intelligent early warning system for construction safety...

12
Research Article Intelligent Early Warning System for Construction Safety of Excavations Adjacent to Existing Metro Tunnels Wei Tian , 1 Jiang Meng, 1 Xing-Ju Zhong, 1 and Xiao Tan 2 1 School of Civil Engineering, Xi’an University of Architecture and Technology, Xi’an, China 2 Glodon Company Limited, Beijing, China CorrespondenceshouldbeaddressedtoWeiTian;[email protected] Received 16 June 2020; Revised 16 November 2020; Accepted 28 December 2020; Published 15 January 2021 AcademicEditor:ElhemGhorbel Copyright©2021WeiTianetal.isisanopenaccessarticledistributedundertheCreativeCommonsAttributionLicense, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited. Withtheincreasingexploitationandutilizationofundergroundspaces,theexcavationofdeepfoundationpitsadjacenttoexisting metrotunnelsisbecomingincreasinglycommon.eseexcavationshavethepotentialtocausesafetyproblemsfortheoperation ofthenearbymetro.erefore,topreventmetrotunnelaccidentsfromoccurringduringtheconstructionprocessandtoensure thesafetyoflivesandproperty,itisnecessarytoestablisharisk-basedearlywarningsystem.Duringtheexcavationprocess,the mainmethodsforpreventingaccidentsinexcavationsadjacenttoexistingmetrotunnelsaremanualanalysesbasedonon-site monitoringdata.However,thesemethodsmakeitdifficulttoenacteffectivecontrolmeasuresinatimelymannerowingtothelag of information processing. However, the trial application of artificial neural networks (ANNs) and building information modelling(BIM)forengineeringprojectsprovidesanewmethodforsolvingsuchproblems.isstudyusesabackpropagation neuralnetworktopredictthereal-timedeformationofthetunnelbasedonmonitoringdatafromtheadjacentconstructionsite.A safetyriskassessmentmodelisthenestablishedbasedontherelevantspecifications.roughtheestablishmentofanintelligent warningsystem,thesafetyrisktothemetrotunnelduringtheconstructionprocesscanbedisplayedinathree-dimensional(3D) formusingtheBIM.eoperationresultsoftheANN–BIMsystemshowthatitcaneffectivelypresentthesafetyrisktoexisting metro tunnels in a 3D manner, which can provide managers with rapid and convenient visual information to inform their decision-making. 1. Introduction Withthebuildingofnumerousmetrotunnelsincitiesand continuous urban construction and development, available land is becoming increasingly scarce, resulting in more frequent excavation of deep foundation pits adjacent to existing metro tunnels [1, 2]. During excavation, the retaining wall will be displaced into the pit, while the soil outside the wall will be deformed, and the surrounding surface will settle accordingly. As the excavation depth in- creases, the settlement and deformation will increase with thedeformationoftheretainingstructureandwillgradually be transferred outward. When these effects encounter a nearby existing metro tunnel, the balanced stress state aroundthetunnelwillbechanged,causingdeformationand displacement of the metro tunnel. However, the safety requirements governing the displacement and deformation of tunnels for metro operation are very strict, which com- plicates the construction process. During the construction process,notonlythesafetyoftheconstructionitselfbutalso thesafeoperationoftheadjacentmetroshouldbecarefully considered. erefore, during the construction process, effective safety risk warnings are particularly important to ensurethesafetyoftheconstructionprojectandtheadjacent metro. However, it is difficult to visualize safety risk warnings for the whole construction period using conven- tional methods. Moreover, it is difficult to determine the source of the risk in a timely manner before an accident occurs.Artificialneuralnetworks(ANNs),withtheirstrong nonlinear prediction and reasoning abilities, are highly suitable for complex prediction, assessment, and identifi- cation tasks. ANNs have been widely used to perform Hindawi Advances in Civil Engineering Volume 2021, Article ID 8833473, 12 pages https://doi.org/10.1155/2021/8833473

Upload: others

Post on 27-Jan-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

  • Research ArticleIntelligent Early Warning System for Construction Safety ofExcavations Adjacent to Existing Metro Tunnels

    Wei Tian ,1 Jiang Meng,1 Xing-Ju Zhong,1 and Xiao Tan2

    1School of Civil Engineering, Xi’an University of Architecture and Technology, Xi’an, China2Glodon Company Limited, Beijing, China

    Correspondence should be addressed to Wei Tian; [email protected]

    Received 16 June 2020; Revised 16 November 2020; Accepted 28 December 2020; Published 15 January 2021

    Academic Editor: Elhem Ghorbel

    Copyright © 2021 Wei Tian et al. *is is an open access article distributed under the Creative Commons Attribution License,which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.

    With the increasing exploitation and utilization of underground spaces, the excavation of deep foundation pits adjacent to existingmetro tunnels is becoming increasingly common. *ese excavations have the potential to cause safety problems for the operationof the nearby metro. *erefore, to prevent metro tunnel accidents from occurring during the construction process and to ensurethe safety of lives and property, it is necessary to establish a risk-based early warning system. During the excavation process, themain methods for preventing accidents in excavations adjacent to existing metro tunnels are manual analyses based on on-sitemonitoring data. However, these methods make it difficult to enact effective control measures in a timely manner owing to the lagof information processing. However, the trial application of artificial neural networks (ANNs) and building informationmodelling (BIM) for engineering projects provides a new method for solving such problems. *is study uses a backpropagationneural network to predict the real-time deformation of the tunnel based onmonitoring data from the adjacent construction site. Asafety risk assessment model is then established based on the relevant specifications. *rough the establishment of an intelligentwarning system, the safety risk to the metro tunnel during the construction process can be displayed in a three-dimensional (3D)form using the BIM. *e operation results of the ANN–BIM system show that it can effectively present the safety risk to existingmetro tunnels in a 3D manner, which can provide managers with rapid and convenient visual information to informtheir decision-making.

    1. Introduction

    With the building of numerous metro tunnels in cities andcontinuous urban construction and development, availableland is becoming increasingly scarce, resulting in morefrequent excavation of deep foundation pits adjacent toexisting metro tunnels [1, 2]. During excavation, theretaining wall will be displaced into the pit, while the soiloutside the wall will be deformed, and the surroundingsurface will settle accordingly. As the excavation depth in-creases, the settlement and deformation will increase withthe deformation of the retaining structure and will graduallybe transferred outward. When these effects encounter anearby existing metro tunnel, the balanced stress statearound the tunnel will be changed, causing deformation anddisplacement of the metro tunnel. However, the safety

    requirements governing the displacement and deformationof tunnels for metro operation are very strict, which com-plicates the construction process. During the constructionprocess, not only the safety of the construction itself but alsothe safe operation of the adjacent metro should be carefullyconsidered. *erefore, during the construction process,effective safety risk warnings are particularly important toensure the safety of the construction project and the adjacentmetro. However, it is difficult to visualize safety riskwarnings for the whole construction period using conven-tional methods. Moreover, it is difficult to determine thesource of the risk in a timely manner before an accidentoccurs. Artificial neural networks (ANNs), with their strongnonlinear prediction and reasoning abilities, are highlysuitable for complex prediction, assessment, and identifi-cation tasks. ANNs have been widely used to perform

    HindawiAdvances in Civil EngineeringVolume 2021, Article ID 8833473, 12 pageshttps://doi.org/10.1155/2021/8833473

    mailto:[email protected]://orcid.org/0000-0002-9046-1139https://creativecommons.org/licenses/by/4.0/https://creativecommons.org/licenses/by/4.0/https://doi.org/10.1155/2021/8833473

  • deformation predictions, risk assessments [3, 4], and costestimations [5] during construction. In addition, Lai et al. [6]noted that ANNs have been applied as a new tool for an-alyzing difficult geotechnical problems and have successfullysolved a series of engineering problems, including the de-formation caused by tunnel excavation in various types ofrock masses. Unlike the classical regression method, ANNsdo not require complex constitutive models to solve thesegeotechnical problems, thus improving the convenience ofobtaining their solutions. Zheng et al. [7] used a back-propagation (BP) neural network to integrate complexenvironmental factors and proposed a visualisation methodto evaluate the deformation risk level of undergroundspaces. *e deformation risk level was combined with thered, green, blue color space model to achieve real-timevisualisation displays. Cao et al. [8] used an ANN to identifythe most important parameters in the horizontal defor-mation of a deep foundation pit, thus providing a generalparadigm for analyzing the sensitivity of influencing pa-rameters. Wang and Huang [9] established a monitoringmodel for deep foundation pit deformation using an ANN,and the proposed model could realize nonlinear predictionof the deformation caused by excavation. Xu et al. [10]proposed an intelligent self-feedback and safety earlywarning system for underground caverns based on a BPneural network and the finite element method; the inversionof the mechanical parameters and the subsequent predictionwere achieved using the BP neural network.

    To date, building information modeling (BIM) technologyhas been applied for planning, architectural design, structuraldesign, construction, operation management, etc. Moreover,BIM has gradually been applied in construction safety man-agement. Sacks [11] demonstrated the feasibility and impor-tance of the three-dimensional (3D) visualization and analysisof BIM in realizing construction safety management. Ruppeland Schatz [12] used BIM to transform a 3D model into avirtual reality model and employed various hardware tosimulate the main senses of the human body in the event of afire; finally, a “game” simulating a fire evacuation was designed.Cheng et al. [13] built a BIM-based intelligent fire protectionand disaster reduction system and created an intelligent, two-way fire prevention system framework that could display real-time dynamic fire information in 3D. Zou et al. [14] showedthat BIM can not only be used as a systematic riskmanagementtool to support project development but also be used as a coredata generator and platform for further risk analysis by otherBIM-based tools. Li et al. [15] proposed a Chinese metroconstruction safety risk identification system and early warningsystem based on the BIM platform.

    *is study adopts the BIM platform for visualization,employs an intelligent monitoring system and manualmonitoring as data sources, and utilizes the strong predic-tion capability of a BP neural network to predict safety risks.In addition, Navisworks software provided by Autodesk isused as the development platform to integrate these aspectsinto the BIM. By connecting to a mobile phone terminalthrough the network, the proposed system can notifymanagers in a timely manner when safety risks occur, toachieve the goal of providing real-time visualized warnings.

    2. Research Approach

    *is study aims to establish an intelligent early warningsystem for construction projects involving excavation ad-jacent to existing metro tunnels. *e early warning system iscomposed of four subsystems: data monitoring, deformationprediction, safety risk assessment, and safety risk earlywarning. Here, the data monitoring subsystem (DMS) iscomposed of wireless sensors and manual monitoring. *edeformation prediction subsystem (DPS) realizes defor-mation prediction through a BP neural network. *e safetyrisk assessment subsystem (SRAS) refers to the provisions ofnational or local codes related to the existing tunnels toassess safety risks. *e safety risk early warning subsystem(SREWS) uses the BIM information model as a platform andintegrates the other three systems on this platform throughapplication programming interface (API) development torealize visual early warnings. *e implementation process isshown in Figure 1.

    3. Methodologies

    3.1. Analysis of Factors Influencing the Safety Risk. To de-termine the main factors that cause the deformation ofmetro tunnels, it is necessary to first determine the factorscausing changes in the stress field of the soil. Evidently, thesize, depth, shape, and methods of support of the foundationpits should be considered [6].*e change in the stress field ofthe soil is also related to properties of the soil andgroundwater [8]. In addition, when an existing tunnel isdeformed under external forces, the deformation is relatedto the stiffness, strength, and embedded depth of the tunnel[16], and thus the characteristics of the tunnels themselvesare also important factors. *rough analysis of these threeaspects, the factors influencing the safety risk of an exca-vation adjacent to an existing metro tunnel can be obtained,as summarized in Table 1. Of these factors, some changegradually during the construction process and are defined asvariable factors, while others remain constant during theconstruction process and are defined as constant factors. Forexample, although the properties of the soil change graduallywith varying soil depth, the soil characteristics of each layerremain almost unchanged.*us, its impact on the safety riskcan be reflected by the soil depth, and thus this factor isdefined as a constant factor.

    3.2. Real-Time Prediction Module for Existing TunnelDeformation. To more rapidly control the safety risk toadjacent existing tunnels, it is necessary to effectively predictthe real-time deformation of adjacent tunnels during theconstruction process (for example, using the excavationcondition today to predict the deformation of existingtunnels tomorrow). *e analysis in Section 3.1 demonstratesthat the factors causing tunnel deformation are very com-plex, and thus, it is difficult to use conventional predictionmethods. BP neural networks have strong adaptability forcomplex nonlinear predictions, which allows the real-timeprediction of tunnel deformation using this method. During

    2 Advances in Civil Engineering

  • application of the deformation prediction model, the vari-able factors are used as inputs. For the constant factors, real-timemonitoring data of the tunnel deformation were used astraining samples to integrate the internal law governing theinfluence of the constant factors into the model and reducehuman intervention. *e trained prediction model can thenbe used to predict the deformation of the tunnels. *e real-time monitoring data can be continuously inputted into thereal-time updated prediction model. *e operating mech-anism of the real-time prediction model for tunnel defor-mation is shown in Figure 2.

    3.3. Safety Risk Assessment Module. After the real-time de-formation of the tunnel is predicted by the model in Section3.2, the limit values for tunnel deformation referring to theChinese specification technical code for protection of existingstructures of urban rail transit are used as the warningthresholds for the deformation of the existing tunnel. Whenthe tunnel deformation reaches 30%, 50%, and 70% of the

    warning threshold, the corresponding risk level and cor-responding warning level are obtained. *e classification ofthe risk levels and corresponding warning levels are sum-marized in Table 2.

    3.4. Establishment of the Safety Risk Early Warning System.*e safety risk early warning system employs BIM as theplatform, wireless sensors and manual monitoring as thedata collection methods, the prediction model for defor-mation of the adjacent existing tunnel caused by deepfoundation pit construction as the basis for data processing,and the allowable deformation limits given in tunnel-relatedspecifications as the early warning thresholds. *e datamonitoring module, real-time tunnel deformation predic-tion module, safety risk assessment module, and safety riskearly warning module are integrated into Navisworks withthe help of API development to establish the early warningsystem. *is system is connected to the BIM collaborativemanagement platform to realize data sharing. *e system

    . . . . . .. . .

    Foundation pit construction

    Soil properties

    Tunnel condition

    a1 an b1 bn c1 cn

    Main influencing factors

    Fact

    ors a

    naly

    sisD

    ata m

    onito

    ring

    and

    tran

    smiss

    ion DMS

    Intelligent monitoring of deformation data corresponding to influencing factors

    Real-time transmission of monitoring data

    Monitoring data input

    Tunn

    el d

    efor

    mat

    ion

    pred

    ictio

    n an

    d sa

    fety

    risk

    asse

    ssm

    ent

    Safe

    ty ri

    sk w

    arni

    ng

    DPS

    Tunnel deformation prediction model based on BP neural network

    API development

    Prediction model integrated into BIM

    Visual model based on BIM platform

    SRASConstruction safety

    standards of metro tunnelsSafety risk assessment

    Tunnel deformation prediction

    SREWS

    Construction safety risk warning

    Visualised output of safety risk

    Figure 1: Intelligent early warning system process.

    Advances in Civil Engineering 3

  • has the ability to provide dynamic, visual, and real-time riskwarnings. *is allows for optimization of the safety riskwarning method for excavation adjacent to existing metrotunnels, which can ensure a smooth construction processand safe operation of the existing metro tunnels. *e overalloperation framework of the built early warning system isshown in Figure 3, and a specific demonstration of the

    early warning system will be given through a case study(Section 4).

    4. System Operation and Case Study

    4.1. Engineering Background. A square construction projectlocated on the east side of the Zhengzhou high-speed railway

    Table 1: Summary of factors affecting safety risks.

    Primary factors Secondary factors Factor categories

    Characteristics of the foundation pit

    Real-time depth of excavation point (a)

    Variable factors

    Real-time width of excavation point (b)Real-time length of excavation point (h)

    Horizontal distance from an excavation point to a tunnel section (d)Vertical distance between an excavation point and tunnel (v)

    Excavation time (t)

    Support methods for the excavation

    Parameters related to the diaphragm wallParameters related to soil stabilization

    Parameters related to anchoragesParameters related to the supporting structure

    Construction schemeConstruction technologyConstruction procedureLoads outside the pit

    Soil properties

    Soil density (c) Constant factorsInternal friction angle (ψ)Cohesive force (c)

    Static lateral pressure coefficient (k)Compressive modulus (E)

    Characteristics of existing metro tunnelsStructural strength of the tunnel

    Structural cracking degree of the tunnelEmbedded depth of the tunnel

    Historical monitoring data of variable factors

    Training samples Historical monitoring data of existing tunnel

    deformation

    BP neural network prediction model

    Model training

    Real-time monitoring data of variable factors

    Trained BP neural network prediction

    model

    Real-time prediction ofexisting tunnel deformation

    Generate Generate

    Data transmission

    Con

    tinuo

    us g

    ener

    atio

    n of

    mon

    itorin

    g da

    ta

    Figure 2: Operation mechanism of the real-time prediction model for metro tunnel deformation.

    Table 2: Security risk classification and alarm signal selection.

    Risk level Total deformation/threshold Risk alarm signal Signal colorLow level (I) δ < 0.3 Risk ignored BlueModerate level (II) 0.3≤ δ < 0.5 Risk concerned GreenHigh level (III) 0.5≤ δ < 0.7 Risk controlled YellowExtreme level (IV) 0.7≤ δ Risk prevented Redδ � deformation amount/threshold.

    4 Advances in Civil Engineering

  • station and the south side of the long-distance bus station isconsidered in this case study. *e shield section of existingmetro line 1 passes through the middle of the square plot.*e main functions of the project are the construction of anunderground garage and underground shopping mall,which are arranged symmetrically on either side of themetroshield. *e depth of each foundation pit is approximately20m, the length is approximately 177m, and the width isapproximately 110m.*e vertical distance between the edgeof the foundation pit and the tunnel is approximately 33m,as shown in Figure 4.

    4.1.1. Engineering Geology. According to the geologicaldrilling results and in situ test results, the project scopecomprises an exploration depth of 55m. With the exceptionof a shallow part composed of miscellaneous fill, the ex-cavation is mainly in quaternary Holocene and upperPleistocene series of alluvial and diluvial formations. *eexposed soil layers are shown in Figure 5.

    4.1.2. Hydrogeological Survey. *e aquifer in the explorationdepth is divided into two layers: phreatic water in the upperlayer and confined water in the lower layer. Phreatic wateroccurs mainly in silt and silty clay above 16.0–18.0m (ab-solute elevation: 70.0m), which are weakly permeable layers.Confined water mainly occurs in fine sand below16.0–18.0m. With high water content, strongly permeablelayers, and a micro-confined aquifer, this layer has a certain

    hydraulic connection with the upper phreatic water. *ephreatic layer is separated from the confined water layer bythe fifth silty clay layer.

    *e groundwater level at the site was measured using anexploration borehole. *e static water level measured in theexploration borehole was between 10.3 and 17.0m below thesurface, corresponding to absolute elevations of between74.81 and 76.79m. *e static water level of the lowerconfined water was approximately 12.0–19.0m below theground surface, corresponding to an absolute elevation ofapproximately 74.0m.

    4.2. Establishment of the Project BIM and Layout of theMonitoring System

    4.2.1. Establishment of the Project BIM. *e project BIM notonly has a realistic appearance but also contains additionalcomponent characteristic information. *e completedBIM is used in various stages of the construction process,replacing traditional communication based on two-di-mensional drawings, which allows information to betransferred among project members more accurately,intuitively, and efficiently. In the construction process,the corresponding BIM structure model and electro-mechanical equipment model are established and appliedfor the layout of the precipitation well, collision in-spection, and engineering quantity statistics, as shown inFigure 6.

    BP neural network

    prediction mode

    TrainingTrained BP

    neural network prediction model

    Tunnel deformation

    prediction

    Tunnel deformationprediction module

    Deformation limitations of tunnel-related

    specifications

    Data monitoring

    module

    Safety risk assessment

    moduleBIM visualisation platform

    Safety risk warning module

    Alarming

    Visualised output of safety risk

    Monitoring points

    Excavation length, excavation width, excavation depth,

    ...

    Monitoring data storage server

    Dat

    a tr

    ansm

    issio

    nM

    onito

    rs

    NavisworksAPI

    Nav

    iswor

    ks

    API

    Nav

    iswor

    ksA

    PI

    NavisworksAPI

    Figure 3: Operation framework for the intelligent early warning system.

    Advances in Civil Engineering 5

  • 4.2.2. Layout of the Monitoring System. To obtain real-timemonitoring data of the tunnel deformation, which is used totrain the prediction model and allow the prediction model tobe updated in real time, reasonable monitoring of the tunneldeformation is required. During excavation, the adjacentexisting tunnel deformation (convergent deformation anduplift deformation) was synchronously monitored. *emonitoring locations are shown in Figure 7. *ere were 31automatic monitoring sections in each tunnel; the distancebetween the monitoring sections at the three cross-passages

    was 5m, while the rest of the monitoring sections wereseparated by 10m.

    4.3. Establishment of the Prediction Model Based on the BPNeural Network

    4.3.1. Establishment of the Prediction Model. *e real-timemonitoring data for the variable factors (manual monitoringor automatic monitoring) are used as the input values. *ereal-time deformation (uplift deformation and convergentdeformation) and deformation rate (uplift deformation rateand convergent deformation rate) of the tunnels are used asthe output values. *e corresponding monitoring data fordeformation of the tunnels are used as the training set for thetraining model to establish a BP neural network predictionmodel that can predict the deformation of the tunnels in realtime. *e training set consisted of 3224 data sets obtainedfrom the monitoring of 31 tunnel sections for 104 d. *edesign of the BP neural network includes defining thenumber of nodes in the input layer, number of neurons inthe output layer, number of hidden layers, and number ofneurons in each hidden layer. According to Kolmogorov’stheory, a three-layer neural network such as the one used inthis study can guarantee a complex mapping from any di-mension, n, to output dimension,m. *erefore, a three-layerneural network model is ideal for conditions in which thetraining set is not large and the dimensions of the input andoutput layers are also not large. *e network topology of theprediction model is shown in Figure 8. *e number of nodesin the input layer is equal to the number of input variables,the number of neurons in the output layer is equal to thenumber of output variables, and the number of neurons inthe hidden layer is preliminarily determined by①; the finalnumber of neurons in the hidden layer is determined by trial

    Bushub

    Shang Ding Rd. Shang Ding Rd.

    ZhengzhouMetro Line no.1

    NZhengzhouMetro Line no.5

    (underconstruction)

    HSR: high speed rail

    ZhengzhouEast HSRStation

    Top-downexcavation pit

    Top-downexcavation pit

    Tieback

    Tieback

    0.8m thickdiaphragm wall

    0.8m thickdiaphragm wall

    110m

    177m

    Soil mixing pile(ϕ850)

    Bored pile(ϕ1000)

    Bored pile(ϕ1000)

    Westbound tunnel(ϕ6000)

    Eastbound tunnel(ϕ6000)

    Cross-passage

    13m

    Xiny

    i Rd.

    Xiny

    i Rd.

    East

    Squa

    re

    North down-top excavation pit

    South down-top excavation pit

    15.4m 19.2m 15.4m

    Figure 4: Location layout of the foundation pit.

    1. Miscellaneous fill2. floury soil3. Silty clay4. Floury soil and silty clay5. Silty clay6. Fine sand7. Silty clay

    8. Fine sand

    9. Silty clay

    10. Fine sand

    Figure 5: Geological sections.

    Figure 6: An integrated model of structure and electromechanicalequipment.

    6 Advances in Civil Engineering

  • calculations. During the trial calculations, the model in-cluding 13 hidden layer neurons produced the smallest meansquared error and the highest precision; therefore, the optimalnumber of hidden layer neurons was determined to be 13.

    M ������n + m

    √+ a, (1)

    wherem and n are the number of output layer and input layerneurons, respectively, and a is a constant between 0 and 10.

    4.3.2. Validation of the Prediction Results. To test the ef-fectiveness of the developed model, the prediction modelwas used to predict the uplift deformation of tunnel sectionDM12 during the excavation process from 9March 2016 to 1June 2016, and the prediction results were compared withthe actual monitoring results to evaluate the predictionaccuracy. *e results showed that the maximum absoluteerror of the prediction was 1.22mm, and the maximumrelative error was 8.1% (under normal circumstances, anerror within 2mm is considered acceptable), which satisfiesthe accuracy requirement. *e comparison between theprediction data and the monitoring data and the

    corresponding error curve are shown in Figures 9 and 10,respectively.

    4.4. Development and Operation of the ANN–BIM-BasedEarly Warning System

    4.4.1. Navisworks Development Platform.

    (1) Selection of development platformIn this study, Navisworks is selected as the platform,and development is carried out to realize eachfunctional module of the safety risk early warningsystem. In addition, .NET API is used to develop thesafety risk early warning system on the Navisworksplatform.

    (2) Implementation of Navisworks API*is study uses the Navisworks API to implementcustom family lookup, access object properties,modify model parameters, and perform other op-erations. *rough the permutation and combinationof these basic operations, the basic functions of thesafety risk early warning system can be realized. *especific methods are described below.

    (1) Custom family lookup: in the safety risk earlywarning system, the monitoring point for each earlywarning indicator will bind a corresponding familycomponent. After opening the model document, theprimary task is to distinguish the component cor-responding to the monitoring point from thecommon components. Navisworks API providesthree methods to find objects: the search class builtinto the .NET API and traversal and LINQ databaselookup in .NET itself. To identify the early warningindicator components more rapidly, the search classand LINQ methods are selected in this study.

    (2) Access to object properties: during use of the safetyrisk early warning system, several monitoring pointsare often required for each early warning indicator.To enable the system to identify the monitoringpoints and type of early warning monitoring indi-cator corresponding to each monitoring component,

    DM

    01

    DM

    02

    DM

    03

    DM

    04

    DM

    05D

    M06

    DM

    07D

    M08

    DM

    09

    DM

    10

    DM

    11

    DM

    12D

    M13

    DM

    14D

    M15

    DM

    16D

    M17

    DM

    18

    DM

    19

    DM

    20

    DM

    21D

    M22

    DM

    23D

    M24

    DM

    25

    DM

    26

    DM

    27

    DM

    28

    DM

    29

    DM

    30

    DM

    31

    NNorth half of the east square

    South half of the east square

    Figure 7: Distribution of automatic monitoring sections in the tunnels.

    Heightdifference

    Tunneldeformation

    Input layer

    Hidden layer

    Outputlayer

    ...Time

    ...

    ...

    ...

    ...

    ...

    Pit length

    Pit width

    Pit depth

    Figure 8: Network topology of the prediction model.

    Advances in Civil Engineering 7

  • the monitoring component in the Revit modelshould be described in detail according to thecomponent type properties, as shown in Figure 11. Inthis case, the monitored tunnel is divided into ninesections, each of which will present the maximumdeformation value in the section.

    (3) Modification of model parameters: the most im-portant feature of the BIM technology is to provide avisual means of browsing. To make full use of theadvantages of visualization in the safety risk earlywarning system, it is necessary to modify the modelparameters; the corresponding spatial position,color, and other appearance parameters of the modelare modified according to the monitoring data forthe variable factors, which allows the risks to bedirectly reflected in the BIM model.

    4.4.2. Integration of the Safety Risk Prediction Model.*e tunnel deformation prediction module based on the BPneural network and the safety risk assessment module areintegrated into the BIM-based early warning system with thehelp of computer language to improve the efficiency andaccuracy of the safety risk prediction. In the process ofcomputer realization, the tunnel deformation predictionmodule is divided into two parts: prediction model trainingand tunnel deformation prediction. *e first step is toimplement the prediction model based on the BP neuralnetwork into a computer language, train the model, andintegrate the model into the BIM platform. *en, theDataReader function is used to read the monitoring data in

    the database and input them into the trained predictionmodel to obtain the prediction results for the tunnel de-formation. *e third step is to read the prediction resultsinto the safety risk assessment module, evaluate the safetyrisk, and make a signal alarm to realize integration of thesafety risk prediction model.

    4.4.3. Operation of the Early Warning System. *emenu forthe safety risk early warning system is embedded in the“Windows” bar under the “View” menu in Navisworks. *esafety risk early warning system menu consists of two parts:the default function of the early warning system and thebrowsing function of early warning signals, as shown inFigure 12.

    To cope with different engineering environments anddifferent national or local standards, the threshold values ofdifferent indicators are preset in the early warning system toensure the safety risk assessment models run correctly, asshown in Figure 13.

    *e browsing function for the early warning signals isthe core function of the system. According to the descriptionin Section 4.3, the safety risk is divided into four levels,corresponding to safety risk warning signals shown in red,blue, yellow, and green from high to low risk. If a safetymanager wants to quickly check the specific safety risk signalof a tunnel section, he or she can select the section, click the“Early Warning System” menu, and input the latest data forthe variable factors based on a large amount of data enteredin the previous period (Figure 14). According to the earlywarning signals, the safety manager can then take corre-sponding risk countermeasures, as shown in Figure 15.

    For example, on 29 April 2016, the safety risk earlywarning system issued a red warning signal indicating“extreme risk”. When one red section was selected, the upliftdeformation exceeded the threshold value (Figure 15).According to the warning signal for the safety risk, corre-sponding countermeasures should be taken promptly toprevent a further increase in the risk.

    5. Discussion

    Predicting the deformation of adjacent existing metrotunnels caused by the construction of deep foundation pits isan important task. Although the conventional finite elementsimulation method is usually carried out before excavation,the environmental conditions of the excavation are oftendifferent from the ideal conditions determined by the nu-merical simulation method, which will introduce certainerrors, leading to serious safety problems, includingfatalities.

    Compared to some risk assessment methods with in-sufficient prediction accuracy [17] or timeliness [18], theabove case study demonstrates that the BP neural networkcan effectively solve this problem. *is method uses thevariable factors affecting the deformation of existing metrotunnels as input variables, and the existing deformation dataas the training signal, in order to integrate the internal lawfor the effect of the constant factors (or those with small

    Monitoring dataForecast data

    8.009.00

    10.0011.0012.0013.0014.0015.0016.00

    Upl

    ift d

    efor

    mat

    ion

    (mm

    )

    3.12

    3.15

    3.18

    3.21

    3.24

    3.27

    3.30

    4.02

    4.05

    4.08

    4.11

    4.14

    4.17

    4.20

    4.23

    4.26

    4.29

    5.02

    5.05

    5.08

    5.11

    5.14

    5.17

    5.20

    5.23

    5.26

    5.29

    3.09

    Excavation date

    Figure 9: Predicted and measured uplift deformation of tunnelsection DM12.

    Error

    –2.50–2.00–1.50–1.00–0.50

    0.000.501.001.502.002.50

    Erro

    r (m

    m)

    4.29

    5.02

    4.26

    4.23

    3.24

    3.27

    3.30

    4.11

    3.12

    5.05

    4.05

    4.14

    4.17

    4.20

    4.02

    3.21

    3.18

    3.15

    4.08

    5.08

    5.11

    5.14

    5.17

    5.20

    5.23

    5.26

    5.29

    3.09

    Excavation data

    Figure 10: Prediction error in the uplift deformation of tunnelsection DM12.

    8 Advances in Civil Engineering

  • changes) on tunnel deformation into the model. In addition,the BP neural network predictionmodel can also realize real-time prediction, thus providing data support for the earlywarning of safety risks.

    In the building of the BP prediction model, the design ofthe input and output neurons of the model is determined bythe number of input and output variables. *e numbers ofneurons in the input and output layers of this model are sixand four, respectively. For the number of hidden layers andthe number of neurons in each layer, because a three-layerBP network structure can complete anym-to n-dimensionalcomplex mapping, one hidden layer is used in the model,which can ensure effective operation and reduce the model

    complexity and calculations. Based on an empirical method,the approximate number of hidden layer neurons is initiallydetermined, and then the optimal number is determinedthrough trials. To balance the accuracy of each output valueand observe its advantages and disadvantages, the meansquared error of each output value is used as a referencestandard in the trial calculation. By changing the number ofneurons in the hidden layer, the mean square error of theoutput was at a minimum with 13 neurons in the hiddenlayer. *erefore, as a whole, the network structure of themodel was optimized.

    After establishing the network structure of the BPprediction model, through development with the API, the

    Figure 11: Revit component type parameter setting.

    Entrance

    Figure 12: Menu of the safety risk early warning system.

    Advances in Civil Engineering 9

  • Figure 14: Manual input interface for variable factors.

    Figure 13: Interface for the preset threshold values.

    Figure 15: Overview of risk indicators on 8 April.

    10 Advances in Civil Engineering

  • model is connected to the BIM-based early warning system.*e model is trained using samples taken from actualmonitoring data, and then the trained model is used topredict the deformation risk of the tunnels. Based on theprediction results of the model, the prediction accuracy cansatisfy the construction requirements.

    For common safety risk early warning systems [9, 10],when a safety risk occurs, the system can only provide a riskalarm, and it is difficult to visualize the safety risk. In thecase study, when the safety risk early warning system forexcavation adjacent to an existing metro tunnel is estab-lished, BIM is used as the data platform, which providessupport for visualizing the safety risk. When a safety risk isidentified, the system can provide visual outputs includingthe risk level, location, and other information, thus greatlyimproving the efficiency of the risk control decision-making.

    6. Conclusion

    *e excavation of a deep foundation pit will cause defor-mation of any adjacent existing metro tunnels. When thedeformation exceeds a certain range, it will create serioussafety risks for the metro operation. To effectively reducethis risk, a BP neural network prediction model is estab-lished in this study, and the proposed model can predict thedeformation of the existing metro tunnel in advance.

    To achieve effective real-time early warnings, this studyemploys the visualization characteristics of BIM, takes BIMas the data platform, and utilizes the .NET API interface andcorresponding information technology to carry out devel-opment in Navisworks. Four submodules (DMS, DPS,SRAS, and SREWS) are integrated into Navisworks, and anintelligent early warning system for the construction safetyrisk of deep excavations adjacent to existing metro tunnels isestablished.

    To validate the feasibility and effectiveness of the pro-posed system, this system is applied to predict the safety riskof the East Square excavation of the Zhengzhou high-speedrailway station adjacent to existing Metro 1 tunnel. *eaccuracy of short-term (more than 7 days) prediction ofsafety risks can reach 98% and the accuracy of long-term(more than 60 days) prediction can reach 92%. *e corre-sponding early warning signals can be simultaneously andaccurately presented in the BIM model. *e results pre-sented in this study demonstrate that this system can ac-curately predict the safety risk.

    Enacting the risk-based early warning system to reducethe on-site accident rate will require further research to beundertaken to simplify the information flow of the systemand optimize the system structure. Furthermore, we try touse control-based applications to access the API anddevelop an independent safety risk early warning system.In addition, although the remote monitoring datatransmission module has been integrated into the system,its application is not widespread in those excavationsadjacent to existing metro tunnels. It seems that thestability and accuracy of this module need to be furtherimproved.

    Data Availability

    Some data used to support the findings of this study areincluded within the article. All datasets generated during thecurrent study are not publicly available because the data alsoform part of an ongoing study but are available from thecorresponding author upon reasonable request.

    Conflicts of Interest

    *e authors declare that they have no conflicts of interest.

    Acknowledgments

    *e authors sincerely thank Zhengzhou TransportationConstruction Investment Co. Ltd. for providing data sup-port for this research. *is research was financially sup-ported by the Ministry of Housing and Urban-RuralDevelopment of China (Grant no. 2015-R3-003) and ChinaScholarship Council.

    References

    [1] R. Liang, W. Wu, F. Yu, G. Jiang, and J. Liu, “Simplifiedmethod for evaluating shield tunnel deformation due toadjacent excavation,” Tunnelling and Underground SpaceTechnology, vol. 71, pp. 94–105, 2018.

    [2] Z. Zhang, M. Huang, and W. Wang, “Evaluation of defor-mation response for adjacent tunnels due to soil unloading inexcavation engineering,” Tunnelling and Underground SpaceTechnology, vol. 38, pp. 244–253, 2013.

    [3] X. H. Deng, T. Xu, and R. Wang, “Risk evaluation model ofhighway tunnel portal construction based on BP fuzzy neuralnetwork,” Computational Intelligence and Neuroscience,vol. 2018, Article ID 8547313, 16 pages, 2018.

    [4] W. Fang, L. Ding, H. Luo, and P. E. D. Love, “Falls fromheights: a computer vision-based approach for safety harnessdetection,” Automation in Construction, vol. 91, pp. 53–61,2018.

    [5] M. Juszczyk and A. Lesniak, “ANN based approach for es-timation of construction costs of sports fields,” Complexity,vol. 2018, Article ID 7952434, 11 pages, 2018.

    [6] J. X. Lai, J. L. Qiu, and Z. H. Feng, “Prediction of soil deformationin tunnelling using Artificial neural networks,” ComputationalIntelligence and Neuroscience, vol. 2018, Article ID 6708183,16 pages, 2018.

    [7] W. Zheng, X. Y. Zhang, and Q. Lu, “A BHR compositenetwork-based visualization method for deformation risklevel of underground space,” Plos One, vol. 10, no. 5, Article IDe0127088, 2015.

    [8] M. S. Cao, L. X. Pan, Y. F. Gao et al., “Neural network en-semble-based parameter sensitivity analysis in civil engi-neering systems,”Neural Computing and Applications, vol. 28,no. 7, pp. 1583–1590, 2017.

    [9] N. Wang and M. Huang, “Deformation monitoring artificialneural network model of deep foundation pit considering theexcavation effect,” Journal of Shanghai Jiaotong University,vol. 43, no. 6, pp. 990–993, 2009.

    [10] L. Xu, T. J. Zhang, and Q. W. Ren, “Intelligent autofeedbackand safety early-warning for underground cavern engineeringduring construction based on BP neural network and FEM,”Mathematical Problems in Engineering, vol. 2015, Article ID873823, 8 pages, 2015.

    Advances in Civil Engineering 11

  • [11] R. Sacks, M. Treckmann, and O. Rozenfeld, “Visualization ofwork flow to support lean construction,” Journal of Con-struction Engineering and Management, vol. 135, no. 12,pp. 1307–1315, 2009.

    [12] U. Rüppel and K. Schatz, “Designing a BIM-based seriousgame for fire safety evacuation simulations,” Advanced En-gineering Informatics, vol. 25, no. 4, pp. 600–611, 2011.

    [13] M.-Y. Cheng, K.-C. Chiu, Y.-M. Hsieh, I.-T. Yang, J.-S. Chou,and Y.-W. Wu, “BIM integrated smart monitoring techniquefor building fire prevention and disaster relief,”Automation inConstruction, vol. 84, pp. 14–30, 2017.

    [14] Y. Zou, A. Kiviniemi, and S. W. Jones, “A review of riskmanagement through BIM and BIM-related technologies,”Safety Science, vol. 97, pp. 88–98, 2017.

    [15] M. Li, H. Yu, H. Jin, and P. Liu, “Methodologies of safety riskcontrol for China’s metro construction based on BIM,” SafetyScience, vol. 110, pp. 418–426, 2018.

    [16] W.-C. Cheng, Z.-P. Song, W. Tian, and Z.-F. Wang, “Shieldtunnel uplift and deformation characterisation: a case studyfrom Zhengzhou metro,” Tunnelling and Underground SpaceTechnology, vol. 79, pp. 83–95, 2018.

    [17] X. M. Zhang, X. F. Ou, J. S. Yang et al., “Deformation responseof an existing tunnel to upper excavation of foundation pitand associated dewatering,” International Journal of Geo-mechanics, vol. 17, no. 4, Article ID 04016112, 2017.

    [18] J. Y. Han, W. Zhao, P. J. Jia et al., “Risk analysis of the openingof shield-tunnel circumferential joints induced by adjacentdeep excavation,” Journal of Performance of ConstructedFacilities, vol. 32, no. 1, Article ID 04017123, 2018.

    12 Advances in Civil Engineering