integrated schedule risk analysis using jacs · integrated schedule risk analysis using jacs...

21
Integrated Schedule Risk Analysis using JACS Antonio Rippe 2017 NASA Cost and Schedule Symposium August 29 – 31 Washington, D.C.

Upload: others

Post on 12-Oct-2020

13 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Integrated Schedule Risk Analysis using JACS · Integrated Schedule Risk Analysis using JACS Antonio Rippe 2017 NASA Cost and Schedule Symposium August 29 –31 Washington, D.C

Integrated Schedule Risk Analysis using JACS

Antonio Rippe

2017 NASA Cost and Schedule Symposium

August 29 – 31

Washington, D.C.

Page 2: Integrated Schedule Risk Analysis using JACS · Integrated Schedule Risk Analysis using JACS Antonio Rippe 2017 NASA Cost and Schedule Symposium August 29 –31 Washington, D.C

Addressing the Paradoxical Elephant in the Room…

1) Integrating multiple programs that are simultaneously independent and highly dependent

2) Run a Schedule Risk Analysis (SRA) on the integrated product

3) Generate meaningful results and insights in timely manner

2017 NASA Cost and Schedule Symposium PRR#: 228

Problem

2

Page 3: Integrated Schedule Risk Analysis using JACS · Integrated Schedule Risk Analysis using JACS Antonio Rippe 2017 NASA Cost and Schedule Symposium August 29 –31 Washington, D.C

2017 NASA Cost and Schedule Symposium PRR#: 228

Setting the Stage – Three Programs

Crew Vehicle: Pegasus

Rocket: Launch System for Space (LSS)

Launch Center: Development & Operations of Ground Systems (DOGS)

Izzy

All names, characters, and incidents portrayed in this production are fictitious.

No identification with actual persons, places, buildings, and products is intended or should be inferred.

3

Page 4: Integrated Schedule Risk Analysis using JACS · Integrated Schedule Risk Analysis using JACS Antonio Rippe 2017 NASA Cost and Schedule Symposium August 29 –31 Washington, D.C

So, Why is This so Difficult?

2017 NASA Cost and Schedule Symposium

The question remains . . .

How do we integrate these programs and run an SRA on the integrated schedule?

PRR#: 228 4

Page 5: Integrated Schedule Risk Analysis using JACS · Integrated Schedule Risk Analysis using JACS Antonio Rippe 2017 NASA Cost and Schedule Symposium August 29 –31 Washington, D.C

Several Methods to Integrate Schedules

1. Integrate the IMS

2017 NASA Cost and Schedule Symposium 5PRR#: 228

Page 6: Integrated Schedule Risk Analysis using JACS · Integrated Schedule Risk Analysis using JACS Antonio Rippe 2017 NASA Cost and Schedule Symposium August 29 –31 Washington, D.C

Integrating the IMS

Pros: Holistic representation of the three programs

Cons: Data Collection

Time & Effort

2017 NASA Cost and Schedule Symposium

Usually leads to…

PRR#: 228 6

Page 7: Integrated Schedule Risk Analysis using JACS · Integrated Schedule Risk Analysis using JACS Antonio Rippe 2017 NASA Cost and Schedule Symposium August 29 –31 Washington, D.C

Several Methods to Integrate Schedules

1. Integrate the IMS

2. Integrating Summary Schedules

2017 NASA Cost and Schedule Symposium 7PRR#: 228

Page 8: Integrated Schedule Risk Analysis using JACS · Integrated Schedule Risk Analysis using JACS Antonio Rippe 2017 NASA Cost and Schedule Symposium August 29 –31 Washington, D.C

Integrating Summary Schedules

Pros: Timely

Summary Schedule size < IMS size

Cons: Summary Schedules hide effort required to accomplish program goals

Loss of ability to link activities between summary tasks

2017 NASA Cost and Schedule Symposium

?

Summary 1

PRR#: 228

Summary 2

Still dealing with multiple schedule platforms, which can lead to added effort and…

8

Page 9: Integrated Schedule Risk Analysis using JACS · Integrated Schedule Risk Analysis using JACS Antonio Rippe 2017 NASA Cost and Schedule Symposium August 29 –31 Washington, D.C

Several Methods to Integrate Schedules

1. Integrate the IMS

2. Integrating Summary Schedules

3. Milestone Schedule with Effort Filled In

2017 NASA Cost and Schedule Symposium 9PRR#: 228

Page 10: Integrated Schedule Risk Analysis using JACS · Integrated Schedule Risk Analysis using JACS Antonio Rippe 2017 NASA Cost and Schedule Symposium August 29 –31 Washington, D.C

Milestone Schedule with Effort Filled In

Pros: Timely

Higher detail than Summary Schedule while maintaining manageable schedule size

Cons: New schedule that requires consistent inputs from three independent

programs

Resulting activity may not represent the entirety of effort required

2017 NASA Cost and Schedule Symposium

Effort Task

A

B

C

D

E

F

G H

I

J

K

LMNOP

PRR#: 228 10

Page 11: Integrated Schedule Risk Analysis using JACS · Integrated Schedule Risk Analysis using JACS Antonio Rippe 2017 NASA Cost and Schedule Symposium August 29 –31 Washington, D.C

Several Methods to Integrate Schedules

1. Integrate the IMS

2. Integrating Summary Schedules

3. Milestone Schedule with Effort Filled In

Of the above, #3 is the most efficient approach

However, I believe we can do better…

2017 NASA Cost and Schedule Symposium 11PRR#: 228

Page 12: Integrated Schedule Risk Analysis using JACS · Integrated Schedule Risk Analysis using JACS Antonio Rippe 2017 NASA Cost and Schedule Symposium August 29 –31 Washington, D.C

The Secret Sauce – Analysis Schedules!

Displays major work-flows of a project

Provides insight into major cross-dependencies within or across management responsibility boundaries

Creates a solid framework for incorporating uncertainties and discrete risk events

Has traceability and transparency to detailed IMS

122017 NASA Cost and Schedule Symposium PRR#: 228

Page 13: Integrated Schedule Risk Analysis using JACS · Integrated Schedule Risk Analysis using JACS Antonio Rippe 2017 NASA Cost and Schedule Symposium August 29 –31 Washington, D.C

How Does an Analysis Schedule Help?

Creating and integrating three analysis schedules may be best approach, however time constraints prevent this approach

Instead, create one analysis schedule for integrator schedule

2017 NASA Cost and Schedule Symposium

DOGS Analysis Schedule

PRR#: 228 13

Page 14: Integrated Schedule Risk Analysis using JACS · Integrated Schedule Risk Analysis using JACS Antonio Rippe 2017 NASA Cost and Schedule Symposium August 29 –31 Washington, D.C

Process Overview

Analysis Schedule created of integrator schedule Uncertainty distributions and Discrete Risks modeled for integrator

schedule

Placeholders created in analysis schedule for deliveries from other programs

Advantages

Allows programs to use schedule platform of their choice

Allows programs to use SRA tool of their choice

Outputs needed as inputs into the model are universally provided by all SRA tools

2017 NASA Cost and Schedule Symposium 14PRR#: 228

Page 15: Integrated Schedule Risk Analysis using JACS · Integrated Schedule Risk Analysis using JACS Antonio Rippe 2017 NASA Cost and Schedule Symposium August 29 –31 Washington, D.C

Insights and Results

Integrated distribution of completion date With all programs contributing to risk-informed result

Risk ranking across the programs Drivers to integration points can be assessed by responsible program

assessing their result drivers

Additional insights can be obtained using JACS…

152017 NASA Cost and Schedule Symposium PRR#: 228

Page 16: Integrated Schedule Risk Analysis using JACS · Integrated Schedule Risk Analysis using JACS Antonio Rippe 2017 NASA Cost and Schedule Symposium August 29 –31 Washington, D.C

Joint Analysis of Cost and Schedule (JACS)

2017 NASA Cost and Schedule Symposium PRR#: 228

Microsoft Project add-in to facilitate SRA/JCLs

Define uncertainty distributions, correlations, and discrete risk events within the schedule environment

Why I chose JACS - Cache file is a treasure trove of dataBuilt in analysis and charts providing unique insights

16

Page 17: Integrated Schedule Risk Analysis using JACS · Integrated Schedule Risk Analysis using JACS Antonio Rippe 2017 NASA Cost and Schedule Symposium August 29 –31 Washington, D.C

Results on One Condition…

Results Conditioned on Criticality Allows for driver analysis based on the subset of simulation results in

which the task/risk lands on the critical path

Allows for focused analysis by concentrating on those tasks/risks that are driving the finish date

Risk Drivers Conditioned on Criticality

Probability of risk being on critical path

Average duration impact of risk when on critical path

172017 NASA Cost and Schedule Symposium PRR#: 228

Page 18: Integrated Schedule Risk Analysis using JACS · Integrated Schedule Risk Analysis using JACS Antonio Rippe 2017 NASA Cost and Schedule Symposium August 29 –31 Washington, D.C

Watch out for that RIFT!

Risk Informed Finish Threshold Provides a threshold for an individual task at which the probabilistic

project finish date will be maintained

“Allocation of probabilistic contingency” to predecessor tasks

RIFT dates provide objective metrics to manage the project on task-by-task basis in a way that ensures this probabilistic finish is on track or in danger of falling behind Assessment can be applied at integration points to evaluate threshold

of late delivery

2017 NASA Cost and Schedule Symposium PRR#: 228

http://www.iceaaonline.com/atl16papers/#RU-03

http://www.iceaaonline.com/pdx17papers/#EV05

18

Page 19: Integrated Schedule Risk Analysis using JACS · Integrated Schedule Risk Analysis using JACS Antonio Rippe 2017 NASA Cost and Schedule Symposium August 29 –31 Washington, D.C

Conclusion

Analysis schedule with integration touch-points is most efficient manner (in analyst’s opinion) to obtain integrated, risk-informed results

Timely, but is not instantaneous

Need IMS and risk data to be set before proceeding

Analysis schedule update/creation could be time-consuming… but worth it!

Comprehensive analysis of integrated impacts

Preserves logical linkages between tasks

Analysis Schedule highly suitable for Risk Analysis

No additional work needed for inputs to model

RIFT provides insights unique to JACS

192017 NASA Cost and Schedule Symposium PRR#: 228

Page 20: Integrated Schedule Risk Analysis using JACS · Integrated Schedule Risk Analysis using JACS Antonio Rippe 2017 NASA Cost and Schedule Symposium August 29 –31 Washington, D.C

QUESTIONS?

202017 NASA Cost and Schedule Symposium PRR#: 228

Page 21: Integrated Schedule Risk Analysis using JACS · Integrated Schedule Risk Analysis using JACS Antonio Rippe 2017 NASA Cost and Schedule Symposium August 29 –31 Washington, D.C

THANK YOU

Antonio [email protected]

[email protected]

212017 NASA Cost and Schedule Symposium PRR#: 228