innovations in program controls integrating primavera and cost systems
TRANSCRIPT
1
Innovations in Program Controls
Integrating Oracle Primavera and Cost Systems
Presented by:Javier Sloninsky
Managing DirectorApril 13, 2011
2
Agenda
Speaker intro
Corporate Introduction
Overview of EcoSys Enterprise Planning & Controls (EPC)
Best Practices and Case Studies in Cost Integration with Oracle Primavera: • Earned Value Management, ERPs, & Alternate Breakdown Structures• Funds Management and Integrated Performance
Q&A
3
Founded in 2000
Enterprise Project Controls Software Experts
Designers & Developers of original Primavera P6 and EcoSys EPC
Professional Services
Enterprise Consulting Expertise: Project Portfolio & Cost Management Best Practices Global Primavera Implementation and Systems Integration Leader
Partnerships with Oracle, SAP, Accenture, Microsoft, IBM
200 Customers in Global 1000 and Public Sector
EcoSys Company Background
• Project Controls System Designers• Project Controls Implementers:
– Owners and Operators – Contractors
– Public sector• Enterprise architecture mindset
• Partnership approach with industry
• Constant evolution
4
Our PerspectiveOur Perspective
Representative Customers
5
Fundamental Cost Controls Questions
• What is the current budget and forecast? • How much has been spent? • How much funding is available and how is it being used? • How and why has my budget and forecast changed? • How is the work package/project/portfolio trending? • Where can we make improvements? • How are project schedules impacting cost? • Are we performing efficiently? • What are our commitments? • What are the contractual, funding or payment rules?
6
In most organizations, Cost Controls is not a simple affair
Departmental Budgets Project ForecastsProject Budgets
Actual TransactionsCommitments
7
ContractDatabase
Project Planning
General LedgerGeneral
LedgerTime Cards
JVFunding
Funds Management
Challenges for Cost Controls
Impact
• Teams of people consolidating data in spreadsheets
• Double entry
• Spreadsheet errors
• Performance reports available too late to address issues
Cost Analysts Spent 61% of Time On
“Wasteful” Activities
20%
16%
13%12%
30%
6%2% 1%
Fixing ERP Feeds
Correcting Labor Coding
Collating Internal &External ReportsManual Downloading
Monitoring & Controlling Costs
Change Management
Forecasting & Trending Analyzing Budgets & Actuals
8
Source: Internal Study by EcoSys Customer
9
Cost Analyst Target Utilization Provides
Much Greater Value Added
65%25%
5%5%
Analyzing Data
Forecasting &Trending
Running ReportsTroubleshooting
Source: Internal Study by EcoSys Customer
10
Strike a balance between flexibility and business rule enforcement
Tailorability /Configurability Terminology Processes Reporting Metrics
Project/Cost Structures WBS CBS OBS Alternate Breakdown Structures Phases/Lifecycle
Financial data structures Actual Expenditures Accruals Revenue Commitments Pricing & Rates Multi-currency
Project schedule data WBS Cash Flows / Time Phasing Time Periods Resource loading
Successful Cost Controls Systems
11
EcoSys – Full Lifecycle Project Controls
12
Bridging Planning & Execution
• Import Projects/WBS from P6• Import Resources• Import Dates • Import % Complete• Import time-phased Resource
Assignments– Units (BL, actuals, planned, remaining)– Costs (BL, actuals, planned, remaining)
• Import/Map P6 Codes/Attributes– Project Codes– Resource Codes– Activity Codes– Cost Accounts– Expense Categories
13
Flexible Primavera Integration Options
Different integration rules can be established for different business areas, departments, project types, etc
• Export Projects, Activities to P6• Export Actuals
– Units– Costs– Resources– Dates– Map to WBS/Activity Codes/Roles
• Export Forecasts– Units– Costs– Resources– Dates– % Complete– Map to WBS/Activity Codes/Roles
14
Planning & Controls Platform
Create Projects and Build WBS in EcoSys, or import from Primavera, MS Project, SAP, etc.
Budget in EcoSys, or Import from Primavera, MS Project, Oracle Projects, etc.
Actuals from General Ledger and/or from Accruals
Import Commitments or Manage in EcoSys
Progress and Forecast in EcoSys, and compare to cost loaded schedules, contractor forecasts
Maintain Each Version in EcoSys, gaining Trending and Audit Trail
15
Departments/Programs > Program > Project > Transactions
Full Drilldown Visibility
16
Customizable Web Spreadsheets for data entry
Project Budgeting
Project Forecasting
Planning & Controls
Contract Commitments
17
From Summary to Variance Analysis
Reporting
18
Dashboards
19
Configurable Cost Processes
Can set up company specific custom criteria:• Group By Capital and O&M• Filter by Outage/Online• Distribute cost manually or by curve
21
Compare/Reconcile P6,Cost Data
22
Capital Project Budgets Report
23
Project Controls Best Practices
• Babcock & Wilcox, Nuclear Power Generation company, establishes EVM standards and reporting mechanisms
• FAA implements Capital Program Management System integrating Long Range Planning and Project Controls
24
• Nuclear Power Generation & Operations company with major R&D, Construction, and Services projects in Canada & US
• Standardized on SAP and Primavera P6
• Requirement for centralized platform went beyond need for integration
• Deployed EcoSys for integrated performance management, reporting, and controls
• Utilized on B&W/Bechtel Joint Venture mPower Program (Small Modular Reactor)
Case Study
25
EcoSys Integration Approach
WBSPercent CompleteLabor plans
Integrated Earned Value ManagementConsolidated Project Cost ReportingBudgets, Forecasts, CommitmentsActual Costs, RevenueChange ManagementHistorical SnapshotsTransaction/Audit Repository
SAP
Actual CostsTimesheetsCommitmentsRevenue
WBS & WBS StatusBudget
Bechtel Timesheets
Approved Change Orders
®
26
• EV Technique Varies by Work Package• Full Time-Phased History of Earned Value by Month• EV Measures based on both Hours and Costs• Performance analysis by Month, Year, and Project Life• Change & Trend Management integrated into Current Budget & Current Forecast• EV Reports can be run by toggling Baseline Budget =Cur Budget or Cur FC• Ability to analyze performance & ETC by Alternate Breakdown Structures:
• Discipline• OBS• Cost Type (Labor, Material, ODCs, etc)
Highlights of B&W Approach
27
Month End Closeout Schedule
Planning
28
DeliverablesMatrix
29
SAMPLE DATA
Standardized Performance Reporting
Cumulative & Periodic Performance
30
SAMPLE DATA
Cumulative & Periodic Performance
By Project, Category Code, and EV Method
31
Flexible Earned Value Analysis
32
EVM Dashboards Comparisons By Alliance Partner
33
CPI / SPI
34
WBS and ABSPlanning Process
FAA TAMR Program
35
Overview:• Terminal Automation Modernization and Replacement (TAMR) Program within Air
Traffic Control – Terminal (ATO-T) Organization• Modernize Air Traffic Control Systems at Nation’s Major Airports• High Visibility Capital Program
Capital Program Management Innovations:• Standardize Contractor Submissions with Oracle Primavera P6 Templates
• EVM Reporting performed based upon FAA’s structures• Resource loaded schedules drive budgets, forecasts and EVM in EcoSys
• EcoSys Database Consolidates Funding Allocations, Budgets, Estimates, Forecasts, Obligations, Commitments, Expenditures, Performance/EVM
• ATO-T Maintains Vendors and Own Cost and Schedule Forecasts as Separate Versions
• G/L Actuals Are Reconciled against Vendor Submissions
Case Study
FAA’s P6 and EcoSys Solution
• Project activities reported in Primavera based on standard EVM techniques such as • Physical % complete – based on weighted Steps• Level of Effort - % duration • Milestone % complete
• Integrated with EcoSys to import Units, % complete and dates • Primavera planned, Actual and Remaining units used to calculate forecast,
Actual and Remaining costs by project• Schedule and Performance % complete info that is calculated based on
duration or Steps used for EVM metrics• Dates imported used for reporting purposes
21
37
Most Activities updated using weighted Steps
22
Performance Measurement
38
Program EVM Reporting
39
Program EVM Reporting
40
Reports / Charts
41
Reports / Charts
42
Example Independent EACs
• IEAC1, assumes future cost performance will be same as past performance
• IEAC2, assumes future cost performance will be influenced by 80% past cost and 20% past schedule performance
• IEAC3, assumes future cost performance will be influenced by the last 3 months cost performance
• IEAC4, assumes future cost performance will be influenced by past cost and schedule performance
Thank you!