INTERNATIONAL ELECTROTECHNICAL COMMISSION “TC57 and the Smart Grid” CIM Users Group, 2011, May 11 th , Prague

Upload: preston-palmer

Post on 02-Jan-2016

219 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: INTERNATIONAL ELECTROTECHNICAL COMMISSION “TC57 and the Smart Grid” CIM Users Group, 2011, May 11 th, Prague

INTERNATIONAL ELECTROTECHNICAL COMMISSION

“TC57 and the

Smart Grid”

CIM Users Group,2011, May 11th, Prague

Page 2: INTERNATIONAL ELECTROTECHNICAL COMMISSION “TC57 and the Smart Grid” CIM Users Group, 2011, May 11 th, Prague

INTERNATIONAL ELECTROTECHNICAL COMMISSION

Thierry LEFEBVRE, TC57 chairman

1. TC57 in brief

2. TC57 & Smart Grid

3. TC57 & other organizations

Page 3: INTERNATIONAL ELECTROTECHNICAL COMMISSION “TC57 and the Smart Grid” CIM Users Group, 2011, May 11 th, Prague

TC57 : Power system information management & associated information exchange

To prepare international standards for power systems control equipment and systems including EMS, SCADA, DA, teleprotection, and associated information exchange for real-time and non-real-time information, used in the planning, operation and maintenance of power systems.

Power systems management comprises control within control centres, substations and individual pieces of primary equipment including telecontrol and interfaces to equipment, systems and databases, which may be outside the scope of TC 57.

3

Page 4: INTERNATIONAL ELECTROTECHNICAL COMMISSION “TC57 and the Smart Grid” CIM Users Group, 2011, May 11 th, Prague

4

Publications of TC57

127 publications, 26 projects

Publication TitleIEC/TR 62357 Power system control and associated communications - Reference

architecture for object models, services and protocolsIEC 61970 Energy management system application program interface (EMS-API)

IEC 61968 Application integration at electric utilities - System interfaces for distribution management

IEC 62325 Framework for energy market communications IEC 61850 Communication networks and systems for power utility automationIEC 60870 Telecontrol equipment and systemsIEC 61334 Distribution automation using distribution line carrier systemsIEC 62351 Power systems management and associated information exchange -

Data and communications securityIEC/TS 61085 General considerations for telecommunication services for electric

power systemsIEC 60495 Single sideband power-line carrier terminalsIEC 60481 Coupling devices for power line carrier systemsIEC 60353 Line traps for a.c. power systemsIEC/TR 60663 Planning of (single-sideband) power line carrier systemsIEC 60834 Teleprotection equipment of power systems - Performance and testing

- Part 1: Command systems

Series thatContributeDirectly toSG arch.

Page 5: INTERNATIONAL ELECTROTECHNICAL COMMISSION “TC57 and the Smart Grid” CIM Users Group, 2011, May 11 th, Prague

TC 57 , production overview

Telecontrol 60870-5

TASE.2 for inter control centres communications (60870-6)

DLMS, Information exchange for metering (with TC13)(61334)

61850 as universal protocol for power system management Distribution automation: substations control, measurement &

protection (local & remote)

Wind power farms control

Hydro power plant

Dispatched ressources management / control

…others…in preparation

CIM, for Common Information Model Energy management systems (61970)

Distribution management sytems (61968)

Communication exchange for markets (62325)

Sec

uri

ty (6

23

51

)

5

Page 6: INTERNATIONAL ELECTROTECHNICAL COMMISSION “TC57 and the Smart Grid” CIM Users Group, 2011, May 11 th, Prague

Interoperability within TC57 in long term Vision Statement

“All new TC57 standards should use/extend the CIM as the common semantics for their configuration/engineering modeling, and 61850 for [SCADA oriented / IED / field / other] communications.

Other existing standards would likely take a mapping approach

Encourage a common data modeling approach across TC57

6

Page 7: INTERNATIONAL ELECTROTECHNICAL COMMISSION “TC57 and the Smart Grid” CIM Users Group, 2011, May 11 th, Prague

61850 & CIM, key standards to fulfill interoperability in

Smart Grid architecture

7

Securit

y

CIM as the common semantics for application-to-application information exchange

61850 for devices communications

62351 for securityCIM

61850

Page 8: INTERNATIONAL ELECTROTECHNICAL COMMISSION “TC57 and the Smart Grid” CIM Users Group, 2011, May 11 th, Prague

In other words…

The goal of Technical Committee 57 is chiefly to publish

standards for

Smart Power Systems

---

Moreover:

Core standards (61850, CIM) are basic components for suporting new SG functions

Several TC57 standards are components of the communication smart grid architecture;8

Page 9: INTERNATIONAL ELECTROTECHNICAL COMMISSION “TC57 and the Smart Grid” CIM Users Group, 2011, May 11 th, Prague

Several TC57 standards are components of the communication smart grid architecture (61850 extensions)

Hydro (61850-7-410)

DER, dispatched energy ressources(61850-7-420, future ed.2)

Communication for advanced distribution application (future 61850-90-6)

Photovoltaic, storage, DER inverters (future 61850-90-7)

Electrical transportation (future 61850-90-8)

Object model for batteries (future 61850-90-9)

Wind turbine control (62400-25)

[…]9

Page 10: INTERNATIONAL ELECTROTECHNICAL COMMISSION “TC57 and the Smart Grid” CIM Users Group, 2011, May 11 th, Prague

TC 57 & NIST (US)

TC 57 & CENELEC (Europe)

10

TC57 & other organizations

IEC SG3

…other organizations

Page 11: INTERNATIONAL ELECTROTECHNICAL COMMISSION “TC57 and the Smart Grid” CIM Users Group, 2011, May 11 th, Prague

TC 57 & NIST

In the US, NIST is facilitating many Smart Grid efforts, which have had significant international involvement

TC57/WG19 had a Smart Grid Task Force, with a focus to coordinate TC57 efforts as related to the Smart Grid

Several TC57 convenors & members are strongly involved in NIST

11

Page 12: INTERNATIONAL ELECTROTECHNICAL COMMISSION “TC57 and the Smart Grid” CIM Users Group, 2011, May 11 th, Prague

NIST PAP Title TC57 WG Directly Involved

TC57 WG Indirectly Affected

PAP 0 Meter Upgradeability Standard

PAP 1 IP 15

PAP 2 Wireless 15

PAP 3 Pricing 16, 14

PAP 4 Schedules 16, 14

PAP 5 Meter Data Profiles 14

PAP 6 Models for Meter Data Tables 14

PAP 7 Electric Storage Interconnection 17 10

PAP 8 CIM for Distribution Grid Mgmt 13, 14, 17, 15

PAP 9 DR Signals 14, 16, 15

PAP 10 Energy Usage Info 14, 15

PAP 11 Models for Electric Transportation 14, 15, 17

PAP 12 61850/DNP3 Mapping 10 13, 14, 17

PAP 13 Time Sync, C37.118, 61850 10

PAP 14 Power System Model Mapping 13, 14 10

PAP 15 PLCs for Home Appliances

PAP 16 Wind Plant Communications 10, 1712

CIM

CIM

CIM

CIM

CIM

CIM

CIM

CIM

CIM

61850

61850

61850

61850

61850

N I

S T

CIM

Page 13: INTERNATIONAL ELECTROTECHNICAL COMMISSION “TC57 and the Smart Grid” CIM Users Group, 2011, May 11 th, Prague

NIST PAP Title TC57 WG Directly Involved

TC57 WG Indirectly Affected

PAP 0 Meter Upgradeability Standard

PAP 1 IP 15

PAP 2 Wireless 15

PAP 3 Pricing 16, 14

PAP 4 Schedules 16, 14

PAP 5 Meter Data Profiles 14

PAP 6 Models for Meter Data Tables 14

PAP 7 Electric Storage Interconnection 17 10

PAP 8 CIM for Distribution Grid Mgmt 13, 14, 17, 15

PAP 9 DR Signals 14, 16, 15

PAP 10 Energy Usage Info 14, 15

PAP 11 Models for Electric Transportation 14, 15, 17

PAP 12 61850/DNP3 Mapping 10 13, 14, 17

PAP 13 Time Sync, C37.118, 61850 10

PAP 14 Power System Model Mapping 13, 14 10

PAP 15 PLCs for Home Appliances

PAP 16 Wind Plant Communications 10, 1713

CIM

CIM

CIM

CIM

CIM

CIM

CIM

CIM

CIM

61850

61850

61850

61850

61850

PAP 7: Electricity storage:Future 61850-90-9: object models for batteries61850-7-420 EV used as storage in future Ed.2

PAP 11: models for electrical transportationFuture 61850-90-8:object models for electrical transportation; to be coordinated with TC69

PAP 16: Wind plant communications62400-25 series based on 61850, JWG TC 88/57

CIM

Page 14: INTERNATIONAL ELECTROTECHNICAL COMMISSION “TC57 and the Smart Grid” CIM Users Group, 2011, May 11 th, Prague

TC57 & CENELEC

European Commission published several « mandates » related to Smart Grid

Mandate 490 on smart grid, and other mandates on smart metering, energy efficiency, security...

A CENELEC/ TC57 have just been created for promoting IEC TC57 standards and IEC smart grid strategy at European level;

14

CE

NE

LE

C

Page 15: INTERNATIONAL ELECTROTECHNICAL COMMISSION “TC57 and the Smart Grid” CIM Users Group, 2011, May 11 th, Prague

SG 3 - Strategic Group on Smart Grid

SG 3 (Strategic Group) on Smart Grid, set up by the IEC SMB (Standardization Management Board), provides advice on fast-moving ideas and technologies likely to form the basis for new International Standards or IEC TCs (Technical Committees) in the area of Smart Grid technologies. 

It has developed the framework and provides strategic guidance to all Technical Committees involved in Smart Grid work and has developed the Smart Grid Roadmap which covers standards for interoperability, transmission, distribution, metering, connecting consumers and cyber security.

The IEC through SG 3 is working in close collaboration with Smart Grid projects around the globe, including NIST (US National Institute of Standards and Technology). IEC Standards are recognized as being crucial in the development of Smart Grids everywhere

15

IE

C/S

MB

/SG

3

Page 16: INTERNATIONAL ELECTROTECHNICAL COMMISSION “TC57 and the Smart Grid” CIM Users Group, 2011, May 11 th, Prague

TC57 & SMB/Strategic Group on Smart Grid

SG3 recommandations towards TC57 ex: com architecture, CIM – 61850 harmonization

NWIP on SG (57/1117/NP) as remaining responses to SG3 questions Identification of use cases which involve systems

connected to the smart grid.

Development of requirements for system interfaces and communication protocols in consideration of

• integration of a large number of massively distributed systems

• domain specific protocols for industrial, home and building automation

• state-of-the-art wireless and wired communication protocol stacks

• efficient installation, commissioning and maintenance

16

IE

C/S

MB

/SG

3

Page 17: INTERNATIONAL ELECTROTECHNICAL COMMISSION “TC57 and the Smart Grid” CIM Users Group, 2011, May 11 th, Prague

In short

TC57, for smart power systems

The mission of TC57 is to published standards and technical specifications for smart power systems ,

to enhance its management, to specify information exchange, for improving interoperability, decreasing costs in long term

TC57 has defined a powerful and consistent architecture for the long term

61850 and CIM

TC57 already published functional standards for communication exchanges in smart grid architecture

61850 and CIM main standards have to be used for standardization of new SG applications (communication, semantics)

Security for information exchange is provided by 61351 and other security technologies

17

Co

ncl

usi

on

1

Page 18: INTERNATIONAL ELECTROTECHNICAL COMMISSION “TC57 and the Smart Grid” CIM Users Group, 2011, May 11 th, Prague

In short

TC57 // global smart grid architecture

SG is a source of strong motivation for TC57 members

TC57 actively maintains several liaisons

TC57 experts are already involved in organizations dealing with smart grid …

… but lack of expert resources remain the main threat

=> this point has to be taken into account for avoiding disillusion when schedules are not met

… The length of time needed under traditional IEC procedures to update object models could limit their acceptance in the Smart Grid industry

18

Co

ncl

usi

on

2

Page 19: INTERNATIONAL ELECTROTECHNICAL COMMISSION “TC57 and the Smart Grid” CIM Users Group, 2011, May 11 th, Prague

INTERNATIONAL ELECTROTECHNICAL COMMISSION

Thank you for your attention !

[email protected]

Page 20: INTERNATIONAL ELECTROTECHNICAL COMMISSION “TC57 and the Smart Grid” CIM Users Group, 2011, May 11 th, Prague

Annexe

TC57 working groups

TC57 Liaisons

20

Page 21: INTERNATIONAL ELECTROTECHNICAL COMMISSION “TC57 and the Smart Grid” CIM Users Group, 2011, May 11 th, Prague

WG 19 (P. Skare): Interoperability . within TC57 long term

WG

15 (F. Clevelan

d) : D

ata an

d com

mu

nication

security

WG 3 (W. Brodt): Telecontrol protocols,WG 10 (C. Brunner): Communication network and systems

for power utility automation,WG 13 (T. Saxton): EMS-Application Programme InterfaceWG 14 (G. Robinson): System Interface for Distribution

ManagementWG16 (J. Waight): Communication for deregulated energy

markets,WG17 (J. Goulet): Communication systems for distributed

energy ressources,WG18 (C. Malcolm): Hydroelectric Power Plants

communication for monitoring and control,WG20 (J. Newburry): Hight voltage power line systems

CAG

21

CIM61850

TC57 Working Groups

Page 22: INTERNATIONAL ELECTROTECHNICAL COMMISSION “TC57 and the Smart Grid” CIM Users Group, 2011, May 11 th, Prague

Liaisons

Present IEC internal liaisons: • IEC TC 4 Hydraulic turbines

• IEC TC 8 System aspects for electrical energy supply

• IEC TC 13 Electrical energy measurement, tariff- and load control

• IEC SC 17C High-voltage switchgear and controlgear assemblies

• IEC TC 38 Instrument transformers

• IEC TC 65 Industrial-process measurement, control and automation

• IEC TC 88 Wind turbines (Projects 61400-25-1 to -6)

• IEC TC 95 Measuring relays and protection equipment

External liaisons and co-operations: • CIGRE: Category A; D2 (Information technology) and B5 (local control, protections)

• UCAIug: Category D with WG 10, WG 13 and WG 14, WG15 & WG16 (under discussion)

• ebIX European forum for energy business information exchange: Category D with WG 16

• ENTSO-E: Category D with WG 13 and WG 16

• IEEE PES PSCC Security Subcommittee: Category D with WG 15

• UN/CEFACT: MoU between IEC and UN/CEFACT

ZigBee alliance (under discussion)

22