investor presentation - gem diamonds · group risk 2010” in “the business review” in our...
TRANSCRIPT
© 2011 GEM DIAMONDS LIMITED
DISCLAIMER
The following presentations are being made only to, and are only directed at, persons
to whom such presentations may lawfully be communicated (“relevant persons”). Any
person who is not a relevant person should not act or rely on these presentations or any
of their contents.
Information in the following presentations relating to the price at which relevant
investments have been bought or sold in the past or the yield on such investments
cannot be relied upon as a guide to the future performance of such investments. These
presentations do not constitute an offering of securities or otherwise constitute an
invitation or inducement to any person to underwrite, subscribe for or otherwise
acquire securities in any company within the Group.
The presentations contain forward-looking statements which are subject to risk and
uncertainties because they relate to future events. These forward-looking statements
include, without limitation, statements in relation to the Group’s projected growth
opportunities. Some of the factors which may cause actual results to differ from these
forward-looking statements are discussed in certain slides of the presentation and
others can be found by referring to the information contained under the heading “Key
Group risk 2010” in “The Business Review” in our Annual Report for the year ended
2010. The Annual Report can be found on our website (gemdiamonds.com).
The presentations also contain certain non-IFRS financial information. The
Group’s management believes these measures provide valuable additional
information in understanding the performance of the Group or the Group’s
businesses because they provide measures used by the Group to assess
performance. However, this additional information presented is not uniformly
defined by all companies, including those in the Group’s industry. Accordingly, it
may not be comparable with similarly titled measures and disclosures by other
companies.
Additionally, although these measures are important in the management of the
business, they should not be viewed in isolation or as replacements for or
alternatives to, but rather as complementary to, the comparable IFRS measures
such as revenue and other items reported in the consolidated financial
statements.
Information in this presentation is as at November 2011
1
© 2011 GEM DIAMONDS LIMITED
AGENDA
Announcement
Letšeng
Uniqueness of Letšeng
Project Kholo
The Value of Gem
2
© 2011 GEM DIAMONDS LIMITED
ANNOUNCEMENT
The expansion project (Project Kholo) at Letšeng approved by the Gem and
Letšeng Boards
Gem is considering all of its options regarding its Ellendale mine asset and has
appointed advisors Gresham Advisory Partners to assist in this regard
The Company’s Cempaka mine in Indonesia has been sold for a cash sum of
$5 million
3
© 2011 GEM DIAMONDS LIMITED
4 THE UNIQUENESS OF LETSENG
The most valuable on EarthProduct Differentiation
0
5000
10000
15000
20000
10 15 20 25 30 35 40 45 50 55
Aver
age
$/¢t
Average size ¢/stone (Elite Rough +25carats, A/B quality)
Catoca
BHP Billiton
Letšeng
De Beers
Rockwell
PetraAlrosa
Rio Tinto
Best of the best – coarseness and Type IIa proportion produces the best elite rough
Source – internal 2010
© 2011 GEM DIAMONDS LIMITED
5 THE UNIQUENESS OF LETSENG
10%
15%
20%
25%
30%
35%
40%
45%
2011 2012 2013 2014 2015
Elite Production Market Share
Letšeng
Alrosa
De Beers
Currently leading producer of Elite – this position to grow after expansion
Source – internal 2010 updated 2011
© 2011 GEM DIAMONDS LIMITED
LETSENG – PROJECT KHOLO
6
Project Kholo will commence in January 2012, and will ramp up to full
production by July 2014
Increasing production to 10 million tonnes per annum (from 5.6 mtpa)
Improving grade through increased liberation
Reducing diamond damage
Reducing unit costs
Increasing value from sales and marketing activities and downstream cutting
and polishing
Current 25 year mining plan with resource extensions expected
© 2011 GEM DIAMONDS LIMITED
LETSENG – PROJECT KHOLO SNAPSHOT
7
Based on a real DCF model with Gem price increases of 2% nominal until 2015 and WWW thereafter
Letšeng Snapshot - (100% project value) November 2011
Total Project Kholo capital expenditure (US$m) 280
Revenue available for Cutting & Polishing up to 50% by 2017
Net Cutting & Polishing uplift 10-13%
Exchange rate (Rand/US$) 8.00
Project Kholo NPV (US$m) 8% discount rate 646
Project Kholo IRR 40%
Project Kholo Payback - from start of project (2012) 2016
Letšeng NPV (US$m) 8% discount rate 2 517
© 2011 GEM DIAMONDS LIMITED
LETSENG – PRODUCTION PROFILE
8
Project Kholo
Increase production to 10mtpa
Increase carat production to
180k -200k per annum
Underground to follow
Conceptual study indicates going
underground post Satellite Cut 5
adds value
Waste stripping peak of 63 million
tonnes reduced to 45 million
tonnes
PFS underway and expected to be
completed by April 2012
Production profile - current
© 2011 GEM DIAMONDS LIMITED
9 PROJECT KHOLO – EXECUTION TIMELINE
2014
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Option Selection Complete
Board approval
Long Lead items
Early Works - Earthworks
Early Works - Site Preparation
Civil Work Starts
Plant 3 Construction Period
Mining ramp-up
Plant 3 Ramp-up
Full Production - July 2014
Detail Design
Construction
2013
Letseng Project Kholo Execution Program
Procurement
2011 2012
PFS / Feasibility study
© 2011 GEM DIAMONDS LIMITED
PROJECT KHOLO NPV SENSITIVITIES
10
REVENUE
0.70 0.80 0.90 1.00 1.10 1.20 1.30
7.40 146 214 280 801 413 813 546 205 678 004 809 459 940 914
7.60 181 797 315 995 448 899 581 060 712 730 844 185 975 640
7.80 215 374 349 281 482 185 614 128 745 675 877 130 1 008 585
EXCHANGE RATE 8.00 247 272 380 903 513 610 645 518 776 973 908 428 1 039 883
8.20 277 614 410 982 543 491 675 289 806 744 938 199 1 069 654
8.40 306 511 439 629 571 950 703 643 835 098 966 553 1 098 008
8.60 334 040 466 943 599 085 730 677 862 132 993 587 1 125 042
CAPITAL
0.90 0.95 1.00 1.05 1.10 1.15 1.20
1.20 363 617 354 474 345 332 336 189 326 906 317 563 308 220
1.15 438 670 429 527 420 384 411 241 402 099 392 842 383 499
1.10 513 669 504 579 495 437 486 294 477 151 468 009 458 779
1.05 588 610 579 594 570 489 561 347 552 204 543 061 533 918
OPEX 1.00 663 551 654 535 645 518 636 399 627 256 618 114 608 971
0.95 738 493 729 476 720 459 711 443 702 309 693 166 684 024
0.90 813 434 804 417 795 400 786 384 777 362 768 219 759 076
REVENUE
0.70 0.80 0.90 1.00 1.10 1.20 1.30
12.0% 126 732 228 096 328 247 427 304 525 752 624 199 722 646
11.0% 151 771 260 205 367 490 473 749 579 434 685 119 790 804
10.0% 179 938 296 073 411 129 525 231 638 797 752 362 865 928
9.0% 211 626 336 144 459 658 582 294 704 433 826 573 948 712
DISCOUNT RATE 8.0% 247 272 380 903 513 610 645 518 776 973 908 428 1 039 883
7.0% 287 355 430 870 573 549 715 512 857 067 998 623 1 140 178
6.0% 332 394 486 599 640 060 792 895 945 369 1 097 844 1 250 319
© 2011 GEM DIAMONDS LIMITED
GROUP – CASH POSITION
11
Current group cash on hand as of 25 November 2011- $151m ($37m at Letšeng)
Standby working capital facility implemented
3 year working capital facility - M250m ($31m) with Standard Lesotho Bank
Agreements signed
Facility available for draw down as from January 2012
Potential to increase the funding facility if market conditions deteriorate
12 LETSENG – PROJECT KHOLO INTERNAL RISKS
Risks Issue Solutions
Power Additional 10 MVA required for
expansion
2 options available. Preferred option costed
into capital estimate ($25m). Possible delay,
cost of diesel generated power will be
required for delay period.
Process water Depending on rainfall, current
water levels may be insufficient
for expansion
Upgrade to plant 1 thickener will increase
return water capacity from slimes ($2.8m)
Slimes dam
capacity
Current slimes dam has
insufficient capacity for
expanded LoM
New slimes dam site identified, designed and
costed into capital estimate (inside lease area)
Ore resource Inherent uncertainty in ore-body
volume and depth
21 hole drill program underway to provide
resource data. Project payback is within the
current indicated level
© 2011 GEM DIAMONDS LIMITED
THE VALUE OF GEM
13
* Internal Valuation - Based on Gem current price increases of 2% nominal until 2015 and WWW thereafter
1,684
484
118
43 36
137
1,586
-
400
800
1,200
1,600
2,000
Letseng Ghaghoo Ellendale Cash Net CHQ Group NPV Current MarketCap
NP
V $
USm
m
GEM NPV – GROUP ASSETS (ATTRIBUTABLE)
Shares in issue – 138m
Current Share Price - £2.03