introduction to geopier system

77
INTRODUCTION TO GEOPIER ® SYSTEM Mr. Gerry Kehler, PE (Georgia) Mr. Tommy Williamson April 14, 2010

Upload: others

Post on 16-Nov-2021

10 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: INTRODUCTION TO GEOPIER SYSTEM

INTRODUCTION TOGEOPIER®SYSTEM

Mr. Gerry Kehler, PE (Georgia)Mr. Tommy WilliamsonApril 14, 2010

Page 2: INTRODUCTION TO GEOPIER SYSTEM

OUTLINE

1. History of Foundation Support

2. Geopier System Construction

3. Engineering Basics

4. Different soil types

5. Limitations

6. Industrial Applications

7. Case study

Page 3: INTRODUCTION TO GEOPIER SYSTEM

Two choices:

History of foundation systems

1. Shallow 2. Deep

Good soil

BadsoilGood

soil

OK soil

Page 4: INTRODUCTION TO GEOPIER SYSTEM

In early 1990’s a third choice emerged:Intermediate Foundation® systems

1. Shallow 2. Deep 3. Intermediate

Good soils

OK soil

Badsoil

Good soil

OK soil

History of foundation systems

Page 5: INTRODUCTION TO GEOPIER SYSTEM

The Geopier® Systems are made up of Rammed Aggregate Pier® elements.

With time, the Geopier System gained popularity with cost and schedule benefits.

History of foundation systems

Page 6: INTRODUCTION TO GEOPIER SYSTEM

1. Created by forming a cavity

Rammed Aggregate Pier Construction

Page 7: INTRODUCTION TO GEOPIER SYSTEM

2. Adding thin lifts of Aggregate, and

Rammed Aggregate Pier Construction

Page 8: INTRODUCTION TO GEOPIER SYSTEM

3. Vertically RAMMING the thin lifts of aggregate

Rammed Aggregate Pier Construction

Page 9: INTRODUCTION TO GEOPIER SYSTEM

Rammed Aggregate Pier Construction

Page 10: INTRODUCTION TO GEOPIER SYSTEM

Temporary casing used to stabilize caving soils

Rammed Aggregate Pier Construction

Page 11: INTRODUCTION TO GEOPIER SYSTEM

Displacement Construction

Page 12: INTRODUCTION TO GEOPIER SYSTEM

Displacement Construction

Then, as hollow

mandrel is

raised, stone

flows from

hopper down

through mandrel.

Impact

hammer

After

driven

to full

depth,

mandrel

is raised

up 3 ft

Then

driven

back

down 2

ft

Dense,

1 ft lifts

Crowd pressure

from rig weight

and hydraulics

First, mandrel

is driven to

full depth,

with sacrificial

cap covering

tamper foot.

Page 13: INTRODUCTION TO GEOPIER SYSTEM

Footing Construction

• Excavate for footings• Compact footing bed• Place steel• Pour concrete

Page 14: INTRODUCTION TO GEOPIER SYSTEM

Types of Foundations Supported

• Isolated Spread footings

• Continuous footings

• Retaining Walls

• Lightly loaded slabs

• Heavily loaded slabs

• Uplift Anchors

Page 15: INTRODUCTION TO GEOPIER SYSTEM

Flexible Continuous Footings

Page 16: INTRODUCTION TO GEOPIER SYSTEM

The keys to success are:

1. Vertical RAMMING (to achieve very low void ratio) and

2. Increase in lateral effective stress from the beveled tamper foot

Geopier System Features

Beveled tamper

Page 17: INTRODUCTION TO GEOPIER SYSTEM

Geopier System Features

• High allowable bearing capacity

• Control settlement

• Uplift resistance

• Lateral load resistance

Page 18: INTRODUCTION TO GEOPIER SYSTEM

How do RAP systems work?

Engineering basics

Push down on footing, the stiff element (pier) takes more of the load

Page 19: INTRODUCTION TO GEOPIER SYSTEM

How do RAP systems work?

The strength and stiffness of the pier determined using a Modulus Test which gives you a spring constant

Engineering basics

• Deflection = 0.25-inch• kg = stress / deflection = 500 pci

0.00

0.25

0.50

0.75

1.00

0 10 20 30 40

Top deflection

RAP Stress (ksf)

Deflection (in)

Telltale deflection

Design(a)

(b)

Page 20: INTRODUCTION TO GEOPIER SYSTEM

Uplift anchors required to resist tensile loads

Steel Plate

Cylindrical shearingsurface

Threaded rods

Uplift Resistance

Page 21: INTRODUCTION TO GEOPIER SYSTEM

Load Test Uplift Element at UC Davis Production Uplift Elements

Uplift Resistance

Page 22: INTRODUCTION TO GEOPIER SYSTEM

Lateral Resistance

Page 23: INTRODUCTION TO GEOPIER SYSTEM

RAP and Soil Types

• Sand, silty/clayey sand, gravel

(SP, SW, SM, SC, GW, GP)

• Clays and silts

(CL, ML)

• Peats and organics

(PT, OL)

• Undocumented fill

Page 24: INTRODUCTION TO GEOPIER SYSTEM

GEOPIER LIMITATIONS

• Extreme loads on extremely soft soils

• Sinkholes

• Expansive / swelling clay

• Obstructions during drilling

Page 25: INTRODUCTION TO GEOPIER SYSTEM

Economics:

Often provide a 20% to 40% cost savings in comparison with Deep Foundations when:

• High capacity > 75 tons and length > 30 feet

• Moderate capacity > 40 to 60 tons and length > 20 feet

• Low capacity < 40 tons and any length

Pile length

Pile capacity

RAP provides MORE economy

RAP provides LESS economy

When To Consider RAP Systems

Page 26: INTRODUCTION TO GEOPIER SYSTEM

Economics:

Often provide a 20% to 40% cost savings in comparison with over-excavation and replacement when:

• The depth of overexcavation exceeds 5 - 8 feet.

When To Consider RAP Systems

Page 27: INTRODUCTION TO GEOPIER SYSTEM

Geopier SystemApplications

Building Foundation Support

Industrial & Tank Support

Floor Slab Support Transportation

Page 28: INTRODUCTION TO GEOPIER SYSTEM

• Five story parking deck

• 63,000 sf footprint

• 77 columns with loads

ranging from

200 to 1220 kips

• Foundation options for

RAPs and auger cast

piles

CASE STUDY

VICTORYLAND PARKING DECKSHORTER, ALABAMA

Page 29: INTRODUCTION TO GEOPIER SYSTEM

SUBSURFACE PROFILE

LOWER ZONE

1220 KIPS

Page 30: INTRODUCTION TO GEOPIER SYSTEM

0.000

0.200

0.400

0.600

0.800

1.000

0 5,000 10,000 15,000 20,000 25,000 30,000

Applied Geopier Stress (psf)

Deflection (inches)

Bottom of Geopier

Top of Geopier

Unload

Modulus test results

VICTORYLAND PARKING DECK

Measured Upper Zone Settlement = 0.3”

Estimated Lower Zone Settlement = 0.2”

Total Settlement = 0.5”

Page 31: INTRODUCTION TO GEOPIER SYSTEM

530 RAP elements installed in 11 days!

VICTORYLAND PARKING DECK

Page 32: INTRODUCTION TO GEOPIER SYSTEM

Elements reinforce soft and compressible soils for support of relatively thin floor slabs.

Replace structural floor slabs on piles.

FLOOR SLAB SUPPORT

Page 33: INTRODUCTION TO GEOPIER SYSTEM

Design Considerations

FLOOR SLAB SUPPORT

Geotechnical (settlement, etc)

Structural (slab design, etc)

Page 34: INTRODUCTION TO GEOPIER SYSTEM

FLOOR SLABS - GEOTECHNICAL

Fill and floor slab support

d

spacing (s)

"competent"

soils

Soft, compressible

soils

Floor load (p)

New Fill

45o

Thickness

RAP

element

(t)

Arching transfers pressures to pier

Page 35: INTRODUCTION TO GEOPIER SYSTEM

FLOOR SLABS – STRUCTURAL

Steel Reinforcement

. . . . . May be required to resist tensile stresses within top of slaboverlying Geopier elements.

Need to:

-Work closely with structural engineer

- Perform finite element analysis

(project SE or GFC SE)

Page 36: INTRODUCTION TO GEOPIER SYSTEM

Results of analysis identify areas of higher bending stresses

Indicate whether added reinforcement or thicker slab is needed

Finite Element Analysis (FEA)

FLOOR SLABS – STRUCTURAL

Page 37: INTRODUCTION TO GEOPIER SYSTEM

FLOOR SLAB SUPPORT

Boeing Building 101, St. Louis, MODelta Marine, Seattle, WA

Costco Retail Store, Tacoma, WA Polaris Plant, Vermillion, SD

Page 38: INTRODUCTION TO GEOPIER SYSTEM

KRAFT CAPRI-SUN WAREHOUSE GRANITE CITY, ILLINOIS

Kraft Capri-Sun Warehouse

Granite City, Illinois

St. Louis, MO

FLOOR SLABS - EXAMPLE

Page 39: INTRODUCTION TO GEOPIER SYSTEM

Floor Slab700 psf pressure

5 ft fill to get out of floodplain

FLOOR SLABS - EXAMPLE

Page 40: INTRODUCTION TO GEOPIER SYSTEM

10 ft

CH & CL, Su = 500 psf

0 10 20 30 40

SP, SM

N-values, M%Subsurface conditions

FLOOR SLABS - EXAMPLE

Page 41: INTRODUCTION TO GEOPIER SYSTEM

Soft Clay

Dense Sand and Silty Sand

Soft ClayFloor Slab

•Winter construction

• Groundwater

Fill

Planned construction

10 ft

FLOOR SLABS - EXAMPLE

OPTIONS?

Page 42: INTRODUCTION TO GEOPIER SYSTEM

Rammed Aggregate Pier stabilized zone

Floor Slab

Dense Sands and Silty Sands

Value engineering proposal

Pier spacing = 14 ft

FLOOR SLABS - EXAMPLE

Page 43: INTRODUCTION TO GEOPIER SYSTEM

-2.50

-2.25

-2.00

-1.75

-1.50

-1.25

-1.00

-0.75

-0.50

-0.25

0.00

0 4000 8000 12000 16000 20000 24000 28000

top of Geopiermiddle telltalebottom telltale

Geopier Stress (psf)

Deflection (in)

15

Modulus test

FLOOR SLABS - EXAMPLE

Page 44: INTRODUCTION TO GEOPIER SYSTEM

-1.0

-0.8

-0.6

-0.4

-0.2

0.0

0.2

12/6/00

12/11/00

12/16/00

12/21/00

12/26/00

12/31/00

1/5/01

1/10

/01

1/15

/01

Settlement Monitoring

Settlement (in)

Time (days)

Pier = 0.5 in (0.6)

Soil = 0.6 in (0.6)

Differential = 0.1 in (0 in)

Differential settlement

FLOOR SLABS - EXAMPLE

Page 45: INTRODUCTION TO GEOPIER SYSTEM

FLOOR SLAB SUPPORT

• 360,000 sq. ft. manufacturing facility addition

• Floor slab pressures = 700 psf

• 2,100 Geopier elements installed in one month

Page 46: INTRODUCTION TO GEOPIER SYSTEM

Mirant Power Plants, MD

POWER GENERATION

Page 47: INTRODUCTION TO GEOPIER SYSTEM

Morgantown Plant

Mat foundation:91-ft x 357-ft

Absorber stacks and building

Design pressures:3 ksf at building6 ksf at stacks

Nanjemoy Formation (N > 30)

ML (N = 8 – 20 bpf)

SM (N = 3 – 15 bpf)

14’

Excavation

18’

~26’Impact RAPs:4 to 6 ft o-c

Est. settlements:~ 2.5 inches

Page 48: INTRODUCTION TO GEOPIER SYSTEM

Chalk Point Plant

Mat foundation:87-ft x 219-ft

Absorber stacks and building

Design pressures:3 ksf at building6 ksf at stacks

Impact RAPs:4 to 6 ft o-c

Est. settlement:~ 3.8 inches

Nanjemoy Formation (N > 30)

MH (N = 11 – 26 bpf)

SM (N = 5 – 11 bpf)

17’

40’

~26’

Excavation

Page 49: INTRODUCTION TO GEOPIER SYSTEM

TANK SUPPORT

Page 50: INTRODUCTION TO GEOPIER SYSTEM

Bearing Capacity

Unsuitable Soil

Competent Soil

DESIGN ISSUES

Page 51: INTRODUCTION TO GEOPIER SYSTEM

DESIGN ISSUES

Settlement

Unsuitable Soil

Competent Soil

Page 52: INTRODUCTION TO GEOPIER SYSTEM

DESIGN OPTIONS

Overexcavation and Replacement

Problems• High groundwater• Cost• Schedule

Page 53: INTRODUCTION TO GEOPIER SYSTEM

DESIGN OPTIONS

Pile-supported concrete pad

Problems• Cost• Schedule

Page 54: INTRODUCTION TO GEOPIER SYSTEM

DESIGN OPTIONS

Granular pad over Geopier reinforced zone

Geopier

Reinforcement Zone

Page 55: INTRODUCTION TO GEOPIER SYSTEM

SAMPLE INDUSTRIAL PROJECTS

• Houston Fuel Oil Terminal Tank Support

• Kinder Morgan Tank 150-27 Repair

• Valero Refinery Tank TK-443

• Lyondell-Citgo Tank Repair

• Kinder Morgan Tank 150-44

• Valero Refinery Tank TK-231

• Industrial Zeolite Plant

• ExxonMobil Tank 2176 Repair

• ConocoPhillips Refinery

Page 56: INTRODUCTION TO GEOPIER SYSTEM

• New tank construction

• 125-foot diameter

• 48-ft tall

• Design pressure = 3 ksf

CASE HISTORY:VALERO REFINERY TANK TK-231HOUSTON, TX

Page 57: INTRODUCTION TO GEOPIER SYSTEM

4 ft

Su (ksf)

0 1.0 2.0 3.0

Clay Fill0 ft

SUBSURFACE CONDITIONS

4.0

V. Soft to Firm Clay

Firm to V. Stiff Clay

10 ft

Page 58: INTRODUCTION TO GEOPIER SYSTEM

GEOPIER SOLUTION

Perimeter Differential Settlement Control

Fill

Soft Clay

Firm to V. Stiff Clay

Page 59: INTRODUCTION TO GEOPIER SYSTEM

GEOPIER SOLUTION

Bearing Capacity – Edge Instability

V. Soft to Firm Clay

Firm to V. Stiff Clay

Geopier

FS for Geopier-reinforced soil = 1.30

Page 60: INTRODUCTION TO GEOPIER SYSTEM

Modulus Load Test Results

-2.00

-1.50

-1.00

-0.50

0.00

0 5 10 15 20

Top of Geopier

Telltale No. 1

Top of Geopier Stress (ksf)

Deflection (in)

Design Stress

Deflection

GEOPIER SOLUTION

Settlement = 0.5 in at design stress

Page 61: INTRODUCTION TO GEOPIER SYSTEM

• Installed 243 piers in 8 days (30 piers / day)

• Increased edge stability (FS = 1.3)

• Limited perimeter differential settlements

GEOPIER SOLUTION

Page 62: INTRODUCTION TO GEOPIER SYSTEM

• Duke Energy

• Ameren (UE)

• Motiva

• Lockheed

• ExxonMobil

• Valero

• Nucor Steel

• General Motors

• BNSF

• Kinder Morgan

• Boeing

• U.S. Food Services

Selected National Clients

• Certainteed

• Kraft

• John Deere

• Case New Holland

• Pfizer

•Wal-Mart

• Michelin

• Maybelline

• Pacific Bell

• Sara Lee

• Anheuser Busch

• General Mills

Page 63: INTRODUCTION TO GEOPIER SYSTEM

Shear reinforcement in Geopier zone

TRANSPORTATION APPLICATIONS

Page 64: INTRODUCTION TO GEOPIER SYSTEM

US-90 & SH-6 Intersection Upgrades, Sugarland, Texas Site Plan

Page 65: INTRODUCTION TO GEOPIER SYSTEM

SCOPE OF WORK

6.7 / 22107 / 353South Ramp

7.3 / 24107.6 / 353North Ramp

8.2 / 2769 / 227South

Abutment

7.3 / 2479 / 260North

Abutment

Max. Height

(m)/ [ft]

Length

(m)/[ft]

MSE Wall

Location

Page 66: INTRODUCTION TO GEOPIER SYSTEM

Typical Soil Conditions

0

2

4

6

8

10

12

14

16

0 10 20 30 40 50 60 70 w%

Depth (m)

GWT

CL

SM

SM, SW

φ' = 22°

c' = 4.8 kPa

φ' = 30°

c' = 0

cεc = 0.11 - 0.14

cεr = 0.03 - 0.05

φ' = 30°c' = 0

0 10 20 30 40 50 60 70 80 90

North Ramp South Ramp

North Abutment South Abutment

Su (kPa)

CL

SM

Page 67: INTRODUCTION TO GEOPIER SYSTEM

Geopier Installation

•Total Number of Piers = 1411 •Two Crews •20 to 25 RAPs•Cost ~ $1,000,000•Bid Through DOT letting•FHWA funded the geotechnical instrumentation

Page 68: INTRODUCTION TO GEOPIER SYSTEM

Modulus Test Results

-60-55-50-45-40-35-30-25-20-15-10-50

0 300 600 900 1200 1500

Top-of-Rammed Aggregate Pier Stress (kPa)

deflection, (m

m)

North Abutment

South Abutment

South Ramp

South Ramp II

North Ramp

Design Stress < 18000 psf< ¾-in top vertical deflection

Page 69: INTRODUCTION TO GEOPIER SYSTEM

Geotechnical Instrumentation Layout

Near the Bridge Abutments at general locations of higher bearing pressure

MonitoringStation 1

MonitoringStation 2

East

West

Page 70: INTRODUCTION TO GEOPIER SYSTEM

Geotechnical InstrumentationHorizontal and Vertical Inclinometers

Vibrating Wire Piezometers

Sondex Settlement System

Page 71: INTRODUCTION TO GEOPIER SYSTEM

Instrumentation Installation

Vibrating Piezometer Cable

Horizontal InclinometerCasing w/Cable Return

ProtectiveInstrumentationBox

Page 72: INTRODUCTION TO GEOPIER SYSTEM

Instrumentation Monitoring Results

Horizontal and Vertical InclinometersPiezometer Nest

South Ramp Monitoring Station-1

0

4

8

12

16

20

24

11/29/05

12/27/05

1/24/06

2/21/06

3/21/06

4/18/06

5/16/06

6/13/06

7/11/06

8/8/06

9/5/06

10/3/06

10/31/06

11/28/06

12/26/06

Date

Pore Pressure (psi)

0

2

4

6

8

10

12

Fill Pressure (psi)

-15 ft

-20 ft

-24 ft

-30 ft

Fill

Spike Caused by Driving of Pile within 5 ft of Piezometers Gradual Rise in

Pore Pressure Caused by General Rise in Groundwater Elevation

Page 73: INTRODUCTION TO GEOPIER SYSTEM

Instrumentation Monitoring Results

Sondex Settlement System- South Ramp-West

-0.60-0.50-0.40-0.30-0.20-0.100.000.100.200.300.400.50

0 5 10

15

20

25

30

35

40

45

50

Depth-(ft)

Downward Movement (ft)

1/27/2006

1/25/2006

1/26/2006

2/1/2006

2/9/2006

2/20/2006

2/23/2006

3/2/2006

3/9/2006

4/6/2006

5/4/2006

7/12/2006

9/19/2006

10/24/2006

Avg

2.5-in (6.4-cm)

Page 74: INTRODUCTION TO GEOPIER SYSTEM

Instrumentation Monitoring ResultsVertical Inclinometers at North Ramp

0

5

10

15

20

25

30

35

40

45

50

-3.0 -2.5 -2.0 -1.5 -1.0 -0.5 0.0 0.5 1.0 1.5 2.0 2.5 3.0

Lateral Movement (in)

Depth (ft)

North Ramp-Sta.2-West

North Ramp Sta. 2 - East

North Ramp-Sta.1-West

North Ramp Sta. 1-East

11/2006 through 5/2007

Bottom of Retaining Wall Footing

2.54-cm

Page 75: INTRODUCTION TO GEOPIER SYSTEM

NORTH ABUTMENT

NORTH RAMP

SOUTH ABUTMENT

SOUTH RAMP

Page 76: INTRODUCTION TO GEOPIER SYSTEM

Conclusions

-Vertical Settlement 2.5 to 3-inches

-Horizontal Displacement < 1.5-inches

-Rapid Pore Water Pressure Dissipation

Afforded by Radial Drainage into RAPs

-Vertical Displacement < 2-inches

Post-Construction

- Complied with FHWA requirements

Page 77: INTRODUCTION TO GEOPIER SYSTEM

Questions?