instrumentation & control knowledge assessment test

102
HERVE BARON © 2015 – Hervé Baron Welcome to this assessment It will test your knowledge in Instrumentation & Control (I&C) mastery of the contents of Chapter 11 of The Guide 1 1 ”The Oil & Gas Engineering Guide”, Hervé Baron, Editions Technip, 2015 http://www.editionstechnip.com/fr/catalogue-detail/1111/oil-gas-engineering-guide-the.html Instrumentation & Control (I&C) knowledge assessment

Upload: herve-baron

Post on 10-Aug-2015

946 views

Category:

Education


3 download

TRANSCRIPT

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

PT JB

Process line

?

Equipment room Control room

System

cabinet

Operator

station

Please name this equipment

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

PT JB

Process line

Marshalling

cabinet Operator

station

System

cabinet

Equipment room Control room

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

PT JB

Process line

Please name this equipment

?

Operator

station

Marshalling

cabinet

Equipment room Control room

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

PT JB

Process line

Marshalling

cabinet System

cabinet Operator

station

Equipment room Control room

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

PT JB

Process line

Marshalling

cabinet System

cabinet

Equipment room Control room

Operator

station

In which cabinet are the I/O cards installed?

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

PT JB

Process line

Marshalling

cabinet System

cabinet

Equipment room Control room

Operator

station

In which cabinet are the I/O cards installed?

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

PT JB

Process line

Marshalling

cabinet System

cabinet

Equipment room Control room

Operator

station

In which cabinet are the controllers installed?

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

PT JB

Process line

Marshalling

cabinet

Equipment room Control room

Operator

station

In which cabinet are the controllers installed?

System

cabinet

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

PT JB

Process line

Marshalling

cabinet System

cabinet

Equipment room Control room

Operator

station

Is this a serial or hard wired link?

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

PT JB

Process line

Marshalling

cabinet System

cabinet

Equipment room Control room

Operator

station

Is this a serial or hard wired link? Hard wired (cross wiring)

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

PT JB

Process line

Marshalling

cabinet System

cabinet

Equipment room Control room

Operator

station

What do you call this cable?

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

PT JB

Process line

Marshalling

cabinet System

cabinet

Equipment room Control room

Operator

station

What do you call this cable? Secondary (or unit) cable

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

PT JB

Process line

Marshalling

cabinet System

cabinet

Equipment room Control room

Operator

station

What do you call this cable?

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

PT JB

Process line

Marshalling

cabinet System

cabinet

Equipment room Control room

Operator

station

What do you call this cable? Multi(core) cable

HERVE BARON

© 2015 – Hervé Baron

What do you call such a drawing?

HERVE BARON

© 2015 – Hervé Baron

What do you call such a drawing? System architecture drawing

HERVE BARON

© 2015 – Hervé Baron

The lead time of a control valve is 1) 3 months 2) 6 months 3) 9 months

HERVE BARON

© 2015 – Hervé Baron

The lead time of a control valve is 1) 3 months 2) 6 months 3) 9 months

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

The main schedule Milestones are the commitments to the Control System Contractor.

There are 2 commitments:

Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,

Software freeze, for the configuration (programming) of the system

In your opinion, which Milestone is reached first?

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

The main schedule Milestones are the commitments to the Control System Contractor.

There are 2 commitments:

Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,

Software freeze, for the configuration (programming) of the system

In your opinion, which Milestone is reached first?

Hardware freeze, for lead time of cabinets. Usually 3 months ahead of Software freeze.

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

The main schedule Milestones are the commitments to the Control System Contractor.

There are 2 commitments:

Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,

Software freeze, for the configuration (programming) of the system

Hardware freeze means instrument index freeze. Right or Wrong?

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

The main schedule Milestones are the commitments to the Control System Contractor.

There are 2 commitments:

Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,

Software freeze, for the configuration (programming) of the system

Hardware freeze means instrument index freeze. Right or Wrong?

Right: Instrument index 100% complete, i.e., number, type & location of instruments, including within packages for centrally controlled packages.

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

The main schedule Milestones are the commitments to the Control System Contractor.

There are 2 commitments:

Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,

Software freeze, for the configuration (programming) of the system

Which of the following documents are required to reach Hardware freeze? 1) Plot Plan 2) IFD P&IDs 3) IFC P&IDs 4) Control narratives 5) Safeguarding narratives and Cause & Effect diagrams 6) JB wiring diagrams 7) Packaged units sequence description and diagrams

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

The main schedule Milestones are the commitments to the Control System Contractor.

There are 2 commitments:

Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,

Software freeze, for the configuration (programming) of the system

Which of the following documents are required to reach Hardware freeze? 1) Plot Plan 2) IFD P&IDs 3) IFC P&IDs 4) Control narratives 5) Safeguarding narratives and Cause & Effect diagrams 6) JB wiring diagrams 7) Packaged units sequence description and diagrams

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

The main schedule Milestones are the commitments to the Control System Contractor.

There are 2 commitments:

Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,

Software freeze, for the configuration (programming) of the system

Which of the following documents are required to reach Software freeze? 1) Plot Plan 2) IFD P&IDs 3) IFC P&IDs 4) Control narratives 5) Safeguarding narratives and Cause & Effect diagrams 6) JB wiring diagrams 7) Packaged units sequence description and diagrams

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

The main schedule Milestones are the commitments to the Control System Contractor.

There are 2 commitments:

Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,

Software freeze, for the configuration (programming) of the system

Which of the following documents are required to reach Software freeze? 1) Plot Plan 2) IFD P&IDs 3) IFC P&IDs 4) Control narratives 5) Safeguarding narratives and Cause & Effect diagrams 6) JB wiring diagrams 7) Packaged units sequence description and diagrams

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

The main schedule Milestones are the commitments to the Control System Contractor.

There are 2 commitments:

Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,

Software freeze, for the configuration (programming) of the system

What is challenging to meet the schedule?

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

The main schedule Milestones are the commitments to the Control System Contractor.

There are 2 commitments:

Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,

Software freeze, for the configuration (programming) of the system

What is challenging to meet the schedule?

When control systems of machinery and packages engineered by Vendors are integrated in the Plant control system, the consolidation of information to be transfered to the Integrated Control System Supplier is complex and requires a specific schedule for on-time hardware & software Freeze.

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

What do you call such a drawing?

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

What do you call such a drawing? Logic analysis & grafcet

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

What do you call such a drawing? Logic analysis & grafcet Who issues it?

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

What do you call such a drawing? Logic analysis & grafcet Who issues it? Package vendors

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

A serial link is a continuous link. Right or Wrong?

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

A serial link is a continuous link. Right or Wrong?

Wrong

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

The following is adjusted at Site during commissioning/Start-Up:

1) settings of controllers (Proportional, Integral, Derivative)

2) Settings of alarms

3) Setting of trips

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

The following is adjusted at Site during commissioning/Start-Up:

1) settings of controllers (Proportional, Integral, Derivative)

2) Settings of alarms

3) Setting of trips

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

What is a serial link?

1) a sequential communication regulated by a protocole,

2) a parallel link,

3) a point-to-point connection,

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

What is a serial link?

1) a sequential communication regulated by a protocole,

2) a parallel link,

3) a point-to-point connection,

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

What does IP level of electrical and instrumentation equipment stand for?

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

What does IP level of electrical and instrumentation equipment stand for?

Ingress Protection. It means mechanical protection and protection again ingress of water, dust etc. Reference code is IEC 60529 "Degree of Protection provided by enclosures". Typically a certain IP level is specified for outdoor equipment and another one for indoor equipment.

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

What do you call the drawing showing all details of wiring, terminations and inter-connections from primary to final element?

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

What do you call the drawing showing all details of wiring, terminations and inter-connections from primary to final element?

The loop diagram

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

Which documents from a packaged equipment Vendor are critical for instrumentation & Control discipline?

1) General Arrangement

2) P&IDs

3) Instrument index, I/O list

4) Junction boxes drawings

5) C&E diagrams

6) hook-up drawings

7) cable routing drawings

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

Which documents from a packaged equipment Vendor are critical for instrumentation & Control discipline?

1) General Arrangement

2) P&IDs

3) Instrument index, I/O list

4) Junction boxes drawings

5) C&E diagrams

6) hook-up drawings

7) cable routing drawings

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

Where are located the main processors of a Process Control System?

1) in the workstation in the control room

2) in the system cabinets in the technical rooms

3) in the marshalling cabinet in the technical rooms

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

Where are located the main processors of a Process Control System?

1) in the workstation in the control room

2) in the system cabinets in the technical rooms

3) in the marshalling cabinet in the technical rooms

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

Process discipline issues "Process Data sheets" and Instrumentation discipline issues "Mechanical data sheets" of instruments. Right or Wrong?

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

Process discipline issues "Process Data sheets" and Instrumentation discipline issues "Mechanical data sheets" of instruments. Right or Wrong?

Right, Instrument data sheets include mechanical data from Piping

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

Pressure gauge/transmitters are fitted a diaphragm seals in case of:

1) low pressure

2) high pressure

3) liquid service

4) risk of plugging of impulse line/instrument

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

Pressure gauge/transmitters are fitted a diaphragm seals in case of:

1) low pressure

2) high pressure

3) liquid service

4) risk of plugging of impulse line/instrument

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

In which document(s) are the set points of process controllers indicated?

1) Process description

2) Instrument list

3) Instrument data sheet

4) Operating Manual

5) Process Flow Diagrams

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

In which document(s) are the set points of process controllers indicated?

1) Process description

2) Instrument list

3) Instrument data sheet

4) Operating Manual

5) Process Flow Diagrams

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

The low low level instrument is part of which system:

1) Process Control System (DCS)

2) Safety Instrumented System (SIS)

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

The low low level instrument is part of which system:

1) Process Control System (DCS)

2) Safety Instrumented System (SIS)

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

The Safety Instrumented System (SIS) includes

1) The ESD system

2) The PSD system

3) The F&G system

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

The Safety Instrumented System (SIS) includes

1) The ESD system

2) The PSD system

3) The F&G system

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

A single equipment shutdown is performed by

1) The ESD system

2) The Process Control system

3) The PSD system

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

A single equipment shutdown is performed by

1) The ESD system

2) The Process Control system

3) The PSD system

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

Hardwired logic is non-programmable. Right or Wrong?

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

Hardwired logic is non-programmable. Right or Wrong?

Right

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

Remote Terminal Units (RTU) are local control stations. Right or wrong?

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

Remote Terminal Units (RTU) are local control stations. Right or wrong?

Right

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

Which segregation is made between signals (different JBs)?

1) Control / Shutdown

2) Analog / Digital

3) IS/non-IS

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

Which segregation is made between signals (different JBs)?

1) Control / Shutdown

2) Analog / Digital

3) IS/non-IS

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

To which of the following is a package PLC normally connected?

1) DCS

2) MCC

3) PDCS

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

To which of the following is a package PLC normally connected?

1) DCS

2) MCC

3) PDCS

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

By which system are these valves controlled? 1) The Process Shutdown System (PSD)? 2) The Emergency Shutdown System (ESD)? 3) Process Control System (DCS)?

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

By which system are these valves controlled? 1) The Process Shutdown System (PSD)? 2) The Emergency Shutdown System (ESD)? 3) Process Control System (DCS)?

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

By which system are these valves controlled? 1) The Process Shutdown System (PSD)? 2) The Emergency Shutdown System (ESD)? 3) Process Control System (DCS)?

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

By which system are these valves controlled? 1) The Process Shutdown System (PSD)? 2) The Emergency Shutdown System (ESD)? 3) Process Control System (DCS)?

HERVE BARON

© 2015 – Hervé Baron

I&C knowledge assessment test

That’s all for now folks, but I won’t be long with tests on knowledge acquisition for the other chapters of the guide…

HERVE BARON

© 2015 – Hervé Baron

The Oil & Gas Engineering Guide - 2nd edition

Table of Contents

HERVE BARON

© 2015 – Hervé Baron

The Oil & Gas Engineering Guide - 2nd edition

Discipline presentation: activities and deliverables

Table of Contents

The overall process

Methods & tools

HERVE BARON

© 2015 – Hervé Baron

The Oil & Gas Engineering Guide - 2nd edition

Table of Contents

Discipline presentation: activities and deliverables

HERVE BARON

© 2015 – Hervé Baron

The work of each Engineering

discipline is described

HERVE BARON

© 2015 – Hervé Baron

Design activities are explained, e.g., Plant

Equipment layout

HERVE BARON

© 2015 – Hervé Baron

Complex activities, such as

QRA, are explained through a practical example.

HERVE BARON

© 2015 – Hervé Baron

How are materials of

construction selected ?

HERVE BARON

© 2015 – Hervé Baron

How and when are Piping

Materials ordered?

HERVE BARON

© 2015 – Hervé Baron

A sample of all common Engineering documents is

included

HERVE BARON

© 2015 – Hervé Baron

A sample of all common Engineering documents is

included

Use this to specify what you

want to your Engineering supplier !

HERVE BARON

© 2015 – Hervé Baron

Verify the contents of

engineering documents with check lists.

HERVE BARON

© 2015 – Hervé Baron

Difference between

Engineering and Shop drawings

HERVE BARON

© 2015 – Hervé Baron

Understand the main

technical aspects, e.g., DCS vs ESD

HERVE BARON

© 2015 – Hervé Baron

The common 2 types of

package control

HERVE BARON

© 2015 – Hervé Baron

The different Plant drainage

systems

HERVE BARON

© 2015 – Hervé Baron

The dynamic forces to

which an Off-Shore Plant is subject

HERVE BARON

© 2015 – Hervé Baron

The Oil & Gas Engineering Guide - 2nd edition

Table of Contents

The overall process

HERVE BARON

© 2015 – Hervé Baron

Use this as standard, question deviations.

HERVE BARON

© 2015 – Hervé Baron

Understand the new 3D-model centered engineering process

HERVE BARON

© 2015 – Hervé Baron

Know the interfaces

between disciplines... and with Vendors

HERVE BARON

© 2015 – Hervé Baron

Understand what drives

the Project schedule

HERVE BARON

© 2015 – Hervé Baron

The Oil & Gas Engineering Guide - 2nd edition

Table of Contents

Methods & tools

HERVE BARON

© 2015 – Hervé Baron

Use these methods as

standard, question deviations.

HERVE BARON

© 2015 – Hervé Baron

Implement powerful

procedures

HERVE BARON

© 2015 – Hervé Baron

Request meaningful progress

reports

HERVE BARON

© 2015 – Hervé Baron

Implement effective Project

Control

HERVE BARON

© 2015 – Hervé Baron

The Oil & Gas Engineering Guide - 2nd edition

This book is destined to both:

Oil & Gas companies Project execution personnel

Oil & Gas contractors Project execution personnel

Date of publication: March, 2015.

HERVE BARON

© 2015 – Hervé Baron

The Oil & Gas Engineering Guide 2nd edition

If your are on the Client side, i.e., contracting Engineering services, this book will help you to:

Specify to an Engineering supplier what you want: what deliverables and with what contents,

Set a standard in Engineering execution that you and your supplier can adhere to: design stages/gates, methods to be used, etc.

Specify the progress report you want, with the meaningful indicators,

Ask the right questions to assess the true progress,

HERVE BARON

© 2015 – Hervé Baron

The Oil & Gas Engineering Guide 2nd edition

If your are on the Contractor side, i.e., performing Engineering activities, this book will help you to:

Understand the work of each discipline and the overall picture,

Challenge what one discipline tells you,

Understand the critical areas,

Put in place the right methods to be successful,

HERVE BARON

© 2015 – Hervé Baron

The Oil & Gas Engineering Guide 2nd edition

Order from the publisher:

http://www.editionstechnip.com/en/catalogue-detail/1111/oil-gas-engineering-guide-the.html

Or on Amazon:

http://www.amazon.com/Oil-Gas-Engineering-Guide-2ND/dp/2710811510/ref=sr_1_1?ie=UTF8&qid=1437160937&sr=8-1&keywords=the+oil+and+gas+engineering+guide