installation step 4. (3 days)
DESCRIPTION
Installation step 4. (3 days). B. A. A. Install temporary support It’s made of 2 halves; the upper one is brought into position through rotation about axis “A” (to avoid risks for the beam pipe) - PowerPoint PPT PresentationTRANSCRIPT
Installation Review
March ‘03
F.Tosello, L.Simonetti – INFN Torino1
Install temporary support It’s made of 2 halves; the upper
one is brought into position through rotation about axis “A” (to avoid risks for the beam pipe)
It has 4 flaps (“B”) at ±45º for fixation of beam-pipe and SPD supports prior to transfer their load to ITS
Align (survey) temporary support to the beam pipe
A
BInstallation step 4. (3 days)
A
Installation Review
March ‘03
F.Tosello, L.Simonetti – INFN Torino2Dummy 3rd cone
FMD – Si1
Installation step 5. (4 days)Fix support for beam pipe and
FMD (“3rd cone”) to temporary support The 3rd cone is made of two
halves containing the FMDs lifting tools allow for slow and
accurate positioning of 3rd cone Spoke structure reduces
material in front of FMDs and allows for visual inspection
Test FMDs FMDs have pigtails up to the
outer edge of the 3rd cone
Lifting tool
Remove 3rd cone lifting tools
Installation Review
March ‘03
F.Tosello, L.Simonetti – INFN Torino3
Installation step 6. (2 days)
Lifting tool
First Beam Pipe Support
Mount and adjust monitoring system of bellow movements Responsibility ALICE Non-touching capacitive sensors
are proposed
Bellows
FlangesDetectors
Beam Pipe Support Adjustment
Third cone FA Mount and adjust 1st
support to the beam pipe Responsibility AT/VAC Survey
Installation Review
March ‘03
F.Tosello, L.Simonetti – INFN Torino4
Section 2 Install the two SPD half-
cylinders (Resp. ALICE) Two half cylinder/cones Specific installation tools
are being designed SPD services (cables,
fibres & capillaries) are pre-assembled in the cones
SPD services
Remove section 2 of beam pipe support (Resp. AT/VAC)
Installation step 7. (8 days)
Fix the two, coupled, SPD half-cylinders to temp. support, above the 3rd cone, using a 2nd series of bolts & precision plugs
SPD fixed in cantilever mode to temp. support, SPD pigtails on RB24 side unconnected
3rd cone
SPD cone
Temporary support
Installation Review
March ‘03
F.Tosello, L.Simonetti – INFN Torino5
Slide outer ITS onto SPDs (Responsibility ALICE) Transfer load of SPD and 3rd cone (beam pipe) from temporary support to ITS
Installation step 8. (7 days)
Mount and adjust 2nd support to the beam pipe (resp. AT/VAC) Survey
Outer ITS, SPD & beam pipe are now an integral unit
TPC/C4
Temp.Support
SPD
SDDSSD
Connect SDD and SSD on RB26 sideFinal fixation of SPD pigtails on RB24
side to ITS cone