innovations in program controls integrating primavera and cost systems

42
1 Innovations in Program Controls Integrating Oracle Primavera and Cost Systems Presented by: Javier Sloninsky Managing Director April 13, 2011

Upload: p6academy

Post on 17-Aug-2015

22 views

Category:

Documents


7 download

TRANSCRIPT

Page 1: Innovations in program controls   integrating primavera and cost systems

1

Innovations in Program Controls

Integrating Oracle Primavera and Cost Systems

Presented by:Javier Sloninsky

Managing DirectorApril 13, 2011

Page 2: Innovations in program controls   integrating primavera and cost systems

2

Agenda

Speaker intro

Corporate Introduction

Overview of EcoSys Enterprise Planning & Controls (EPC)

Best Practices and Case Studies in Cost Integration with Oracle Primavera: • Earned Value Management, ERPs, & Alternate Breakdown Structures• Funds Management and Integrated Performance

Q&A

Page 3: Innovations in program controls   integrating primavera and cost systems

3

Founded in 2000

Enterprise Project Controls Software Experts

Designers & Developers of original Primavera P6 and EcoSys EPC

Professional Services

Enterprise Consulting Expertise: Project Portfolio & Cost Management Best Practices Global Primavera Implementation and Systems Integration Leader

Partnerships with Oracle, SAP, Accenture, Microsoft, IBM

200 Customers in Global 1000 and Public Sector

EcoSys Company Background

Page 4: Innovations in program controls   integrating primavera and cost systems

• Project Controls System Designers• Project Controls Implementers:

– Owners and Operators – Contractors

– Public sector• Enterprise architecture mindset

• Partnership approach with industry

• Constant evolution

4

Our PerspectiveOur Perspective

Page 5: Innovations in program controls   integrating primavera and cost systems

Representative Customers

5

Page 6: Innovations in program controls   integrating primavera and cost systems

Fundamental Cost Controls Questions

• What is the current budget and forecast? • How much has been spent? • How much funding is available and how is it being used? • How and why has my budget and forecast changed? • How is the work package/project/portfolio trending? • Where can we make improvements? • How are project schedules impacting cost? • Are we performing efficiently? • What are our commitments? • What are the contractual, funding or payment rules?

6

Page 7: Innovations in program controls   integrating primavera and cost systems

In most organizations, Cost Controls is not a simple affair

Departmental Budgets Project ForecastsProject Budgets

Actual TransactionsCommitments

7

ContractDatabase

Project Planning

General LedgerGeneral

LedgerTime Cards

JVFunding

Funds Management

Challenges for Cost Controls

Impact

• Teams of people consolidating data in spreadsheets

• Double entry

• Spreadsheet errors

• Performance reports available too late to address issues

Page 8: Innovations in program controls   integrating primavera and cost systems

Cost Analysts Spent 61% of Time On

“Wasteful” Activities

20%

16%

13%12%

30%

6%2% 1%

Fixing ERP Feeds

Correcting Labor Coding

Collating Internal &External ReportsManual Downloading

Monitoring & Controlling Costs

Change Management

Forecasting & Trending Analyzing Budgets & Actuals

8

Source: Internal Study by EcoSys Customer

Page 9: Innovations in program controls   integrating primavera and cost systems

9

Cost Analyst Target Utilization Provides

Much Greater Value Added

65%25%

5%5%

Analyzing Data

Forecasting &Trending

Running ReportsTroubleshooting

Source: Internal Study by EcoSys Customer

Page 10: Innovations in program controls   integrating primavera and cost systems

10

Strike a balance between flexibility and business rule enforcement

Tailorability /Configurability Terminology Processes Reporting Metrics

Project/Cost Structures WBS CBS OBS Alternate Breakdown Structures Phases/Lifecycle

Financial data structures Actual Expenditures Accruals Revenue Commitments Pricing & Rates Multi-currency

Project schedule data WBS Cash Flows / Time Phasing Time Periods Resource loading

Successful Cost Controls Systems

Page 11: Innovations in program controls   integrating primavera and cost systems

11

EcoSys – Full Lifecycle Project Controls

Page 12: Innovations in program controls   integrating primavera and cost systems

12

Bridging Planning & Execution

Page 13: Innovations in program controls   integrating primavera and cost systems

• Import Projects/WBS from P6• Import Resources• Import Dates • Import % Complete• Import time-phased Resource

Assignments– Units (BL, actuals, planned, remaining)– Costs (BL, actuals, planned, remaining)

• Import/Map P6 Codes/Attributes– Project Codes– Resource Codes– Activity Codes– Cost Accounts– Expense Categories

13

Flexible Primavera Integration Options

Different integration rules can be established for different business areas, departments, project types, etc

• Export Projects, Activities to P6• Export Actuals

– Units– Costs– Resources– Dates– Map to WBS/Activity Codes/Roles

• Export Forecasts– Units– Costs– Resources– Dates– % Complete– Map to WBS/Activity Codes/Roles

Page 14: Innovations in program controls   integrating primavera and cost systems

14

Planning & Controls Platform

Create Projects and Build WBS in EcoSys, or import from Primavera, MS Project, SAP, etc.

Budget in EcoSys, or Import from Primavera, MS Project, Oracle Projects, etc.

Actuals from General Ledger and/or from Accruals

Import Commitments or Manage in EcoSys

Progress and Forecast in EcoSys, and compare to cost loaded schedules, contractor forecasts

Maintain Each Version in EcoSys, gaining Trending and Audit Trail

Page 15: Innovations in program controls   integrating primavera and cost systems

15

Departments/Programs > Program > Project > Transactions

Full Drilldown Visibility

Page 16: Innovations in program controls   integrating primavera and cost systems

16

Customizable Web Spreadsheets for data entry

Project Budgeting

Project Forecasting

Planning & Controls

Contract Commitments

Page 17: Innovations in program controls   integrating primavera and cost systems

17

From Summary to Variance Analysis

Reporting

Page 18: Innovations in program controls   integrating primavera and cost systems

18

Dashboards

Page 19: Innovations in program controls   integrating primavera and cost systems

19

Configurable Cost Processes

Can set up company specific custom criteria:• Group By Capital and O&M• Filter by Outage/Online• Distribute cost manually or by curve

Page 20: Innovations in program controls   integrating primavera and cost systems

21

Compare/Reconcile P6,Cost Data

Page 21: Innovations in program controls   integrating primavera and cost systems

22

Capital Project Budgets Report

Page 22: Innovations in program controls   integrating primavera and cost systems

23

Project Controls Best Practices

• Babcock & Wilcox, Nuclear Power Generation company, establishes EVM standards and reporting mechanisms

• FAA implements Capital Program Management System integrating Long Range Planning and Project Controls

Page 23: Innovations in program controls   integrating primavera and cost systems

24

• Nuclear Power Generation & Operations company with major R&D, Construction, and Services projects in Canada & US

• Standardized on SAP and Primavera P6

• Requirement for centralized platform went beyond need for integration

• Deployed EcoSys for integrated performance management, reporting, and controls

• Utilized on B&W/Bechtel Joint Venture mPower Program (Small Modular Reactor)

Case Study

Page 24: Innovations in program controls   integrating primavera and cost systems

25

EcoSys Integration Approach

WBSPercent CompleteLabor plans

Integrated Earned Value ManagementConsolidated Project Cost ReportingBudgets, Forecasts, CommitmentsActual Costs, RevenueChange ManagementHistorical SnapshotsTransaction/Audit Repository

SAP

Actual CostsTimesheetsCommitmentsRevenue

WBS & WBS StatusBudget

Bechtel Timesheets

Approved Change Orders

®

Page 25: Innovations in program controls   integrating primavera and cost systems

26

• EV Technique Varies by Work Package• Full Time-Phased History of Earned Value by Month• EV Measures based on both Hours and Costs• Performance analysis by Month, Year, and Project Life• Change & Trend Management integrated into Current Budget & Current Forecast• EV Reports can be run by toggling Baseline Budget =Cur Budget or Cur FC• Ability to analyze performance & ETC by Alternate Breakdown Structures:

• Discipline• OBS• Cost Type (Labor, Material, ODCs, etc)

Highlights of B&W Approach

Page 26: Innovations in program controls   integrating primavera and cost systems

27

Month End Closeout Schedule

Planning

Page 27: Innovations in program controls   integrating primavera and cost systems

28

DeliverablesMatrix

Page 28: Innovations in program controls   integrating primavera and cost systems

29

SAMPLE DATA

Standardized Performance Reporting

Cumulative & Periodic Performance

Page 29: Innovations in program controls   integrating primavera and cost systems

30

SAMPLE DATA

Cumulative & Periodic Performance

Page 30: Innovations in program controls   integrating primavera and cost systems

By Project, Category Code, and EV Method

31

Flexible Earned Value Analysis

Page 31: Innovations in program controls   integrating primavera and cost systems

32

EVM Dashboards Comparisons By Alliance Partner

Page 32: Innovations in program controls   integrating primavera and cost systems

33

CPI / SPI

Page 33: Innovations in program controls   integrating primavera and cost systems

34

WBS and ABSPlanning Process

Page 34: Innovations in program controls   integrating primavera and cost systems

FAA TAMR Program

35

Overview:• Terminal Automation Modernization and Replacement (TAMR) Program within Air

Traffic Control – Terminal (ATO-T) Organization• Modernize Air Traffic Control Systems at Nation’s Major Airports• High Visibility Capital Program

Capital Program Management Innovations:• Standardize Contractor Submissions with Oracle Primavera P6 Templates

• EVM Reporting performed based upon FAA’s structures• Resource loaded schedules drive budgets, forecasts and EVM in EcoSys

• EcoSys Database Consolidates Funding Allocations, Budgets, Estimates, Forecasts, Obligations, Commitments, Expenditures, Performance/EVM

• ATO-T Maintains Vendors and Own Cost and Schedule Forecasts as Separate Versions

• G/L Actuals Are Reconciled against Vendor Submissions

Case Study

Page 35: Innovations in program controls   integrating primavera and cost systems

FAA’s P6 and EcoSys Solution

• Project activities reported in Primavera based on standard EVM techniques such as • Physical % complete – based on weighted Steps• Level of Effort - % duration • Milestone % complete

• Integrated with EcoSys to import Units, % complete and dates • Primavera planned, Actual and Remaining units used to calculate forecast,

Actual and Remaining costs by project• Schedule and Performance % complete info that is calculated based on

duration or Steps used for EVM metrics• Dates imported used for reporting purposes

21

Page 36: Innovations in program controls   integrating primavera and cost systems

37

Most Activities updated using weighted Steps

22

Performance Measurement

Page 37: Innovations in program controls   integrating primavera and cost systems

38

Program EVM Reporting

Page 38: Innovations in program controls   integrating primavera and cost systems

39

Program EVM Reporting

Page 39: Innovations in program controls   integrating primavera and cost systems

40

Reports / Charts

Page 40: Innovations in program controls   integrating primavera and cost systems

41

Reports / Charts

Page 41: Innovations in program controls   integrating primavera and cost systems

42

Example Independent EACs

• IEAC1, assumes future cost performance will be same as past performance

• IEAC2, assumes future cost performance will be influenced by 80% past cost and 20% past schedule performance

• IEAC3, assumes future cost performance will be influenced by the last 3 months cost performance

• IEAC4, assumes future cost performance will be influenced by past cost and schedule performance

Page 42: Innovations in program controls   integrating primavera and cost systems

Thank you!