Project NameMSC Corporate Headquarters
Project LocationDavidson, North Carolina
Project TeamOwner: MSC Industrial Supply Co.General Contractor: ChoateConstruction Company
Commercial OfficesMarkets
Architect: Rule Joy Trammel + Rubio
Specializations
Pipe Shop PrefabDesign/Assist
Engineer: Barrett, Woodyard& Associates, Inc.
Sheet Metal Shop Prefab
McKenney’s provided design/assist services and installed a condenser water cooling system and controls at MSC’s new corporate headquarters in North Carolina.
The ChallengeThe McKenney’s team had to maintain a tight budget and meet an aggressive five-month installation schedule including the entire upfit in the new commercial office building—before precast panels blocked the team. The job was won based on the design/assist experience of the McKenney’s team which also had to prove it could seamlessly execute the installation.
The SolutionTo stay on track and within budget, McKenney’s expedited approval of shop drawings to ensure everything was coordinated ahead of precast panel installation. In lieu of a buckhoist, a unique “trailer flying” approach was used to efficiently lift materials, pipe, duct prefab and equipment to each elevated slab during the rough-in phases. McKenney’s also fabricated all the sheet metal and used grooved piping to speed up pipe installation.
The content of this document is not intended as an endorsement.
The ResultsMcKenney’s used its design/assist knowledge and unique installation capabilities to fast track the job and allowed MSC to move in on schedule.