BEFORE INSTALL THE NEW BULKHEAD ( REMOVE THE EXISTING LONG. BULKHEAD 13.3M off C.L )WITHOUT CUT MAINDECK FOR ACCESS )

Condition : Full Ballast, Empty Oil. ( IN FLOAT CONDITION )

Result : Acceptable under Allowable Stress 355 x 0.8 = 284 MPA ( 279 MPA )INSTALL HALF THE NEW BULKHEAD FOR REINFORCEMENT ( REMOVE THE EXISTING LONG. BULKHEAD 13.3M off C.L ) WITHOUT CUT MAINDECK FOR ACCESS )

Condition : Full Ballast, Empty Oil. ( IN FLOAT CONDITION )

Result : Acceptable under Allowable Stress 355 x 0.8 = 284 MPA ( 239 MPA )