General Notes
Time allowed 1 hour.
Use the answer sheet provided.
Completing the answer sheet
Use HB pencil to complete the answer sheet.
Provide only one answer per question.
Each entry is to be made with a HORIZONTAL line in the spaces indicated.
Errors must be removed using a good quality eraser.
Enter the Test Code and your Candidate Number (which can be found on your examination card) on to your answer sheet, following the example set out below.
Answer all 60 multiple choice questions
Do not open this paper until instructed by the invigilator.
This question paper must not be removed from the examination room.
Candidate Number
Exam Date
Exam Location
Test Code
Reference
IPMA Level DExamination Sample Paper
Project Management
DM Sample Paper v1.0
SAMPLE
2
IPMA Level D Examination Sample Paper
Question 1
A project manager can take responsibility for their actions by:
A amendingcontractualtermswithasupplier.
B consultingwithseniorinternalstakeholders.
C realigningtheirjobdescriptiontoactualtask.
D takingownershipofbothpositiveandnegativeresults.
Question 2
Which of the following is not a benefit of producing a high-level project overview?
A Uniformrolesandresponsibilities
B Limitedplanning
C Consistentterminology
D Standarddocumentation
Question 3
Which of the following is the best way in which a project manager could develop and get agreement on the project plan?
A Useeffectivecommunication
B Usetransitionmanagement
C Adoptaproactivemanagementstyle
D Adoptareactivemanagementstyle
Question 4
When assessing the use of critical success factors, which one of the following would demonstrate they are being used correctly?
A Criticalsuccessfactorsremainfixedthroughouttheproject
B Criticalsuccessdactorsaremeasuringiftheprojectisleadingand/orlagginginperformance
C Criticalsuccessfactorsarederivedfromkeyperformanceindicatorstomeasureiftheprojectisachievingstrategicgoals
D Criticalsuccessfactorsaredirectlyalignedtobothorganisationalandprojectobjectives
Question 5
Which of the following project manager behaviours is most likely to facilitate open communication?
A Engagingintwo-waycommunicationwithstakeholders
B Creatingaprojectcommunicationplan
C Conductingprojectteambriefings
D Talkingwithmembersofaprojectteam
SAMPLE
3
IPMA Level D Examination Sample Paper
Question 6
Configuration management contributes to the scope configuration by:
A ensuringthatprojectcostsarecontrolled.
B minimisingdeficiencies,errorsandunintendedscopecreep.
C preventingchangestotheprojectscope.
D controllingchangestotheprojectmanagementplan.
Question 7
Which of the following must a project manager do when prioritising and deciding a project’s requirements and acceptance criteria?
A Documentandagreetheprojectgoalhierarchy
B Documentandagreethesponsor’sneedsandrequirements
C Documentandagreestakeholderneedsandrequirements
D Documentandagreelessonslearned
Question 8
Which of the following best explains why a project manager should address personal and professional shortcomings?
A Addressingpersonalandprofessionalshortcomingswillalwaysresultinthecompletionoftasks
B Addressingpersonalandprofessionalshortcomingsshouldremovebarrierstoprofessionalsuccess
C Addressingpersonalandprofessionalshortcomingswillalwaysresultinprofessionalsuccess
D Addressingpersonalandprofessionalshortcomingsshoulddemonstrateownershipofproblems
Question 9
What might the project manager do to best get early buy in to the project?
A Organiseandfacilitateaprojectstart-upworkshop
B Tellallteammemberstheirroles
C Produceariskregister
D Startassoonaspossibletosavetime
Question 10
Which of the following statements concerning how a responsible individual evaluates and selects potential suppliers is true?
A Theyensurethefirstresponsescoresthehighest
B Theyensurethecheapestproposalscoresthehighest
C Theydefineandapplyasetoflogicalstepsintheselectionprocess
D Theydevelopselectioncriteriaonreceiptoftenderresponses
SAMPLE
4
IPMA Level D Examination Sample Paper
Question 11
Alignment of a project to an organisation’s mission and vision and compliance with organisational constraints and objectives can be effectively achieved by:
A establishingadetailedprojectbudget.
B usingdiagnosticmanagementcontrolsystems.
C developingabalancedscorecard.
D writingaprojectcommunicationstrategy.
Question 12
Which of the following questions is the most appropriate one which a project manager should ask when evaluating decisions and actions?
A Willthedecisionoractionimprovecommunication?
B Willthedecisionoractioninformtheproject’sstrategy?
C Willthedecisionoractionexplainhowtomeettargets?
D Willthedecisionoractionthreatentheproject’sobjective?
Question 13
If the cost of implementing the response is not an issue, what is the best strategy to take the opportunities associated with a positive risk?
A Tomitigatetheopportunity
B Toaccepttheopportunity
C Toexploittheopportunity
D Totransfertheopportunity
Question 14
When determining key performance indicators, which statement best describes how they can be used?
A Keyperformanceindicatorscanonlybeusedforprojectdeliverytimeliness
B Keyperformanceindicatorscanbeleadingorlaggingmeasures,eitherprecedingorfollowinganevent
C Keyperformanceindicatorsmustremainfixedforthedurationoftheproject
D Keyperformanceindicatorscanbeusedtodefinecriticalsuccessfactors
Question 15
Which of the following is not a feature of a negotiation strategy?
A BestAlternativetoaNegotiatedAgreement
B Budgetaryconditionsandpolitics
C What-ifscenariosandpower-balance
D Negotiatingteam,theirrolesandresponsibilities
SAMPLE
5
IPMA Level D Examination Sample Paper
Question 16
Which of the following would be the most likely way a project manager would review the project’s success criteria?
A Byschedulingmeetingsmonthlytoreviewprogresstodate
B Byschedulingmeetingsatregularintervalsforsponsorandstakeholders
C Byreviewingworkloadweeklywiththeprojectteam
D Byregularlycheckingtheproject’sprogressagainsttheformalandinformalsuccesscriteria
Question 17
Which of the following statements is false? When identifying the need to procure a product or service, the project manager:
A prepares,producesorcollectsnecessaryinformationasinput.
B definestenderdocumentsandselectioncriteriabasedonneeds.
C defineswhichsupplierwillbeawardedthework.
D definesreasons(basedonneeds)forprocurementorpartnership.
Question 18
What should be considered when planning a project activity where the general public could be put at risk?
A Healthandsafetyregulations
B Planningregulations
C Environmentallegislation
D Employmentlegislation
Question 19
What would be the best approach for a project manager when identifying areas for personal learning and development?
A Ignorefeedbackfromtheteambutseekdiscussionwithprojectsponsor
B Measureownperformance,usefeedbackandthenreview
C Identifytrainingcoursesandthendiscusswithlinemanager
D Waittohearfromlinemanagerifimprovementisnecessary
Question 20
Reporting on progress by exception would usually be used when:
A theprojectteamhasnoleader.
B theprojectteamhasexternalcontractors.
C theprojectteamisexperienced.
D theprojectteamisnewlyformed.
SAMPLE
6
IPMA Level D Examination Sample Paper
Question 21
As a project manager you have identified a high impact commercial risk suitable for mitigation through transfer. Which of the following is the most appropriate action to address this risk?
A Handoverownershipoftherisktothehealthandsafetymanager
B Escalatetheriskownershiptothesponsorandsteeringcommittee
C Arrangefortherisktobeownedbyaninsurancecompany
D Arrangefortheriskownershipbetakenoverbytheriskmanager
Question 22
Identifying the social and environmental consequences of a project will help to ensure a project:
A complieswithsustainabilityprinciplesandobjectives.
B alignstoappropriatecodesofconduct.
C establishesrelevantprofessionalstandards.
D developsrequiredhealthandsafetyprotocols.
Question 23
Which of the following is most likely to facilitate open, honest and frank communication?
A Arewardandretributionsystem
B Permittingdisagreementandconflict
C Amutuallyrespectfulatmosphere
D Astrongapproachtoleadership
Question 24
When prioritising and deciding a project’s requirements and acceptance criteria, a project manager should document and agree:
A lessonslearned.
B stakeholderneedsandrequirements.
C theprojectplanandfinancialbudget.
D theprojectgoalhierarchy.
Question 25
Which one of the following statements best describes how agreement can be reached from a negotiation process?
A Italwaysmakesuseofbestpracticetoolsandtechniques
B Itcanbereachedoveranextendedtime-frameandmayproceedinphases
C Itcanbereachedbyfocussingonshorttermgainsforbothparties
D ItalwaysmakesuseoftheBestAlternativetoaNegotiatedAgreement(BATNA)
SAMPLE
7
IPMA Level D Examination Sample Paper
Question 26
Preparing and implementing a contingency plan will most likely help to:
A assurestakeholderriskiscontrolled.
B improvescheduleandcostaccuracy.
C reducecostofriskmitigation.
D addressrisksandopportunities.
Question 27
Which of the following would help a project manager to control performance against the project plan and take remedial action where necessary?
A Anintegratedworkbreakdownstructure
B Anintegratedlessonslearnedlog
C Anintegratedprojectreportingsystem
D Anintegratedcommunicationplan
Question 28
When defining and developing the project goal hierarchy, a project manager should:
A createanappropriateworkbreakdownstructureandworkpackages.
B establishtherelationshipbetweentheorganisationalandprojectgoals.
C establishtheneedsofkeyinternalstakeholdersonly.
D createandcommunicatetheprojectcharterwithallstakeholders.
Question 29
When seeking to overcome resistance to change from those most affected by the change initiative, a project manager should:
A collaboratewiththesponsor.
B designmanageableworkpackages.
D communicatewithallstakeholders.
C designacoherentinterventionplan.
Question 30
Which of the following is most likely to help a project manager define work packages?
A Thepurposeofthegoalhierarchy
B Theresourcesrequiredandtheirduration
C Theaimsandobjectivesoftheproject
D Theenvironmentinwhichtheprojectislocated
SAMPLE
8
IPMA Level D Examination Sample Paper
Question 31
Which of the following should be done by the project manager when selecting a supplier for the project?
A Makeachoiceofsupplierfromthosepreviouslyusedwhenallocatingworkastheywillknowtherequirements
B Alwaysusethecheapestquoteasprojectsarecostdriven,aslongasitsatisfiesthecontractconditions
C Allocateonrecommendationfromotherswithinthecompanyaslongascontractconditionsaregenerallysatisfied
D Goouttotenderandevaluatethebidscheckingthedetailandallocatingtothesupplierthatsatisfiesalloftherequirement
Question 32
A project manager seeking to identify how to influence organisational strategy must:
A usetheirnetworktoinfluencetheboardabouttheiropinions.
B showstakeholdersthatfailingprojectsreflectpoorlydefinedstrategy.
C reflectonpre-setstrategicgoalsandthetoolsandmethodsneededtoquestionthesegoals.
D applytheoreticalstrategymodelstotheorganisation.
Question 33
Which of the following statements is false when preparing for a negotiation?
A Thebestalternativetoanegotiatedsolutionshouldbeidentified
B Trade-offsshouldbedevelopedduringpreparationandshouldn’tchange
C Trade-offsshouldbedevelopedduringpreparationandmodifiedasneeded
D Alternativesolutionsshouldbedevelopedbeforetheprocessbegins
Question 34
Which of the following would best help the project manager to select an overall project management approach?
A Assessmentoftheconstraintsandcomplexityoftheproject
B Understandthestrengthsoftheprojectteamandworkaccordingly
C Identifytheapproachusedonapreviousprojectandcopyit
D Discusswhatwouldbestsuittheprojectsuppliers
Question 35
What of the following would be the best way for a project manager to show responsibility for own personal learning and development?
A Byseekingnewroleswithintheorganisation
B Byneveracceptingcriticismandseekingotherstoblame
C Bydiscussionwithlinemanagertoidentifytrainingcourses
D Byacceptingfeedbackandfocussingonimprovingownworkandcapacities
SAMPLE
9
IPMA Level D Examination Sample Paper
Question 36
Assessing and prioritising project requirements will help a project manager to:
A focusoncontinuousimprovement.
B promotetheprojecttoallstakeholders.
C optimiseprojectoutcomesandsuccess.
D demonstrateanabilitytogetthingsdone.
Question 37
Tools and techniques such as scenario planning, probabilistic impacts, Monte Carlo analysis and decision trees are most closely associated with which of the following disciplines in project management?
A Riskassessment
B Planningandscheduling
C Budgetsandcostcontrol
D Trackingandcontrols
Question 38
Establishment of the project deliverables is best achieved by the use of:
A scopedefinitiontechniques.
B usingexpertjudgement.
C theavailableresources.
D stakeholderwishlists.
Question 39
Which of the following would help a project manager to choose an appropriate communication style?
A Takingaunilateraldecision
B Useanorganisationaltemplate
C Adoptingapreviousprojectstyle
D Establishingthetargetaudience
Question 40
When initiating and managing the transition to a new phase of the project, a project manager would usually:
A facilitateastart-upworkshop.
B reconfirmtheprojectmanagementplans.
C changethecommunicationplan.
D controlprojectperformance.
SAMPLE
10
IPMA Level D Examination Sample Paper
Question 41
Which of the following is the best way a project manager could maintain effective communication with virtual teams?
A Holdregularfacetofacemeetings
B Providereliablecommunicationequipment
C Holdregulartele-conferences
D Establishclearlinesofcommunication
Question 42
When managing deviation from contracts, the first thing a project manager must do is to:
A takeactionwithintheirorganisation.
B issueapenaltyassoonaspossible.
C requestarenegotiationassoonaspossible.
D takelegalactionassoonaspossible.
Question 43
How would a project manager most likely evaluate and monitor risk responses?
A Requestareportofprogressfromtheprojectteam
B Performareviewoftheprojectriskwiththeriskownerperiodically
C Evaluatetheriskregisteratprojectgatereviews
D Checkwithseniormanagementtoensurebuyin
Question 44
Which of the following would best explain how project managers could establish their contribution to the success of a project?
A Produceapersonalreflectionwhichincludesageneraloverviewofthecontribution
B Produceapersonalreflectionwhichfocusesontheworkallocatedbythesponsor
C Produceapersonalreflectionontheareaswheretheprojectmanagerhasinfluenceddecisions
D Produceapersonalreflectiononinputinallareasandidentifyhowvaluehasbeenadded
Question 45
When identifying and assessing project stakeholder needs and requirements, a project manager must understand that needs and expectations are:
A notthesameasstatedrequirements.
B thesameasstatedrequirements.
C internalconsiderations.
D externalconsiderations.
SAMPLE
11
IPMA Level D Examination Sample Paper
Question 46
Any changes to the project scope should be evaluated against which one of the following?
A Theprojectmanager’savailability
B Theproject’sobjectivesandagreedoutcomes
C Theviewsoftheprojectteam
D Thedisruptiontoworkalreadycompleted
Question 47
Which of the following would be the best way for a project manager to identify and reflect on personal motivations to set goals and maintain focus?
A Identifyprofessionalgoalsduringannualappraisal
B Identifylongtermandshort-termgoalswithmanagementinfluence
C Setpersonalandprofessionalgoalsandpriorities
D Discusspersonalandprofessionalgoalswithmentor
Question 48
When establishing and maintaining scope configuration, it is important for a project manager to know that scope configuration management is a:
A continuousprocess.
B timeboundprocess.
C featureofaworkbreakdownstructure.
D workpackageboundary.
Question 49
A project manager seeking to ensure the ongoing validity of the business justification for their project must:
A identifyhowthescopewillshapethesuccesscriteria.
B identifytheprojectobjectivestoshapethebenefits.
C awaitthedevelopmentofthebusinesscasebytheprojectsponsors.
D reflectonanddefinethebusinessjustificationinaformaldocument.
Question 50
Which of the following best describes why it is important for a project manager to complete tasks thoroughly?
A Projectmanagershaveresponsibility
B Demonstratescorrectactionstobetaken
C Meetsqualityrequirement
D Givesothersconfidenceintheprojectmanager’sability
SAMPLE
12
IPMA Level D Examination Sample Paper
Question 51
In preparing for a negotiation, the best way an individual can understand the interests of all involved parties, is to:
A ensuretheygettoknowtherelevantpartiesbeforethenegotiationbeginsandconductanalysislater.
B collect,documentandanalyserelevanthardandsoftinformationabouttheparties.
C gatherfactsonindividual’sinterestsasthenegotiationprogresses.
D useformalmeanstocollectandanalyseinformationtheyhavefoundduringthenegotiation.
Question 52
Which of the following best explains what a project manager should do to understand the impact of change on an organisation to ensure the project’s continuing success?
A Establishnewkeyperformanceindicatorsbasedonthechange
B Adoptaflexibleapproachtochange
C Reviewtherequirementsofthechange
D Assesstheorganisation’sabilitytochange
Question 53
Which of the following is a project manager most likely to do when seeking to overcome continued resistance to change once the change initiative has been implemented?
A Collaboratewiththesponsor
B Communicatewithallstakeholders
C Redesigntheworkpackages
D Usereinforcementtechniques
Question 54
Which of the following best explains what a project manager should do to identify and ensure a project complies with codes of conduct and professional regulation?
A Identifyrelevantcodesofconductandprofessionalregulationandensuretheyarecompliedwith
B Identifyallcodesofconductandprofessionalregulationandensuretheyarecompliedwith
C Identifybreachestorelevantcodesofconductandprofessionalregulationandensuretheyarecorrected
D Identifybreachestoallcodesofconductandprofessionalregulationandensuretheyarecorrected
Question 55
Which of the following best explains what a project manager should do to help ensure a project complies with health, safety, security and environmental (HSSE) regulations?
A Knowtheprofessionalstandardswhichapplytoallprojects
B KnowalloftheHSSEregulationsandpolicies
C KnowtheHSSErisksassociatedwithaproject
D KnowwhichoftheHSSEregulationsarerelevanttotheproject
SAMPLE
13
IPMA Level D Examination Sample Paper
Question 56
Which of the following is not a likely benefit, to a project manager, of having a change or transformation strategy?
A Organisationalcapacitycanbeincreased
B Selectedinterventionscanbeplanned
C Resistancetochangecanbeaddressedatanearlystage
D Reinforcementtechniquescanbeplanned
Question 57
Which of the following best explains how a project manager could demonstrate an ability to act, take decisions and communicate in a consistent way?
A Resistingaflexibleapproachtothesituation
B Completingtasksthoroughlydespitethesituation
C Makingsurethatwords,behavioursandactionsmatch
D Takingresponsibilityforownactionsinasituation
Question 58
Which of the following best explains when a project manager should evaluate the current project’s approach and lessons learned?
A Periodicallyandattheendoftheproject
B Periodicallyduringtheproject
C Attheendoftheproject
D Wheninstructedbythesponsor
Question 59
Which of the following best explains what a project manager should do to use professional standards for a new project?
A Adopttopprofessionalstandardsanddevelopimprovementswherenecessary
B Implementasetofwiderangingstandardsfortheprojectteam
C Implementbenchmarkstomeasurecompliancewithstandards
D Implementthestandardsusedinpreviousprojects
Question 60
What would best help a project manager balance the needs and means of the project?
A Awarenessofplannedqualityaudits
B Understandingthesponsor’sbonustargets
C Availabilityofapreferredsupplier
D Clarityontheprioritiesoftheproject
SAMPLE
14
IPMA Level D Examination Sample Paper
Answer Key
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
D B C D A B C B A C B D C B A
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
D C A B C C A C B B B C B D B
31 32 33 34 35 36 37 38 39 40 41 42 43 44 45
D C B A D C A A D B C A B D A
46 47 48 49 50 51 52 53 54 55 56 57 58 59 60
B C A D D B D D A D A C A B C
SAMPLE
Ibis House, Regent ParkSummerleys RoadPrinces RisboroughBuckinghamshire HP27 9LE
Copyright © 2018 APM
Tel. (UK) 0845 458 1944Tel. (Int.) +44 1844 271 640Email [email protected] apm.org.uk
Association for Project Management
SAMPLE