installation and maintenance micro 10 - xylem applied...
TRANSCRIPT
Installation and Maintenance
Micro 10 Polyethylene packaged pumping stationfor lifting waste water
3
FOREWORD
This manual must remain available close
to the machine/installation. All work carried
out must be undertaken by professional
personnel. Current national regulations and
local safety and hygiene requirements must
be complied with.
Disclaimer
Design modifications may have been carried
out on technical characteristics. In conse-
quence, the product as supplied may differ
from the illustrations and information con-
tained in this manual. Copying, transcription,
translation and any other form of reproduc-
tion of this manual are only authorised with
prior written agreement by the manufacturer.
This stipulation also applies to passages ex-
tracted from the text.
TABLE OF CONTENTS
Safety
Guarantee
Technical Characteristics
Transportation, unloading and storage
Installation
Cam locking mechanism option
Electrical connection
Maintenance
General Arrangement
List of spare parts
Declaration of conformity
467910131414151617
4
SAFETY
Security instructions to be followed bythe operator / user Current national regulations and local safety
and hygiene requirements must be complied
with. All danger of electrocution must be
avoided (for more detailed information,
please consult the regulations drawn up by
the local electricity supplier).
Modifications to the pumping station anduse of spare parts. No modifications to equipment and its instal-
lation may be carried out without prior con-
sultation with the ITT Lowara company. In
order to guarantee the performance of the
equipment it is essential to use original spare
parts or accessories authorised by the man-
ufacturer. Use of other spare parts may in-
validate any claims on the basis of the
guarantee or requests for compensation.
Disassembly and reassembly During maintenance of the pumping station
(for example, draining), it is crucial to avoid
endangering persons and/or the environ-
ment.
All refuse and waste (e.g. grey cooling liquid)
must be handled in an appropriate manner in
order to avoid harm to the environment.
The lifting equipment must be constantly
kept clean and in normal working order.
All applicable regulations must be adhered to.
Because of the nature and
level of performance
required for the equipment,
noise levels may reach
70 dB.
This manual contains essential information
on installation, operation and maintenance.
These instructions must be meticulously fol-
lowed. Installation and maintenance person-
nel must read these instructions carefully
before installation and commencing opera-
tion of the pumping station. This installation
and maintenance manual must be available
at the pumping station site at all times.
Safety and warning pictograms used inthis manual.
Danger of death
This pictogram is a reminder
that any failure to respect
the safety instructions set
out in this manual may have
fatal consequences.
High voltage
This pictogram indicates that
there is a risk of electrocution.
WARNING! Failure to heed this warning
may cause damage to
equipment or affect its
operation.
Personnel qualifications
Work must be carried out exclusively by
qualified personnel.
5
DANGER (Gas, dust, fumes, smoke)
Before any work on the
equipment, authorisation
must be obtained.
Gases may form within the
pumping station and
compliance with specific
rules for installation in an
explosive environment is
imperative.
Welding, cutting by means of a blowtorch,
or grinding present real risks of fire and/or
explosion.
For these operations, carefully remove in-
flammable dust or materials present in the
work area and the surrounding space. Be
careful to ensure sufficient ventilation (risk
of explosion).
SAFETY
Safety instructions The rules set out below must be scrupu-
lously adhered to in order to reduce accident
risks during servicing, installation and main-
tenance.
- Ensure that electrical equipment is discon
nected from the power supply and cannot
be reconnected inadvertently.
- Never work alone. During any work on the
interior of the pumping station, beware of
harmful gases and make systematic use
of a safety harness and rope as well as
breathing apparatus. Do not under-esti
mate the risks of drowning!
- Compy with local regulations for working
in confined spaces.
- Monitor the absence of toxic gases within
the work area.
- Do not under-estimate health risks.
Meticulously ensure that equipment is
clean.
- Beware of electrocution risks.
- Ensure that lifting equipment is in perfect
condition.
- Install appropriate barriers around the
work area, for example a security rail.
- Ensure that there is a safe exit route in
case of emergency.
- Wear a safety helmet, goggles and shoes.
- All persons working within sewage
facilities must be vaccinated against any
diseases which may develop there.
- A First Aid kit must be permanently
available near the facility.
- Comply with local safety instructions.
- Systematically re-close and lock the cover
before leaving the pumping station.
6
This guarantee does not therefore apply to
defects resulting from lack of maintenance,
inappropriate installation, repairs incorrectly
carried out or normal wear and tear.
Lowara moreover declines any responsibility
in the case of physical injuries, or material or
economic damages if the above mentioned
conditions have not been
respected.
Lowara guarantees supply of spare parts for
fifteen years following the termination of
manufacture of the product.
For any claims concerning a guarantee, con-
tact your nearest Lowara Representative
who will provide full information.
.
GUARANTEE
Lowara undertakes to remedy any defect
which may be presented by the products
sold by their intermediary subject to:
- The defect resulting from a design,
materials or manufacturing fault
- It being reported to Lowara or to the
local ITT Lowaraagency within the
guarantee period
- The product having been installed and
operated in compliance with the
instructions in this installation and
maintenance manual, and solely for the
applications for which it is intended
- The electrical surveillance equipment for
the pumping station has been correctly
installed and is in service
- All maintenance and repair works having
been entrusted to a service centre
approved by Lowara
- Only original Lowara spare parts are
used.
Location of series number
7
Weight Micro 10 1300 mm 130 Kg
Micro 10 2000 mm DN 50 150 Kg
Micro 10 2000 mm DN 65 210 Kg
Riser 350 mm 23 Kg
Total weight without pumps
Volume of tank (litres) Micro 10 1300 mm 1200 L
Micro 10 2,000 mm 1900 L
Pump DN50 DN 65
Refer to pump installation manual
Fuse boxRefer to instructions supplied with this equipment.
TECHNICAL CHARACTERISTICS
Applications The Micro 10 is delivered completely assem-
bled and ready to be put into service.
This pumping station is intended for pumping
raw sewage, black water with or without par-
ticles or fecal matter (bathroom and toilet fa-
cilities, WC, showers, kitchens), water
loaded with fabric, fibres or straw, slops,
rainwater or wastewater, discharged by:
Individual dwelling Collective dwelling
Housing development Campsite Hotel
Muncipal showers Restaurant kitchen
Sports complexes Milking parlour
Livestock pen Abattoir
Equipment The pumping station is delivered already
equipped with the following items:
1. Cover
2. Internal gates and tubing
3. Pump glands
4. Inlet gasket
Important Pumps, fuse box, levels controllers, chains
and shackles are delivered separately.
Temperature of pumped liquid: 35°C Max.
Depth of excavation: 2.7 m Max.
External constraints The pumping station is designed for a water
table which may reach ground level. The
pumping station must be installed in such a
way that loads caused by vehicular traffic are
not felt less than 1.0 metre from the edge of
the pumping station.
Tank and cover materials The Micro 10 tank is manufactured from ro-
tationally-molded polyethylene .
Guide bar materials A2 Stainless Steel
Pipework materials PVC DN 50 or DN 65 discharge pipes
Inlet to be drilled for pipe Ø 160(mm) ext.
The pumping station is not
intended for use in an
explosive environment or
for inflammable liquids
8
TECHNICAL CHARACTERISTICS
The pumping station is not
intended for use in an
explosive environment or
for inflammable liquids
PUMPS
DXGM 25-11
DXVM 50-11
DXVM 50-7
DXM 50-7
DP 3045 MT 234
DP 3057 MT 238
CP 3057 MT 264
DXG 25-11
DXV 50-7
DXV 50-15
DP 3057 MT 232
DXVM 50-11
DXVM 50-7
DXM 50-7
DP 3045 MT 234
DP 3057 MT 238
CP 3057 MT 264
DXV 50-7
DXV 50-15
DP 3057 MT 232
DP 8022 MT 215
DP 8022 MT 211
DP 8022 MT 208
ø DISCHARGE
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
65
65
65
REFERENCE
58 60 670
58 60 210
58 60 900
58 60 240
58 60 170
58 60 190
58 60 200
58 60 680
58 60 230
58 60 220
58 60 180
58 60 370
58 60 910
58 60,400
58 60 340
58 60 350
58 60 360
58 60 390
58 60 380
58 60 330
58 60 510
58 60 500
58 60 490
BOX
CPEM Z BOX
BOX CPEM Z
BOX
COMMANDER
MICRO
10 1300
MICRO
10 2000
9
TECHNICAL CHARACTERISTICS
Figure 1. Dimensions(Dimensions in mm)
Opening Ø 800
Opening Ø 800
460 <
F.E
.A <
75
0 D
rilli
ng
fo
r in
let Ø
16
0
460 <
F.E
.A <
14
50
Drilli
ng
fo
r in
let Ø
16
0
Checks:
Before installation or storage, check that the
Polyethylene tank and internal pipework are
in proper working order.
principle
Use both lifting handles to raise the pumping
station and place it in the pit.
Storage
Outdoor storage periods must not exceed
four months and the tank must be covered
(for example by a tarpaulin).
TRANSPORT, UNLOADING AND STORAGE
Transport:
1. Ensure the tank never comes into contact
with sharp edges.
2. Protect the tank from impacts.
Loading and unloading:
1. Carry out loading and unloading
operations with the greatest care.
2. Ensure that the pumpstation is unloaded
from the lorry by means of appropriate
lifting equipment.
3. Always use lifting slings with the correct
dimensions (reminder: maximum weight of
tank is 180 kg).
10
Filling: Important: during filling, ensure that the tank
is vertical.
Fill material must have a granulosity of be-
tween 2 and 36 mm. Filling must be carried
out before the water table surface reaches
the top of the fill material.
1) Spread a layer of fill material 300 mm
thick (B) Compact and level the surface, then
place the Micro 10 tank on top.
2) Add a layer of fill up to a minimum height
of 700 mm.
Compact in successive layers with a maxi-
mum thickness of 50 mm.
Fill of the upper part (C) must not contain
stones more than 50 mm. in calibre.
Water table: Figure 2B
In the case of difficult surfaces (impermeable
or clayey) or of ground water, the bottom of
the pit must consist of a concrete base 0.20
metres thick.
Concrete ballasting must be poured around
the pumping station
INSTALLATION
Installation of the pumping station is always
under the entire responsibility of the firm in
charge of the installation. General informa-
tion and instructions in accordance with EN
976-2:1997
Warning: Never install pumps before covering the tank
with earth.
Installation in the groundThe pumpstation is designed to resist
stresses linked to the presence of a water
table flush with ground level.
The pumping station must not be installed in
soil composed of peat. When the pumpsta-
tion is installed in soil which is argillaceous
(clayey) , granular, or silty, a geotextile fabric
must be laid over all excavation surfaces.
The geotextile fabric prevents the fill material
from becoming mixed with the soil (A).
Excavation dimensions: 1) Depth: 300 mm greater than the level in-
tended for installation.
2) Width: two metres greater than the pump-
station.
Fig 2 Fig 2B
CONCRETE BASE
Version Height (mm) Ø of concrete base Approximate volume of concrete (m3)
MICRO 10 Between
2000 and 2700 1,8 m 1,4
MICRO 10 Between
1300 and 1650 1,8 m 0.9
Note: Dimensions indicated In figures 2 and 2B are minimum dimensions
Remarks
Soil analysis MUST BE CARRIED OUT for all pumpstations and must comply
with DTU 64-1 and the Order of 6th May 1996.
11
INSTALLATION
Connection of inlet pipe (fig 2) • Fix the self-adhesive drill former on the drill
area (flat piece shown)
• Drill the tank with a jigsaw or similar
• Fit gasket Ø160
• Chamfer exterior of tube Ø160
• Pass the tube through the gasket
Connection of discharge pipe Connect the pump discharge pipe to the net-
work pipe with the PVC threaded/smooth fix-it
coupling (fig. 3)
Use of a flexible pipe fitting between the pump-
station and the network pipe is recommended in
order to avoid stresses or breakage of piping
due to any ground compaction.
Passing cabling through (fig. 4) In the upper part of the flat delivery input drilling
area is the assembly location for the two pump
glands.
Pass the cables through these pump glands.
Ensure that sufficient length of cable is left for
any subsequent work on the pump.
Note: Separate the earth cable from the live cable on
the pump.
Above the hooks for the regulators, in the flat
area, is the assembly area for the pump glands
for the level regulators.
Pass the cables through the pump glands.
Ensure that sufficient length of cable is avail-
able. Adjust the length and hook the cables
over their hook.
Hooks for supporting chains (pumps) (fig. 5)
The hooks are located on the stainless steel
cross-beam.
There are 2 small folded lugs on the cross
beam which enable the chains to be hookedup
(fig. 5).
Tank
Tube
Gasket
Fig 2
Fig 3
Fig 4
Fig 5
Glands for level regulators
Pump glands
Hooks
12
INSTALLATION
Ventilation Ventilation
This can be mounted on the upper part of one
of the two flat pieces
1. Drill a hole of the same dimensions as your
ventilation pipe.
2. Connect the ventilation duct using a gasket
(equipment not provided) (fig 6)
Note:
Ventilation duct and electrical connections
must be installed inside separate sheaths
The gasket The access point cover gasket is made of foam,
with a self-adhesive rectangular section.
This gasket is mounted fixed to the lower part of
the access point cover.
Tightness is achieved when the access point
cover is clamped over the tank.
Ensure a minimum of two full turns in order to
achieve perfect tightness.
Riser The riser is screwed on the upper part of the
tank in the place normally occupied by the
cover. The cover is then screwed to the upper
part of the riser
Up to two may be fitted (Fig. 8)
Figure 5. Angular position of hook on riser.
Ground rod and earth strap (optional)
Hook the earth strap between the guide bar support
and the cross beam
Pump Installation
Refer to instructions supplied with the pump.
Check the direction of the pump’s rotation
before the pump is installed in the pumpstation.
WARNING! Before installing the pump
or pumps, remove any
earth or gravel which may
have fallen into the tank.
Tank
Gasket
Fig. 6
Fig. 7 Gasket position
Access point cover
Fig. 8
13
CAM LOCKING MECHANISM OPTION• Take the cover and drill a Ø 21 mm hole in
the centre of the hollow cylindrical shape
provided for the locking mechanism
• Insert the upper part of the barrel (1) in the
hole which has been drilled (the triangular
shape of the barrel should be outside the
cover) as indicated in the diagram below.
• Next thread the nut (2) over the barrel
(inside of the cover)
• Then place the locking lug (3) over the
square form of the barrel and insert the
screw (4) to keep the lug in place.
• Using the spanner (5) release the locking
device so that the lug (3) does not project
outside the cover. Screw the cover over
your lift station, then lock the cover with the
spanner. Remove the spanner and position
the cap supplied over the cover in order to
prevent clogging with dirt.
14
ELECTRICAL CONNECTIONS
Information for the electrician connecting the
Micro 10 pumpstation.
When making connections inside the station,
do not forget that this is a humid environ-
ment and that appropriate electrical protec-
tion devices are indispensible.
Condensation forms inside the pumpstation
and the connection casings.
Do not use terminal boards as these can
easily cause short-circuiting. Use isolated
connectors filled with silicon. For even
greater safety and to avoid condensation
forming, fill the casings with Vaseline
(or petroleum jelly).
Fix the motor cable giving it a wide curve.
If the cable is too long, it may be sucked into
the pump. Shorten the cable to an appropri-
ate length.
Be careful to ensure that the cable ends are
not immersed; water can be sucked into the
cable by capillarity.
Hang the level regulators on the hooks or to
a support which can be easily removed when
the pump needs to be lifted up. Adjust the
cable to the desired length.
Note: Monitor the direction of wheel rotation.
If the direction of rotation is inverted, the
pump will still work but with reduced perform-
ance.
Monitoring operation
1. Open the stop cock with the valve key
supplied.
2. Start the pump from the control panel.
All electrical work is to be carried out under the supervision of an authorised electrician. Strictly comply with local codes and regulations. Before beginning work, check that the electrical supply cable is disconnected from mains power.
Check the supply voltage on the pump’s data
plate.
Check that the specifications on the motor’s
dataplate match the mains voltage and
frequency.
Carefully read the installation and mainte-
nance manual supplied with the pump to-
gether with that on the electrical control box.
Pass the cables (motor cable, level regulator
cable and equipotential bonding) through the
cable entrance to the electrical control box.
Connect the wires in accordance with the
wiring diagram.
Use the appropriate ITT Lowara clamps to
retain cables inside the pumping station.
Installation of level regulator
Two Flygt ENM-10 level regulators are
provided for startup and for alarms.
The regulators are suspended from hooks in-
side the pumping station. It is recommended
that you install the startup level regulator at
the height of the pump lifting handle and the
alarm regulator 50 cm, higher.
MAINTENANCE
- Refer to the SAFETY section of this
manual for safety measures.
- (Visually) check that the system is tight.
- Lift the pump and check that the dis
charge outlet gasket on the Hook up
system is in a proper state of repair.
- Systematically re-close and lock the
cover before leaving the pumping station.
Pump
Comply with instructions regarding the
frequency of inspection. See Pump Installation
Manual.
Equipotential bonding
Ensure that all connections are tight and show
no signs of corrosion.
Carry out any necessary replacements.
If the pump within the station runs dry or hums,
the surface of the pump and surrounding liquid may be hot.
Be careful of the risk of burning.
15
GENERAL ARRANGEMENT
40 3
2 5 3 4
2728
1 8
14
16
15
26
23 24
25
22 24
2119
13
20
119
7
Discharge 2 pvc
Inlet drilling for
pvc tube Ø 150
with gasket
16
GENERAL ARRANGEMENT
Figure Qty DESIGNATION REMARKS
1 1 Tank polyethylene
2 1 Cover polyethylene
3 1 Cover gasket epdm
4 1 Cover locking system cam type
5 1 Plug polyethylene
7 1 Keyed joint Ø 160 ext. epdm
8 2 Dn50 pump (material according to type)
9 2 Dn50 mounting base cast iron
10 1 Reinforcing plate for mounting base galvanised steel (tbc)
11 2 Fixing insert for mounting base stainless steel
13 4 Guide bar Ø026.9 2.65 th 4x850 length galvanised steel
14 2 Guide bar support stainless steel
15 1 Cross-beam (guide bar-pipework) galvanised steel
16 3 Clip for dn50 return tube pvc
17 1 Support for regulator 4 pts Stainless steel
18 1 Pump gland (to be advised)
19 1 Pipework dn50 total length Pvc
20 2 Male 2” female 63 endpiece Pvc
21 4 Female 45° elbow joint dn63 Pvc
22 2 Loose flange dn50 Pvc
23 2 Fixed flange dn50 pvc
24 4 Flange joint dn50 epdm
25 2 Ball valve dn50 with drilled flange cast iron
26 2 Dn50 gate – female 63 Pvc
27 3 90° elbow joint female dn50 Pvc
28 1 Female tee dn50 Pvc
29 1 Female pipe fitting 63 Pvc
30 1 Feedthrough male 63 –male 2” Pvc
40 * Spacer Polyethylene (option+cover gasket)
LIST OF PARTS
17
DECLARATION OF CONFORMITY
About XylemXylem (XYL) is a leading global water technology provider, enabling customers to transport, treat, test and efficiently use water in public utility, residential and commercial building services, industrial and agricultural settings. The company does business in more than 150 countries through a number of market-leading product brands, and its peo-ple bring broad applications expertise with a strong focus on finding local solutions to the world’s most challengingwater and wastewater problems. Launched in 2011 from the spinoff of the water-related businesses of ITT Corpora-tion, Xylem is headquartered in White Plains, N.Y., with 2011 revenues of $3.8 billion and 12,500 employees worldwide.
The name Xylem is derived from classical Greek and is the tissue that transports water in plants, highlighting the engineering efficiency of our water-centric business by linking it with the best water transportation of all -- that which occurs in nature. For more information, please visit us at www.xyleminc.com
Lowara UK LimitedMillwey Rise Industrial Estate Axminster, Devon EX13 5HU - UK Tel: 01297 630230 Fax: 01297 630270e-mail: [email protected] http://www.lowara.co.ukhttp://completewatersystems.com
Xylem Water Solutions Ireland Limited50 Broomhill CloseAirton RoadTallaght - Dublin 24Tel. (+353) 01 4524444Fax (+353) 01 4524795e-mail: [email protected]://www.lowara.ie
Lowara is a trademark of Xylem Inc. or one of its subsidiaries.
© 2011 Xylem, Inc.
Lowara reserve the right to make modifications without prior notice.
Order code UKLIT0036 P 09/12