insight into offshore wind technological developments with statoil and senvion
TRANSCRIPT
Looking Forwards for Offshore Wind: A Focus on Technology
Offshore Wind Structures
Produced in association with:
London, UK14-15th April 2015
Looking Forwards for Offshore Wind: A Focus on Technology
With the offshore wind industry continuing to gather momentum, new projects
accessing the favourable wind conditions of deeper waters will be striking out
into new technological territory, with increased capacity turbines, novel founda-
tion types, and updated installation and servicing techniques.
Independent analysis forecasts 40GW of installed offshore wind capacity across
Europe by 2020 and 150GW by 2030. Surging towards these key dates, innova-
tion is occurring across the industry; turbines and foundations with capacities
and designs that are far beyond what had previously been thought possible are
revolutionising the entire supply chain.
With a view to maximising the potential of technology at this pivotal time in the
offshore wind industry, companies and independent experts are looking to the
benefits of an integrated design process between the conceptors and manufac-
turers of this new technology, to bring the industry together in collaboration to
achieve the ultimate goal of lowering the levelised cost of energy.
In conjunction with the Offshore Wind Structures summit (14-15th April 2015,
London) Wind Energy Update has brought together experts at Statoil and
Senvion, two key players contributing to the momentum in offshore wind
technology development, to instigate the conversation about which offshore
technologies are key for the future.
Amy Allebone-Salt
Project Director | Wind Energy Update
Join the conversation: linkd.in/Mi6eaN @W_E_Update #OffshoreWindStructures
The Next Generation of Offshore Wind Turbines
Upscaling available turbine technology, in order to allow increased rotor
diameter and megawatt capacity, is one of the primary ways to achieve cost
reductions in offshore wind energy production. Being able to employ fewer
turbines for the same energy output reduces time and money spent on
installation and maintenance.
Marc Seidel, Leading Expert on Offshore Engineering at Senvion, comments:
“From a turbine perspective, we are increasing the energy yield per turbine
constantly, for example by erecting our prototype of the 6.2M152 this month,
where we increase rotor diameter from 126m (of the 6.2M126) to 152m, which
significantly increases annual yield. Generally, the trend is to increase turbine
size to 6MW (or more) for forthcoming projects.”
Eirik Byklum, Technology Manager for floating wind at Statoil, points out that
the maturation of the industry means that installation and maintenance are
both seeing better levels of operational efficiency, again bringing costs down.
“Because the industry is now maturing the installation process itself is getting
better. Specialised installers that are becoming quicker and safer are coming to
the fore,” he says, “and the access vehicles and systems too have become much
more fit-for-purpose, safer, and able to operate in extreme weather conditions.
This all contributes significantly to cost simply because the underlying support
infrastructure can then work to keep the turbines running and producing power.”
2012 2-3MW turbines
<25m water depth<25km from shore
2020 4-7MW turbines
<60m water depth<100km from shore
20308-10MW turbines
120m+ water depth120km+ from shore
An immediate impact of larger turbines – combined with increasing water
depths – is that advancing offshore foundation design and fabrication is a
prescient concern. As the maximum perceived monopile diameter approaches,
the role of technology is to stretch that limit whether through incremental
developments, or step change to different foundation concepts. This expanding
of limits refers not only to the physical sense of the size of the monopole, but
also to the supporting installation and maintenance.
As both turbine and foundation technology develops, the design processes are
becoming more integrated, and tools to optimise structural weights are having
an impact.
Seidel comments: “As monopiles have proven to be very cost effective, we
are pushing the limits in terms of water depths and site conditions, where we
are currently already at 40m water depth in the North Sea with monopiles of
~1200t weight… This improves cost compared to using jackets.”
Jacket technology, too, is being tested and Byklum believes that the seemingly
open discussion prevailing in the industry right now around foundation types
and suitability is a positive one.
“Jackets do not need to be driven as deep into the seabed and this is easier,
quieter and thus a promising development. But testing in various scenarios
needs to be carried out and there is a lot of interest in how this will go,” he says.
Indeed, if the technology for jackets can be matured in the same way as
happened with monopile technology then mass production at reduced cost
would become viable. The same principle can also be applied to the mass
production of up-scaled turbines.
What does this mean for foundations?
How will this mix change in 2014 and beyond?
Market share of installed structures in 2013
Gravity 0.2%
Tripile 1%
Jacket 6%
Tripod 14%
Monopiles 79%
Thus far, up-scaling turbines is one of the most important solutions to the
perennial challenge of bringing down costs. Looking forwards, an important
theme for both foundation and turbine considerations is the need for a margin
to allow incremental improvements, rather than to be constantly operating at
the limits of a given technology solution. In practical terms, this means estab-
lishing solutions now with genuine longevity to allow for further development.
Being able to make incremental changes is a key means of increasing opera-
tional efficiency. This is well demonstrated by wind farm layout and positioning,
where changing the distances between turbines in order to maximise the
amount of wind being captured and reduce loss through uncaptured energy
has reaped real rewards.
Byklum explains: “The layout of the turbines is something that can have a great
deal of impact on productivity. It draws upon various variables, notably the
actual area of the wind farm, the seabed beneath and the direction from which
the wind is coming. The calculations around layout have become more accu-
rate and so getting the right configuration and the distance between turbines
has become easier to get right.”
The seabed itself also has an important role. The soil conditions are crucial for
stiffness conditions, which is one of the most important parameters. Seabed
conditions may also be very important for installation, especially if they feature
weak soils at the top.
Byklum comments: “Developers have learnt the hard way that poor conditions
on the sea bed can have a very negative impact - they are much more aware of
this and its cost implications.”
Turbine Positioning The Seabed
How can the design process improve?
Advancing technology in order to bring costs down and progress the indus-
try relies heavily upon cooperation and communication between its various
components; nowhere does this apply more than in the interplay between the
turbine manufacturer and foundation designer in the design stages.
Seidel comments: “Direct interaction between the lead engineers at the wind
turbine manufacturer and the foundation designer is key to the success of the
project.” He points out that establishing interaction with the foundation design-
ers as early as possible has historically yielded good results. “Communication
has enabled us to successfully complete jacket designs as early as 2005,
whereas other projects (with other turbine manufacturers) experienced delays
due to problems in the design process in recent years. But direct interaction is
not always wanted by owners, as they want to handle the interface between
the two separate contracts. This is a mistake, as this complicates processes and
causes delays,” he says.
In particular, interaction between foundation designer and turbine manufac-
turer would improve the process significantly because the turbine manufacturer
could participate in the design work of the structure, thus mitigating any
incompatability in the interface between loads and structural design.
Seidel thinks that this is “particularly efficient” in the early phases of the project.
“Alternatively, the foundation designer could work with a ‘black box’ turbine
model, which would enable him or her to generate substructure loads inde-
pendently from the turbine manufacturer. Cross-checks are of course needed in
this case, but the process could be much improved,” he says.
And Byklum comments: “Although the interaction is getting better both in
terms of general openness between companies and also project specific
communications, it is still variable and needs to be improved.”
One solution to this could be more structured networking and specific informa-
tion-sharing networks to enshrine the spirit of collaboration into the industry as
a whole.
“It is important to realise that without better cooperation then the end result
will always be sub-optimal,” Byklum says.
A collaborative approach to engineering, procurement and design is
believed to be able to reduce costs by at least 10%
How important is certification for new technologies?
Looking forwards…
But design optimisation is not just about communication and the actual
design itself; it can also be affected by red tape that effectively acts as a bind
to progression, occupying time and energy that would be better spent else-
where, according to Seidel. “The involvement of certification bodies should be
minimised. In my experience, they don’t add much value to the project, but
the process is delaying things. Energy is focused on managing the certification
process with its many assumptions and the risks associated with it, rather than
focusing on optimization of the design. Many people subscribe to this point of
view, but only few dare to say this openly, due to the power that certification
bodies – strangely enough – have acquired.”
Looking to 2020 and beyond, both Seidel and Byklum think that offshore wind
is going to be venturing into the unknown, technology wise. The consequence
of potential step-changes in offshore wind technology is that new innovations
will be based upon theoretical calculations rather than tested and upgraded
versions of existing technology that has a proven track record. However,
although treading the fine line between the reduced risk profile of existing
technologies and bringing costs down through further innovation is always
going to be difficult, these professionals believe it will prove central to the long-
term prosperity of the industry.
Marc Seidel
Leading Expert,
Offshore Wind
Senvion SE
Eirik Byklum
Technology Manager for
Floating Wind,
Statoil.
Representatives from Statoil and Senvion will be continuing the conversa-
tion with EDF, Mainstream, MHI Vestas Offshore, HR Wallingford, BVG
Associates, The Carbon Trust, ETI, and more from across the industry at
Offshore Wind Structures in London, 14-15th April 2015.
The carefully selected agenda and speakers reflect the most important techno-
logical developments as selected by you: the professionals.
Attend Offshore Wind Structures – the only event to consider the whole struc-
ture and so to unite the industry disciplines and across the supply chain – to
add significant value to your project and achieve the goal of reducing the cost
of energy.
Experiences with Wind Energy Update:
“Good especially because it is much more about the problems and less commercial.” Acciona
“This conference was a great opportunity to meet different actors in the offshore wind industry to share knowledge and best practices. It gave me the opportunity for networking with other professionals as well. The conference
as a whole was quite excellent.” Vattenfall
“The WEU events are the only conferences worth attending. The events are detailed, concise and contain the decision makers. It’s always great to be able to attend an event where the speakers stay and spend time networking with
the audience.” GCube Underwriting Ltd
Including Representatives from:
Offshore Wind StructuresLondon, UK | 14-15th April 2015
ORDER NOW
View the forum brochure for more information
Thank you for reading Looking Forwards for Offshore Wind: A Focus on Technology.
If you have any feedback, or ideas for what you would like us to publish next, get in touch.
Contact Amy Allebone-Salt
Project Director | Wind Energy Update
For more information go to www.windenergyupdate.com
Join the conversation: linkd.in/Mi6eaN @W_E_Update
Looking Forwards for Offshore Wind: A Focus on Technology © 2014 FC Business Intelligence®
The information of this document was prepared by Wind Energy Update (part of FC Business Intelligence) and its partners. Wind Energy Update has no obligation to tell you when information in this
document changes. Wind Energy Update makes every effort to use reliable, comprehensible information, but we make no representation that it is accurate or complete. In no event shall Wind Energy Update
and its partners be liable for any damages, losses, expenses, loss of data or profit caused by the use of the material or contents of this document.
Wind Energy Update
Offshore Wind Structures
Produced in association with:
London, UK14-15th April 2015