Installation status
Control RoomPC farm room
Detectors EB
Infrastructure
918
ECN3
A lot of activity!
It’s a fake!
PC farm room
JuraSaleve
Old System
Router
PC farm room
• The first two PC (Mainz PC) are installed problem for remote configuration in the old NA48 network
• The 4 additional PCs have been ordered three days ago, due to a burocratic problem
• Jonas will arrive the 2/7
Mainz PCs
PC farm room
• In the twiki you can find a proposal for IP numbering for each switch and sub-net
• The network is working!
• The configuration will be completed soon (before the end of the week)
PC Farm Room: Questions
• What is the status of the Merger PC HW? When it will be installed?
• What is the status of the CDR (HW and SW)?• What about the “light version” of the Jonas
program? It’s easy to do or it’s better to resume the old TELL1 DAQ software?
• …
Control Room
Control Room
Control Room
• DCS User Interface PC ready• 11 monitors ordered• 3 PC for DAQ ordered (delivery foreseen next
week)• The furniture will be installed next week• HVAC, power, etc. will be finish for the
beginning of the Dry Run: no activity foreseen at the moment in the 918 during the dry run.
Control Room• A CAD PC will be
installed in the CR. • Some doubt about the
possibility to access to the licenses server
• Workaround: use the CAD software on centralized Virtual Machine
• Instructions on twiki
Control Room
• July 10th we will do a first test for the run Control
• The run control will run on a PC in the CCR: some issue about the interaction of the TN with our config network will be fixed in the next days.
• Online Monitor: Antonio is working, but still we need the Merger PC to run the Online Monitor.
Control Room: Questions
• Proposal for ELOG?• …
Infrastructure
Optical splitters
Choke/error panel
Patch panels
DSS
Switch
STRAW-02 CEDAR-01
Infrastructure
LAV-03 LAV-01
Infrastructure
• The path cords, patch cables and remaining parts will arrive this week (and will be installed next week)
• Small issue with the power in the racks
RICH-01
IRC-01
Infrastructure• Not all the
optical splitters have been installed
• The switches have been installed and will be tested in the next days
Infrastructure
EB36
StarPoint
Infrastructure
• L0TP primitive cables: almost done• Choke/error cables: almost done• TTC fibers: almost done• Network fibers: almost done
Infrastructure: Questions
• What is the status of the CHEF board?• Choke/error adaptor?• When the Can Bus will be available?
Electronics Barrack
Electronics Barrack• Marian already prepared a crate with all the
LTU we need• Next Friday Andrea will install the LKR/L0 TEL62
crate• The TALK board will be installed in the week of
July 9.• We had a HW problem with the TIMING PC. We
have a new PC ready to be tested (Riccardo)
Electronics Barrack: Questions
• When and where the CCPC server will be installed?
• Which kind of preliminary test are you planning before the dry run with the TALK board?
• Is the clock already installed?• …
Detectors
Detectors
• TEL62 & TDCB documentation already available on twiki
• Information about the hardware status are available on twiki (for instance the cables)
Detectors
• The TEL62 cables support prototype will be build by Tonio in the next days
Detectors: Questions
• TEL62:– Which is the status of the TEL62 HW?– Which is the status of the TEL62 FW?
• TDCB:– Which is the status of the TDCB HW?– Which is the status of the TDCB FW?
Detectors: Questions
• CEDAR:– Which is the status of the test for the NINO
boards?• CHANTI:– Which is the status of the Chanti board?– When are you planning to install the detector?
• LAV:– Are you planning to help the other detectors for
the board installation?
Detectors: Questions
• CHOD: – When are you planning to install the FE electronics?
• LKr:– Which is the status of the SLM readout?– Which is the status of the trigger distribution system?
• MUV2 & MUV3– Which is the status of the TRAM board?– When the CFD will be installed?– How the cabling of the MUV2/3 will influence the dry
run?
Detectors: Questions
• STRAW:– The VME readout will be installed during the dry
run?– When?
• SAC– When the SAC cabling will be done?– Since the SAC electronics is in “common” with the
MUV electronics, how the resources sharing will be “managed” during the dry run?
Next meetings
• 4 July: no meeting• 11 July: Summary
Useful numbers:Gianluca: 163714Riccardo: 160619