INSPECTION AND TEST PLAN FOR ROW,CLEARING& GRADING CLIENT: GAIL( INDIA) LIMITED DATE CONSULTANT: MECON LIMITED REPORT NO: CONTRACTOR:JAIHIND PROJETCS LTD DOCUMENT NO: JPL/KKBMPL/CIVIL/01 Activities Inspection Frequency REMARKS By JPL By MECON/GAIL 1 WC Rw 2 WC Rw WC HP 3 WC Rw 4 WC S 5 WC S 6 WC S 7 WC S 8 WC S . 9 WC Rw LEGENDS "HP" HOLD POINT "S" SURVEILLANCE INSPECTION BY MECON "W" WITNESS POINT "WC" 100% EXAMINATION FOR JPL MECON/GAIL SIGN : NAME : DATE : KOCHI-KOTTANAD-BANGLORE-MANGLORE PIPELINE PROJECT(PHASE-I) Sr. No Taking over ROU from client/owner Calibration/testing of survey equipments a) Review of certificates b) Rechecking , if any Submission & approval of work procedure Staking markers for IPs, TPs, Km thickness Availability of approved AFC alignment sheets Recording of level before & after grading Setting of reference line and TBM Existence of structure/obstruction INSPECTION & TEST DOCUMENTS Review test and inspection documents "RV" REVIEW * W : In case ROU is in client’s Scope *S : In case ROU is in contractor’s scope

Upload: sachein-anand

Post on 04-Dec-2015

212 views

Category:

Documents


0 download

DESCRIPTION

ERW-1 Overview of Resistance Welding

TRANSCRIPT

Page 1: IR -Inspection Formate

INSPECTION AND TEST PLAN FOR ROW,CLEARING& GRADING

CLIENT: GAIL( INDIA) LIMITED DATE

CONSULTANT: MECON LIMITED REPORT NO:

CONTRACTOR:JAIHIND PROJETCS LTD

DOCUMENT NO: JPL/KKBMPL/CIVIL/01

Sr. No ActivitiesInspection Frequency

REMARKSBy JPL By MECON/GAIL

1WC Rw

2 WC Rw

WC HP

3WC Rw

4WC S

5WC S

6WC S

7 WC S

8 Existence of structure/obstruction WC S

.

9WC Rw

LEGENDS

"HP" HOLD POINT "S" SURVEILLANCE INSPECTION BY MECON

"W" WITNESS POINT "WC" 100% EXAMINATION

FOR JPL MECON/GAIL

SIGN :

NAME :

DATE :

KOCHI-KOTTANAD-BANGLORE-MANGLORE PIPELINE PROJECT(PHASE-I)

Taking over ROU from client/owner

Calibration/testing of survey equipments

a)      Review of certificates

b)      Rechecking , if any

Submission & approval of work procedure

Staking markers for IPs, TPs, Km thickness change and others

Availability of approved AFC alignment sheets

Recording of level before & after grading

Setting of reference line and TBM

INSPECTION & TEST DOCUMENTS

Review test and inspection documents

"RV" REVIEW * W : In case ROU is in client’s Scope *S : In case ROU is in contractor’s scope