ir beam launching
TRANSCRIPT
-
7/27/2019 IR Beam Launching
1/2
INSPECTION REQUEST FORM FOR BEAM LAUNCHING WORK NO:
Unless otherwise approved,this inspection request form shall be submitted during the daily
morning meeting among LTA,Contractor and QP(S).
Contractor: Project:
To: Date:
LTA Time:
The work described below has been inspected by our Site Engineer and is completeand read for our ins ection. A checklist is attached overleaf.
Location
Checked and Requested By:
Chainage
Activity
Drawings Used for Construction
Other DescriptionContractor's PM Name & Signature
INITIAL INSPECTION DECISION QP(S)
We have inspected the above referenced works and found them acceptable. You may proceed.However, please return the completed checklist upon completion of the remaining work.
You cannot proceed. Please carry out corrective works as noted on the checklist and
submit a fresh request for inspection.
Other comments:
RTO/RE Name & Signature/ Date
FINAL INSPECTION DECISION BY QP(S)
work approved to start: __________________
LTA
The above process for request for inspection of work by Contractor and approval by QP(S) is noted.
________________________________
QP(S) Name &Singnature/Date
work completed on:____________________
LTA's representative/Date/Time
SAMWOH CORPORATION PTE LTD SK E & C ER296-CONSTRUCTION AND COMPLECTION OF SENTOSAGATEWAY TUNNEL FROM TELOK BLANGAH ROAD TO KEPPEL
ROAD / KAMPONG BAHRU ROAD/ LOWER DELTA ROAD AND
ASSOCIATED ROAD WIDENING WORKS INTERCHANGE
The meeting noted that information provided by Contractor is adequate/not adequate*.
QP(S) may proceed Request Rejected
*delete where appropriate
-
7/27/2019 IR Beam Launching
2/2
CHECKLIST FOR BEAM LAUNCHING WORK
Location:
S/No Description of Works Checked by Confirmed by
Contractor QP(S)
1 Check preparation work for launching
1.1 Check availability of method statement of beam launching
submitted by Contractor's PE including safety precautions
1.2 Check certificate of fitness for lifting crane and lifting chain /
cable / hook etc.
1.3 Check certificate of competency of crane operator
1.4 Check certificate of competency of lifting supervisor
1.5 Check availability of traffic diversion plan
(if road closure is required)
1.6 Visual inspect beam for any cracks, defects and damages
at casting yard
1.7 Check safe means of access for inspection of beam
1.8 Check no physical obstruction eg. Tree, lamp post,
overhead cable affecting launching
2 Check before launching
2.1 Check adequate lighting provided on site
(for night launching)
2.2 Check road and access leading to launching site closed
2.3 Check sufficient warning signs, rotating lights, barricades,etc
placed on site according to C P for Temp Traffic Control
2.4 Check crane parked on firm ground
2.5 Check beam reference number to ensure correct beam
delivered and beam oriented correctly for launching
2.6 Visual inspect beam delivered on site for any cracks,defects and damages
2.7 Check all dowel holes in the beam, if any, are opened and
unobstructed
3 Check during launching
3.1 Check beam properly secured to the lifting chain / cable
before lifting
3.2 Check all workers kept at a safe distance during lifting of
beam to position
3.3 Check beam properly and securely seated on cross head or
temp steel wedge before releasing from the lifting hook
3.4 Check hook completely removed from the beam before
moving the crane
3.5 Check at least 3 independent systems fo restraints provided
to prevent movement of beam immediately after launching4 Check after completion of launching
4.1 Check all warning signs, lights, barricades, etc removed and
road open to traffic
4.2 Check 4.5 m high restriction sign installed
(for beam across carriageway only)
5 Check sufficient temporary traffic devices if lane
closure is required
6 Others
No.
Date/Time: Chainage: