Page 1: Irish Prison Service Energy Management Strategy · the Irish Prison Service Estate EPC contract partnership IPS Services Finance Procurement Estate Management BSD Services Facility

Irish Prison Service Energy Management Strategy

Exemplar Energy Project

Wheatfield / Cloverhill Campus

13th of October 2015

Page 2: Irish Prison Service Energy Management Strategy · the Irish Prison Service Estate EPC contract partnership IPS Services Finance Procurement Estate Management BSD Services Facility

• 2020 Vision –Public Sector •“The public sector will improve its energy

efficiency by 33% and will be seen to lead by example –showing all sectors what is possible

through strong, committed action”. •SI 542 of 2009, Public Sector must be...

–“Exemplar”... In its •“Energy management practices”

•“Procurement practices” •“Audits”

• National Energy Efficiency Action Plan 2009

Page 3: Irish Prison Service Energy Management Strategy · the Irish Prison Service Estate EPC contract partnership IPS Services Finance Procurement Estate Management BSD Services Facility

What is an Energy Performance Contract ( EPC )

• The important principal of an EPC is that energy efficiency investment is paid for over time by the value of the energy savings delivered.

• The EPC undertake to improve energy efficiencies

• The EPC guarantees the performance.

• There is an agreed method of measuring and verifying the performance

Page 4: Irish Prison Service Energy Management Strategy · the Irish Prison Service Estate EPC contract partnership IPS Services Finance Procurement Estate Management BSD Services Facility

Prison Population Area m2 Electricity € Gas € Oil € Solid Fuel € Water €

Midlands 587 55,900 498,398.38 452,230.64 5,249.38 204,456.46

Mountjoy 559 45,000 759,393.60 792,849.24 434,363.78

Wheatfield 722 45,000 463,090.80 559,744.37 73,288.24 314,929.13

Cloverhill 390 25,000 249,29.44 56,629.92

Limerick 246 12,000 254,842.83 232,413.45 84,528.00

Cork 240 6,000 219,474.12 149,010.10 37,554.83

Castlerea 359 21,000 275,179.54 81,962.62 273,883.92 15,268.92 112,251.04

Loughan House

131 11,100 102,029.07 138,326.14 3,699.84

Portlaoise 269 30,920 407,628.33 231,939.55 2,003.59 134,323.11

Arbour Hill 141 16,000 141,194.28 115,291.23 177,589.41

Page 5: Irish Prison Service Energy Management Strategy · the Irish Prison Service Estate EPC contract partnership IPS Services Finance Procurement Estate Management BSD Services Facility
Page 6: Irish Prison Service Energy Management Strategy · the Irish Prison Service Estate EPC contract partnership IPS Services Finance Procurement Estate Management BSD Services Facility

Wheatfield Electrical Consumption

Page 7: Irish Prison Service Energy Management Strategy · the Irish Prison Service Estate EPC contract partnership IPS Services Finance Procurement Estate Management BSD Services Facility

Wheatfield Gas Annual Consumption

Page 8: Irish Prison Service Energy Management Strategy · the Irish Prison Service Estate EPC contract partnership IPS Services Finance Procurement Estate Management BSD Services Facility

• Field Study: On-site survey & calculations

• Statistical Analysis: Building areas, usage, energy prices, maintenance, operational information

• Energy Consumption: Heating – 55,000 MWh/year Electricity – 45,000 MWh/year

• Pre Study area – 55,000 m2

• Pre Study selected sites: Cloverhill and Wheatfield

Pre-Study Methodology & Pre-Requisites

Page 9: Irish Prison Service Energy Management Strategy · the Irish Prison Service Estate EPC contract partnership IPS Services Finance Procurement Estate Management BSD Services Facility

• Project Scope

• Upgrade heating system secondary controls and delivery systems

• Provide for the potential of CHP for heat generation to Cloverhill

• Replace existing gas detection and R22 air con systems

Page 10: Irish Prison Service Energy Management Strategy · the Irish Prison Service Estate EPC contract partnership IPS Services Finance Procurement Estate Management BSD Services Facility

• Project plan • Site energy evaluation completed.

• Feasibility report carried out on approved site.

• Scope of works and indicative cost developed for project

• Potential for EPC developed in partnership with SEAI

Page 11: Irish Prison Service Energy Management Strategy · the Irish Prison Service Estate EPC contract partnership IPS Services Finance Procurement Estate Management BSD Services Facility

Project Status • Meetings held with a number of providers.

• IPS minimum requirements identified.

• Metering systems in place for the last 12 months.

• Base line information completed.

• Project stage 1 to 4 completed.

• 4 companies through PQQ stage

• Requirements for ITPCD developed for issue in October

Page 12: Irish Prison Service Energy Management Strategy · the Irish Prison Service Estate EPC contract partnership IPS Services Finance Procurement Estate Management BSD Services Facility

• Project management team

Estates Director

Governor of Works

Contract Manager

Project Manager

Finance

C P U

Page 13: Irish Prison Service Energy Management Strategy · the Irish Prison Service Estate EPC contract partnership IPS Services Finance Procurement Estate Management BSD Services Facility

• Project Aims

• To upgrade heating infrastructure.

• To develop a partnership with the appropriate EPC, to enable correct solutions to be provided and managed to ensure energy reductions can be achieved over the life time of the contract.

Page 14: Irish Prison Service Energy Management Strategy · the Irish Prison Service Estate EPC contract partnership IPS Services Finance Procurement Estate Management BSD Services Facility

What is the aim of this strategy

The Energy performance contract would provide the guaranteed energy savings . It will also provide the necessary expertise to manage those services to ensure their capital return

What will this achieve •Reduce the dependency on the facility maintenance service contract •Provide the necessary training and exposure to capital return for on site staff. •Provide the asset management expertise to ensure KPI are achieved in accordance with contract requirements •The aim of this pilot project is to identify the potential for this financing and services management model across the Irish Prison Service Estate

EPC contract partnership

IPS Services

Finance

Procurement

Estate Management BSD Services

Facility Maintenance

services contract

Page 15: Irish Prison Service Energy Management Strategy · the Irish Prison Service Estate EPC contract partnership IPS Services Finance Procurement Estate Management BSD Services Facility

Energy Management Strategy

Principals of energy management

Pay less per unit of energy consumed

Reduce energy consumed

Environmental Management System Corporate Approach

Partnership Approach with

SEAI & OPW

EMS Senior Management

Commitment

Assess Current situation

Set Goals and Targets

Set Action Plan

Review and Evaluate

Allocate Resources

Implement Plan

Page 16: Irish Prison Service Energy Management Strategy · the Irish Prison Service Estate EPC contract partnership IPS Services Finance Procurement Estate Management BSD Services Facility

Legal Requirements •SI 542 of 2009, Public Sector must be...

–“Exemplar”... In its •“Energy management practices”

•“Procurement practices” •“Audits”

NEEAP 2 Feb 2013 Public Sector Energy Reduction 33% by 2020 Energy Efficiencies Directive 2012/27/EU

SI 147 of 2011 SI 542 of 2009 & 151 of 2011 Energy Performance of Buildings

SI 873 of 2012