inputs and outputs to aggregate production planning
DESCRIPTION
Capacity Constraints. Strategic Objectives. Company Policies. Demand Forecasts. Financial Constraints. Aggregate Production Planning. Size of Workforce. Units or dollars subcontracted, backordered, or lost. Production per month (in units or $). Inventory Levels. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/1.jpg)
1DSCI4743
Inputs and Outputs to Aggregate Production Planning
AggregateProductionPlanning
CompanyPolicies
FinancialConstraints
StrategicObjectives
Units or dollarssubcontracted,backordered, or
lost
CapacityConstraints
Size ofWorkforce
Productionper month
(in units or $)
InventoryLevels
DemandForecasts
![Page 2: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/2.jpg)
22DSCI4743
Material Requirements Planning (MRP)
• A computerized inventory control & production planning system
• Schedules component items when they are needed - no earlier and no later
![Page 3: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/3.jpg)
33DSCI4743
When to Use MRP
• Dependent and discrete items
• Complex products
• Job shop production
• Assemble-to-order environments
![Page 4: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/4.jpg)
44DSCI4743
Demand Types
Two Types of Demand: Independent
• Not related to the demand for any other product & must be forecast
• MPS items are independent demand items
Dependent• Directly related to other items or end items• Such demand should be calculated should not be
forecast
![Page 5: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/5.jpg)
55DSCI4743
MRP Inputs & OutputsMaster Production Schedule
MaterialRequirements
Planning
Planned Order Releases
Work Orders Purchase Orders Rescheduling Notices
ProductStructure
File
InventoryMaster
File
![Page 6: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/6.jpg)
66DSCI4743
MRP Inputs
• Master production schedule
• Product structure file
• Inventory master file
![Page 7: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/7.jpg)
77DSCI4743
Master Production Schedule
• Drives MRP process with a schedule of finished products
• Quantities represent production not demand
• Quantities may consist of a combination of customer orders & demand forecasts
• Quantities represent what needs to be produced, not what can be produced
![Page 8: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/8.jpg)
88DSCI4743
Product Structure TreeLevel 0
Level 1
Level 2
Level 3
Clipboard
Rivet (2)
Iron Rod
(3 in.)
Spring (1)
Spring Steel
(10 in.)
Bottom Clip (1)
Top Clip (1)
Pivot (1)
Sheet Metal (8 in2)
Clip Assembly (10)
Sheet Metal (8 in2)
Board (1)
Pressboard (1)
Finish (2oz.)
![Page 9: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/9.jpg)
99DSCI4743
Indented Bill of Material
LEVEL ITEM Unit of Measure Quantity0 - - - - Clipboard Ea 1- 1 - - - Clip Assembly Ea 1- - 2 - - Top Clip Ea 1- - - 3 - Sheet Metal In2 8- - 2 - - Bottom Clip Ea 1- - - 3 - Sheet Metal In2 8- - 2 - - Pivot Ea 1- - - 3 - Iron Rod In 3- - 2 - - Spring Ea 1- - - 3 - Spring Steel In 10- 1 - - - Rivet Ea 2- 1 - - - Board Ea 1- - 2 - - Press Board Ea 1- - 2 - - Finish Oz 2
![Page 10: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/10.jpg)
1010DSCI4743
Specialized BOMS
• Phantom bills• transient subassemblies• never stocked• immediately consumed in next stage
• K-bills• group small, loose parts under pseudoitem #• reduces paperwork
![Page 11: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/11.jpg)
1111DSCI4743
Specialized BOMS
• Modular bills• product assembled from major subassemblies
& customer options• modular bill kept for each major subassembly• simplifies forecasting & planning• automobile example
- 3 x 8 x 3 x 8 x 4 = 2,304 configurations- 3 + 8 + 3 + 8 + 4 = 26 modular bills
![Page 12: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/12.jpg)
1212DSCI4743
Inventory Master File
Description Inventory Policy
Item Board Lead time 2
Item no. 7341 Annual demand 5,000
Item type Manuf. Holding cost 1
Prod/sales Ass’y Ordering/setup cost 50
Value class B Safety stock 25
Buyer/planner RSR Reorder point 39
Vendor 07142 EOQ 316
Phantom code N Minimum order qty 100
Unit price/cost 1.25 Maximum order qty 500
Pegging Y Multiple order qty 100
![Page 13: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/13.jpg)
1313DSCI4743
Inventory Master File, Con’t.
Physical Inventory Usage/SalesOn hand 100 YTD usage/sales 1,100Location W142 MTD usage/sales 75On order 50 YTD receipts 1,200Allocated 75 MTD receipts 0Cycle 3 Last receipt 8/25Difference -2 Last issue 10/5
CodesCost acct. 00754Routing 00326
Engr 07142
![Page 14: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/14.jpg)
1414DSCI4743
Inventory Accuracy
1. Maintain orderly stockrooms2. Control access to stockrooms3. Establish & enforce procedures for inventory
withdrawal4. Ensure prompt and accurate entry of inventory
transactions5. Take physical inventory count on a regular basis6. Reconcile inventory discrepancies in a timely manner
(use cycle counting)
![Page 15: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/15.jpg)
1515DSCI4743
The MRP Matrix
Gross Requirements
Scheduled Receipts
Projected On Hand
Net Requirements
Planned Order Receipts
Planned Order Releases
ITEM: LLC: Lot Size: LT: PD 1 2 3 4 5 6 7 8 9
![Page 16: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/16.jpg)
1616DSCI4743
Parts Of MRP Matrix
• Item name or number identifying scheduled item
• LLC low-level-code; lowest level at which item appears in a product structure
• Lot size order multiples of this qty; can be min/max qty
• LT (lead time)-time from order placement to receipt
• PD (past-due)-orders behind schedule
• Gross requirements-demand for item by time period
![Page 17: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/17.jpg)
1717DSCI4743
• Scheduled receipts- quantity already on order & receipt date
- released orders become scheduled receipts
• Projected on hand - expected on-hand inventory at end of period
• Net requirements - net amount needed after on-hand adjustments
• Planned order receipts - net requirements adjusted for lot-sizing
• Planned order releases - planned order receipts offset by lead time
Parts Of MRP Matrix
![Page 18: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/18.jpg)
1818DSCI4743
MRP Example
Item On Hand Scheduled Receipts Lot Size MPS
A 10 0 1 100, period 8
B 5 0 1 - - -
C 140 0 150 - - -
ALT=3
B (3)LT=4
C (2)LT=2
![Page 19: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/19.jpg)
1919DSCI4743
MRP Matrices For A & BItem: A LLC: 0 PeriodLot size: 1 LT: 3 PD 1 2 3 4 5 6 7 8Gross requirements 100Scheduled receiptsProjected on hand 10 10 10 10 10 10 10 10 0Net requirements 90Planned order receipts 90Planned order releases 90
Item: B LLC: 1 PeriodLot size: 1 LT: 4 PD 1 2 3 4 5 6 7 8Gross requirements 270Scheduled receiptsProjected on hand 5 5 5 5 5 0 0 0 0Net requirements 265Planned order receipts 265Planned order releases 265
![Page 20: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/20.jpg)
2020DSCI4743
MRP Matrices For C
Item: C LLC: 1 PeriodLot size: 150 LT: 2 PD 1 2 3 4 5 6 7 8Gross requirements 180Scheduled receiptsProjected on hand 140 140 140 140 140 110 110 110 110Net requirements 40Planned order receipts 150Planned order releases 150
![Page 21: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/21.jpg)
2121DSCI4743
Manufacturing Resource Planning (MRP II)
• Extension of MRP
• Plans all resources needed for running a business
• Usually includes capacity planning, but
• Has many different modules
![Page 22: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/22.jpg)
2222DSCI4743
MRP II Modules
Forecasting
Customer order entry
Production planning / master production scheduling
Product structure / bill-of-material processor
Inventory control
Material requirements planning
Capacity planning
Shop floor control
Purchasing
Accounting
Financial analysis
![Page 23: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/23.jpg)
2323DSCI4743
Capacity Requirements Planning (CRP)
• Computerized system that projects loads from the planned order releases of MRP
• Creates load profile
• Identifies underloads and overloads
![Page 24: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/24.jpg)
2424DSCI4743
Feasible?
MarketingPlan
FinancialPlan
BusinessPlan
ProductionPlan
No
moreYes
MRP II Diagram
![Page 25: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/25.jpg)
2525DSCI4743
Master productionschedule
Material requirementsplanning
Capacity requirementsplanning
Manufacture
InventoryShop floor
control
Purchaseorders
Workorders
Feasible?No
Yes
Feedback
MRP II Diagram
![Page 26: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/26.jpg)
2626DSCI4743
Problems with MRP
• Material requirements plan is first; capacity is an afterthought
• MRP assumes fixed lead times
• Excessive reporting requirements
![Page 27: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/27.jpg)
2727DSCI4743
Using the Material Requirements Plan
• Computer performs all calculations & creates planned order releases,
• Computer software can create exception messages & suggest types of action
• Computer does not (usually) issue purchase or manufacturing orders or reschedule open orders
• Therefore, a Planner is needed
![Page 28: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/28.jpg)
2828DSCI4743
The Basic Responsibilities of a Planner
• Launch (release) orders to purchasing or shop floor• Reschedule due dates of open (existing) orders as
required• Reconcile errors & try to find their cause• Address critical material shortages by expediting or
re-planning• Coordinate w/other planners, master production
schedulers, production activity control, & purchasing
![Page 29: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/29.jpg)
2929DSCI4743
Prospects for MRP/MRP II
• Coordinates strategy among different functional areas• Responds quickly to what-if? questions at various levels• BOM processors, purchase modules, & customer order
entry are standard requirements for Manufacturing Information Systems
• Monitors design & vendor quality, & customer service• Builds trust, teamwork, & better decisions• Cash-flow planning & profit/cost projections
![Page 30: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/30.jpg)
3030DSCI4743
Advanced Planning & Control Systems
• Enterprise Resource Planning (ERP)• updates MRP II with relational DBMS, GUI &
client/server architecture; covers entire enterprise
• Customer Resource Management (CRM)• links business planning & mgmt control systems
• Customer-Oriented Manufacturing Management Systems (COMMS)
• unites departments & suppliers around customer
• multi-plant planning, multiple languages & currencies
![Page 31: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/31.jpg)
31DSCI4743
Hierarchical Planning ProcessItems
Product lines or families
Individual products
Components
Manufacturing operations
Resource level
Plants
Individual machines
Critical work centers
Production Planning Capacity Planning
Resource Requirements Plan
Rough-Cut Capacity Plan
Capacity Requirements Plan
Input/Output Control
Aggregate Production Plan
Master Production Schedule
Material Requirements Plan
Shop Floor Schedule
All work centers
![Page 32: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/32.jpg)
3232DSCI4743
The Alpha Beta Company
Item On Hand Scheduled Receipts Lot Size MPS
A 10 0 1 100, period 8
B 5 0 1 200, period 6
C 140 0 150 - - -
D 200 0 250 - - -
ALT=3
C (3)LT=4
D (2)LT=2
D (3)LT=2
BLT=2
![Page 33: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/33.jpg)
3333DSCI4743
MRP Matrices For A & BItem: A LLC: 0 PeriodLot size: 1 LT: 3 PD 1 2 3 4 5 6 7 8Gross requirements 100Scheduled receiptsProjected on hand 10 10 10 10 10 10 10 10 0Net requirements 90Planned order receipts 90Planned order releases 90
Item: B LLC: 0 PeriodLot size: 1 LT: 2 PD 1 2 3 4 5 6 7 8Gross requirements 200Scheduled receiptsProjected on hand 5 5 5 5 5 5 0 0 0Net requirements 195Planned order receipts 195Planned order releases 195
![Page 34: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/34.jpg)
3434DSCI4743
MRP Matrices For C & DItem: C LLC: 1 PeriodLot size: 150 LT: 4 PD 1 2 3 4 5 6 7 8Gross requirements 270Scheduled receiptsProjected on hand 140 140 140 140 140 20 20 20 20Net requirements 130Planned order receipts 150Planned order releases 150
Item: D LLC: 1 PeriodLot size: 250 LT: 2 PD 1 2 3 4 5 6 7 8Gross requirements 585 180Scheduled receiptsProjected on hand 200 200 200 200 115 185 185 185 185Net requirements 385 65Planned order receipts 500 250Planned order releases 500 250
![Page 35: Inputs and Outputs to Aggregate Production Planning](https://reader036.vdocuments.site/reader036/viewer/2022062408/56813715550346895d9e9f03/html5/thumbnails/35.jpg)
3535DSCI4743
Alpha Beta Planned Order Report
Period Item Quantity
1 C 150
2 D 250
3 D 250
4 B 195
5 A 90