs in the customers 33kV switch gear (at a cost of

approximately £2,000) which is located 70 metres from the Defined Metering Point. The applicant has

assessed the electrical losses between the Boundary Point and the Actual Metering Point and concludes that

they are negligible and can be disregarded as they amount to a very small percentage of the allowable

accuracy of CoP2.

2.5 The applicant also assesses the materiality and risk to Settlement of approx 60-70kWh per year. This is

based on the electrical loss at full export capacity for an estimated run time of approximately 125 hours per

year.

Page 2: ISG130/01 Metering Dispensation D/371 - ELEXON · PDF fileISG130/01 Metering Dispensation D/371 ... 2.2 During the process of application for connection to CE-Electric’s network

ISG130/01 v1.0

Page 2 of 2 © ELEXON 2011

ISG130/01

2.6 We issued the application to the Metering Dispensation Review Group (MDRG) for comment and received 4

responses. All four members support the application.

2.6.1 One MDRG member queried whether the estimation of active power loss quoted at 0.05% was, in fact,

correct. The applicant has confirmed that this figure in the application should read 0.005%.

2.7 This MDRG member also noted that the estimation of electrical losses did not cater for no load loss. We

asked the applicant to comment on this and have received an amended calculated estimate of losses which

includes no load losses of 6.39W (Attachment B).

3. ELEXON's View

3.1 We believe that locating the CTs and VTs in the customer’s switchgear is a reasonable and cost effective

solution. We therefore fully support this application for Metering Dispensation on the grounds of negligible

risk to Settlement.

4. Recommendations

4.1 We invite you to:

a) NOTE the application and MDRG views; and

b) APPROVE Metering Dispensation D/371.

Attachments:

Attachment A – Metering Dispensation D/371 Attachment B - D371 Cable loss calculations

For more information, please contact:

Keith Campion, Metering Analyst [email protected]

020 7380 4011

Page 3: ISG130/01 Metering Dispensation D/371 - ELEXON · PDF fileISG130/01 Metering Dispensation D/371 ... 2.2 During the process of application for connection to CE-Electric’s network

ISG130/01 - Attachment A

Page 4: ISG130/01 Metering Dispensation D/371 - ELEXON · PDF fileISG130/01 Metering Dispensation D/371 ... 2.2 During the process of application for connection to CE-Electric’s network

ISG130/01 - Attachment A

Page 5: ISG130/01 Metering Dispensation D/371 - ELEXON · PDF fileISG130/01 Metering Dispensation D/371 ... 2.2 During the process of application for connection to CE-Electric’s network

ISG130/01 - Attachment A

Page 6: ISG130/01 Metering Dispensation D/371 - ELEXON · PDF fileISG130/01 Metering Dispensation D/371 ... 2.2 During the process of application for connection to CE-Electric’s network

ISG130/01 - Attachment A

Page 7: ISG130/01 Metering Dispensation D/371 - ELEXON · PDF fileISG130/01 Metering Dispensation D/371 ... 2.2 During the process of application for connection to CE-Electric’s network

ISG130/01 - Attachment A

Page 8: ISG130/01 Metering Dispensation D/371 - ELEXON · PDF fileISG130/01 Metering Dispensation D/371 ... 2.2 During the process of application for connection to CE-Electric’s network

ISG130/01 - Attachment A

Page 9: ISG130/01 Metering Dispensation D/371 - ELEXON · PDF fileISG130/01 Metering Dispensation D/371 ... 2.2 During the process of application for connection to CE-Electric’s network

ISG130/01 - Attachment A

Page 10: ISG130/01 Metering Dispensation D/371 - ELEXON · PDF fileISG130/01 Metering Dispensation D/371 ... 2.2 During the process of application for connection to CE-Electric’s network

ISG130/01 - Attachment A

Page 11: ISG130/01 Metering Dispensation D/371 - ELEXON · PDF fileISG130/01 Metering Dispensation D/371 ... 2.2 During the process of application for connection to CE-Electric’s network

EN3392 - Calculation of cable losses for Metering Dispensation Load current for 12MW export at 0.95 power factor:

kVAI L [email protected]

10123

6

Cable details Cable type: 3 x single core cables to BS7870-4.10 in Triplex Voltage: 33kV Cross-sectional area: 150mm2

Conductor length: 70m ac resistance R (90o) 0.159 ohms/km reactance (50Hz): 0.129 ohms/km sheath resistance Rs: 0.379 ohms/km Distance between cable centres S: 0.043m approx Mean diameter of sheath dm: 0.039m approx I = phase conductor current Conductor losses Active Power Loss per phase

222 0111.0701000

159.0IIRIPloss

Reactive Power Loss per phase

222 0090.0701000

129.0IIXIQloss

Dielectric Losses Dielectric losses are negligible compared to the conductor losses for cables up to 50kV, as the power factor of the cable insulation is of very low order. Dielectric losses are dependent on voltage and so will be present when the cable is energised even if it is not carrying load current. They are given by the following equation:

kmW

UCfP Od

/2.91

004.03

1033102.0502

tan..2

23

6

2

ISG130/01 - Attachment B

Page 12: ISG130/01 Metering Dispensation D/371 - ELEXON · PDF fileISG130/01 Metering Dispensation D/371 ... 2.2 During the process of application for connection to CE-Electric’s network

Sheath Losses The sheath losses are made up from eddy current losses and sheath circuit losses. For single core cables connected in triplex formation and bonded and earthed at both ends the eddy current losses will be negligible, however the sheath circuit losses should be taken into account. The sheath circuit losses are due to the e.m.f. which is induced in the sheath by the a.c. conductor current by transformer action, which causes a current to flow in the sheath. The sheath current losses per phase are given by the following equation:

22

2

2

sm

mssheathloss

RX

XRIP (BICC Cable Handbook, equation 2.16)

Where Xm is the mutual reactance of the sheath and can be calculated from

kmohms

kmohmsd

SLogfX

e

m

em

/0497.0

10039.0

043.02log2.0502

/102

2.02

3

3

For 70m run of cable, the sheath losses will therefore be:

2

22

22

0004.0

1000

70

379.00497.0

0497.0379.0

IP

IP

sheathloss

sheathloss

Actual Loses at 12MVA at 0.95PF

pfWP

IIRIP

loss

loss

[email protected]

0111.0701000

159.0

2

222

pfVarQ

IIXIQ

loss

loss

[email protected]

0090.0701000

129.0

2

222

pfWP

IP

sheathloss

sheathloss

[email protected]

0004.0

2

2

W

Pd

39.6

1000

702.91

ISG130/01 - Attachment B