Page 1 of 15 Invitation to bid on tender for Colocation Services for DATA Center Staff in charge of the Acquisition Procurement office AOS. Inquiries regarding this tender and submission of bids [email protected] Tender Title Colocation Services for DATA Center Procurement Method Open competitive bidding Announced Date of the Tender 29 th /01/2020 Expiry Date of the Tender 17 th /02/2020 INVITATION TO BID: You are invited to offer a best bid for provision of the above tender as per attached specifications outlined in the scope of work Please read the instructions on the tendering procedures carefully. Failure to comply with them may invalidate your proposal which must be returned by the date and time given below. Electronic copy of your bid must be submitted to [email protected] no later than 17 st ,February 2020 @6 PM Rwanda Time. Late tenders will not be considered. Site Visit is voluntary. The recipient of this invitation is not allowed to pass this invitation on to other companies. For any additional clarification, please feel free to send your request to [email protected] look forward to your response. Yours sincerely, Seong Woo KIM Chief Executive Officer AOS Ltd

Upload: others

Post on 21-Feb-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Invitation to bid on tender for Colocation Services for DATA Center · 2020. 1. 30. · secure data center for IT operations and services. The current data center doesn’t have enough

Page 1 of 15

Invitation to bid on tender for Colocation Services for DATA Center

Staff in charge of the Acquisition Procurement office AOS.

Inquiries regarding this tender and

submission of bids

[email protected]

Tender Title Colocation Services for DATA Center

Procurement Method Open competitive bidding

Announced Date of the Tender 29th /01/2020

Expiry Date of the Tender 17th /02/2020

INVITATION TO BID:

You are invited to offer a best bid for provision of the above tender as per attached specifications

outlined in the scope of work

Please read the instructions on the tendering procedures carefully. Failure to comply with them

may invalidate your proposal which must be returned by the date and time given below.

Electronic copy of your bid must be submitted to [email protected] no later than 17st

,February 2020 @6 PM Rwanda Time. Late tenders will not be considered.

Site Visit is voluntary.

The recipient of this invitation is not allowed to pass this invitation on to other companies.

For any additional clarification, please feel free to send your request to [email protected] look

forward to your response.

Yours sincerely,

Seong Woo KIM

Chief Executive Officer

AOS Ltd

Page 2: Invitation to bid on tender for Colocation Services for DATA Center · 2020. 1. 30. · secure data center for IT operations and services. The current data center doesn’t have enough

Page 2 of 15

Table of Contents

TENDER TO IMPLEMENT COLOCATION SERVICES FOR AOS DATA CENTERError!

Bookmark not defined.

1 Introduction & Background ................................................................................................ 3

2 Scope of Work .................................................................................................................... 4

3 Detailed Scope of Work ..................................................................................................... 4

3.1 Colocation Setup ............................................................................................................. 4

3.2 Cooling & Containment .................................................................................................. 4

3.3 Fire Suppression Requirements ...................................................................................... 5

3.4 Network Requirements & Pathway ................................................................................ 5

3.5 Facility Management ...................................................................................................... 6

3.6 Implementation Timeline ................................................................................................ 6

3.7 Qualifications ................................................................ Error! Bookmark not defined.

3.8 Proposal Requirement .................................................................................................... 7

3.9 Proposal Assessment ...................................................................................................... 7

4 Reporting............................................................................................................................. 7

5 Annex 1 ............................................................................................................................... 8

Annex 2: Floor Plan and 3D design ........................................................................................ 14

Page 3: Invitation to bid on tender for Colocation Services for DATA Center · 2020. 1. 30. · secure data center for IT operations and services. The current data center doesn’t have enough

Page 3 of 15

1 Introduction & Background

Since 2014, AOS has been operating the national datacenter offering IaaS, Colocation, Web and

Mail hosting, Domain name service. Due to a new demand in terms of increase of customers, high

availability and flexibility in service delivery, AOS wishes to revamp majority of its systems.

The current AOS data center facility is a physically controlled facility which hosts and maintains

mission and business-critical information, data, IT equipment, applications, et al for different

customers these include private, civil societies, NGO and government institutions to name a few.

The current date center is among critical GoR’hub of information and network services/resources

which comply with tier 3 data center requirements. This data center is a self-managed, reliable and

secure data center for IT operations and services. The current data center doesn’t have enough

space to provide colocation services requested by so many customers. It’s in line with the above

background that AOS is planning to extend the current data center in order to solve the issue of

colocation space in the data center, the scope of work will include among others: cooling, racks

installation & server’s colocation among others.

AOS is looking for a reliable local, international or a joint-venture company who can supply,

install, Commissioning, testing and IMPLEMENT COLOCATION SERVICES FOR AOS

DATA CENTER in good quality at AOS main site located at Telecom house.

Criteria of Supplier Selection

• Best financial proposal.

• Short Delivery Period.

• Terms of Payment.

• Local suppliers to bid in local currency

• International suppliers to bid in United States Dollars

• Warranty period.

Tender Process

• Suppliers can participate in this tender by submitting required submissions by email to

[email protected] before the expiry date, 6:00PM, 17th February 2020.

• The submission after the expiry date will be automatically disqualified.

Other Conditions

• If there is a bad item among supplied in the acceptance test, the supplier must substitute

it.

• If suppliers have any inquiries about this tender, please email to [email protected]

Page 4: Invitation to bid on tender for Colocation Services for DATA Center · 2020. 1. 30. · secure data center for IT operations and services. The current data center doesn’t have enough

Page 4 of 15

Required Submission documents :

1. Detailed Quotation for supply with DDP Delivery and delivery period schedule

2. Introduction of each and every item to be proposed (Datasheet).

3. Manufacturer Authorization certificate / Partnership for main items like PDU,

Rack,CRAC, Fire Suppressions System.

4. Biodata and CV of the technical implementers (National ID or Passport)

5. Valid Tax Clearance Certificate.

6. Copy of Rwanda Social Security Certificate

7. Copy of Trading License

8. Company Profile.

9. Warranty Period for each and every item in scope of work.

Note: required documents no 5 and 6 are not required of international companies.

2 Scope of Work

The scope of work comprises colocation services for the new AOS data center.

This scope will be:

− Colocation services which can accommodate 22 racks, including cooling, network, fire

detection and suppression systems, monitoring and containment system.

2.1 Implementation Timeline

− 3 months

3 Detailed Scope of Work.

3.1 Colocation Setup

The current IP operation room and monitoring for AOS IDC will be transformed and become the

new collocation. Some civil works will be needed to customize this room to meet standards for

DataCenter Colocation room.

Below are the minimum works to be conducted by the successful bidder :

− The room will accommodate 22 racks with their associated peripherals,

− The supplier will provide and install the 22 racks to be used the colocation, this including

powering them with appropriate PDU (preferably IEC-309 Blue type)

− Precision air conditioner will be provided to the colocation room

− Ductwork with appropriate environmental controls for IT equipment will be provided

− No water sources traversing, entering or residing in or directly above the colocation room

− No sinks, furnaces or other moisture-producing devices

− Supply an automatic fire detection and suppression system

3.2 Cooling & Containment

− Supply, delivery, installation and commissioning of Environmental protection system for

Data Center

Page 5: Invitation to bid on tender for Colocation Services for DATA Center · 2020. 1. 30. · secure data center for IT operations and services. The current data center doesn’t have enough

Page 5 of 15

− The system should be Cold Aisle containment to maximize airflow efficiency

− The containment system should provide a flexible solution which can be easily upgraded

as demand in cooling increases

− Supply and install mechanical Systems as needed, the vendor is expected to include all

auxiliary works like ducting, inlet and drain piping, piping between indoor and outdoor,

cabling acoustic and thermal insulation etc with related civil works as per the site

requirements

− The heating and cooling capable of controlling and sustaining a constant temperature

between 15-21 degrees Celsius, dry-bulb temperature between 10-35 degrees Celsius

− Adequate equipment to control, maintain and sustain humidity range between 48-52% with

maximum dew point of 15 degrees Celsius with humidifier capacity of 5kg/hour

− Humidity and temperature monitoring and control (with console alerts if possible)

− Sound/noise control of the HVAC system and adequate insulation of ductwork

− Having a local or regional maintenance and support presence

3.3 Fire Suppression Requirements

The successful will supply and install a cabinet types for fire detection and suppression system. A

total of 2 fire suppression cabinets with 3 gas bottles will be supplied, 1(one) 1B/T type and 1(one)

2B/T type.

The fire detection and suppression systems will have the following functionalities:

− Fire detection and early warning system and should be a cabinet type with two cylinders

of gas inside. The below will be the minimum requirements:

o Fire detector, discharger, discharge inducing duct, extinguishing power storage,

receiver and operator.

o Ability to detects fire and smoke and automatically sprays extinguishing powder.

o In case of a blackout, it switches to backup power (DC24V) and will performs the

same function.

o Having a fire alarm with siren and voice alarm

o Discharge time from 10 sec min to 30 sec maximum

o Independent external connection parts

− External input will be connected to the insulated circuit to minimize external noise and

interference

3.4 Network Requirements & Pathway

The data center’s wired local area, and storage area networks must link with the existing data

center. Before the actual implementation, the successful bidder will provide a plan for designing,

installing and maintaining the system pathway plan based to the colocation room layout

specifications. The systems pathway plan must be provided in both AutoCad and PDF format.

The system pathway plan is subject to final approval by AOS.

The system pathway plan must include one or more diagrams which display the building’s

proposed floor plans with the physical different wiring system elements. The wiring system

elements include but are not limited to horizontal wiring and distribution system cables, intra-

Page 6: Invitation to bid on tender for Colocation Services for DATA Center · 2020. 1. 30. · secure data center for IT operations and services. The current data center doesn’t have enough

Page 6 of 15

building wiring (if needed), backbone wiring, equipment location/disposition in the rooms,

operation and monitoring rooms, building main distribution frame (MDF), entrance facility (EF),

demarcation point with the existing date center, wiring support racks with central points, patch

panels, cross-connects, raceways, conduit, sleeves, lan & network fiber, data management

connections (outlets/drops/jacks), cctv system connections and power poles/drop.

For LAN cabling UTP cables (Cat6A or CAT7) will be required of the proposed facility. The type,

size, rating, location, spacing, placement, fill rate, tracking, continuity, origin, construction,

fastening, grounding, administration, installation and labeling of all rooms, , support racks, wiring,

cable, fiber, conduit, patch cord, ports, interfaces, cross connects, outlets, jacks, faceplates, and all

related hardware must meet the specifications and requirements for data center tier III.

3.5 Electrical installation

− Assess the current electrical installation and recommend any improvement if required for

− Provide appropriate electrical provisions and protections for the 22 racks to be installed in

the colocation room

− Provide adequate electrical supply for equipment racks not limited to power distribution

modules for PDUs

− Supply and install appropriate circuits breakers & panels serving the new colocation room

and must be located within the controlled space of the colocation room and any panel not

serving the data center must not be located within the controlled space of the colocation

room

− Provide appropriate lightings for the colocation room

− Cable trays

− Emergency lighting of room and related access hallways with rechargeable batteries with

no less than 90 minutes of backup power per 2000 IBC

3.6 Facility Management

− Water Detector Sensor

− Appliance System

− Temperature & Humidity Sensor

− Development

− Sensor Port

N.B: Supplier are free to provide better and more efficient facility management system

3.7 Implementation Timeline

− 3 months including delivery and implementation after AOS issues a purchase order

Page 7: Invitation to bid on tender for Colocation Services for DATA Center · 2020. 1. 30. · secure data center for IT operations and services. The current data center doesn’t have enough

Page 7 of 15

3.8 Qualifications.

− At least 3 references of the work scope 4.1, 4.2, 4.3 and 4.4 in Rwanda or any other country

over the last five years

− Stable Financial status for the last 3 years

− Preferably the bidder or bidder’s partner (third party) has a local presence or partnership with

local company

3.9 Proposal Requirement.

− Technical Proposal

o General Information

▪ Company introduction (including financial performance of three years)

▪ Partners (third parties) company information

▪ Project experience relevant to the work scope (including its proofs)

o Implementation plan

▪ Key milestones and implementation timeline

▪ Equipment arrangement plan of 4.1, 4.2 and 4.3 (CAD)

▪ Network connection plan of 4.4 not only for new colocation but also for the

connection to main center

o Manpower allocation plan (Manager and engineers)

▪ Brief CV of allocated manager and engineers (including experiences relevant

to the work scope)

o Skills transfer plan of equipment maintenance

o Project management plan (Reporting plan, quality assurance plan etc.)

o Warranty and technical support plan

− Financial proposal (including detailed bill of material)

3.10 Proposal Assessment.

− Technical Proposal (70%)

o Project experience: 30%

o Quality of allocated manpower (manager and engineers): 20%

o Implementation plan: 10%

o Skills transfer plan of equipment maintenance: 5%

o Project management plan: 5%

− Financial proposal (30%)

4 Reporting

− The successful bidder will report to the Director of AOS IDC

− Provide a weekly report during the implementation of the project

− The successful bidder shall provide as-built drawing for electrical wiring, network, topology

and pathway design after the installation

Page 8: Invitation to bid on tender for Colocation Services for DATA Center · 2020. 1. 30. · secure data center for IT operations and services. The current data center doesn’t have enough

Page 8 of 15

− These reports may be furnished electronically, but a paper copy will be used during acceptance.

5 Annex 1

MODEL SPECIFICATION Unit Q'ty

1. Electric/ Fire Protection

1.1 1st Power Cabling

MAIN Distributor Panel UPS OUTPUT, Power

Meter SET 2

Normal Distributor Panel CRAC & Normal Power,

Power Meter SET 1

Main Cable & Tray

Old Center to New

Center(Only Ground

Floor)

SET 1

Power Cable

0.6/1kv F-CV 1C×70 ㎟

[L-UPS OUT A/B MAIN]

Average length 80m

Standard A, B or

equivalent

M 640

Power Cable 0.6/1kv F-CV 4C×25 ㎟

[CRAC INPUT] 2 lines M 60

Ground Cable 35㎟ [GROUND] M 300

Terminal lug Copper 1 HOLE 70 ㎟ EA 40

Terminal lug Copper 1 HOLE 35 ㎟ EA 40

Terminal lug Copper 1 HOLE 25 ㎟ EA 20

Terminal lug Copper 1 HOLE 35 ㎟ EA 20

1.2 Cable Tray(New center)

Mesh Tray STRAIGHT,

W300x150Hx1.2t M 21

Mesh Tray Accessories HOR. ELBOW, W300 x

H150 EA 2

Mesh Tray Accessories HOR. TEE, W300 x H150 EA 2

Mesh Tray Accessories JOINER SET, W300 x

H75 EA 70

Tray Support Accessories W300-1way SET 1

Mesh Tray STRAIGHT,

W500x150Hx1.2t M 21

Mesh Tray Accessories HOR. ELBOW, W500 x

H150 EA 4

Mesh Tray Accessories JOINER SET, W500 x

H75 EA 70

Page 9: Invitation to bid on tender for Colocation Services for DATA Center · 2020. 1. 30. · secure data center for IT operations and services. The current data center doesn’t have enough

Page 9 of 15

Tray Support Accessories W500-1way SET 1

Mesh Tray STRAIGHT,

W100x60Hx1.2t M 21

Mesh Tray Accessories HOR. ELBOW, W100 x

H60 EA 4

Mesh Tray Accessories JOINER SET, W100 x

H75 EA 70

Tray Support Accessories W100-1way SET 1

1.3 2nd Power Cabling

Power Cable

0.6/1kv F-CV 3C×6 ㎟

[SERVER RACK UPS

POWER A/B]

M 600

Receptacle Open-type 32A 250V 3P EA 40

Consent Closed-type, 250V 2hole EA 10

Terminal lug 6 ㎟ EA 150

Cable Label Port No. SET 1

1.4 RACK ATS

RACK Auto Transfer Switch

for single Power

system(Supply Power

Capacity 32A)

EA 2

1.5 Fire Protection

HFC227ea Package 68L/50KG*2B/T SET 1

HFC227ea Package 68L/50KG*1B/T SET 1

Self control Panel DC-24V EA 1

Led Lamp display DC-24V EA 1

Siren DC-24V EA 1

Detector Differential Temperature

detector EA 2

Detector Smoke detector EA 2

Leading Light Medium EA 2

Solenoide Velve Control Panel DC-24V SET 1

Flexible(SF) 16C M 100

Flexible(SF) 22C M 100

Outlet BOX Box type 54mm EA 20

Power Cable HFIX 1.5sq M 600

Power Cable HFIX 2.5sq M 900

Power Cable F-CV 4SQ/3C M 100

Page 10: Invitation to bid on tender for Colocation Services for DATA Center · 2020. 1. 30. · secure data center for IT operations and services. The current data center doesn’t have enough

Page 10 of 15

Crac Interlock SET 2

F.M.S Interlock SET 1

1 - Sub Total

2. Rack/ Containment/ Access

Floor

2.1 SERVER RACK

W600 x D1200 x

H2030(42U), Vertical

Cable Management Kit

EA 20

Horizontal Cable

Management Kit, 1U EA 20

1U Blank panel EA 200

2.2 NETWORK RACK

W800 x D1200 x

H2030(42U), Vertical

Cable Management Kit

EA 2

Horizontal Cable

Management Kit, 1U EA 2

1U Blank panel EA 200

2.3 Containment Frame

Top Frame Aluminum/ Powder

Coating M 20

Bottom Sub Frame Aluminum/ Powder

Coating M 20

Accessories Material SET 1

2.4 Containment Finish

Auto Sliding Door

Aluminum/ Powder

Coating / Sub Battery

Included / W1800mm

SET 2

Basic Top Box Frame 1600*900mm SET 4

Different Size Frame Different Size Frame SET 2

Top Sliding Window 1694*900mm EA 2

Space Panel

2400*600mm 4T PC

Compounding

Panel+Aluminium Frame

EA 4

2.5 Control Panel Installation

Control Panel 1 Containment Group 1

Control Panel SET 1

Sliding Motor EA 1

Sliding Motor Interlock Sliding Install & Sliding

Guide SET 1

2.6 Power Distributor Unit P.D.U Metered 32A/3P

CEE C13(36), C19(6) EA 44

Page 11: Invitation to bid on tender for Colocation Services for DATA Center · 2020. 1. 30. · secure data center for IT operations and services. The current data center doesn’t have enough

Page 11 of 15

AP8853, Network

monitoring

2.7 Access Floor

Wood Type 600*600*38T(H400mm) ㎡ 60

Air Grating Panel Steel / Poudercoating EA 22

Koldlok Cable Hole End Material EA 22

SLOOP Moving Sloop SET 1

2 - Sub Total

3. CRAC/ Access Control/

CCTV

3.1 CRAC INDOOR UNIT

Indoor Unit 10R/T Down Floor TYPE

or equivalent SET 2

M/f AR

Model PA010-A2ST

Power : 3P4W 400V 50㎐

Cooling : Air Cooled

System

Capacity : 35.1kW

Compressor : 2

Ref. Circuit : 2

Max Air Volume :

110CMM

Electric Reheater : 15kW

Humidifier : 8lit/Hr

Outdoor Unit Cap : 5R/T SET 4

Model CD005-A Input Power :

1Ph/220V/60Hz

3.2 CRAC Installation

Gas Pipe 10R/T IN/OUT M 200

Base Frame steel / Underfloor SET 2

Drain & water pump Drain(stainless steel) SET 1

Supply Water Pipe Humidification SET 1

3.3 Access control

BIOSTATION L2 CARD + F/P + Number

Lock Reader EA 2

Power Adapter 12V 5A EA 2

Page 12: Invitation to bid on tender for Colocation Services for DATA Center · 2020. 1. 30. · secure data center for IT operations and services. The current data center doesn’t have enough

Page 12 of 15

Lock Accessory MAGNETIC EA 2

Lock Bracket LZ EA 2

3.4 CCTV

IP Dome Camera 2Mpixel , Infrared ray ,

4mm EA 10

Switch Hub Gigabit POE 24PORT EA 1

NVR Recorder

16CH , ( Include HDD

4TB, Monitoring Soft

Ware SSM )

EA 1

UTP CABLE CAT 6 BOX 3

CD PIPE ROLL 22C EA 2

CD PIPE ROLL 28C EA 2

Flexible 22C EA 1

Accessories PVC Mold SET 1

3 - Sub Total

4. Data Cabling / Facility

Management System

4.1 Main Patch Zone

FDF FDF(4 MPO CASSETTE)

1U EA 4

CASSETTE MPO CASSETTE(OM3

MPO-12core LC) EA 16

MPO Cable MPO Trunk Cable 80m EA 16

F/O Patch Cord OM3 LC-LC F/O Patch

Cord 10m EA 200

Patch Panel Cat.6A UTP 24port Patch

Panel 1U EA 40

UTP Cable Cat.6A UTP Cable Box 30

UTP Patch Cord Cat.6A UTP Patch Cord

3m EA 960

LABEL LABEL_Cable Tag PORT 960

4.2 Sub Patch ZONE

Patch Panel Cat.6A UTP 24port Patch

Panel 1U EA 40

UTP Patch Cord Cat.6A UTP Patch Cord

3m EA 960

TEST LINK TEST Report PORT 960

LABEL LABEL_Cable Tag PORT 960

4.3 Facility Management

Page 13: Invitation to bid on tender for Colocation Services for DATA Center · 2020. 1. 30. · secure data center for IT operations and services. The current data center doesn’t have enough

Page 13 of 15

Appliance system 2LAN, 1RS232, 1RS485,

5DI, 2RO, Dashboard EA 1

Sensor Port

Ethernet, IP WatchDog,

DI 2Port, Relay 2Port, AI

2Port

EA 3

Development

Power/ Crac/ Fire/ Temp/

Humi/ Water/Door

Customizing

Development

EA 1

Water Detector Sensor Cable Type 30M EA 2

Temp/Humidity Sensor Cable size 10m Type EA 4

Installation Hardware & Software EA 1

3D Layout 3D Design SET 1

Page 14: Invitation to bid on tender for Colocation Services for DATA Center · 2020. 1. 30. · secure data center for IT operations and services. The current data center doesn’t have enough

Page 14 of 15

Annex 2: Floor Plan design

Page 15: Invitation to bid on tender for Colocation Services for DATA Center · 2020. 1. 30. · secure data center for IT operations and services. The current data center doesn’t have enough

Page 15 of 15

Colocation