ir site clearance,demolition

Upload: wr-ar

Post on 02-Apr-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 IR Site Clearance,Demolition

    1/2

    INSPECTION REQUEST FORM FOR SITE CLEARANCE

    (DEMOLITION OF BUILDINGS & STRUCTURES)

    Unless otherwise approved,this inspection request shall be submitted during the daily mor

    meeting among LTA,Contractor and QP(S)

    Contractor: Project:

    To: Date:

    LTA Time:

    The work described below has been inspected by our Site Engineer and is complete

    and read for our ins ection. A checklist is attached overleaf.

    Location

    Checked and Requested By:

    Chainage

    Type of Structure

    Activity

    Other DescriptionContractor's PM Name & Signature

    The meeting noted that the information provided by the Contractor is adequate/not adequate*

    *delete where appropriate

    INITIAL INSPECTION DECISION BY QP(S)

    We have inspected the above referenced works and found them acceptable. You may proceed.

    You cannot roceed. Please carr out corrective works as noted on the checklist andsubmit a fresh request for inspection.

    Other comments:

    LTA's RE/RTO Name & Signature/ Date

    FINAL INSPECTION DECISION BY QP(S)

    work approved to start:__________________ work completed on:______________________

    ________________________________

    QP(S) Name & Signature/Date

    LTA

    The above process for request for inspection of work by Contractor and approval by QP(S) is noted.

    LTA's representative/Date/Time

    NO.

    SAMWOH CORPORATION PTE LTD SK E&C

    ER296-CONSTRUCTION AND COMPLECTION OF SENTOSA

    GATEWAY TUNNEL FROM TELOK BLANGAH ROAD TO KEPPEL

    ROAD / KAMPONG BAHRU ROAD/ LOWER DELTA ROAD AND

    ASSOCIATED ROAD WIDENING WORKS INTERCHANGE

    QP(S) may proceed Request Rejected

    _____________________________

  • 7/27/2019 IR Site Clearance,Demolition

    2/2

    CHECKLIST FOR SITE CLEARANCE NO.

    Chainage:

    S/No Description of Works Checked by Confirmed by

    Contractor QP(S)

    1 Confirm affected buildings, structures for demolition

    are those indicated on site plan

    2 Check contractor has notified services depts of his

    intention to demolish structure

    3 Check all meters and services removed /

    disconnected

    4 Check contractor has notified ENV (Sewerage)

    5 Confirm with ENV that sewer mains and manholes

    properly protected and sealed

    6 Check contractor has obtained necessary approval /

    license from Chief Inspector of Factories7 Check sufficient machinery, scaffolding

    hoarding etc.

    8 Check all warning signs for traffic and pedestrian

    9 Check temporary provision of footpath

    10 No burning of debris

    11 Sweeping and clearing of roadway after each

    demolition exercise is completed

    12 Check sufficient temporary traffic devices if lane

    closure is required13 Others

    (DEMOLITION OF BUILDINGS & STRUCTURES)

    Date/Time: Location: